No reservations relevant to MRP exist for project

Hi all,
While doing MRP for WBS through MD51 i have got an error " No reservations relevant to MRP exist for project " . I am not getting where the problem is occurs.
Regards,
Swapnil Vaidya

Dear .
1.Please check wether in your project builder(CJ20N) Project Status is REL  and  Procurement Type is  :Reservation for WBS element . then it will not create this masg.
2.Check whether MRP run date is after the project start date as well as the WBS element is also with in the time frame
3.Check the material master parameters(MRP1-MRP4 view ) for Project material which are to be planned by that Project WBS .
Check and revert
Regards
JH
Edited by: Jiaul Haque on May 1, 2010 2:27 PM

Similar Messages

  • MRP run for Project

    Hello Experts,
    I want you experts help with regards to the following scenario
    This is a construction scenario. In this industry, during the Project estimation stage productivity Norm of the company plays a vital role
    For Example
    Say for excavation of 1 M3 of Soil following resources are required (this is productivity Norm)
    1.     Labour – 2 Hours
    2.     Excavator – 1 Hour
    In order to capture this, I have created a Material BOM, with Header Material as “EXCAV” (Material Type – FERT & UOM – M3) and Components as “LABOUR” & “EXCAVATOR” (Material Type – DIEN & UOM – Hours).
               EXCAV (Material Type – FERT & UOM – M3)
    LABOUR     EXCAVATOR (Material Type – DIEN & UOM – Hours)
    I have created a project with an activity called “EXCAVATION”, for which I have assigned the material “EXCAV”.
    I want to generate the requirement for the components “LABOUR” & “EXCAVATOR”; hence I’m trying to run Project MRP (MD51). But no requirements are getting generated for any material.
    Please help me out.
    Thanks in advance & any suggestions will be rewarded.
    Regards
    Tanya

    Hi Taanya,
    When ever components are allocated to the activity in a Network, system creates only reservation for the components. In your case also it should have created reservation.
    If so run MD02 for "EXCAV" - (Assumption you have populated the material master with all MRP view and related fields), system should now generate Procurement proposals.
    Another check what I would suggest is to check in the Component overview "Res./Purc. Req." field hope this is not populated with value "1". If it was "1" change it to "3" so that reservations are created immediately once the Network is saved.
    Hope this helps... you. Reward your points if so,
    Regards,
    Prasobh

  • MRP for Project MD51

    Hi all,
    I have a problem that is showed below:
    Our general stock is 100 for material ABC (procurement type is F: external procurement).
    We have 3 project stock for 3 WBS element. They are
            - Project stock 1: 0
              OrdRes: 50
            - Project stock 2: 0
              OrdRes: 30
            - Project stock 3: 0
              OrdRes: 60
    Total requiment for 3 WBS element is 140.
    When I run MRP for PS by tcode MD51, the system generate 3 PR for material ABC particular for each of OrdRes.
    1. I think that the system will generate 3 transfer posting for each of OrdRes, doesn't is? That is the first system.
    2. The system will generate one PR (quantity 40) to cover 3 OrdRes based on current stock (quantity 100), doesn't is? That is the second question.
    3. Are there any distribution key to distribute auto from general stock to project stock? And when I run MRP by MD51, the system will generate PR with quantity exactly for each OrdRes, doesn't is?
    Thanks all
    Regards,
    Hoai Vu

    Hi Mario
    I have checked by assign "2" in field individual/collect on tab MRP4. When I have assigned this material to activity in project and release. in MD04, I can't see Order Reservation be assigned in project stock. So, when I run MD51 for project, the system does not generate planned order for this material while I want run MRP for WBS element
    Besides, if field individual/collect on tab MRP4 not be assigned "2", the order reservation will be appear follow project stock in MD04. And when I run MD51, the system will not check stock in general stock.
    I wonder why SAP does not support for me to run MRP for each WBS element and generate planned order base on check general stock and project stock at the same time?
    Can you aupport me to solve this case
    Thanks and regards
    Hoai Vu

  • Manual reservation for Project Stock / wbs element

    Dear Gueus,
    In Project base Industry,
    For Production order confirmation I want to transfer Project stock of raw Materials from Main Storage stock  to Production WIP stock,  from this WIP Stock,  I will consume raw mtl at the time of Order confirmation.
    Now at the time of Manual Reservation in MB21 system is not allowing  311 Q  Mvt type  for Project stock reservation.
    Is there any other procedure / t- code to reserve project stock.
    Pl guide me for the same.
    Thanks
    Umesh

