Update price condition in scheduling agreement (ME32L)

Hi,
I have to update scheduling agrrement (ME32L).
The input data that i would like to update are price amount, validity start date and valdity end date.
Is there any function or bapi which can be used to update.
Any help in this would be highly appreciated.
Thanks,
Mandeep

hi
did you update the conditions and validity period of scheduling agreement?  If yes then plz send me the details of parameters
  ITEM_COND_VALIDITY           =
  ITEM_COND_VALIDITYX         =
  ITEM_CONDITION                  =
  ITEM_CONDITIONX                =
I am also facing the same issue.
waiting for your reply.

Similar Messages

  • Auto Update of conditions in Scheduling Agreement

    Dear experts,
    i have a requirement like this..
    when we create a scheduling agreement ...we enter material,vendor,target qty and validity date ,price and enter tax code.
    After that we maintain condition types Vendor, material and Plant level....
    So in the same scheduling agreement we are adding one more material and giving same tax code.....Is there any possibility,so that system should copy condition types when we choose this tax code....rather than entering again and again for each material....
    Please do reply me...
    Thanks and Regards
    MK

    Hi MK,
    Are you asking about pricing conditions or tax conditions?
    Tax conditions flow auto when you enter tax code
    Whereas pricing conditions if those are manual conditions have to be maintained
    manually
    for conditions to flow automatically you have to customize the condition type for "changes can be made" with manual entries indicator as B
    and maintain the condition record
    Diwakar
    reward if useful

  • Valuation Price error in Scheduling Agreement

    Hello Experts,
    I am getting inflated valuation while doing MIGO for delivery schedule.
    It always comes as more than price of material in scheduling agreement and varies from 1.5 times to 4 times.
    Example
    Material Moving Average price: 3
    stock : 0
    Purchase price: 3.05
    QTY RECEIVED 100
    Value of goods at the time of MIGO has 4.27 price
    I can give few more data
    Pr. Date Cat: 5
    Condition type is not group condition
    Moving average price changes to 4.27.
    This moving average price comes down to 3.05 once I do MIRO. But my , point is, why we getting inflated valuation at the time of GR.
    Please let me know if anybody has come across such issue
    Thanks and Regards
    Gyanesh Kumar Jha

    Allen
    please check the details
    Mater stock zero at the time of creation
    mov avg price 1 at the time of creation
    val class: 3000, price control V,
    scheduling agreement net price: 1.28(1.5 with tax)
    mat doc              mat no          mvt    date                qty   unit   value       Sch Agmt       item no
    5000002301     409031796     103     15.03.2011     100     EA     0.00             7500000075     1
    5000002302     409031796     105     15.03.2011     100     EA     256.41     7500000075     1
    Let me know if you can find any details out of this.
    Thanks and Regards
    Gyanesh Kumar Jha

  • Change Net Price of Scheduling agreement (ME32L/MEK2)

    Hi,
    I need to modify via ABAP program the net price of scheduling agreements.
    My current program edits price conditions through batch-inputs on MEK1 / MEK2 but they don't automatically update the net price.
    The ME32L allows editing of price conditions and automatically updates the net price, but is not suitable for a batch input.
    Any ideas?
    Thanks and regards
    Francesco

    Dear Frans,
    As per i know You can use ME32L for batch input,. you can try to record the script using SHDB.

  • Conditions in scheduling agreement.

    Hello Guru,
    I am creating scheduling agreement through ME31L.While entering conditions I am only able to enter few conditions like  gross price,discount etc.which are in pricing procedure RM1002.When tried to enter condition FRA1 got error "Condition type FRA1 is not in procedure A M RM1002".
    1) My query is how procedure RM1002 is picked up by system as when created normal order for same vendor purchase order pricing procedure is shown as RM1000.
    2) How for same vendor different pricing procedure are picked up in different document as procedure is picked up from schema group in vendor master.
    Regards
    Vinay

    Hi,
    Thanks for feedback.
    1) Upon entering  purchase organization data in ME31L i am getting pop up "Purchasing org.  xxxx is not assigned to company code.Please enter company code".Upon entering company code i can proceed ahead.
    But with same purchasing organisation  with same company code standard order is created without any pop up.
    2) yes Same vendor.
    3) No  vendor subrange
    4) It is not STO .
    Regards
    Vinay

  • Pricing Condition in scheduling agreement

    Hi Gurus,
    I'm working with scheduling agreements and I figured that whenever I create scheduling agreements, pricing condition PB00 gets defaulted to the scheduling agreement,
    Can you guys be kind enough to tell me what configuration is driving this?? How can we make changes to the config settings so that I can have a condition type of my choice assinged to the scheduling agreenment??
    More over I have a requirement to have a tiered pricing in scheduling agreement. I do know that this is driven by SCALES in SAP however as per my requirements I need to have SCALES per formulas. In the condition type configuration we do have a field for SCALES where we can assign the formulas but whenever I click on this field a screen pops up with some ROUTINES.
    Can someone tell me how can I define the ROUTINES and the ABAP formula for this ROUTINE so that I can have my tiered pricing conditions accomplished??
    Any feedback on this will be highly appreciated!!
    Thanks folks,
    Dhaval Joshi

