SAP APO process

Hi Team.
Let me list down our entire demand planning process which we are currently doing and help me how we can improve the process in APO.
Every starting of the ,sales sending us the sales order and forecast for next month and we are updating the same in our allocation file.
Allocation file is summary of total demand and total supply.
Demand from sales team and supply is the file from planners (planning also manual process, running BOM and getting the SF requirement)
So the summary is :demand planning is manual..Planning is also almost manual .
Please know how APO this process will be solved.
Thanks for the help.
Regards,
Vijesh

Vijesh,
At a very high level:
1.  The most common solution is that Sales Forecasts are entered in Demand Planning.
2.  If ECC is used as the online transaction processing (OLTP) system, the Core interface (CIF) is activated. Regardless of what your OLTP is, Material numbers and Plants must be replicated in APO.
3.  Master data for planning is replicated in APO (Bills of Material, Routings, production versions, purchase info records, Special procurement keys, etc etc)
4.  Transactional data, such as Sales orders, FGs and SFGs stock, and FGs and SFGs supply orders are also replicated in APO.  It is possible to plan the entire BOM in APO, if such a solution is desired.
5.  SNP and/or PP/DS are typically activated as planning engines.  Or, for a more complex, but higher quality solution, Capable to Match (CTM) or Optimizer can be used as planning engines, to create FEASIBLE plans.
6. Finalized forecast is released to Planning.  This means the forecasts are copied from Demand Planning into the active area that is accessible to the planning engine.  Appropriate consumption of forecast is transparently done.  These released forecasts can optionally be replicated back to the OLTP.
7. Planning is then run against the combined consumed forecast and sales demand.  Output of planning is generally planned orders and/or purchase requisitions.  These 'procurement proposals' can optionally be transparently sent back to the OLTP.
In general, only planning is done in APO. Execution is generally not done in SCM, but is done within the OLTP.
There are hundreds of variants of the above high-level overview.  I suggest that if you wish to pursue APO as a planning solution, you engage an external resource who can assist you to create a solution that meets all your business requirements, and can also help you through the implementation.
Best Regards,
DB49

Similar Messages

  • How to change process chain in SAP APO, in RSCP tcode.

    HI SAP APO Experts
    I am from SAP ABAP background, I need to change a 'AND' operator in process chain in RSCP tranaaction in SAP APO.
    I dont have any idea how to change process chain.
    Could you please help me how to change process chain in SAP APO in RSCP tcode.
    Appreciate your help or comments.
    Sandeep..

    Hi Sandeep,
    The t-code RSCP does not exist in SAP APO.  The correct t-code is RSPC. 
    Step 1:- In RSPC t-code, select the process chain which you need to change. 
    Step 2:- Double click on it. 
    Step 3:- It will display the various programmes attached to the process chain.  Go to change mode by clicking on the change indicator (Control + F9)
    Step 4:- Select the programme area where you need to do the correction or change.  Double click on it.
    Step 5:- It will take you to the programme and its selection contents.  Make the relevant changes.  You can directly carry out the change in se38 also if there is variant kind of changes for that particular programme.
    Step 6:- Once the changes are done, save the changes and press F3 button which will take you to the home page of the process chain
    Step 7:- Save again so that the change in the programme alongwith the process chain will get saved.
    Regards
    R. Senthil Mareeswaran.

  • SAP APO and WM

    Hello All,
    Is it possible to put some warehouse related controls and limitations in SAP APO (SCM) without having EWM? For example, a certain warehouse can only process 300 orders and if anyone tries to place order beyond 300 then it automatically pushes the CGID to next day?
    Second example can be on availability of truck? If the Truck leaves Warehouse only twice a day for a certain customer, then APO (SCM) automatically place the order on those two days?
    Thanks,
    Ali

