Why SAP force GR non valuated for invoicing plan?

Hi Xperts,
Need some clarification of why SAP will force for GR non valuated when invoicing plan is chosen. Is there any BADI or user exit to make GR valuated for invoicing plan?
Thanks.

Thanks Priyanka,
But this "special" scenario is different, where there is a GR to be performed (physically and in system) and the business still need the physical invoice from the vendor before they perform the LIV/MRIS. And the invoice is a milestone invoice (partial invoicing plan (%)).
Example:
PO : Qty = 10 ; price = $10 ;
        invoicing plan :
                              01.01.09   50%    $50
                              01.02.09   40%    $40
                              01.03.09   10%    $10
GR : Qty = 6 ($60)
        Debit    Expenses   $60
        Credit   GR/IR         $60
LIV = 50% ($50- Qty 5)
         Debit   GR/IR         $50
         Credit  Vendor        $50
Conclusion is during GR, it can be any quantity but during LIV/MRIS, system will read the invoicing plan schedule.
I also believe (i've tried looking all BAdi exist in purchasing) that there is no user exit or BADI to make the GR valuated for invoicing plan.
Really need feedback from all other experts.
Thanks again.
Edited by: MM1974 on Jun 2, 2009 9:10 AM
Edited by: MM1974 on Jun 2, 2009 9:11 AM

Similar Messages

  • Why SAP is better than Oracle for timber plantation industry

    Dear Experts,
    I have to prepare a ppt regarding Why SAP is better than Oracle for timber plantation industry? please supply me some precious points that could convince my client to go for SAP rather than Oracle.
    I u have a ppt ready for this then please help me by sending that. Pleease help me asap.
    Thank u all
    Sankhajeet

    Hi,
    if anyone have any other docs or links on this...please send me...
    Thanks in advance
    krishna
    [email protected]

  • Why the ios 8 non is for iphone 4?

    why the ios 8 non is for iphone 4?

    Because iOS 8 requires a dual-core processor. The iPhone 4 has a single-core one.
    (113179)

  • Why isnt there a none option for the billing options ?

    Why isnt there a none option for the billing options ?
    It use to be there...
    Please solve this problem as i only download free apps...

    There should such an option only if you try purchasing a free app within your iTunes on your computer.

  • Payment terms for Invoice plan

    Hello All,
    I've a Partial Invoicing plan for my equipment purchase. The first milestone payment is along with Purchase order. Means need to pay immediatly.
    My PO is having payment terms - Payment 90days after end invoice month. This payment term is ok for all milestone payments. But for the first one, I need to pay immediatly.
    Is it possible to have different payment terms / bye pass payment terms for the first milestone?
    I don't want to use downpayment option for this.
    RaviChandran

    Hello.. Thanks for your feedback.
    But in IV, normally due date is calculated from baseline date. Base line date will be defined by IV creation/posting date (Based on IMG setting). So by making the START Date for invoice Plan as Past Date will not work.
    SS

  • Chnage log for Invoicing Plan

    HI Friends ,
    Need your help on the below issue
    We are making a customised PO change report
    We want to capture the details which was done in Invoicing Plan in PO line item
    I tried chaging the Invoicing plan in PO line item but the change log does not show that the chnages are done in Invoicing plan
    How to know from PO change report that a invoicing plan has been changed ? Which tables to be seen
    I checked the FPLA and FPLT table but not getting any clue on change log for invoicing plan
    Please help
    Thx
    Deva

    Hi,
    unfortunately there is no change log kept in the standard for the tables FPLA and FPLT. Please check in transaction SE11:
    Display technical settings -> "Log data changes".
    The logging flag defines whether changes to the data records of a table should be logged. If logging is activated, every change (with UPDATE, DELETE) to an existing data record by a user or an application program is recorded in a log table in the database.
    Unfortunately I can only confirm that there is missing functionality       
    for change management in area of MM invoicing plan. No change documents    
    are created in CDHDR and CDPOS tables for any change for invoicing         
    plan.                                                                      
    Regards,
    Edit

  • T. code for invoicing plan report

    anyone knows what's the T.code to get a invoicing plan report which has vendors infomation ? please reply.

    Hi
    T.Code for invoice plan is MRIS.
    or path Logistics->MM->Log.Inv.Verification->Automatic Settlement->Invoice plan
    Regards
    Raghavendra

  • User exit for Invoice plan settlement

    Hi
    Can any tell me the user User exit for Invoice plan settlement to display PO# on the check?
    All your efforts are appreciated.
    Thanks

    ref link below
    http://www.easymarketplace.de/userexit.php
    http://www.planetsap.com/userexit_main_page.htm

  • Gr for invoicing plan?