    Hi Ramesh,
    Thanks for the heads up. I looked at the config for the schema dtermination and I see that the pricing procedure RM0002 has not been assinged to any vendor POrg schema in this configuration.
    I then looked at the config for the condition type PB00 --> pricing procedure RM0002 has been assigned to the condition type PB00 and since we don't have any entries maintained for RM0002 in the schema determination config I was just wondering if this is what is influencing the automatic proposal of the condition type PB00 in my scheduling agreement.
    Also can you please tell me what is a difference between a Purchasing Document (BIG) and Purchasing Document (Small) in the schema determination config.
    All I wanted to accomlish here is my teired pricing to work when I assign scales on the condition type in the scheduling agreement ( not in the PIR)
    What currently happening in my case is ....
    Example: Scale From 1 pc - 100.00 USD
    from 50 pc - 90.00 USD
    from 100 pc - 80.00 USD
    Target quant. 100 pc
    schedule lines 30 pc
    20 pc
    The problem is  that the goods receipt of 30 pc is valuated at the price 80.00 USD It always takes a lowest price on the scale.
    I've tried looking for OSS notes and also looked enough on the forums but I could not get any resolution to this question.
    I would appreciate if I could get any heads up from your side.
    Cheers,
    Dhaval

  • Update purchasing group in scheduling agreements

    Hi gurus,
    I'm trying to update purchasing group field in scheduling agreements, which are time-independent (EKKO-STAKO = ' ').
    In my environment, I'm not authorized to use CALL TRANSACTION statement.
    If possible, I'd need a way that works both in 4.6c and 6.0 versions.
    I have tried several options, but none works:
    -BAPI_SAG_CHANGE: "Scheduling agreements with time-independent conditions are not supported" (OSS note 1046794) (Also, this is not available in 4.6c)
    -BAPI_SCHEDULE_MAINTAIN: "Scheduling agreements with time-independent conditions are not supported" (OSS note 1046794) (Also, this is not available in 4.6c)
    -BAPI_AGREEMENT_MAINTAIN: Does not have the possibility to change field 'purchasing group'. (Moreover, it internally performs a CALL TRANSACTION).
    -ME_UPDATE_AGREEMENT_PO: I've been not able to change field 'purchasing group'.
    I'd be grateful about any hint. Thanks in advance!

    In case it is useful for anyone else, I have solved the problem using:
    CALL FUNCTION 'ME_UPDATE_DOCUMENT'
    Thanks anyway!

  • Pricing Conditions in Scheduling Agreement

    Hi All,
    When i create a Scheduling Agreement, i Want to Add conditions like Discount and Freight along with the net price.
    Where can i see these condition types as i see in Po?

    hi,
    After defining the material select the item and press shift +f6 ie. item conditions...
    and for header condition firstly go into the header details(hat button) and then press(ctrlshiftf4)
    You can see there to enter...
    Regards
    Priyanka.P

  • Price conditions in Shceduling  Agreement

    Hi All,
    I have one query:
    How to make the price conditions greyed out in Shceduling  Agreement of document type LP?
    I even tried out making the price and price unit field display in the field selection but was of no use.
    Any help highly appreciated..
    Regards,
    Abhijit

    Hi
    Try it out in SPRO- Material amnagement- Purchasing- Scheduling agreement - Define screen layout at document level.
    Then select PT0L and change the price into dispaly.
    It will work
    Regards,
    Raman

  • Problem updating Volume in Sales Scheduling Agreement

    Hi gurus,
    we have problem with Sales Scheduling Agreement. It's about volume of material. First, I create a Scheduling Agreement for material A, what is 100 CCM of volume in its register master material. I create several forecast delivery schedule. After, I modify by other reasons the volume of material A in master material to 200 CCM. What is the problem? The problem is when system creates the deliveries for Scheduling Agreement, the packaging is did in base 100 CCM of volume and not is for 200 CCM.
    Besides of this, after if modify volume in master material I will add new forecast delivery schedules, the volume is calculated based in old volume factor: 100 CCM.
    We don't understand this behaviour in system.
    Thank you!!!!

