Subcontracting Purchase order-With scrap or extra qty.

Dear Experts
How we can define the Scrap  or extra Qty in subcontarcting purchase order, suppose PO qty is 10500 , and we want to receive 10000 only then how we  can take care about the  500 qty and there mantioned BOM.,we want to give the material of 10500 .
Rgds
Pankaj Agarwal

Hi,
it is common scenario that when u give material to sub contractor,off cuts will get generated.
so u cant get the 10500 qty in the material mentioned in the BOM for that,
u can overwrite the value at the time of GR for consumtion.
for 543 movet type.
means if as per BOM for 1000 qty material requirement is 1000 but actual consumption is 1050 qty.
then overwrite the 1000 by 1050 at GR for 543 movt type line item
regards,
sujit

Similar Messages

  • Subcontracting Purchase Order with Delivery Cost

    Hello Experts,
    I am facing issue during Goods Receipt against Subcontracting Purchase Order.
    Note:
    a) Subcontracting PO has delivery cost given 200 /pc.
    b) Condition type Z001 for Delivery has Condition Category "B" with accrual checked.
    c) Pricing Procedure has Accrual Key FR1 with condition type Z001
    d) Condition Z001 is common for Standard Item Category PO and Subcontracting PO for delivery cost.
    During Goods receipt, system generates following accounting.
    BSX     Inventory-SemiFinish     M     S     521.12
    WRX     GRIR Clrg-Mat A/c     S     H     100.00-
    BSV     Inc/Dec. in Semi-F     S     H     521.12-
    FRL     Job Work                          S     S     100
    FRN     Freight Clearing A/c     S     S     100
    FR1     Freight Clearing A/c     S     H     100.00-
    BSX     Inventory-RM(Domest)     M     H     321.12-
    GBB     RM Consumed-Domestic     S     S     321.12
    As shown above FRN is the account which is the resultant of Devliery cost during Subcontracting. Entry of this Key is not completely knocked off in this transaction and next transaction for invoice verification MIRO.
    My query:
    A) Can we stop account posting for FRN.
    B) If not How will FRN entry be knocked off, (Entry for FR1 gets set off during MIRO- Invoice verification.)
    C) In case B is not possible, Posting in account  assigned to FRN Key will always show values.
    Can any one help me to confirm that Entries above during Goods Receipt are ok, If not what sort of changes are required.
    Can we use same condition types for Delivery cost for Standard Item category PO and Subcontracting PO .
    Awaiting reply,
    Regards,
    Manish

    Hi Vaibhav,
    a) I am not able to understand why do you think the above entries are not correct.The entries are perfect.
    My Reply:  Ok I do agree for a movement that entries are ok, No Issues
    b) If you want that freight entries should not go to separate account then you can include the freight charges in the same condition as basic price condition so that charges will go to FRL and WRX.
    My Reply: How can I include Freight Charges in the same condition as basic price condition, so that charges will to go FRL & WRX, Can you please explore this,
    Regards
    Manish

  • Subcontracting Purchase order with Sales order Reference

    Hi friends,
    I am facing a problem during GR of Purchase order with Acc. Assignment E and Item Cat L i.e. purchase order is MTO and of Subcontracting.
    During GR, system is purposing movement type 543 E instead of 543 O for BOM components. Please suggest how can I get the correct movement type during GR. I would like to appreciate for your kind response.
    Kraheja.

    Hi
    Go to SPRO->Logistic general->Tax on goods movement->India->Movement types.
    Here you will find the group of movement types check which movement types is mantained for the out side movement groups or inward movement.
    also check the Material Master in MRP view if the collective requirements (02) is mantained.
    Regards
    Sujoy

  • Subcontract Purchase Order with delivery address from Sales Order Ship-to?

    Hi
    My client has a Sales order for a subcontracted product.  The subcontractor should send the product directly to the customer that is on the sales order.  Currently, the delivery address on the PO is the home address of the client.
    My first option is to create a vendor address matching the ship-to and enter that manually in the Delivery Address field in the PO. But, i would like this to populate automatically.  Is this possible?
    thanks for your suggestions.
    Oll

    >
    Oll wrote:
    > Hi
    >
    > My client has a Sales order for a subcontracted product.  The subcontractor should send the product directly to the customer that is on the sales order.  Currently, the delivery address on the PO is the home address of the client.
    >
    > My first option is to create a vendor address matching the ship-to and enter that manually in the Delivery Address field in the PO. But, i would like this to populate automatically.  Is this possible?
    >
    > thanks for your suggestions.
    >
    > Oll
    a mixture of third party order (vendor ships directly to customer) and subcontract is not possible. third party order would need a S as item category in the PO, while subcontract order needs a L at the very same field.
    We created a storage location and a shipping point for the subcontractor. The sales order is created as a standard sales order that makes use of this storage location and shipping point.
    MRP run then creates a request to produce that material, based on the special procurement indicator in material master it is known that the material is to be procured via subcontract order.
    We then receive the finished good into this storage location that represents the subcontractor.
    Then we create a delivery in VL01N to ship this material to the customer.