    Hi,
    A word of caution, before processing any mass transactions such as COHV etc, its always better to double check the data. Reason is because the program performs mass update & any reversal would be a time consuming process.
    Now for mass confirmations of orders via COHV
    1. Execute COHV, in the first screen, select Order Headers, specify the order numbers in the field. If you have saved the list as a text file, then click on multiple selection & click the green icon at the bottom right corner, specify the file & the orders will be read.
    2. In the tab - Mass Processing, select confirmation for the field Function & if you want to execute immediately, then select the same in execute function. Depending on your rqmt, you can have the log & also output the logs.
    3. Click execute or F8, then select all the orders & then click on the mass processing drop down icon & click execute. The processing begins in foreground. Once the processing is done, system puts out a log showing the once which were confirmed & the once which were not able to be processed & the reason for the same. (For background processing, select the same in mass processing tab in the selection screen).
    Please note, for order confirmation to take place the status has to be REL, also if any user status is active, check if the same allows confirmation.
    I would strongly suggest, first try in your sandbox server & once you're familiar with its processing, then proceed to use in production system.
    Hope the above helps.
    Regards,
    Vivek

  • How to determine process template for existing team project ?

    Hello,
    I have existing team project ( TFS 2013 ) but I don't have information about which process template have been used.
    Is there any way to figure out which process template has been configured in existing team project ?
    Thank you in advance !
    Kind Regards,
    Dipti Chhatrapati

    You could also check the Process Template version If you have integrated TFS with SharePoint 
    Here are the steps:
    Team Explorer->Click on Documents -> Expand Process Guidance ->Click on ProcessGuidance.aspx 
    Based on the process template you have used, it will redirect you the guidance page.
    Example: You are being redirected to the guidance for the following process template: Microsoft Visual Studio Scrum 2013.4... (Here i have created a new project on TFS13.4 server with Scrum template)
    Thanks, BHSR

  • User exit for CJ20n (to check budget when create Reservation) for project

    Dear All,
    Plz advice, is there any user exit for CJ20n(project builder) in order to check available budget when we create reservation under a network/activity for a project?
    Many thanks in advance.

    Hi,
    Budget functionality is available against actual / commitment items, but n't against reservation of materials as there cane be reservation at projects or plant level. Morever there is no such user exit in CJ20N.
    If you can make developments of reservation agsinst network as committments items then budget functionality may work in that case.
    Hope this will help you.
    Regards,
    Rakesh Pradhan

  • Production Order For Project with plant stock

    Hi,
    We have a scenario where in we are required to create a production order for a project.
    But the material(raw material) is in a storage location and is a stock item. Even the header material is also a stock item and it to stored in the storage location.
    But the order is to be created for Project and to be settled to the Project. Now the system is not allowing me to create the order.
    The error is :
    "Project  does not allow make-to-order stock
    Message no. CO746
    Diagnosis
    There is no project stock for the project.
    To create a production order with reference to a WBS element the project must allow project stock to be maintained.
    Procedure
    You should select a project that allows project stock."
    Now,
    I don't want to have a project stock. How to go forward...
    Regards
    Pavan

    Hi,
    What is the strategy you are using. If you are using strategy 20, then chnage it to 40.
    Also maintain individual/collective indicator to "1" - individual in MRP-4 view. So that when the order is created, the stock will be reserved as Q-project stock.
    thanks and regards
    Murugesan

  • Cannot import other existing imovie projects

    I believe iMovie 5 is suppose to be able to import other existing iMovie projects. When I attempt this through the import function on another iMovie 5 project (in this case a single clip smaller than 600mb) it say "Error:Quicktime cannot parse clip" it says a little more than this actually but this is the part that seems to have any relevance.
    It does this with bigger or smaller clips. I am running Quicktime 7 and have all the updates in place
    .Anyone have any ideas.
    G4dualproc   Mac OS X (10.3.9)  

    If I read you correctly, you tried to import another iMovie HD project directly into a second project. You selected a project icon to import, correct?
    iMovie HD can't do that, although the programmers forgot to tell iMovie HD. When we try, we get a "cannot parse" error. (The import dialog shouldn't allow us to select an iMovie HD project to import. It's a bug.)
    There are other ways to do the same thing:
    1) Do a Save As to copy Project A to a new Project B. That duplicates the entire project.
    2) If you have an existing project you want to import clips to, you can Copy and Paste the clips from Project A to Project B. With Project A running, select all the clips, Copy, open Project B, Paste. Repeat for the audio clips.
    Note that when Copying and Pasting try to copy all the clips you want together. If you don't, then any clips you copy and paste separately which share the same source file will cause iMovie HD to deliver TWO copies of the source file to Project B. That can hugely increase the size of Project B.
    That occurs because Copy/Paste preserves the non-destructive editing of the clips. The Pasted clips behave just like the clips in Project A. A split clip can be restored to its original length, for example.
    Karl

