REM Planning table - Capacity requirements and Levelling.

Hi i have few queries in REM planning table.
In REM planning table MF50 my selection is based on entire plant. Here in total capacity data tab for any particular plant it will show the list of work centers which are maintained in particular plant to know the capacity details as per our requirement.
1.When i select any WC line and click on change capacity display from CRP it is giving break up with required and available capacity hours for any particular WC available time is assume 22.5 hrs per day which is given in operating time in capacity header in WC but in MF50 it is showing 23hrs.I have defined shift sequence in OP4A and assigned in capacity header grouping which have 3 shift with 30 mins break in each shift which results in 22.5 hrs working for a day so in shift sequence and operating time it is mentioned as 22.5 hrs is the time available for day but in MF50 it is showing 23 hrs available for day?
2.What is due% in MF50 total capacity data for any work center and how required time would be calculated?
Appreciate if any one has any example.
Cheers
KK

Hi bump for any suggestions?
i have noticed one thing the time available is a round up value actual time available as per capacity header is 22.5 but in MF50 it is showing as 23..if i change to 21.5 then it is showing 22hrs available per day is this the standard behaviour?
can anyone tell me how the required time is calculated?
Cheers
KK

Similar Messages

  • Splitting in REM planning table

    Hello,
    I am presently working with REM planning table.In planning table there is functinality of splitting the monthly quantities to daily quantities or weekly quantities.
    When you split the quantities what calculation system is doing internally?
    How system determines the start and end dates for the splitted orders.
    If I want to split the quantities on the basis of fixed percentages that is 18  % first week , then 23 % second week , 25 % third and rest percentages for last week.
    Can this weekwise varying distibution is possible in Planning table ?
    Waiting for reply from the REM Gurus.
    Regards,

    Hi ravindra,
    if u are working with longer lead time planned order, u can use various functinality to split the order qty for day or shift wise.
    The Avilable Capacity of the workcenter plays important Role.With refernce to this Avilable capacity the sytem schedules (spilts) order qty as per your need.
    Lead time scheduling will be carried out to determine start and end date of planned orders.
    For example u want distribute planned order day wise, system schedules the planned order with reference to Daywise Avilable capacity of WC. if the capacity requirements of planned order exceeds the avilable capacity of one day, system will automatically spilit the order qty for next day for remaining capacity requirements.
    This is way, system works to spilit the order. Before that u have to select correct scheduling data under "scheduling" tab of planning table.
    For your last question, system will schedule planned order according to Avilabale capacity and capacity requirements.
    i think u can spilit manually accorting to your need .Since  u have Avilable capacity for full week why do u want to spilit with some percentage.
    Regards
    pradeep

  • Dispatching problem in REM Planning Table

    Hi,
    I have encountered a problem in REM planning Table, from REM planning table when i m accessing Bar char planning table and try to dispatch the planned order it is not dispatching the order. I have checked the scenario is previously it was working fine but now it is not working with same settings can u guide me tht which settings affect the planning table dispatch. neither it was showing the capacity requirements, i have maintained the rate formulas is work centre and formula was working fine, i doubt it relate to SPRO settings kinldy give me hints where i can check n wht standard settings i have to make for planning table..

    Plz give some suggestion on this....

  • Capacity requirement and scheduling process

    Hi Experts,
      please explain me how capacity requirement and scheduling (please explain with configuration  settings)    will help in SAP PP.
    Regards,
    Bhaskar.
    Edited by: basi123 on Nov 7, 2011 1:12 PM

    Dear
    Capacity Requirement Are those Which is used  For Operation And Calculate the Time with help of Dervied Formulas
    for instance i take an Example To Describe so that u get clear Picture
    Ex: Suppose i have machine Drilling u assume that Drilling machine as a one capacity under capacity catergory
    here to operate this i need to make my machine set up first then machine time i need to arrange a labour
    so total i required Setup Machine Labour so Here in sap we define a standard value key with all these combination and there we will assign formula for HOW Much to Produce so on...... and in turn it is assigned to control key to perform all the Actions.....
    Scheduling : Scheduling is Nothing but to sechedule Right time at Right job This helps in shop floor to over come overload on machines.scheduling used in
    scheduling for Production orders
    scheduling for Planned Orders
    scheduling for Plant maintainence Order
    Configuration :
    1. Capacity Requirenemnt ;
    SPRO>>>production >>> capacity requirement >>>> Define capacity catergory
    2.Capcity planner
    3.Define parameters OP7B
    4.Assign this to OPCM
    Scehduling
    1. go to OPU3
    With regards
    Pushpalas

  • Planned order capacity requirement load on holiday

    Hi ,
    We have some cases , the planned order capacity requirements be load at weekend (holiday), but we have no same issue for process order , that's means the resouce set up is correct.
    Is any customizing related with planned order capcaity requirment ?
    Thanks !

