Raw mat and procured finish product cost

we need to run cost run for both raw material and product, we want have the following scenario:
first mark the raw mat. cost run,  then our finished product will get the future price of raw mat and base on BOM to update the future price of finished product.
after we mark finished product, we then release raw mat standard price and subsequently release finished product.
is any solution we can define  costing variant for above scenario?
we have another scenario, we need to run costing run for finished good A, but this product A 's BOM contain only one procured finished product B, B doesn't have BOM and purchase info record, how can we change product B 's price, so finally finished product A 's standard price will be updated upon costing run?

Hi ,
In Costing Variant .. we have a Tab for valuation variant . In the valuation variant type , we have seperate valuations for raw Materials , activities, subcontracting etc .
Cost Estimate with Quanity Structure will refer to the Costing Variant and compute costs .. Hence , maintain Costing Variant and Valuation Variant properly..
This will solve both your issues..
Kindly revert back for any further questions..
Regards
Sarada

Similar Messages

  • How to add depreciation and interest in product costing?

    how to add depreciation and interest in standard cost estimate and actual costing in product costing ?

    Hi,
    WHy the admin and sales overhead will be deited to cost of product. The cost of product should include only the factory related direct cost and overhead cost .. not the sales and admin ovehead. exp. for those treat them as period expense and pass on the same to COPa and there those can be analysed there..
    I hope i am clear..
    Regards
    Prabhat

  • I noticed that when I develop in light room 5 that the raw files are larger and the finished product is 80 percent smaller

    anybody have an idea why or is that the norm
    my raw file was 11,2 and my JPEG was 1.26

    The RAW files are the same size as the camera made them. Lightroom doesn't change the file size or image size.
    The JPG size depends on a dozen or so things, some of which you can control and some of which you cannot control, but almost always the JPG is smaller than the corresponding RAW.. I see no particular problem with a JPG that is smaller, depending on the export options you chose, and I have never yet seen Lightroom produce an incorrect size JPG
    By the way, normally numbers have units, you did not mention any units, so I really can't comment further without knowing the units for the numbers you show

  • Allocating Standard and Variances of Production Costs into CO-PA

    Hi Experts,
    I would like to ask you about the process of allocating eg. humal labour into CO-PA.
    Lets have an example:
    We have planned to spend 10 hours on some action. But actually we have spent 20 hours.
    When we allocate our time from some PC, we have to allocate actuals, that means 20 hours, which will come into CO-PA online.
    At the end of the period we run Production Order Settlement and find the variance.
    What will now happen do distinquish between the planned costs and variances?
    Thanks in advance for your answers!
    Kindly Regards,
    Radek

    Hi,
    I am not really sure about your question
    We have planned to spend 10 hours on some action. But actually we have spent 20 hours.
    When we allocate our time from some PC, we have to allocate actuals, that means 20 hours, which will come into CO-PA online.
    At the end of the period we run Production Order Settlement and find the variance
    The 20 hours will only flow to Production order and not to COPA online. 
    Whatever the difference between the planned actual vlaues in the cost centers, they will come a cost center variance report. It does not effect any where else.
    But if there are any balances left out (difference between the total cost collect to the cost centers and the cost obsorbed to production orders etc), this values need to be assessed to COPA using COPA Assessment cycles
    I hope i touched your question.
    Please do let me know if your question is different. If it is different, please rephrase your question
    best regards
    Surya

  • Raw Material V/S Finish Product

    Hi Experts,
    Bellow i am giving the my scenario, kindly check it
    I am creating 100 FG
    For that FG i issue 100kg Raw Material
    After Production i got 100Nos. FG
    But in KG i got only 80 Kg., Because 15 Kg. is Rejection And 5 Kg. is Process Loss.
    I have problem with process loss , where and how can i track this process loss .
    Thanks
    Utkarsh

    Dear Utkarsh,
    Because 15 Kg. is Rejection And 5 Kg. is Process Loss
    1) Can you let us know, in confirmation screen how ur giving rejection & process loss
    2) based on above experts can give some inputs
    3) more if ur going with rework, scrap or by-product process
    4) you can track in COOIS against Prd order
    Regards
    Madhu

  • Allocation of overhead cost to finished goods through vendors and raw mat.