  • 'No detailed information exists for this person'  while adding new reviewer

    Hi All,
    <b>This is an extremely urgent issue.</b>
    We are getting the following message in SRM while adding a new approver to the Shopping cart once the - 'No detailed information exists for this person'
    <b>We have implemented the following OSS Notes in the SRM 5.5 system, Release 700 after rasing a call with SAP.
    SAP Pilot OSS note - 1002957
    Other OSS Notes -
    999528 Adding Ad Hoc Approver fails due to comit erro...
    722357 Ad hoc: Commit control with ad hoc enhancement...
    990467 Commit Problem with AdHoc Agents...
    984582 Problems with Posting Container Data (ad Hoc
                            agent...
    947296 Inserted/changed approver is not transferred...
    910925 SRM Workflow: Ad-hoc agent not found...
    803628 BADI workflow: You cannot add an approver</b>
    Here are the details
                          <b>Cannot add additional approver</b>
                            We are now on SRM 5.5 and a document attached shows the
                            patch levels
                            from SPAM.
                            In shop transaction, it is possible to change the
                            default approvers,
                            but not possible to Add.
                            When we add, the system shows the list of available
                            approvers, allows
                            selection, but "transfer" button does not actually
                            transfer.
                            When the cart is saved, the added approval shows as "no
                            approval
                            available".
                            We are using the standard workflows for 2 step approval.
                            A document is attached to show what happens and the
                            results of checks
                            we have performed.
                            BUS2121 also shows as ok when checked.
    Any pointers what could be possible reasons.
    <b>Points for sure. !!</b>
    Regards
    - Atul

    Hi Atul,
    Here is the list.
          |-----     0000702787 EBP 4.0: Message "Enter a country"
          |-----     0000732828 E-mail messages for work items with incorrect line break
          |-----     0000735026 Memory problems at BBP_GETLIST_INDEX_FILL
          |-----     0000804317 SRM40/SUS/PO: PO inbound with error BBP_PD 147
          |-----     0000862851 PO not ordered due to different locations error
          |-----     0000902956 Changing Account assignment category BE Limit service PO
          |-----     0000911446 No reservation is created
          |-----     0000917869 SRM 5.0: PPOMV_BBP - Vendor address tab page
          |-----     0000919553 SRM 5.0: Termination of output preview for invalid partner
          |-----     0000920363 Shopping cart transfer: Sourcing indicator is not set
          |-----     0000924218 SRM 5.0: wrong error message for non existant auth. PurchOrg
          |-----     0000924811 SRM5.0: Javascript error on document screen
          |-----     0000926750 Shopping cart: Unit of measure is not restored
          |-----     0000926878 Link for expanding details in the shopping cart too small
          |-----     0000927142 SRM5.0: Browser hangs up during attachment upload
          |-----     0000938168 SRM50: Message "No default value from vendor master"
          |-----     0000938296 JavaScript runtime error in the bid invitation
          |-----     0000940805 BBPS_SC_APP_SOS cannot be enhanced
          |-----     0000941935 External requirements displayed as a reference
          |-----     0000942742 Update is cancelled if new source of supply is found
          |-----     0000944592 No location when vendor has changed
          |-----     0000944918 ECS: Find back end purchasing group as a responsible group
          |-----     0000945601 Termination when you display purchase order item detail
          |-----     0000948425 Shopping basket changeable although already approved
          |-----     0000953238 Shopping cart history in the sourcing cockpit
          |-----     0000954066 Follow-On Documents Tab does not get Highlighted
          |-----     0000954409 Error message during approval of a confirmation
          |-----     0000955377 Long runtimes for workflows with blocks
          |-----     0000956108 Empty worklist after clicking button 'Find'
          |-----     0000956723 BBPMAININT:Bus. partner display switches to maintenance mode
          |-----     0000956797 RUSRM50: Limit Purchase Order Functional Area Error Message
          |-----     0000957884 Category Management: Data disappears after program SAVE
          |-----     0000958045 BBPSC04: Delete icon not hidden despite screen variant
          |-----     0000958349 Final delivery with quantity 0
          |-----     0000959528 During PO creation wrong error message BBP_PD 428
          |-----     0000960169 Favorites not saved for 'Purchase for'
          |-----     0000961422 BBP_MON_SC: No search help for 'Created By'
          |-----     0000962093 BBP_VENDOR_CREATE: Refresh BP data
          |-----     0000962252 BBP_GETLIST_INDEX_FILL: Incorrect processing statistics
          |-----     0000962474 Error after changing partner data
          |-----     0000964132 Approval Preview for Rejected Items: Wrong User's Inbox
          |-----     0000964361 Cannot find employee of vendor
          |-----     0000964455 Country for the PO box is initial
          |-----     0000964911 Kopieren von Alertkategorien: Containerelemente verschwinden
          |-----     0000966072 Download of material fails - set type COMM_PR_UNIT
          |-----     0000966323 Service Item: Not able to create PO in ERP backend
          |-----     0000967429 Approval buttons not updated after release
          |-----     0000967615 Performance of BBP_PD_PO_GETDETAIL may be poor
          |-----     0000968110 Transfer canceled, account assignment acc. to value/quantity
          |-----     0000968251 BBPSC02:In source of supply preferred vendor not validated
          |-----     0000969091 SRM does not support passwords longer than 8 characters
          |-----     0000982293 Ext requirements: Purchasing group data not transferred
          |-----     0000982448 Impossibility to delete an item in PO
          |-----     0000982674 Change PO quantity does not update account assign quantity
          |-----     0000983130 Search for back-end purchase orders using the requester name
          |-----     0000984184 BADI BBP_ALERTING active but its implementation isn't called
          |-----     0000985179 Delete button active for backend service entry sheets
          |-----     0000990264 Multiple confirmations cannot be posted for service & limit
          |-----     0000996104 No catalog when confirming back-end blanket purchase orders
          |-----     0001003408 BBPCF: Cannot Add Catalog Item to Confirmation for Limit PO
         0001010791 Flag Confirmation based Invoice Verification set erroneous
    Kind regards,
    Yann