    Hi,
    If you select the Workday indicator  = 1 (Working days (overrides factory calendar) at "Interval of available Capacity Screen" of Workcenter screen system will schedule the  Order during the Holiday.(CA02)
    This is applicable for Both Planned Order and Process Order.
    Pradeep

  • Problem in REM Planning table.

    Hi PP Gurus,
    We created one material with REM profile 0004 with MRP1, 2, 3, 4, BD1, 2, Accounting 1, 2, Costing 1, 2 and Work scheduling views. In Work scheduling view weu2019ve not maintained any Production Scheduler and Production Scheduling Profile except Production storage location. Whenever weu2019re accessing Planning table (MF50) getting the errors
    1.     Date adjust. level incorrect: Plant 1001 /ord.type PE / prod.sched. *
    2.     No lead time scheduling: Plant 1001 / order type PE / prod.sched. *
    3.     No capa. data determined: Plant 1001 / Ord. type PE / Prod. sched. *
    One more thing. If we donu2019t put any sales order OR PIR using MD61 Planning table is not showing any details in Material Data rows of Planning Table. And system is not allowing to create any Planned Order manually. What might be the problem?
    If we put any Sales order or PIR using MD61 though the Rows in Material Data get visible but system is not showing any calculation changes in u2018Complete capacity datau2019 rows. We mean to say system is showing Available capacity but not showing any Required Capacity at Production line.
    Thanks & Regards,
    Abu Arbab

    Hi,
    In OPU5 Rate base scheduling active tick mark for scheduling and generate capacity with selection ID 02.
    Scheduling level -rate-based scheduling
    Scheduling type- Backward.
    Then check the planning table section parameter
    SPROProductionRepetitive ManufacturingPlanningPlanning Table--Maintain Entry Parameters.
    Please check scheduling level and other parameters?
    I hope u have not maintained any prod scheduler at work scheduling view.
    Please change this and try again run MRP with planning mode -3 deleted and recreated with lead time scheduling and check the result
    The production line what u have selected at planning table should be same with, production line define at "production version"
    Regards,
    R.Brahmankar

  • IMG setting for REM Planning Table

    Hi Gurus,
    Can any one throw light on following IMG settings-
    Path -
    IMG --> Production --> REM --> Planning --> Planning table --> Maintain Row selection --> Reciepts Other version
    Relevance of "Other version - in IMG setting for visible rows in planning table".
    Planning table output does not change with check or uncheck of version.
    Which check or unchecking, planning table is considering all the production versions of the materials maintained.
    What is purpose of having a check or uncheck, if system is giving the same result.
    Regards,
    Srini

    Hi Srini,
    We create production version to OPTIMIZE the production. We mention the routing and the BOM in the production version. Actually speaking, in the REM scenario we don't even need a planned order. Production order is absolutely not needed. So in the planning table, it shows the production data for all the versions that you have created, irrespective of whether or not you check the indicator. During planning run, the system will take the first production version by default. So in the planning table you can see the optimum production and you can do leveling also, possible through the row selection option in IMG. Hope this sheds a light on your concern.
    Regards,
    Sreekant.

  • Rough -cut plan with capacity requirment calculation

    Hi all,
    We checking SOP with rough-cut plan
    We created Rough-cut profile in mc35 for our bottle neck work center with base quantity -1 and time span - 1
    then we selected new work center (there is no existing cap req). and assigned base unit measure:min.
    and we assigned 1min for each day and saved the profile.
    Now we went to mc88 and checked the material's active version production plan. (period split- DAY)
    in View -> capacity situation -> rough cut planning -> show.
    System calculates some capacity requirement for our production plan.
    Say for tomorrow's date i given 1000 qty - production plan.
    but system showing capacity req
    Work center:  TESTWC3                  Plant: 0001         Capacity:  001
    Info structur  Material          Plant   Order qty     Unit     From              To          Capacity reqmts      Unit
    S076            TESTFERT14    0001  1000.000       EA    29.01.2010  11.02.2010   9000.000              MIN
    with 9000min and cap load more than 652% ( Actuallly  it has to show 1000min as per rough cut plan profile)
    Our available capacity of work center per day - 1380 min
    We cant understand the capacity requirement calculation in MC88..
    Help us out...
    Thanks in advance

    Hi,
    Rough cut planning is genrally done for the group of material say product group, group of workcentre rather than individual material or workcentre.
    As standard, in resource table whatever the value you enter that corresponds to no. of days. Each column represents one day.
    Pl. refer this link for clear understanding of the same.
    http://help.sap.com/saphelp_47x200/helpdata/en/a5/63212e43a211d189410000e829fbbd/frameset.htm
    Madhava