    We are trying to allocate a cost base in our purchasing department of around 200 mio dkk to our finished products. These products we manufacture ourselves. The cost represents salaries and external services
    The outcome of an ABC study has been to allocate these costs, first on vendor level based on the total spent on each vendor and subsequently to the raw materials from each vendor based on value. The cost of purchasing should then be included in cost estimate of the raw material and hence in the cost of the finished goods through the bill of materials.
    Our challenge now is to implement this algorithm into our product costing system in SAP.
    The easy solution from the point of view of the SAP department is to have cost controllers doing the math of calculating the cost per material number in Excel and then allocate this rate through a costing sheet or a template.
    But this solution on the other hand leaves the users with an extra manual task which again leaves room for error and it reduces transparency.
    So has anyone tried implementing such a calculation scheme in product costing?

    Hi
    As far as I know, SAP does not support this... What you can do is
    1. Calculate this price outside the system and include this overhead in the Plan Price of raw material (Costing 2 View).. So, this gets included in raw mat price itself
    or
    2. if you want to see it as an overhead, you need to arrive at an overhead% which you may calculate as Amount of these Expenses / Total raw material cost and apply this % across
    Study the historic data of past 3-4 years to see if the % remains more or less stable
    br, Ajay M

  • Change in finished product inventories / cost components

    Hello,
    We are in the process of implementing SAP and couldn't get an answer to the following.
    Our understanding is that the production cost of each finished product is calculated by SAP based on cost components. After manufacturing, the finished products are transferred to the finished product inventory. The change in finished product inventory account (say 713000) is credited with the production cost of the product.
    Instead of having this single 713000 account impacted, we would like to have the change in finished product inventory broken down into several, say 713001 raw material component in finished product, 713002 labour cost component in finished product, 713003 subcontracting cost component etc. Can we get SAP to credit automatically each of these accounts based on the cost component (or group of cost components) information in the system ? How should we configure it ? (is there a link between the cost component or group of cost component and the account)
    Many thanks for your help
    Best regards

    Hi Vincent,
    In my understanding you are not clear with the requirement and therefore you are struggling with SAP. Please understand the following:
    1. The posting of GL accounts are determined by valuation class in material master. So if you want to post on different GLs please define those many valuation class in MM and assign the correct Valuation class to FG goods.
    2. When you confirm the production, SAP post the goods issue (i.e. material you define in BOM) by debiting the Material consumption account and credit  the invertory accounts. And also post the goods receipt posting by debiting the FG inventory account and credit the Factory output a/c.
    3. Here you have to convience your client that it is best pratice to have one inventory account for one material type, like RM inventory, SFG inventory and FG inventory. Normally we classify the consumption posting in different GLs like Material consumption, Labour consuption, Overhead utilization etc. and that you can define in your cost component structure by grouping the relevent GLs in given cost component items.
    4. You have to explain them how SAP works in product costing and how GL documents are posted. You have to also explain them the posting impact in P&L and BS.
    I will suggest that you should rediscuss the requirement and explain them the SAP way of valuation and posting. It is a big change management issue and as a CO consultant it is most challenging task.
    Thanks and all the best,
    Vivek

  • Average Costs of the Finished Products

    Hi,
    We are using the process order concept and we are calculating the costs of each FG seperately and our finished products are different kind of sizes and types.
    And the requirement here is that if we want to calculate the average cost of the two FG how we can do this ?
    For Example
    Product 1 is manufactured and the arrived cost is $ 30
    Porduct 2 is manufactured and the arrived cost is $ 10
    And if we use the ratios of 60 and 40 and we determine the avergae cost of (3060%+1040%)/100= $ 22
    And we adjust this $ 22 with Product cost of A and Product B.

    What is FG?

  • Standar cost and product cost collector not updating the new price

    Hi,
    Created Standard cost estimate for one FG product and runned the product cost collector. Based on that consumption delivery everthing is made. Later on the work center and activity type changed in routing. Now i am trying to run the standard cost with new activity price (due to work center change) for the current period, system is showing only the previous rate(previous period) and it is not updating the new price becuase of already we have created the product cost collector.
    Can any one give the suggestion for how to update the new price in standard cost as well as new price updation in product cost collector.
    govind.