  • Sale Order MRP Run for All Order Line Items

    Greetings...
                     I have One Sales Order , in which i have ten different Line Items .
    Now I have to Run the MRP on basis of Created sales Order so that all Line items wi get consider insingle MRP Run on sales order base MRP Run.
    How to take MRP Run of One Sale Order for all Line Items.???
    In MD50 , we can have sales Order with Item..

    In MD50 you can give only one item at a time.
    Its a standard transaction meant to accomodate changes relevant for MRP after plant level MRP run  related to specific sales order Item.
    so either you need to do it multipal times by changing material or you need to go for MD02.
    Please explain bussiness case in detail why you want to restrict your MRP run for items in a specific sales order.
    Regards

  • Can I copy iPhotos from an existing iMovie Project to a new one?

    Hi---I have iPhotos in an existing iMovie project (currently iMovie 11 version). For some reason, I cant seem to find them in my iPhoto library. But I want to use those photos in a new iMovie 11 project. I can highlight the photos and it allows me to click "Copy", but when I go to my new project to hit paste, they just don't show up. What am I doing wrong? Thanks in advance for any help you can give me. I really want to use these photos in my new project, but can't seem to figure out how to use them again. Thanks, Todd

    Hi Todd,
    It appears that your photos have been converted to video - hence the DV file extension. There are 3 things I can think of that may help.
    Firstly, play the movie project full screen. Use the slider to locate the first image you want. While paused in that position, use the key combination Command>Shift>4 - a cross hair cursor will appear. Click and drag this diagonally across the image - as you release the mouse button (or track pad) the image will be saved to your Desktop.
    The second option (and probably better) is to use MPEG Streamclip to extract stills from the video. It's available as a free download from the developer here:
    http://www.squared5.com/svideo/mpeg-streamclip-mac.html
    Drag the the first video clip containing the still you want onto MPEG Streamclip's interface. Navigate to the exact frame, then from the menu select File>Export Frame - you can choose between JPEG, TIFF and PNG.
    Another option is to duplicate the iMovie project then delete everything but the images you want from the duplicate. Rename the duplicate and use that as your starting point for your new project. To duplicate, while in Project Library view (not Edit view), click on the project then select File>Duplicate Project from the menu.
    John