  • Planned Order Capacity Requirement CM29

    Hi All
    This may be a trivial question for you guys, but I am couldnt find the problem, need your help again please:
    In CM29 my planned order and process orders are visible, and I am using the standard overall profile: SAPSFCG013.
    Earlier I use to see a continous red bar for length of the planned order / process order in the graph, but somehow now it just show up as a single line, irrespective of the order quantity.
    Can you please let me know how to resolve this!
    Thanks in advance!
    -Rahul

    Hi Vivek
    Here is the link for attached screen shot for CM29 with weekly and daily split:
    CM29 with weekly split:
    [CM29 Screenshot|https://picasaweb.google.com/110467857304221340164/CM29?authkey=Gv1sRgCNLYw_uHj8-lUA#5626401198199374018]
    CM29 with daily split:
    [DailySplit|https://picasaweb.google.com/110467857304221340164/Jul72011?authkey=Gv1sRgCLKtzPPn5_SARQ#5626402521518801586]
    I have trie changing hte qty to 1000 and more, the capacity (detailed capacity and roughcut capacity requirement) changes as expected but the graph does not moves
    Thanks in advance
    Rahul

  • Error message in capacity planning table

    Hi,
    I am  using REM planning table.I enter the planning table by giving the selection criteria of Plant and production line.
    System is giving following error message,
    the error message and dignosis of the error message is given here.
    'No prod. dates for material MTI_FERT011, version 0001, production line 2279'
    Message no. REMPT315
    Diagnosis
    The planned order has no production dates for the combination of material, production version and production line you specified.
    This may be as a result of the following, for example:
    The planned order was scheduled but not using the production line you selected. (The production line is determined by the production version you entered in a planned order.)
    Procedure
    One possibility of finding out what is causing the problem is:
    To access the planned order from the detailed dialog box in the table via "Change" and reschedule the planned order. Check the scheduling log by choosing "Goto --> Scheduling log". More information is displayed in the log's warning or error messages.
    But which master data to be corrected is not known.
    Experts please guide me.
    Regards,
    Ravindra

    Hello,
    I had the same error while working with the REM planning table, despite the consistency of the data.
    Another cause that can lead to the error message REMPT315 is that in the production version detailed screen, "Planning data" table you have entered the routing next to rate-based planning. You must enter the routing (number of the group and the group counter) on the line detailed planning.
    After that, choose check again and try to introduce new quantities in the planning table. It worked for me!
    Irina

  • Planning Table MF50

    Hello experts,
    Can some one please explain the purpose of the planning table MF50 and how to use it for capacity levelling. I am in a REM environmnt.
    Thanks
    Raman

    HI
    1)In Repetitive Manufacturing, the master plan is represented by the planning table. The planning table is a tool for operative planning and is used to plan the production quantities:
    2) In a repetitive manufacturing environment, planning and control is usually carried out in a period and quantity basis. The layout of the planning table has been designed to support this requirement and is also based on periods to provide a very clear, easy-to-interpret overview of materials and production lines.
    3)The planning table is the planneru2019s/MRP controlleru2019s most important tool for planning the production quantities. At a glance the planner can check production quantities, monitor the available capacity of the production lines and check up on the availability situation of the products produced on each line.
    4)You can directly enter and change production quantities in the planning table. You can assign u2018non-assignedu2019 production quantities to the production lines or you can reassign production quantities to alternative production lines.
    5) You create the production quantities or assign them to the production line in the planning table.
    6 )You can also use the planning table with capacity planning. Here, planning is based on lead time scheduling. The basis for lead time scheduling is the routing. You can access the capacity planning table directly from the REM planning table.
    Regards
    Anupam Sharma

  • Distribution of planned cost of activity and its linked to PS cash flow

    Dear PS Gurus
    Kindly tell us how to distribute my planned cost (in result of internal,external activities ) should be equally distributed in the over planning period of activity (Say six months) and  also it should  have linked to my cash flow  also.so that by fund get adjusted .
    For Eg My activity A has planned cost 1,20,000 /-  which is going to complete in  6 Months  .Hence my planned cost should be distributed 20,000 / month and that should be reflects in cash flow.
    Regards
    Project Team 1

    Hi,
    You can distribute your planned costs at activity level based on the distributionkey you specified. The distribution is done for the entire duration of activity depending on the Dist key you select. If you do not put any Dist key, then the costs would be distributed equally across the entire duration of activity. If you want to have equal distribution of costs, you can use DK- SAP020 which distributes on earliest dates of activity using Factory calender. If you want you can also define your own DK in SPRO under: Production->capacity requirements planning->operations->capacity requirements->distribution.
    Hope this clarifies..
    Best regards..

