% wise PO Creation

Hi
I want to create a PO to a vendor as per the below format. How can i do. The payment want to be released as per the below % as per the period specified in the PO.
Scope Study - 10%
Configuration - 25%
Realisation - 35%
Go Live - 30%
Vijay

Hi
I hv created a PO with doc type FO and
Validity Start  01.01.2009
Validity End    30.04.2009
Item text SAP Implementation
Value 10,000.00
Inv. plan type  20 Sample Partial Invoice Plan
Start date      20.01.2009 01 Today's Date                      Reference       0000000184
Invoicing Plan
31.01.2009     0010     Project stage     20.00     2,000.00      INR     30     1     A
28.02.2009     0003     Contract Conc     50.00     5,000.00      INR     30     1     A
31.03.2009     0012     Project stage     30.00     3,000.00      INR     30     1     A
I did MIGO.
When i try to do MIRO at that time the value is not flowing from PO to MIRO which i required to pay to vendor as per the invoicing plan
In MRIS am getting a msg as
No documents selected
Message no. M8702
Diagnosis
There are no documents that comply with your selection criteria.
Procedure
You can enter new selection criteria or exit processing.
Pls tell me wats going wrong?
Vijay
Edited by: Vijay on Jan 20, 2009 1:43 PM

Similar Messages

  • Network wise PR creation in CJ20N (PS)

    Hi all,
    I have one requirement regarding PR creation through CJ20N. In PS scenario, under one project there will be number of WBS elements and under each WBS element number of network will be there and under each Network there will be number of activities. We will add materials under these activities. There are two type of PR creations by releasing networks in CJ20N, they are
    1) Network wise PR creation - through the network PR number will be same and line items will be different.
    Example : P->W->N->A1-> M1   ---> PR1/1
                                            M2  ---> PR1/2
                                    A2-> M3  ---> PR1/3
                                            M4  ---> PR1/4
    2) Material wise PR creation - for every material, PR number will be different.
    Example : P->W->N->A1-> M1  ---> PR1/1
                                             M2  ---> PR2/1
                                    A2 -> M3  ---> PR3/1
                                             M4  ---> PR4/1
    Through customization, we can create Network-wise PRs or Material-wise PRs. But my requirement is to create Activity-wise PRs, in which PR number will be same with in an activity and it will differ with another activity under same network.
    Example : P->W->N->A1-> M1   ---> PR1/1
                                            M2  ---> PR1/2
                                    A2-> M3  ---> PR2/1
                                            M4  ---> PR2/2
    For this, there is no option in customization. Please let me know is this possible through enhancements/BADIs? or is there any other way to do?
    Thanks in Advance,
    Siva Sankar.

    Dear All,
    We had a similar requirement in one of our client, the details are as follows:
    Client’s requirement was to generate plant wise number range for Purchase Requisition created in Project System though T-Code CJ20N. Standard SAP don’t have any facility for plant wise document type or plant wise number range for Purchase Requisition created in Project System.
    Plant wise document types and its number ranges are already defined in system but as per standard settings of PS system - PRs created from project system are considering only for one document type i.e. maintained in the configuration. There is no facility to select document type as per plant in CJ20N in standard SAP.
    We have implemented two user exists EXIT_SAPLCOZF_001 & EXIT_SAPLCOZF_002 for attaining the specified functionality.
    Please let me know if this is useful to you, I will update the complete solution in the thread.
    Regards,
    Dhaneshwari

  • Date wise archive creation

    Hi Team,
    is there any parameter to set for automatic creation of archive date wise folder and backup date wise folder in oracle database 10g or 11g ?
    Thanks & Regards
    Ravi Kumar

    993467 wrote:
    Hi Team,
    is there any parameter to set for automatic creation of archive date wise folder and backup date wise folder in oracle database 10g or 11g ?
    Thanks & Regards
    Ravi Kumar
    If you use the Fast Recovery Area, by default Oracle will dump archivelogs into date-named directories ("directories" = "folders" for those wedded to their GUI)

  • Need Date wise Vendor Creation Report

    Any one knows How to check How many vendors are created in particular period?

    Hi,
    Using T-code MKVZ - List of Vendors : Purchasing, give input data purchasing organization, Account Group and execute the report display all vendor details which is already stored in data base and report top line click Change Layout button(blue color) it will open new window right side required data field selected and click <--- mark selected field come to left side and then press tick mark. now the report shown vendor related all data's are displayed.
    Hope, it is useful for you.
    Regards,
    K.Rajendran

  • Regarding material wise purchase order creation with reference to pr

    Dear sir
    I have a scenario depending on the  material wise pos creation
    I have two type of material
    1) raw material
    2) consumables
    When user will create purchase order for raw material, system should ask purchase requisition. ( i.e with out purchase requisition for raw material , system should not allow to create the purchase order)
    Where as for all consumables materials system should allow to create the purchase order
    Without purchase requisition also, for user.
    Regards
    Jrp.