    Hi,
    Can we have GR for invoicing plan? If yes, what impact it will make? I no...than what is the reason?
    Regards,
    Satyendra

    Hi Satya,
    I think GR will not be ther for Framework Document pos.
    Multiple invoices can be processed. Main point is that invoices must be processed within the validity period spesified in PO. The total value of invoices must also not exceed the limit spesified in PO item. The validity period is spesified on PO Header Level, while the Limit is on Item level. The creation of Purchase requisition is Optional.
    Purchase Requisitions doesn't have validity period fields, although the limit can be spesified on item level. So if users create PR's then they could type the validity period simply as text in one of the long text fields.
    During invoicing, if the date is outside validity period or the amount is bigger, either a Warning or Error will occur. This setting is done in customising.
    Examples on where this business process can be used include: Services: example buying flowers, travel. Perticular if the receipt process is not very formalised. It is also sometimes used for utilities (water, electricity...).
    Look at processes where Financial invoices (no PO) are used. To improve control, a lot of vendor invoices could be moved to Blanket Order process.
    Reg,
    Ashok

  • Not working Billing Block functionality for Invoicing Plan

    Hi Experts,
    I am using Invoicing plan functionality to purchase materials by using Milestones from Network of Project System. The system is allowing to post Vendor Invoice (MIRO) without removing of Billing Block of Invoicing Plan from PO and the system should give error message because of non removal of Billing block.
    The following configuration was done in Invoicing Plan of PS.
    1. Assigned Date Category to Invoicing Plan Type (30)
    2. Assignment of Invoicing Plan Type to Network Profile
    The following configuration was done in Invoicing Plan of MM.
    1. Assigned default date category to Partial Invoicing Plan type
    2. Maintained Date category to Invoicing Plan type
    3. Assigned Date proposal category to Invoicing Plan Type
    4. Maintained Date Proposal to Invoicing Plan Type
    What are the changes needs to do in configuration or transaction to prevent to post vendor Invoice because of nonremoval of Billing block from Invoicing Plan?
    Please give me the solution.
    Thanks in advance,
    Rao

    Hi Rao
    You need to have the invoicing plan done in Project System (PS) under the project with Milestones and save the plan. On dong this, the system would generate a 'Reference Number'. This can be seen when you again go to the invoicing plan.
    Use this reference number in the MM invoicing plan to link the PS & MM plans. This would create a block automatically in MM which can be lifted only on confirmation of the appropriate Milestone in PS.
    Hope this helps
    Venu

  • PO Number and Line Item Number for Invoice Plan Number

    Hi Experts,
    Can somebody please guide me how to fetch the PO Number and respective PO Line Item Number for an Invoice Plan (FPLNR).
    In FPLA Table, PO number is available but line item number is not available.  If a PO is having multiple line items, different line items will have different Invoice Plan numbers.
    Thanks in Advance.
    Radha Krishna Madineedi

    Hi Ramesh,
    I have got the answer after posting this thread.  We can get the PO Number and the Line Item from EKPO Table itself by passing the FPLNR.
    Anyway,  thanks for your reply.
    Regards
    Radha Krishna.

  • Confirmation of Finish Goods Non Valuated for MTO

    Hello SAPper Friends,
    I was doing a Make to Order production with Strategy 20. When I was doing the confirmation with at least four operations, in the first operation was fine, movement type 261 was posted for the components and also in the last operation I have successfully confirmed the production order for the Finish Goods. However when I checked in CO03 - Display Production  Order > Goto > Documented Goods Movements, the Finish Goods has a goods movement = 4 - Goods REceipt for Production, Movement Type = 101 with D/C indicator = S with the Amount in LC = 0.00.
    It was only now that I have taken notice of this. How can I check cost of the production order if these is no cost provided by te confirmation? Please assist me to have this validated.
    Many Thanks,
    Nap

    Hello Mario,
    Thank you very much for your assistance. Btw, I have informed already the client of the strategy 20 that will answer their problem regarding the MTO, i was not aware of the product costing. I have checked that there is a strategy group 25 that might be resulting with a cost for the production of the Finish Goods.
    I need to check on this, again.
    Many Thanks,
    Nap

  • Non valuated Goods Receipt for materials with multiple account assignments

    We have been using multiple a/c assignments for services on purchase orders for sometime with no issues.  Recently we used a multiple a/c assignment distribution for a material P/O.  this didn't work the same and the Goods Receipt was set as non valuated.
    This leaves the cost showing as a commitment and we do not get any actual costs charged at the GR point until we get and post the invoice.  This only happens with multiple account assignments, all material P/O goods receipts for single assignments get valuated.
    Were not sure why this happens, and want it treated the same.  Is there any way we can get these valuated the same way single assignment materials or multi assignment services are.
    The non valuated GR flag is getting set automatically, but we can't see where this is coming from for this scenario, so were a bit stuck.
    Any advice/direction would be greatly appreciated.
    Thanks
    Graham