    Hi
    1. If the original cost estimate was run in the current month - Then you cant re-release cost estimate unless you reverse it from CKR1
    If the cost estimate was of previous months - then you can definetely release it again
    2. In cost collector, you need to manually cost it again using the Preliminary costing feature... Your cost coll will then show 2 cost estimates i.e. One from Original date to current date-1, and 2nd from Current date to 31.12.9999
    br, Ajay M

  • All the raw materials for finished products

    Can anyone please help me how to find all the raw materials for a finished product. The desired result which i am expecting is same that we get through TCode CS15.
    Please help me to solve this issue.
    anyone who answers will be rewarded..
    thanx in advance

    Hi,
    Please note what you are talking is multi-level blow up & the logic given by me is for Single Level blow up. In any case you can modify the above mentioned logic as follows so that you will get the desired result.
    Once you get all the first child materials of a BOM i.e. 800024 then check in MAST if there is a BOM for this child material. IF you get sy-subrc = 4 in Select of MAST it means there is no BOM Present for this child material hence no need to take any action. However for child material 800120 you will get sy-subrc = 0 indicating that there is a BOM for this child material so write these child material in ANOTHER INTERNAL TABLE SAY 'X' & DO NOT WRITE THIS CHILD MATERIAL in your current internal table. Follow this procedure for all child materials of this BOM. Once your thru with all child materials. loop at internal table 'X' which contains all materials which are haveing a BOM so repeat the above mentioned procedure for all child materials of material from 'X" i.e. in your case 800120. Stop this process till internal table 'X' is empty. I hope this helps,
    Regards
    Raju Chitale
    Edited by: Raju Chitale on May 5, 2008 12:55 PM

  • Flow of product costing

    Hi All,
    Iam new to controlling area. I want to know the entire process flow of product costing and what are journal entries reflect in this flow.
    Thanks,
    chandu

    Hi,
    The requirement of batch wise capturing of costs can be achieved by creating a separate production order for each batch of production. The production order captures all the cost, which are incurred during the production process. The details of each cost are as below.
    1.For every batch of production a production order is raised in the production department. The production order contains the details of BOM and recipe.
    2.The Bill of Material (BOM) details the raw material and packing material in the required portions that are required for production.
    3.The recipe contains the detail process of production activity including resource such as manufacturing machineries, equipment. Each operation is assigned to its resource and each resource assigned to relevant activities such as Labour, fuel, power etc. (maximum of six parameters for each resource). Each resource is attached to a cost centre.
    4. The recipe and BOM are copied to production order automatically when the order is created. The quantities of materials and activities are determined at standard levels (Planned costs).
    5. A production order may contain several phases and each phase requires individual confirmation.
    6.Once a phase in production process is complete the production person gives his approval by the way of confirmation.
    7. At the time of giving confirmation he inputs the actual quantities incurred for material and activities. Using these inputs the Actual Cost can be arrived.
    8. From controlling module, the planned rates of activities are uploaded on periodical basis. monthly or annually. The cost of material is taken at Moving Average price.
    Once the batch production is complete the production person gives his final approval to the order as u201CTechnically completed (TECO)u201D.
    9. At the month end / period end all these process orders are settled at the costing department.
    10. The settlement results in calculating the overheads on predetermined rate and transferring the total cost of the production on to the finished product. The following entry is generated
          Finished goods stock Account    Dr
              To factory output Account       Cr.
    11.The work-in-process is calculated based on the status assigned to production order. If the order has a status of u201Cu201CTechnically completed (TECO)u201D. the work-in-process is not calculated, but the order will be totally settled.
    12.The standard cost of finished product is released at the beginning of every month. The standard cost is calculated based on the Bill of Material and recipe defined independently for each finished and semi finished product.
    13.The variance is calculated on the difference of standard cost of material and the actual cost incurred in the production.
    14. When the actual cost of power, fuel, Labour are accounted against respective cost centres in the month end, the system automatically determines the under absorption or over absorption of production costs. This difference cost will be apportioned to all the batches on a predetermined basis.
    Revaluation of Production orders
    Initially cost planned in cost centre accounting against activity types are used for valuating the materials that are produced. At the month end when actual cost are booked from financial accounting, revised activity price calculation is carried in cost centre accounting and with this prices the production orders are revalued. The revaluation is carried to the extent of difference between planned vs. actual activity prices. The revaluation production orders will not be carried, as production orders will be settled Immediately.
    The actual cost of every batch is determined using above process. A report is generated to know the cost for each batch.
    The standard cost fixed with each customer for each product is maintained in a separate database. The Costing department should compare these details with the actual cost of production and identify the difference. Accordingly a Debit/Credit note can be generated.
    Once a standard cost estimate is created, it updates the material master with that rate.
    Cost Object Controlling is an area in cost accounting that assigns the costs incurred in the production of company activities (such as internally manufactured materials) to those activities. Cost Object Controlling supports you in:
    Reaching make-or-buy decisions
    Determining price floors
    Performing complex cost analysis (such as target/actual analysis)
    Determining inventory values
    Cost component Structure:
    A control of how the results of activity price calculation or material costing are stored.
    In Product Cost Controlling (CO-PC), the cost component structure determines the attributes for passing on the following costs:
    Material costs passed on to material valuation as the standard price or inventory price
    Product cost components are
    Material
    Accessories
    Power
    Fuel
    Sal & wages
    Depreciation
    R&M/ Stores
    Others
    Admin OH
    Standard Cost Estimates (Applicable for trading activity)
    At the start of the fiscal year standard cost estimates will be released based on the planned raw material prices and planned manufacturing overheads. These standard prices are updated in the respective material master. These cost estimates are run only for make-to-stock materials.
    The various components of cost are incurred in producing a product is captured. The following cost components are considered for materials cost, consumables and fuel, direct
    Labour cost, utilities. Repairs and maintenance gases, depreciation, administrative overheads. A costing sheet will be created to capture administrative overheads cost which are not absorbed in the products as activity cost but are to be considered for inventory valuation In the first step planned activity outputs for each cost centre are planned, then planned cost that will be incurred against each activity type and primary cost element are planned, by carrying out activity price calculation the planned price of each activity is arrived. These activity types are entered in the work centers and routings. When cost estimates are created, system captures material cost from the prices mentioned in material master. The manufactured overheads are updated from the activity cost planned in cost center accounting.
    Sadashivan