    Ali
    You might be able to get GATP to meet at least some of your requirements with some creative thinking and enhancements. Standard GATP does not consider warehouse (field is not transferred from ECC to GATP during the ATP check), so you would add that to the field catalog through an enhancement (relatively simple). You could then use Product allocation functionality to limit the warehouse to 300 orders per day. Standard product allocation functionality is based on order quantities, not number of orders, so you would need an enhancement to modify this behaviour (sounds simple, but you would have to explore).
    I don't understand what you mean by 'CGID', but you could get GATP to commit material availability dates based on warehouse limitations (push out material availability date based on next available free 'slot' in the warehouse). As long as you run the delivery due list with a short (say 1 day) window, this might work.
    Configurable Process Scheduling (CPS) functionality within GATP may also work for your requirement of 'truck leaving warehouse only twice a day to a certain customer' - using customer-specific condition tables for transportation activity calendar determination.
    One thing to remember is that GATP works only on commit dates of Orders (Sales Orders/ Stock Transport Orders), it doesnt directly influence actual pick/ pack/ ship activities in the warehouse (it does affect warehouse operations indirectly .)
    Rishi Menon

  • SAP APO Transportation Managment 5.0

    Hi,
              I would like to know the the process to Implement Transportation and Planning 5.0 in SAP APO environment ,presently the client is using SD for transportation and distribution.
              If you could mail me implementation guide in regards to Transportation Managment it would help me a lot.
                Could u send me some links which will help me.I have refer to master Data sep-up and understood the process in help.sap.com.
    Thanks
    Partha

    Dear Partha,
    Pl. find the below link
    http://help.sap.com/bp_scmv140/BBLibrary/documentation/S12_BB_ConfigGuideEN_DE.doc
    This guide will show you basic configuration settings to be made in both the systems. Though it does not list all the configuration, but it is quite useful guide to begin with.
    Regards
    Sandeep Patil

  • Whr should maintained a business system group in SAP APO

    hi gurus,
    where should i maintain business system group in SAP APO
    can u explain me, what is the process, how it will work, why need BSG in APO
    prasad

    Hi,
    We maintain Business System Group in APO IMG.
    IMG >> SCM Basis >>Integration >> Basic Settings for Creating the System Landscape >> Maintai n Business System Group
    In this IMG activity, we determine the assignment to a business system group of this system and the ERP systems that are to be connected. By doing this, you create areas with the same naming conventions. These guarantee that the same names are used for master data and also their synchronization in distributed system landscapes.
    In addition to the ERP systems, this system too must be assigned to a business system group (BSG) as an independent logical system.
    Proedure :
    u2022     Choose New Entries.
    u2022     On the New Entries: Overview screen, specify the following information for the business system group:
                 o     An alphanumerical key (maximum of 10 characters).
                 o     A description of your choice
    u2022     Save your entries.
    Example :
    An SCM System is to be connected with the two ERP systems A and B in which two different materials (for example a hammer and a screw), have the same material number (100). The two materials are to be represented as two different products in the SCM system.
    Assign The two ERP systems to different BSGs. Assign the SCM system to one of the two BSGs.
    u2022     ERP system A (material number 100 = hammer) -> BSG A
    u2022     ERP system A (material number 100 = screw) -> BSG B
    u2022     SCM system -> BSG A
    Hope this gives you insight.
    Regards
    Datta

  • Want to learn SAP APO

    HI Experts,
    I have 4+ years of experience in SAP BI, now I am planning to learn SAP APO. Please give me sugessions is it is useful to future carrier and what are the best materials or documents to learn.
    Regards,
    SVS

    Hello
    As you have good exposure in BI , DP would be a good area to explore. Let me tell you , BPC is the area that might help you more in the long run.
    In DP what is going to happen is you may have to read lot of functional processes and get yourself acquainted with mapping them to the system.
    If you are bent on APO then spend sometime with DP. Before that first read Forecasting and if you google this word you can see lots of good sites.  Please let me know if I can be of any help.
    Regards
    KK