  • Good receipt problem for subcontracting purchase order

    Good receipt problem for subcontracting purchase order
    with account assignment type ‘E’.
    After update to ECC 6.0. Do good receipt for subcontracting purchase order with account assigment 'E'.The system show the error message(KI235)----Two cost elements (Change in Stock (Subcontracting)&Outside processed fee) haven't CO account assignment.but the field status  for sale order is option entry , when I default cost center for the cost element  in OKB9.the system post the material document and generate the following accounting document.
    Doc.Type : WE ( Goods receipt ) Normal document
    Doc. Number    5000056065       Company code    1000         Fiscal year     2007
    Doc. date      2007.12.04       Posting date    2007.12.04   Period          12
    Calculate Tax
    Doc.currency   HKD
    tm PK Account    Account short text   Tx Cost Ctr   SaleOrder               Amount
    1 89 13500000   Stock-Work in proces                   1007823  10             274.4
    2 96 21210010   GR/IR Clearing                             1007823  10             205
    3 91 41010102   Chg in Stock(Subcon)    10901099  1007823  10            274.4
    4 86 41031000   Outside processed fe     10901099  1007823  10            205  
    5 99 13500000   Stock-Work in proces                    1007823  10            69.4
    6 81 41010101   Cost of Prod (Subco)                      1007823  10           69.40
    My problem is:
    When use MIGO to do good receipt for subcontracting Purchase order, for consumption account((Change in Stock (Subcontracting)-41010102&Outside processed fee--41031000) ,why the system don’t recognize the sale order filled as CO account assignment?

    Dear fanny chen
    Did you get a solution for your open question?
    I`m facing the same problem, so any help yould be appreciated.
    Regards

  • How can I select alternative BOM when creating subcontract purchase order?

    In our business, a finish good material always has different production versions at the same time. Each of production versions has its own alternative BOM. When I create a planned order, I can select wanted BOM through specifying production version.
    But, when I creating subcontract purchase order, there is no field for me to specify the production version or which alternative BOM I prefer. In this case, I need to create a planned order at first. And then, convert the planned order to purchase. Only through this way, I can create a subcontract purchase order with my wanted BOM.
    So, I wonder if there is any way to select alternative BOM directly when creating subcontract purchase order.
    Thanks a lot!
    Regards
    Robbie

    Dear Mr. MM
    can you give me additional information about your solution?
    BUT I would not expect the sytem to offer you during the Purchasing cycle the different Production Versions as it is not meant to be. I remember having the same requirement some time ago and we solved it the way I described above, additionally we created a Pop up window with a user exit during the PO creation which offered the different production versions and if the one linked with the quota arrangement, the standard PV, is used in the PO.
    We also have the same problem, we activated businessfunction SCM_GEN_02 so that it is possible to have several production versions for one supplier, but unfortunatly it is not possible to change the production version in the purchase order. (business function does not seem to be very integrated)
    So i would be very interested in your solution because acually it seems that i have to modify the sap standard.
    Thank you and best regards
    Lisa

  • Individual purchase order with subcontracting material

    Hi all,
    I've implemented a individual purchase order in a sale order by means of 'TAB' category item. The material has been set as 'subcontracting'.
    When I create the sale order, a purchase requisition is automatically created with M imputation and special stock 'E'.
    Once I create, the purchase order with reference to purchase requisition, I set 'L' category item. Then I save the purchase order.
    In order to simplify the flowchart, the vendor has enough stock to manufacture the required material.
    Then, Tx. MIGO, stock input with reference to purchase order.
    For the FERT material --> movement 101 E + is set.
    For the component --> movement 121 E - is set.
    How can I obtain 121 'O' - movement for components in order to decrease SC vendor stock?
    Thank you very much in advance for your support.
    Best regards,
    Alberto Ramos.