  • Product Costs by Sales Order - Settlement Options?

    Hello All -
    I am trying to understand if I need to settle to a sales order (SDI) or directly to material (MAT) or to COPA (PSG).
    If i look at my sales order, it has item category ZPSF, which product costs by sales order configuration shows a requirement class ZKE.  ZkE has a valuation of M, which means separate valuation of reference to sales document/project.
    Does this mean I need to settle to sales order first?
    Then i run vA88 to settle sales order to copa?
    if ZKE valuation is blank, does that mean its not valuated?  I have read on other sap help pages that means it is valuated.  Please clarify.
    also, when does one directly settle to MAT? what scenarios?  this confuses me.
    Thanks!
    Emmas

    I'll give this a try. When working in a make-to-order environment there are 2 settings in the requirments class that you must consider in determining how to settle the costs (and maybe the revenue as well).  The first setting is the account assignment category.  In the standard system "E" is used to designate the sales order as a cost collector.  "M" is used to if you don't want the sales order to be a cost collector.  Whether the sales order is a cost collector or not will determine your settlement options. 
    The second critical field is the valuation setting.  If you set it to "M" then the stock assigned to the sales order will be valuated (by valuated I mean that once the goods are produced they will be held in inventory as sales order stock with a value).  If you leave the valuation field blank then the stock assigned to the sales order will be held in inventory without a valuation. 
    If the sales order is not a cost collector then the cost to manufacture the order will be collected in your production order and the settlement rule for the production order will be to the material you are producing.  Since the material has a valuation, the costs collected in the production will be reduced by the material's valuation once it is received into finished goods inventory.  Any remaining costs are settled to wip or variance based on the production order's status and the RA key and variance key settings.
    If you have set the sales order as a cost collector then the production order costs can either settle to the finished material or to the sales order.  If you are using valuated sales order stock you would normal have the costs settle to the material and the production order would behave very much like the previous example.  If you are not using valuated stock then you would need to settle the costs to the sales order and all the production costs would accumalte in the sales order.
    If you are using the sales order as a cost collector than you will probably want to settle the sales order as well.  During the sales order settlement you have the option of settling the cost and revenue assigned to the sales order to COPA.  The settlement profile along with the RA key assigned to the sales order controls how these are settled.