  • SAP SCM and SAP APO: Best practices, tips and recommendations

    Hi,
    I have been gathering useful information about SAP SCM and SAP APO (e.g., advanced supply chain planning, master data and transaction data for advanced planning, demand planning, cross-plant planning, production planning and detailed scheduling, deployment, global available-to-promise (global ATP), CIF (core interface), SAP APO DP planning tools (macros, statistical forecasting, lifecycle planning, data realignment, data upload into the planning area, mass processing u2013 background jobs, process chains, aggregation and disaggregation), and PP/DS heuristics for production planning).
    I am especially interested about best practices, tips and recommendations for using and developing SAP SCM and SAP APO. For example, [CIF Tips and Tricks Version 3.1.1|https://service.sap.com/form/sapnet?_FRAME=CONTAINER&_OBJECT=011000358700006480652001E] and [CIF Tips and Tricks Version 4.0|https://service.sap.com/form/sapnet?_FRAME=CONTAINER&_OBJECT=011000358700000596412005E] contain pretty useful knowledge about CIF.
    If you know any useful best practices, tips and recommendations for using and developing SAP SCM and SAP APO, I would appreciate if you could share those assets with me.
    Thanks in advance of your help.
    Regards,
    Jarmo Tuominen

    Hi Jarmo,
    Apart from what DB has suggested. you should give a good reading on the following.
    -Consulting Notes (use the application component filters in search notes)
    -Collective Notes (similar to the one above)
    -Release Notes
    -Release Restrictions
    -If $$ permit subscribe to www.scmexpertonline.com. Good perspective on concepts around SAP SCM.
    -There are a couple of blogs (e.g. www.apolemia.com) .. but all lack breadth.. some topics in depth.
    -"Articles" section on this site (not all are classified well.. see in ECCops, mfg, SCM, Logistics etc)
    -Serivce.sap.com- check the solution details overview in knowledge exchange tab. There are product presentations and collaterals for every release. Good breadth but no depth.
    -Building Blocks - available for all application areas. This is limited to vanilla configuration of just making a process work and nothing more than that.
    -Get the book "Sales and Operations Planning with SAP APO" by SAP Press. Its got plenty of  easy to follow stuff, good perspective and lots of screen shots to make life easier.
    -help.sap.com the last thing that most refer after all "handy" options (incl. this forum) are exhausted. Nevertheless, this is the superset of all "secondary" documents. But the maze of hyperlinks that start at APO might lead you to something like xml schema.
    Key Tip: Appreciate that SAP SCM is largely driven by connected execution systems (SAP ECC/ERP). So the best place to start with should be a good overview of ERP OPS solution overview, at least at the significant level of depth.). Check this document at sdn wiki "ERP ops architecture overview".
    I have some good collection of documents though many i havent read myself. If you need them let me know.
    Regards,
    Loknath

  • What is the Role of R/3 BASIS administrator in SAP-APO

    Hi can any one tell me, what is the role of a BASIS admin. in SAP-APO. Please list the responsibilities. 
    Thanks in advance.
    Regards,
    bompally.

    Thank you very much manish,
    Actually I am a BASIS admin. I want to explore the BASIS -APO administration side. What do you suggest on this.
    Please provide me some more information on the following also.
    CIF Performance Questions.
    What is CIF?
    1) Check and ensure that same qRFC versions and supplements are used in both R/3 and APO Side. Make sure that latest available qRFC Version and supplement is being used.
    2) Review the Integration models used currently and identify if they can be reorganized to reduce the duplication?
    3)Review the background processes for Activation and generation of the integration models.
    4)Identify if there are any bottlenecks in the CIF queues.
    5)Review the process of transferring the Product/Material master changes? Are the change pointers being used or BTE's?
    6)Review and check the schedule of the following background jobs: (Which transaction we use to do these functions?)
    Deleting old integration models?
    Deleting old application logs.
    Processing of change pointers.
    Deletion of old change pointers.
    Live Cache consistency Check jobs.
    Planning area consistency checks.
    Reorganize OMS Data (/SAPAPO/OM_REORG_DAILY and /SAPAPO/OM_DELETE_OLD_SIMSESS)
    7)Monitor the QRFC Tables-ARFCSSTATE, ARFCSDATA, ARFCRSTATE,
    TRFCQDATA, TRFCQIN, TRFCQOUT and TRFCQSTATE.
    8)Monitor the Optimization server performance.
    Thanks and Regards,
    Pradeep

  • Simulation of Planning in MSP(SAP APO) Error

    Hi All,
    I am trying to Simulate the Planning Process in MSP in SAP APO server.
    I followed the Configuration step as per the documentations in SAP.
    But when I try to create a Maintenance Plan through /SAPAPO/MSP01 , I am getting an error "No Activity Selected OR No Activity Exist"
    But I have created the activities in in the Stock Task List Linked to the Maintenance Profile used to create the Maintenance Plan.
    Has anyone encountered a similar scenario. If so please let me know a possible solution or your suggestion on this.
    Thanks in advace.

