Picking not done for a serialized material using Idoc type SHPCON/DELVRY03

Hi All,
I am using Idoc of type SHPCON/DELVRY03 to do the picking for an outbound delivery.
The value 'PIC' is populated in the qualifier of segment E1EDL18 . In order to update the batch number of the material in a delivery the qualifier of segment E1EDL19 is populated with value 'BAS' .
To update the serial numbers for a serialized material in an outbound deliverfy , BDC for transaction vl02n is used. Also the segment E1EDL24 is populated with material no. POSNR and other details , then segment E1EDL11 is having the value of serial no.  Similarly for other serial number there is one more segement E1EDL24 with same material no. but  E1EDL11 with other serial number.
The issue is that after the Idoc is successfully processed , picking quantity is updated only for one serial number for a serialized material of the outbound delivery. The picking quantity for other serial number is not updated . Initially the delivered quantity for the serialized material was 2  but after processing the Idoc the picking qunatity updated is 1 ( for one serial number only ).
Please provide any pointers on this.
Thanks & Regards,
Tanushri.

The firs thing I would do is verify the config.  Make sure the message type of the created IDocs matches the message type to which the filter is applied in the distribution model.  If everything looks ok, place break-points at the following locations:
In FM MASTER_IDOC_DISTRIBUTE, on the call PERFORM DIST_MODEL_READ_FOR_MESTYP.  This subroutine reads the filters from the distribution model.  Verify the values in internal table RECEIVERS_AND_FILTERS are correct.
In FM MASTER_IDOC_DISTRIBUTE, in FORM IDOC_SELECTION_AND_SERVICES, on the call to FM IDOC_DATA_APPLY_FILTER_VALUES.  This function should return the filtered results.  IDOC_DATA contains the data segments of your IDoc and CONDITION_BLOCKS contains the filter.
When you run BD21, you should hit these break-points.

Similar Messages

  • Packing Serialized material using packing Station(HUPAST)

    We are not able to pack serialized material to HU using packing station.
    We are getting error
    " Message no. IO 304  "
    Packing station does not seem to have option to pack new serial numbers for Inventory managed HU compared to Delivery related  HU.
    I could not find related note on SAP.
    In case anybody has any solution or recommendation,  Response would be highly appreciated.
    -Deepak-

    Hello,
    if you have many sales order that must be delivered in the same handling unit "Palette", you need to create one Outbound delivery against these  sales orders.
    so
    manys sales orders==> One outbound delivery===> One handling unit
    It seems logic for me
    best regards

  • Depot Sales - Goods issue not done for the delivery

    Hello Experts,
    I am trying to capture a Excise Invoice in the Depot Sales Process TCode - J1IJ.
    I am getting the follwoing message - GI not done for the Delivery.
    Process which we are following here is
    Depot
    SO - Delivery - Picking - Packing - J1IJ - Shipment creation - Shipment Planning - Loading Start - Shipment Start (Will do PGI) - Shipment end (Will create invoice & Excise Invoice).
    Excise invoice is captured during MIGO at Depot.
    Can you please suggest..
    Thanks & regards
    Mahesh

    Hi mahesh
    Change the process to following manner
    Depot
    SO - Delivery - Picking - Packing - Shipment creation - Shipment Planning - Loading Start - Shipment Start (Will do PGI) - Shipment end -J1IJ(Will create invoice & Excise Invoice).
    u r problem will be solved.
    Regards
    kedasu.a

  • Error in posting Inventory documents for a serialized material

    hi.,
    Can someone update me the reason for:
    1. Error in posting inventory documents for a serialized material
    What are the steps to be followed during the
    1. Creation of Serialized material
    2. Creating a Purchase document for a serialized material
    3. Generating a G/R for a serialized material.
    4. Generating an inventory document for a serialized material.
    Any update is much appreciated.
    Tx.
    Mahesh

    Hello Mahesh,
    Let me try to answer your queries.
    <b>1. Generally, how does the flow of Cycle counting go w.r.t to the Indicators A.B.C and D which has been configured in OMCO.
    Would that be as per the Consumption/usage of the materials?</b>
    The following link will help to understand the cycle count process
    http://help.sap.com/saphelp_46c/helpdata/en/4d/2b8e3d43ad11d189410000e829fbbd/frameset.htm
    <b>2. How are the indicators of A,B,C,D to be set up for the other materials in the particular plant which have not been fixed as CC.</b>
    If you run the MIBC (Set ABC indicator) report, it will automatically set the ABC indicator based on your selection parameter.
    <b>3. How does the system take up the inventory count for materials that have not been flagged as CC Fixed.</b>
    Cycle counting inventory will be carried out only for the material with ABC indicator for cycle count, if you exclude the material from MIBC report or manual ABC setting then that material will not be considered under cycle count when you execute MICN report to create cycle count inventory doc.
    <b>4. How does the sytem take up the inventory count for materials for materials which have been flagged as Fixed.</b>
    Material with CC fix indicator means when MIBC report will not change CC indicator for that material with fix indicator, so when you run MICN report at that time system will take last inventory date from MARD table for that material and calculate the next due date based on ABC indicator in material.
    Hope this helps.
    Regards
    Arif Mansuri
    Frankly speaking I also dont know the process for rewarding the points, I put only one question so far but with no reply, so never got a chance to assign rewards.
    But there is a way always, this link will help you..
    https://www.sdn.sap.com/irj/sdn/crphelp#posted