  • Capacity requirement showing up in previous month in RCCP

    Hi Experts,
                     I am doing RCCP through MC88. But when i am giving the sales quantity in January and generating a synchronous production quantity, the capacity requirement and load are shown in the month of December instead of in January.
                     How can i get the requirement and load in January, please suggest.
    Regards
    Sm.

    Hi Jiaul,
                I cannot find a provision to change the profile dynamically from MC88 screen. This is possible in my understanding in capacity levelling/planning screens like CM38/CM01, etc.
                But even in such screens the same problem remains. For example when i did LTP for this material with PIRs in Feb 2011, the capacity requirements in CM38 appeared from current period that is from 09.12.10, though my planning scenario was valid from 01.01.2011. I changed the period and evaluation period dynamically from  the CM 38 screen, but that did not solve the problem as the requirement and load which was wronly showing up in Jan instead of Feb 2011 ( just as it happened in RCCP) merely vanished from the output and now i have the available capacity in Feb 2011 showing up but without any capacity requirement or load in the month.
    Regards
    Sm.
    Edited by: Sm on Dec 9, 2010 1:02 PM

  • How is Reqmts calculated in CM01( capacity Planning: Detailed Capacity List.

    I believe Reqmts is the difference between the 'To be confirmed' and 'confirmed hours'.
    If let suppose standard hours for a part to be manufacture is 100hrs and we have already work 52 hrs off 100hrs then if i go and look up this order in CM01 then the Reqmts should say 48hr (100-52).
    But when I am going to CM01 it still saying 100 hours which is not correct. Can some one help me solve this issue

    Hi Pankaj,
    Once confirmation is done, hours must be deducted and it should show the remaining hours in CM01 based on the below settings in work center/resource in Capacity tab.
    Control: Calc. of Remaining Req./Duration After Confirmation
    Controls how, after partial confirmations the
    Remaining capacity requirement and
    Remaining duration in a rescheduling is calculated.
    The following are possible:
         Formula-Related: The remaining requirement / remaining duration of a
         partially confirmed operation is determined when the formula defined in the work
         center is evaluated. It is the remaining quantity and not the operation quantity
         that is taken into account after the confirmation.
         Completely for Partial Confirmation: The remaining requirement /
         remaining duration is reduced completely when there is a partial
         confirmation.
         Completely for Final Confirmation: The remaining requirement /
         remaining duration is reduced completely when there is a final confirmation.
         There is no adjustment through partial confirmations.
         Proportional to Service: The remaining requirement / remaining
         duration of a partially-confirmed operation is reduced proportional to the
         service that is assigned to the relevant capacity segment in the work center in
         your record type group.
    Dependencies
    When there is a final confirmation the remaining capacity requirement of the
    operation is always completely reduced.
    Please check your settings accordingly.
    Thanks.

  • Capacity planning and levelling

    Hi,
    My client has around 8 different production areas and I have created 8 different order types,production schedulers,capacity planner groups and production scheduling profiles for the same. I have also created a list profile,selection profile, graphical profile, optional profile and an overall profile with my understanding.
    1. I want to see for a given production area, In the morning, the user has to take the list of work centres pertaining to his area and fix priorities. In case he wants to move certain orders to next day and want to insert new orders in place of that, how to do this?
    2. How can I utilise the feature of capacity planning, to evaluate my capacity requirements for new projects?
    3. I want the step by step instructions for doing the capacity levelling both in graphical/tabular forms. Also please explain the purpose of different profiles used for capacity planning like selection,option,list etc.
    Regards,
    Sridharan M

    Dear
    Capacity planning comprises the following partial components:
    Capacity Evaluation
    In the capacity evaluation, available capacity and capacity requirements are determined and compared with each other in lists or graphics.
    You can use capacity evaluations to analyze capacity loads in your company.
    Capacity leveling
    The objectives of capacity leveling are:
    1.     Optimal capacity commitment
    2.     Selection of appropriate resources
    3.     In most applications, you can use two types of planning table (graphical and tabular versions) to display the capacity situation and to carry out capacity leveling.
    4.     In some applications such as Repetitive Manufacturing (PP-REM) or Sales and Operations Planning (PP-SOP), there are application-specific planning tables for capacity leveling.
    The objectives of capacity leveling include:
    u2022     Leveling overloads and under loads at work centers
    u2022     Achieving optimum commitment of machines and production lines
    u2022     Selection of appropriate resources
    Dispatching Operations
    Dispatching operations is the main function of capacity leveling. Operations are dispatched to the time when there is sufficient capacity for them to be executed. You can also dispatch sub-operations and work elements.