    Hi Vijay,
    Seems like there are some inconsistencies exist.Run /SAPAPO/OM17 specifically for product-location combination.Ensure your doing the consistency check in background mode.COM Routine error will occour if you try to change one of the keyfigures setting of planning area in foreground.
    Hope it will be helpful for you.
    Regards,
    Kannan

  • Distribution Planning within SAP - APO 3.0 or SCM 4.0

    Hi,
    Can do any 'Distribution Planning' within SAP SCM V4.0 or V5.0. 
    We are trying to  improve  'decision-making' associated with selection of a particular warehouse  for shipments coming out of a specific plant. The application should be able to produce a recommended set of shipments by week from each plant. Critical inputs that go into the process will be (a) Procurement Forecast; (b) Production Forecast; (c) Warehouse Space; (d) Production Plan etc
    Can this be done utilizing SAP APO 3.0, SCM 4.0 or SCM 5.0?
    Thanks

    Hi Tushar,
    APO 3.0, SCM 4.0 nd SCM 5.0 all provide replenishment, distribution and deployement along with basic transportation planning functionalities wihin SNP (Suppluy Network Module) of APO. With SCM 5.0 you get other applications (along with APO) like EWM (Extended Warehouse Management) and better transportation planning features.
    Moreover it makes sense to go in for the lastest version of the solution to get the latest set of features. Please check on help.sap.com under my SAP Business Suite >> SCM >> APO >> SNP or http://www.sap.com/solutions/business-suite/scm/featuresfunctions/index.epx for more details.
    Thanks,
    Somnath

  • Need help on SAP APO

    Hi,
    We are in process of evaluating SAP APO for one of our subsidiaries which is into computer AMC business.
    I undersatand that SAP APO has a service part management module and i need some clarity on certain functionality aspects of the product, for example
    - Does SAP APO manage alternate part list?
    - Does it compute reorder level for spares and also can it provide ROL for multiple plant location
    - Does it compute ROL considering the Alternate Parts Availability?
    - Does the system consider spares reparability factor while planning for spares?
    - Does the spares planning logic modeled on consumption of spares or on some other logic?
    We are currently on SAP R/3 ECC 6.0.
    Standard MM & SD modules are used for the subsidiary in discussion.
    FI is also used but posting is done only for few cases as it is under control of corporate Finance.
    Thanking in advance for the responses.
    Regards,
    HRS

    Hi
    I am also intrested to know about this. One of our client wants to implement SPP. At present they are in ECC 6.0.
    Can any please share the information on SPP.
    Now if they want to enter in to SCM system what are the other modules they have to implement along with SPP?
    Thanks in advance
    Vijaya

  • SAP APO or SAP-PP?

    I am in a decision making process of my industry scenario to map in SAP
    My scenario is as below
    My sales regional heads input their requirement for 1 months in system as below
    Input is
    •     region(in SAP it is route destination)
    •     Qty
    •     Material number
    •     Selling price
    •     Period
    Once they enter the data system should collect all the data from each regional and run a statistical calculation taken fast history and generate a unconstrained sales plan/regional for 18 months.
    It will be passed to a optimizer where in we will put the following constraints
    •     Capacity of production line with respect to that material grade
    •     Selling price (from input data)
    •     Minimum allocation qty per region/Grade
    •     Customer grading ABC, A is good C is worst
    •     Inventory available in all region and production plant for that grade
    •     Net back that material can fetch
    •     One of the important sub assembly/intermediate material – availability for future months
    •     Grade change over loss in USD.
    With the above constraint system should generate a region plan giving details of which material (grade wise) and qty
    Second output is the production plan telling which grade how much to produce and when
    Is it possible to do the above in normal SAP PP or we need to go for SAP SCM?