    Hi,
    The reason is, the link of updating automatically from material master data to sales SA is broken!
    You should double check the volume at item level in Sales SA, enter the sales SA, select menu>Goto>Item-->Shipping, see the value of field "Volume", whether it's 200 CCM, or not? I think it should still be 100 CCM, change it to 200 CCM, that will be okay!
    Good luck
    Z.T

  • Price changes in Scheduling Agreement

    Hi,
    What is the best way to handle price changes in a Scheduling Agreement? From what I saw, the validity periods of the prices maintained in a scheduling Agreement is based on the GR date. Is there any way we can change this? The requirement is to make the validity price work on the delivery schedule date.
    Right now, whenever a price change happens, we have to add a new line in the scheduling agreement. This doesn't seem right. Please advise.
    Thanks
    Ranjeet

    Hi,
    Your date for pricing is controlled by Pricing date category u maintain in Vendor master >Purchasing view
    If you select delivery date as your pricing and if there are many delivery dates the first delivery date is taken as
    the reference for pricing
    But if there is no much price variation between delivery schedule date and Goods receipt you can keep that as
    goods receipt date
    Check out whatever suitable
    BR
    Diwakar

  • Planned Conditions in Scheduling Agreement

    Dear Expert,
    We are using Scheduling Agreement for external procurement of materials,for few materials Condition like ZNMC Cess are applicable,In Purchase Order these conditions are automatically pickup if it is maintain  in MEK1,In Scheduling Agreement these conditions are not coming automatically,How to Maintain these conditions directly,Please advice
    Regards,

    SOLVED

  • Price Change in Scheduling Agreement

    Dear All,
    I have created a SA for one material. Here we want to procure that material for 10 plants/Company codes. So i have created 10 different line items. After partial GR the price got changed for this material. Now I want to change the price which effects from today onwards for all the plants/CC. Is there anyway so that instead of changing the price in all the line items, i will change once, so that new price will apply to all the line items. Looking for inputs
    regds,
    CB

    Hi
    There are 2 options.
    Either you have to change the price for all the line item in the scheduling agreement
    Or Change the price in the Purchasing Inforecord for all the plants and set the price date category as 5-GR Date. And change price date category in Scheduling agreement as well. In future you can maintain the price only in the Purchasing inforecord.
    Since the valuation area is at plant level you have no option to enter the price in one place to effect on all the plants.
    Hope it helps
    Thanks/karthik

  • Unable to create new price validity in Scheduling agreement

    Dear Experts
    We are SAP 4.7 version.
    We have 4 companies and 17 plants in same client server.We are facing problem in a particular company having two plants not able to change price in scheduling agreement with validity period.But in other company code allowing to create new price validity period.
    Any configuration missing out please help us to resolve the issue.
    Most urgent
    SS

    Hello Suresh,
    There are two possibilities
    1. Missing authorization :Check if you have the same authorization profile for maintaining data in all company code/plant/purchasing organizaiton.
    2. Release streatagy: Check if you have activated release procedure in such a way that once it is release it will not allow any changes in scheduling agreement.
    Hope this helps.
    Regards
    Arif Mansuri

  • Price Scaling behind Scheduling Agreements

    We create a Scheduling Agreement with reference to Purchasing Contract.
    Several of the Contracts have pricing scales behind the material, based on quantity ordered and these scales are also required behind the Scheduling Agreement.
    Our problem occurs when we goods receipt;  the valuation of goods is taken from the total amount being ordered rather than the quantity received e.g. The delivery schedule has a total scheduled quantity of 500KG; the price for 500KG = £3.50 per KG.  We have the first scheduled delivery of 250KG and a second to follow in 3 weeks.   The price for 250KG = £4.50 per KG.   The goods receipt of 250KG is valuated at £3.50 per KG but the vendor invoices us at £4.50 per KG.
    Is there a way to valuate the goods receipt in accordance with the price for the quanity received rather than the total scheduled quantity?
    We are using version 4.7.

    Hi Christine,
    I also found this User Exit EXIT_SAPLEINR_003.
    But i don't know how to pass in the GR qty which it is structure table (GOITEM-ERFMG)..
    I need to retrieve the qty to recalculate the price before the GR document is posting..
    Lina..

Maybe you are looking for

  • How do I determine the # of times a song has been down loaded; 7 is max?

    How do I determine the # of times a song has been down loaded? Is 7 max?

  • Why can I not open this now I have updated to version 5

    I updated to version 5 and promtly lost my google toolbar which I understand may be rectified later but today I could not open mozilla firefox at all either by icon or going into programmes

  • Grayed out

    Once I bring in a clip or multitrack from final cut to soundtrack pro...the options such as normalizing are grayed out. What am I doing wrong? I can play the clip fine but can't do anything to it, like normalize...all effx are grayed out.

  • Trouble displaying text in uploaded site

    The site is audiomed.com. The page is: http://audiomed.com/Audiomed.com/ClinicalAudiologyPDFs/Entries/2008/10/10Audiometers%3AGrason-Stadler.html The problem is two-fold: 1) in the box marked "Audiology: Clinical: PDF Files:" there should be larger,

  • Htmldb_item_popupkey_from_query - returning a value.

    Hello, I have created a dynamic parameter page, based on some tables that I have. I was using select_list_from_query to generate a select list from a query stored in my ref_tbl. I switched to htmldb_item_popupkey_from_query because the query was gene