    Dear Charlie,
    Thank you very much for your response. As you comment, I made a mistake with the number of movement. Certainly the movement for raw material consumption is 543.
    I have executed the flowchart you describe. In your case, an independent subcontracting purchase order is done. This flowchart works correctly (with the results you comment. Actually the raw consumption are related to mov. 543 O -).
    The problem is when purchse order is related to a sales order. That is:
    1. Sale order TA with only one position material A. Category item 'TAB'.
    2. Material master for material A --> MRP 2 view --> Special procurement field: 30 - Subcontracting
    3. An automatic purchase requisition is created (thanks to 'TAB' category item, schedule line, ...)
    4. Tx. ME21N --> I create a purchase order with reference purchase requisition:
        4.1. Account assignment category field is set to 'M' from sales order / purchse requisition
        4.2. I manually set Item category field to 'L' for indicating subcontracting (I don't force this to be 'L' from sales order / purchase requisition because I need to use the same flowchart for subcontracting and not subcontracting materials)
    5. Tx. MIGO
        5.1. For Fert material the system executes mov. 101 E +  (as in your description)
        5.2. For raw materials the system exectures mov. 543 E - ( instead of 543 O -). I would like to obtain the reduction of subcontracting stock, because this material is in my center but povided to SC manufacturer.
    Should I do a 'Subsequent adjustment' by means of Tx. MIGO the movement are:
      - FERT material 121 E - (depending on adjustment)
      - Raw materials 543 E - (again 'E' instead of 'O' which is the result I would like to obtain).
    I will very much appreciate your comments.
    Thank you again,

  • Purchase order with -ve Qty

    Hi,
    Is it Possible to create purchase order with negative  Quantity, right now it is issuing msg "negative Quantity will not be allowed for service based invoice verification".
    If yes please suggest the config steps.
    Regards,
    Rani

    not possible.
    negative stock can be maintained for storage location for goods issue

  • LTP Planning for Subcontracting Purchase Order

    Hi All,
    I am doing LTP run for the Finished Material.
    Finished Material is having few open subcontracting Purchase order's.
    When I take the LTP run  in MS02, system is considering the Open PO's and adjusting (netting) it with the Planned independent requirements of finished material. This is ok.
    But the planning is not creating depending procurement proposals for the child items.
    It is subcontracting PO of finished material, system suppose to create the dependent requirements.
    In the MRP run it is working fine in MD02. But not working in LTP planning run in MS02 Transaction.
    Rgds /  Shailendra
    Edited by: Shailendra Hadkar on Apr 7, 2010 10:44 AM

    Hi All,
    I have found one BAdi u201CMD_CHANGE_MRP_DATAu201D  for showing up Subcon requirements in MS04 for child materials.
    This BADI "MD_CHANGE_MRP_DATA" requires to implement using method "CONSIDER_RESB".
    But implementation of this BADI using method "CONSIDER_RESB" will open up Dependent requirements/reservations of phantoms in phantom assembly planning and other reservations also.
    How I can implement this BADI for specific Subcon requirements or Specific MRP element??
    Regards,
    Shailendra
    Please refer below post by Nethi Venkata R... 
    LTP Doubt

  • Report to Purchase Orders with Good Receipt and pending for Invioce Receipt

    Hello,
    I'm looking a report bring me Purchase Orders with Goods Receipt and waiting for Invioce Verificacion (MIRO).
    I appreciate any help.
    Regards,
    Hector

    Hi,
    ME2N - In selection screen, enter Selection parameters as
    WE102 i.e. Goods receipt exists and in output screen put a filter on "Still to be invoiced (qty)" and "Still to be invoiced (val.)" as not equal to zero OR greater than Zero.
    OR use RECHNUNG i.e. Open invoices and execute the report
    OR Use MB5S - GR/IR Balances

  • Open Po quantity in subcontracting Purchase Order

    Hi,
      In case subcontracting purchase order,If order quantity 10 and recept quantity is 05 then in delivery shedule tab I didn't got any open purchase order quantity means  05 quantity why?
    Thanks and Regards
    Anil Patil

    Hi Anil.
    Please check the following fields in schedule line:
    - 'Scheduled qty': 10
    - 'Delivered' (quantity): 5
    (This means the goods were partially delivered for the PO)
    If your situation is this you don't have to expect SAP to create new shedule line I think.
    I think you have to modify the schedule line manually if you want a 'Delivery date' different from that was defined in the line of the PO item.
    BR
    Csaba