  • Changing Valuation Type for Non Serialized Material

    Dear Experts,
    May i know how to change the valuation type for Non serialized Material.
    Scnerio :
    Issued New  Material from warehouse with Valuation type -C1,
    Once i used shop floor it damaged and now i want to return back to store with Valuation type C3.
    May i know how can i do this.
    Regards,
    Kavvya

    Hi Seenu,
    Actually when i am using t-code IE4N and changing the valuation type C1 to C3 without changing the valuation type the system return the material to store. But for serialized material first i changed the valuation type through IQ02 then i am using the IE4N.
    But  i dont know how can i cahnge the valuation type for Non serialized material.
    Also may i know why i am facing problem in IE4N, Is it required some configuration to directing changing the valuation type in IE4N itself.
    Kavvya

  • My iphone 4 does not ring for messages when i use the handsfree..

    my iphone 4 does not ring for messages when i use the handsfree..

    iPhone supports A2DP audio streaming. If you have it paired to a handsfree kit that supports this, for example, an in car audio system, and are currently tuned to a source other than the phone, the phone will send the audio for things like text message alerts to the handsfree system, but you will not hear them. This is just the nature of the beast. If you do not intend to use audio streaming from the phone, you may be able to disable this in the in car system. This should not affect Bluetooth calling. There is no option to disable this on the phone itself.

  • Upload material using idoc in lsmw

    hi ,
    i m trying to upload material using idoc inbound processing in lsmw. but whnever i m giving partner name as lsmw & port name as lsmw (even i tried with different name also ).  it gives error like port does not exits.
    regards,
    swapnil

    Hi ,
    Please foloow Link:[Check|http://****************/Tutorials/LSMW/IDocMethod/IDocMethod1.htm]
    Regrads
    Jana

  • Check Connection of Communication Arrangement for SAP ERP Financials Using IDoc Failed

    Dear experts,
    We are checking outbound connection from C4TE to ERP in Communication Arrangement for SAP ERP Financials Using IDoc Failed.
    We get the attached error message:
    Checking connection failed
    Error accessing service; Service Ping ERROR: Forbidden (403)
    What could be the reasons, in ERP side, through Tcode SMICM, we didn't see any log from C4TE side, and we cannot ping the ERP side successfully.
    One more thing, in C4TE, we tried to set the connection to an SAP internal ERP system, and the connection was successful. But when relinked to the customer ERP system, connection failed.
    Could it be firewalls reason?
    Thanks!
    Best regards,
    Wendy

    Hi Wendy,
    Yes the assumption could be one reason as well for the error (403 forbidden), but there could be several other aspects also to get the 403 error, for better understanding the reason for the error,  may I request you to create an incident send it to us.
    Also please try once running the scenario in C4T and check if the relevant documents are being sent through Outbound Service or not.
    Thanks & Regards,
    Bharath

  • Posting goods issue using Message type SHPCON and idoc type DELVRY03

    Hi SAP Gurus,
    I am using message type SHPCON and idoc type DELVRY01 with processing code DELV to post goods issue for a delivery note.
    I tried to simulate the inbound entry via WE19. The scenario should be posting goods issue based on the delivery order.
    In some cases, quantity issued is less than the quantity in the DO. For this, I need to change the delv quantity in the DO via VL02N before I select Post goods issue button. This will change at the same time post the goods issue.
    What I have filled up are the fields:
    E1EDL20-VBELN = DO num
    E1EDL20-VSTEL = Plant
    E1EDL18-QUALF = "PGI"
    E1EDTH13-QUALF = "006"
    E1EDTH13-NTANF = date today
    E1EDL24-POSNR = 000010
    E1EDL24-MATNR = material num
    E1EDL24-WERKS = delv plant
    E1EDL24-LGORT = sloc
    E1EDL24-LFIMG = updated quantity
    But everytime I simulate using WE19, the entire quantity in the DO is not changed at all. The goods issue quantity posted is still the original DO quantity.
    May I know how to do this? Thanks.