    Dear Ratan,
    thanks for the reply.
    My question is the sceanrio given above is it possible to map in SAP APO or SAP PP...I tried...but only problem is the seling price and the capacity optimization.
    Forecast, I could do it using Std SAP forcast methods...But during optimization i failing to understand how to do it... I prepared a Z program where in user will tick the check box on what basis with priority he wants the optimization...using LP. It is giving faairly okay results...but fully okay. Takes more than 2 hrs to compute the results which is not at all accptable...maximum 1/2 hr is okay and in foreground it is not working at all.

  • How to "roll back" SAP APO PPDS planning batch run from infeasible batch mid-point to before start of planning batch run?

    Hi Experts,
    We are investigating if any SAP customer that implemented SAP APO PPDS has ever attempted to establish a "roll back" of the SAP APO PPDS created supply plan to a defined point before the start of the SAP APO PPDS planning batch run?  
    We have a situation where - in the middle of the planning batch run - randomly or intermittent the batch run hangs or runs a step for multiple hours that normally, at most days, takes only a few minutes to run.  In a situation like this, the supply plan is not in a state where customer sales orders can be promised  (using GATP CTP) or planned orders can be converted to production orders and published to SAP ECC, etc since the plan may be capacity infeasible or simply partial or incomplete.   To not hold the business operations hostage to wait resuming operations (promise customer sales orders, convert and release and execute orders to transfer, deliver, produce, or purchase) for hours or days, we need to find a way back to the original plan right before the nightly PPDS batch planning job started.
    We already close all the queues from ECC to APO, thus, no CIF traffic from ECC to APO.  We also shut down the customer sales order feed into ECC as normal process for duration of the APO PPDS batch planning run.  Thus, functionally,  we are theoretically in a situation to simply go back to a PPDS and active planning version save prior to the run.  Yet, many more technical and BASIS-related questions remain on how to roll back to a state where the plan was not compromised.
    This inquiry is to learn if any other SAP customer has ever established a process to roll back SAP APO PPDS to a previous point in time supply plan to resume operations?  Whatever the reasons are, be it after a failed  batch run, or any time during the normal interactive plan day.  
    Additional information about our design and plan:  
    1.  We have a two year horizon supply plan in PPDS
    2.  We only publish to ECC 14 days worth of planned orders, stock transfer requirements, and purchase requirements
    3.  We convert planned orders to production orders and release production orders in ECC 2 days before first operation starts
    4.  We convert PR's to PO's and STR's to STO's in ECC  2 days before execution (ship or submit to vendor)
    Any indication where a SAP customer has developed and uses a process to roll back an SAP APO PPDS- planned supply plan to an earlier point in time or version would be helpful to know.
    Regards,
    Manimaran M.

    Hi  Manimaran,
    Saving in Simulation means in DS board when you click on save it provides you option to save sim version or adopt to active version. If you copy to inactive version you cannot copy back  trasaction data specially PPDs orders back to active version again while if you save in simulation you can adope it to active version at any point of time. YOu can adopt simulation version changes to active version using T-code /SAPAPO/CDPSS0
    Copying to active version means you copy data from version 000 to some other active version while here results are kept simulation,

  • SAP APO-DP Learning material

    Dear Friends,
    Please suggest me any good reference book for ' SAP-APO DP ' which can cover all the fatures of the tool with business processes.
    As i am in learning phase, your suggestions can help me a lot...:)
    Thanks..
    Bye

    Hi ved123,
    You can refer the book "'Sales and Inventory Planning with SAP APO', Author Marc Hoppe".  You can buy this book even online in sappress website.
    Regards
    R. Senthil Mareeswaran.

  • T-code or Table to find total errors in SAP APO like ST22 in ABAP

    hi all,
    Could please tell me the T-code or Table to find total errors in SAP APO like ST22 t-code in SAP ABAP.
    Thanks.
    Suryam S

    Hello Venu,
    Do you mean other functional errors?
    You can check SLG1, /SAPAPO/C3, STAD
    Best Regards,
    R.Brahmankar