  • Problem for Goods Receipt for Subcontracting Purchase Order

    Dear all,
    Presently, we are using SAP version 4.6C and we need to introduce GR for
    Subcontracting Purchase Order. We have developed a ABAP program to handle
    subcon Goods Receipt by uploading flat-files from our subcontractor. The
    scenario is as follows :
    Goods Receipt for Subcontracting Purchase Order
    1. In the ABAP program, function BAPI_GOODSMVT_CREATE will be used for goods
    movement.
    2. Data provided to the function are as follows :
    - Posting date
    - Document date
    - Material number
    - Plant
    - Storage location
    - Batch
    - Movement type (101)
    - Quantity
    - Purchase order number
    - Purchase order item
    - Movement indicator (B - Goods receipt for purchase order)
    3. The function will do data verification and automatically determine GI
    item for subcon stock:
    - Movement type (543)
    - Special stock (O - parts prov. vendor)
    - Material
    - Quantity
    - Plant
    Our problem is that :
    Only the GR item in the interface is to be transferred and the GI item is
    determined by the system. So, the quantity for subcon stock cannot be
    changed using this BAPI. Then the system will continue processing the goods
    receipt and create material document.
    Manually, by using transaction code MIGO, the user can display the subcon
    stock data and then change the quantity.
    By using transaction code MB01, after the user fills in all the GR fields,
    the system comes to line item 002 (subcon stock data) and then quantity can
    be changed.
    As per user requirement, quantity for GI item must be same with the quantity
    that has been transferred to subcon vendor in Delivery for Subcon
    (transaction code VL02N).
    We cannot achieve this requirement by using the BAPI mentioned above. Would
    appreciate any valuable help from anyone who is able to help us on this
    matter. Are there any other BAPI's that can help us to achieve the same
    result ?
    Thank you in advance and best regards.

    As far as i understood the problem I suggest u to create the
    BDC according to user actions that are performed in he manual
    operation.
    I can't say that the BAPI performs the exac solution what you want.
    I have done some BDC work using MB01 and suggest you to be careful
    and try to keep the complete in the logic as some chages in rows in BDC will
    change the complete scenario.And throw correct quantity val in correct
    material
    row.
    This methodology will help u even in mass uploads.
    Or in case of automation u can perform the call transaction BDC in
    background mode.
    so As per my understanding bdc program is the solution. pls try and let me
    know.

  • Acct determination for Account-assigned purchase order with keys not define

    Hi,
    I'm trying to post an IDOC of type BBPIV through XI to an R/3 system.
    The posted idoc in R/3 is in status 51 (Application document not posted) with the error message "Acct determination for Account-assigned purchase order with keys not defined in chart of acts WP2P"
    As per my understanding this is something related to FI.
    Long text of the error is "The system cannot generate an automatic posting because there is no account determination defined for Account-assigned purchase order with keys   in chart of accounts WP2P.
    Correct the account determination for Account-assigned purchase order"
    Please help me how to solve this.
    Regards,
    Rashmi

    Hiya,
    This looks like its a MM posting / transaction.
    You need to go to OBYC and maintain the account assignment. If you provide the business scenario (GR into Stock, Subcontracting, etc.) for the process, I may be able to help.
    VKOA is for SD account assignment and I don't believe you can use that here.
    Cheers.

  • Purchase order with quantity range value

    Hi All,
    I want to have PO price to be taken from vendor info with quantity based values.
    For ex: The vendor has fixed a rate for 500 qty with X rate. and above 500 qty Y rate.
    My scenario is i want to raise the PO with this rate. How can i do this?
    Note: If i do first PO with 300 qty, then rate it is taking is X*300
    Now if i do second purchase order, with 300 qty, then the first 200 qty should go with X rate and remaining 100 should go with Y rate. ie, this purchase order will have combination of X & Y rate.
    Please give the solution for this.

    hi...
    U can perform this pricing by doing some modification in ur conditon type...
    In M/06 open ur condition type and under Scale tab...chooose scale type ..here assign scale type "D" i.e. Graduated-to interval sc
    And config the scale in purchase-info record..
    S Type    s quantity     amount            
         to            200               X
                         300               y
    then it will calculate : 200X+100y=Z
    try this out...
    Hope it works,,
    Thnks
    Edited by: ashish2210 on Jul 20, 2011 3:20 PM

  • Service purchase order with quantity

    Hi all,
    Is it possible to create a service purchase order with quantity ?
    Our client is using sap b1 2005b pl39.
    Expecting you all valuable reply.
    Jeyakanthan

    Hi, Jeyakanthan,
    I guess there are 2 ways out for this:
    1. Define the Service as an item ...i.e. create aitem master for it.Then you can define the quantities for it.
    2. Use a UDF in the service type document as quantity and put a FMS to calculate the qty.
    Nagesh