    Put value in E1EDL24-LGMNG for qty to pgi.

  • ERROR IN CREATING SALES ORDER,USING IDOC TYPE ORDERS05

    I am using exit to write my code for creating sales order of IDOC Type ORDERS05 and order type ZDRX.
    IF I proceess the Idoc in background each time error message comes
    FIELD kuwev-kunnr(ship to party)is not an input field.
    but if i run in foreground in debugging mode,sales order is getting created..
    please suggest something.

    If thats not working..
    try BAPI_SALESORDER_CREATEFROMDAT2
    If BAPI is not working. try creating a bdc for the same if there's not error on trying from VA01

  • PO Delivery date change using IDOC type "PORDCR101"

    Hi All,
    I am trying to create a PO using idoc type "PORDCR101". Everything is fine, PO is getting created. But the problem is that, even if I pass delivery date at item level system is automatically changing delivery date to future date (some of the PO's have delivery date in past and they need to be created as it is).
    I am populating all the required fields (PO_ITEM, SCHED_LINE, DEL_DATCAT_EXT, DELIVERY_DATE, QUANTITY, STAT_DATE) in both the segements "E1BPMEPOSCHEDULE" and "E1BPMEPOSCHEDULEX" (in this segement with X). It's updating the quantity exactly with what I am passing, but it's not considering delivery date. But when I am creating PO manually using ME21N I am able to set delivery date to past date.
    E1BPMEPOSCHEDULE
    PO_ITEM=20
    SCHED_LINE=0001
    DEL_DATCAT_EXT=1
    DELIVERY_DATE=20060509
    QUANTITY=101584
    STAT_DATE=20060509
    E1BPMEPOSCHEDULEX
    PO_ITEM=20
    SCHED_LINE=0001
    PO_ITEMX     =X
    SCHED_LINEX=X
    DEL_DATCAT_EXT=X
    DELIVERY_DATE=X
    QUANTITY=X
    The funny part is IDOC is not even thowing a warning message for this...
    Any idea what I am missing???
    Thanks for your time.
    Paul
    null

    Ok, I got the answer. For delivery date category (DEL_DATCAT_EXT) we should not be passing 1, but we have to convert it into 'D' (And relevant format for others).

  • Seeburger help required for 810 and Dispatch Advice (IDOC type DESADV).

    Hi All,
    1. Please let me know blogs which clearly shows settings for Seeburger components for 850 (Purchase Order) to IDOC Scenario
    --- Seeburger Workbench
    --- Seeburger Mapping Designer (BIC)
    --- Seeburger Counter and Varaibles
    --- Seeburger AS2 Spoke
    --- Any other Seeburger Component setting required
    I have understand blog for 850 -- /people/rajeshkumar.pasupula/blog/2009/08/05/wanna-implement-seeburger-for-edi-find-the-booster
    2. Anybody has blog for 810 or Dispatch Advice (IDOC type DESADV).
    3. Can anybody provide me Mapping Logic (at field level) done in XI/PI for 850, 810 , Dispatch Advice (IDOC type DESADV) .
    Regards

    Hi Rickkk,
    1. Please let me know blogs which clearly shows settings for Seeburger components for 850 (Purchase Order) to IDOC Scenario
    --- Seeburger Workbench
    --- Seeburger Mapping Designer (BIC)
    --- Seeburger Counter and Varaibles
    --- Seeburger AS2 Spoke
    --- Any other Seeburger Component setting required
    For SEEBURGER workbench please go through this blog and navigate the enbebbed links furthur to know about Seeburger workbench too.
    /people/prateek.srivastava3/blog/2009/08/01/seeburger--part-1--the-basics
    2
    2. Anybody has blog for 810 or Dispatch Advice (IDOC type DESADV).
    For 810 i think the procedure would be the same but themseeburger mapping program that validates the ANSX 810 would be different.As far as 997is concerned 997 is a functional acknowledgement.Its a genric format that is used to send acknowledgement for any EDI transaction set that has been sent.
    3. Can anybody provide me Mapping Logic (at field level) done in XI/PI for 850, 810 , Dispatch Advice (IDOC type DESADV) .
      The logic will be based on the trading partner guidelines which will contain the description of all the semantic and syntactiic description about the segments ,its feilds.we need to consider the guidelines and target side specifications too while mapping.
    Thanks,
    Ram.

  • Valid size not available for this creation when using Greeting Card feature

    Using PSE9 with a Mac.  When attempting to create a greeting card, after selecting the photo, the Greeting Card, I receive a pop up error message as follows:
    "Valid Size Not Available For This Creation".  (All other Create functions such as Photo Book, Photo Calendar, and Photo Collage appear to be working).  I have been in contact with Adobe Support and have been instructed to do a number of things from creating a new preferences file to uninstalling and re-installing the PSE software, with no result.  Has anyone else run into this problem, and if so have found a fix?  Thanks.