  • Help error on activation  -       No active nametab exists for SY

    In ABAP web dynpro I create a SERVICE CALL. Everything looks ok, but when I activate this project,
    it displays an error message as the following:
    Web Dynpro Comp. / Intf. ZW_Test_BAPI, Web Dynpro Component Controller
    No active nametab exists for SY
    When I click on the error message, it brings my cursor to the import value of the component controller context.
    What is going on here? Can someone help me?
    Thanks

    Changed the type to something other than SY-datum

  • No active nametab exists for SY

    Hi,
    I have created a BAPI and it has IMPORT and EXPORT values. I have checked the REMOTE-ENABLED MUDULE redio buttoms.
    This bapi works perfectly well for Java Web Dynpro.
    I now create a ABAP web dynpro and create a SERVICE CALL. Everything looks ok, but when I activate this project,
    it displays an error message as the following:
    Web Dynpro Comp. / Intf. ZW_Test_BAPI, Web Dynpro Component Controller
    No active nametab exists for SY
    When I click on the error message, it brings my cursor to the import value of the component controller context.
    What is going on here? Can someone help me?
    Thanks
    AS

    Hi Anna,
    I got the same problem with a customer of mine. I'm looking for a solution but I am unable to find anything at this moment.
    I thought that regenerating objects from SGEN transaction would solve this problem. Also, I've checked inactive object in SE80 transaction but nothing yet.
    Could you please tell me how did you solve this?
    Thanks in advance,
    Tomás Vírseda

  • SE 518 No account assignment exists for service li ne 0000000000 error

    Hello all,
    We have raised a Shopping cart for a service with reference to a contract with the account assignments item category "D" and account assignment category "P". the product type is 02 for the service. The shopping cart saves fine however when trying to transfer to create the PO in the backend we are getting the error "SE 518 No account assignment exists for service li ne 0000000000"
    we have checked all the notes below:
    1064139 already implemented.
    1222877 already implemented.
    767284 failed to correct the error.
    1140132 should be in our system but has been removed by note 1226132. I have checked all the other notes but they do not seem relevant in our scenario. Does anybody have any idea as to how we should solve this problem?
    Thanks

    Hi Andrew!
    There are other notes related to this issue. Please verify if they can help you.
    1244427    SE518 error in external requirement service shoppin
    1236355    BAPI_PO_CREATE1:Purchase Order created with ref. to
    1226132    SE518 Error message from back-end system for servic
    1030206    BAPI: Multiple service type items cannot be created
    1398742    Error message SE 518 PO transfer to backend
    Best regards,
    Christian Zeuch

  • No tax item exists for tax code O0 in a G/L account item.

    while posting the credit memo  for sales return accounting document is not created. its shows the error as No tax item exists for tax code O0 in a G/L account item.
    plz help me in solving the issue

    Dear Venkatesh,
                  1.First check that material wether that is relevent for taxes or not.
    Check wether Tax indicator set or not in the material master Sales org data1 or 2
    2.Check condition record exists for that material or not
    3.Then check the Tax code and G/L account assignment in the transaction FTXP
    I hope it will help you,
    Regards
    Murali.
    Edited by: Murali Mohan.T on Feb 13, 2008 10:42 AM

Maybe you are looking for

  • Bapi to  create customer Master

    Dear all, As far i know there is no standard bapi to create a customer.  There i s standard fm used her is SD_CUSTOMER_MAINTAIN_ALL. I tried to create customer master using this and making the function module as remote enabled. i tried to created a 

  • Windows 7 Clean Install Elements 7 Install

    I am going to upgrade Windows Vista to Windows 7 with a clean install. I will have a backup of my hard drive. After I do the clean install of Windows 7 and install Elements 7 how do I get Elements 7 back to the way it was in Vista. I am particularly

  • Adobe 9.2 won't open pdf file in Firefox 3.5.3.

    No error message, just blank screen. Adobe plug-in is Enabled in Firefox, and Adobe Reader Internet preferences set to display pdf in browser.  Adobe 9.2 does open in IE 8.  I did not have any issues in Firefox until the Adobe upgrade, so I don't bel

  • ORACLE RAC HOTBACKUP?

    oracle rac 환경에서 hotbackup 시에 정보를 구하고 있습니다. 싱글 모드에서는 begin backup 하고 !cp 하고 end backup 진행하면 되는데 rac 환경에서는 어떤 방식인지(dd??사용법) 어떤 것을 백업을 받아야 되는지 알고 싶어요

  • Pop Up Input Screen

    Hi Experts,    I have this requirement:      Scenario: I have one table control, with two radio buttons say R1 and R2.                     a) When R2 is selected, a button outside the table control should get activated.                     b) On Clic