  • Valuated Sales Order stock for Semi-Finished Products

    Dear Gurus,
    One of my client faced the issue that the semi-finished products is valuated-sales order.  We are in Mill Industries, downstream (steel processing).  The situation is:
    1.  We use configuration material for both finished and semi-finished products. Both are valuated at standard costs with valuated sales order stock.
    2.  Once the sales order is created, the cost estimates are created for both Finished, and semi-finished products.
    3.  The production orders is created for the semi-finished products.  During production, several semi-fg and fg can be manufactured at the same time.   We are using the co-products feature to cover that.
    4.  During the goods receipt of semi-finished products, instead of using the standard costs in sales order cost estimate, it use the planned costs in production orders which against our design.
    I tried to use the user exit COPC002 and influence the standard costs.  But it seems that the routine is not called for semi-fg at all.  Anyone has any light on this?
    Regards,

    Hi
    I think you are talking about Special Stock "E"...ie) Sale Order Stock...
    If my understanding is correct then,
    If you go and see the Table T156....For the
    Movement Type: 101,
    Special stock Indicator : E,
    Qty. Updation Checked,
    Val. Updation Checked,
    Movement Indicator : Against PO,
    Consumption Indicator: Sales Order Stock.....combination....the transaction Event Key....GBB only has been Assigned....these  settings you cannot change...
    This linkage you can view in OLMW-----> Account Determination -
    > Acc. Determination W/O Wizard -
    >Account Grouping....also
    Reward if useful
    Regards
    S.Baskaran
    Edited by: baskaran srinivasan on Dec 20, 2007 12:18 PM

  • Product costing by sale order

    Dear all,
    Please tell me the process in product costing by sales order.
    In my client place, i have done the configuration but i dont know the process.
    Please guide me.
    Thanks & Regards,
    AR

    Hi,
    Product cost by sales order is useful when  a finished product is manufactured  for a specific customer rather than for the normal make-to-stock inventory. You can use the Product Cost by Sales Order component in the following situations:
    When you are manufacturing in-house with reference to a sales order in complex make-to-order production
    When you are purchasing customer-specific trading goods with reference to a sales order and reselling them to your customers
    When you are providing services whose costs are assigned to a sales order
    When you want to collect the sum of the actual costs incurred for the sales order item on the sales order item (standard cost of goods manufactured of sales plus variances) For detailed information, refer to the sections Valuated Sales Order Stock and Settlement in Product Cost by Order or Period.

  • Product costing by sale order(urgent)

    Dear all,
    1. Please tell me all the configuration steps to do product costing by sale order.
    2. Also please tell me how to test it after configuring.
    3. Please explain me the end user part also.
    I will award full points.
    Thanks & Regards,
    A.Anandarajan.

    Hi,
    Product cost by sales order is useful when  a finished product is manufactured  for a specific customer rather than for the normal make-to-stock inventory. You can use the Product Cost by Sales Order component in the following situations:
    When you are manufacturing in-house with reference to a sales order in complex make-to-order production
    When you are purchasing customer-specific trading goods with reference to a sales order and reselling them to your customers
    When you are providing services whose costs are assigned to a sales order
    When you want to collect the sum of the actual costs incurred for the sales order item on the sales order item (standard cost of goods manufactured of sales plus variances) For detailed information, refer to the sections Valuated Sales Order Stock and Settlement in Product Cost by Order or Period.

Maybe you are looking for

  • How to Disable the download a copy option of SharePoint Library Item .

    Hi I want to Disable the Download a copy sub menu for SharePoint Library Item. How would I accomplish that? Thanks...

  • Locked thread

    Hi, might i know why this thread User exit for T-code MIR7 has been locked? Best regards.

  • Service PO with Validity

    Hi, I am creating a Service PO with Document type :NB standard Item category service where can i enter the validity periods. [like for Document type : FO (Frame work Order) we wil get validity period from and to ].Please suggest me , i need to update

  • Want to convert a tag add target = "_blank"

    Hello My English ability is very poor sorry I want to <a href ="www.yahoo.co.kr"> => <a href ="www.yahoo.co.kr" target="_blank"> <a href ="www.yahoo.co.kr" target="_blank"> => <a href ="www.yahoo.co.kr" target="_blank"> (same) <a href ="www.yahoo.co.

  • Console Errors from Time Machine

    Time Machine starts normally, but soon gets stuck.   No progress backing up, and the time estimate steadily increases. The console logs repeat this message every 15 seconds: 5/29/12 11:13:20.000 PM kernel: /SourceCache/AppleFSCompression/AppleFSCompr