    I've been tearing my hair out over this one also. I've been on hold for over 10 hrs with Adobe Support waited over almost 2 weeks and still no resolution. I'm trying to create the Save the Date cards for my wedding and I can't wait for Adobe. Removing the preferences file and uninstalling/reinstalling does not fix the problem.
    That said I did figure out a workaround for this. It's easy but it does require Windows. For me this was no big deal as I do own a Windows box.
    Get the free trial version of PE9 for Windows and install it. If you don't have a Windows computer get to a friend that has one
    Upload some of your photos to the PE9 Windows Organizer (it's identical to the mac version)
    Select Create and then Greeting card. Photoshop will launch the guided edit feature for greeting cards.
    Select the Layout feature and once you find out that you like save it as Photoshop project. Repeat this step for as many layouts as necessary.
    Copy your Photoshop project files (and any folders) to your mac.
    Open the project files as you would with any other Photoshop file.
    You can now select the Create feature. You will be able add your pictures and resize them, you will be able to add/remove text, you'll be able to change the backgound/borders, add graphics...pretty much anything...EXCEPT automatically modify the layout. If you click on Layout, PE9 returns nothing. You can however go into full edit mode and if you have decent Photoshop skills you can make any changes to the layout manually.
    If I had to put money on this I'd say that there is a problem with the PE9 Mac installation package. For some reason it is not deploying the layout data/files or it is not putting them in the right place. For this reason the program can't find the layouts when the user selects the greeting card guided edit.
    Good luck.

  • Assign Source of supply is not working for contract with material group

    Dear Experts,
    I have searched all the threads and gone through before posting my query. So i would ask moderators to go through the thread properly before rejecting this.
    We have value contracts with respect to a particular material group without material and with item category W in the contract item, Please note that for the materials with this material group, the source determination is not set and source list is also not maintained.
    When we create PR for the material with this contract, and when we click on assign source of supply contracts used to get popped up, but recently from few days, when we click on assign source of supply we are getting an error " no source found for this item ".
    Can anybody help on this.
    Regards

    @ Biju,
    As mentioned earlier, we are not creating PR with reference to contract.
    first we are creating contract with item category W (material group), without material and plant details.
    we create PR with or without material with account assignment K and with the material group in the transaction ME51N, and after inputting all the fields, we click on assign source of supply, it was proposing the existing contracts with respect to material group earlier, but it is not happening for particular material group(it is working for all other material groups)
    Hope it is clear.
    @ Dev Patra,
    we are using DIEN-Service material types and we assign that particular material group to only service material type.
    we have not ticked, source list in the material master, we donot have any source list for the materials under that material group.( please check the note 457110- question number 14.)
    Regards

  • Output type not created for outbound delivery while using SHMNT05 idoc type

    Hi Experts,
    Please help me to solve the below issue.
    Problem:- I want to to generate an IDOC(using type SHPMNT06) once the PGI is done for an outbound delivery.
    Already it is working fine when used DESADV.DESADV01 or DESADV.DELVRY07. But now the output type is not getting created when used SHMNT.SHPMNT06. I have created a separate output type ZPJ7 just as a mirror copy of the earlier output type(ZPJ6) used for DESADV.DELVRY07.
    Question:- Is it possible to use idoc SHPMNT06 instead for DESADV01 or DELVRY07? If yes then what are steps to be followed?
    The reason why SHPMNT06 idoc is planned:- We have a scenario to send outbound delivery to 3rd party system via XI. If the outbound delivery is for National(Not for Export) and PGI is completed then send the idoc straight forward to XI otherwise DO NOT generate the idoc, but just create the delivery. Collect all the deliveries in a transport and send it in a shipment. The shipment details can be sent using SHPMNT idoc. Now from XI perspective, if we can utlitze the same SHPMNT idoc for the National delivery(1st case) then perhaps this will require less effort. Hence shipment idoc is required to be generated when the delivery is created and PGI is done.
    Also it would be great if you can advice some better way to solve above mentioned scenario.
    Many Thanks,
    Sanjay

    There could be several reasons. Go to the document and in the extras-output check output determination analysis in the processing log.
    If the output has been created successfully then you need to see your printer determination. Ask basis to check it up. If the problem is that even the print preview is not coming. Check your communication in the output analysis and ensure LOCL is selected. Any other printer will need to be configured.
    If thats done already then check whether you have maintianed the condition record.
    If that too is done then check whether your output type has been assigned to the output procedure and that the output type is listed in the procedure.
    regds
    Jude