    Hi Deshamol, No the materials are all valuated, as mentioned, they all work fine when used as single a/c assignment.
    Anupam, Your answer doesn't make sense to me, this is 1 line on the P/O, therefore 1 material.  It can't be both valuated and none valuated for each a/c assignment. 
    I have read in a note there there is a business function that you can apply to get this working, has anybody tried it?
    Thanks
    Graham

  • When posting GI for Non valuated material in Delivery geting error (M8147)

    Hi Experts
    We have a problem that we are trying to send a material from one plant in one company code to another plant in another company code (Inter Company Stock Transfer Order). The material is of type Non Valuated (So it has no valuation class). The PO Order type used and the PO account assignment category is of type saying GR Non Valuated.
    Problem is in the outbound delivery (movement type 645 determined) when posting GI do we get a account determination error (M8147 = Account determination for entry 1000 GBB Z001 not possible), saying that no account could be determined.
    Our understanding is that the GI for the delivery demands a Valuation, which we can not do as the material is NON Valuated.
    How to set the GI non valuated for the outbound delivery, so we can avoid this error? please help
    BR

    >
    Krishna Rao wrote:
    > We assigned the GL for GBB in OBY. But, still the error is coming. Is there any other setup we need to do for Non Valuated material to post goods issue from delivery?
    I cant believe that the same error message is coming up after the maintenance.
    you either maintained an entry at a wrong level within GBB or the message must have changed.
    Make sure that you take any information of this message into account (even the spaces)
    the message is certainly not like you posted here: Account determination for entry 1000 GBB Z001 not possible
    the message carries 4 variables , not only 3

  • Splitt valuation for non valuated material

    Hi all,
    Is it possible to make splitt valuation for non valuated material? if yes how?
    Our business scenerio
    Large no of spare parts (ERSA).Divide spare parts material type into 2,
    1 for valuated and another for non valuated,
    For non valuated spares,copy from ERSA make  it ZBLB for non val spares
    now
    How to make the split valuation for ZBLB material type material's ??
    Do u have any idea ??
    Regards,
    Hareesha

    Hi
    Split valuation is the concept used for individual valuating of different lots of same material.
    Here you have created a new material type ZBLB from ERSA for maintaining non-valuated materials. There are several significant points in your actions.
    1) When u  are able to maintain materials seperately with different material types, what way u want to use split valuation concept?
    2) As the non-valuated material implies for no value updating, the material type does not provided with accountign view. So no valuation class and obviously no valuation type. The prpcurement of non valuated material will be account assigned.
    3) For non-valuated materials, either u have to use standard material type UNBW or copy from UNBW. donot copy from ERSA.
    I hope your doubts are cleared. Please come out with your comments if any specific.
    warm regards
    sairam akundi

Maybe you are looking for

  • Ipod nano is not recognized by itunes.  it is also locked and no password known

    Ipod Nano 4th generation (the slim colored one) - the screen is locked - didn't set a passcode.  Also will not sync with itunes so can't reset that way.  When plugged into computer cycles between being 'connected' to the black Apple screen.  I have W

  • Error Executing J2EE server PLZ help

    Hi All Im using Windows 2003 professional J2SDK 1.3.0, J2SDKEE1.2.1 Please help me in this...can't able to start the server. When I gave j2ee -verbose, it gave the following result. D:\>j2ee -verbose J2EE server Listen Port: = 1049 org.omg.CORBA.INTE

  • I have a plug-in that won't stop 'waiting' when I try to install it. How do I get it removed?

    I have a plug-in I've tried to download from another website. For some reason it got stuck 'waiting' during installation. I want to get rid of it so I can try again, but I can't do anything.

  • MW600 first hang until battery ends within 7 days

    Hi I have purchased a new MW600 wireless head phone from Amazon UK (I am in London) and it has hanged first time within 7 days of working. It was hangcompletely and it was showing full battery icon and buletooth icon only. I can not restart it any wa

  • Nester inner joins

    SELECT order_head.ID col FROM order order_head INNER JOIN customer customer_2 ON order_head.customerID = customer_2.ID WHERE order_head.orderDate BETWEEN '12/12/2001' AND '12/12/2009' AND order_head.ID <> 0 AND customer_2.LastName = 'smith' AND order