    You have to create two different document type for purchase order.
    1) Raw Material Purchase
    2) Consumables Purchase
    You can create two different document type for purchase order with below mention path: -
    SPRO >> Materials Management >> Purchasing >> Purchase Order >> Define Document Types.
    After define two different document type, You can change field status for two different document type with below mention path.
    SPRO >> Materials Management >> Purchasing >> Purchase Order >> Define Screen Layout at Document Level.
    Select document type and change field status of purchase requisition.
    Regards,
    Mahesh Wagh

  • Document type wise PO with refer PR

    Dear All,
    my clients requirement is that Document type wise PO creation with refer PR & Purchasing group is mandatory.
    but some document type wise PO generation withour PR & purchasing group is mandatory.
    please suggest me.
    Thanks
    Shital

    Hi,
    1. Create Seperate document types one for PO with PR and one for PO without or with PR.
    Follow the pthe SPRO->MM->Purchasing->PO->Define Document types
    Here copy from the standard document type NB and create your own.
    2. Cretae two seperate field selection grps one with PR field manadatory and one with PR field non mandatory.
    Follow the pthe SPRO->MM->Purchasing->PO->Define screen layout at doc level.
    here copy from the standard fields selection grp NBF and create your own two diffrent field selection grp.
    Then once created go to selection group Ref data item and for Purchase requisition as required entry and save it for one field sel grp and for the other as optional.
    3. Assign thease fields selection grps to document types as per your requirement.
    Follow the pthe SPRO->MM->Purchasing->PO->Define Document types
    Define new numbe ranges for your both the document types.
    hope it helps.
    Regards,
    Sujoy
    Edited by: Sujoy on Jun 24, 2009 7:09 AM

  • Problem in Workflow during activity step with "Requested start" time.

    Hi,
    I am working on SAP workflow.
    In my workflow there is a activity step (wait step) where the workflow should wait before going to step after that wait step. To achieve this, I have used requested start as +10 min with WIS workitem creation. After 10 min, the workflow should proceed to further step but my workflow does not go further.
    It was working good I tested couple of days back but now it doesn't. Can someone please help ?
    Thanks.
    Regards,
    Rajesh.

    Please check the settings in SWU3. Most probably  the settings is not correct. You will get a lot of discussion from this forum if you search with SWU3.
    Thanks
    Arghadip

  • Alert intimation as mail

    Hi SAP Experts,
    Is there be any option with the help of which i can have a mail in my inbox if the planned completion date of an activity has crossed and its not been confirmed.
    let say there is an internal activity with duration 2 days so my question is if any how the particular activity is not getting completed in 2 days so just to have a remainder kind of thing i need to check the same what is wrong with the completion.
    can i have a mail in my inbox that the particular  activity is late or not completed so that i can revaluate the thing and work on the same.
    so its kind of alert which shud come when a particular work has not been done as per the schedule.
    let me if it is possible to have the same in standard sap ps  or any other option i can try for the same.
    Regards,
    Kamal rana

    Hi Kamal,
    can i have a mail in my inbox that the particular activity is late or not completed so that i can revaluate the thing and work on the same.
    You need to use Deadline monitoring for this. Add a Latest End for the activity you need to track.
    Add a time duration of 2 days and create a Refer date/time as 'WIS workitem creation' to it. Action 'Modeled' and give a recipient message.
    In the branch created, add a Send mail step to send reminder mail to you. You would recieve this mail if the activity is not acted on within 2 days.
    Hope this help!
    Regards,
    Saumya

  • Details about BSP...

    Hi can any one give me details about BSP? thanks in advance

    Please see the step wise BSP creation example:
    http://www.sapdevelopment.co.uk/webapps/bsp/bsp_exam.htm
    For execution see more details on thread:
    BSP Execution
    Thanks

  • How can we restrict creation of enquiry VA01 plant wise

    How can we restrict creation of enquiry VA01 plant wise
    Pradeep

    Hi Pradeep,
    You can restrict through the user exit.
    MV45AFZZ ( MOVE_FIELD_TO_VBAP).
    Check the entered plant here and the user name.
    Make a custo table with plant and user name combination.
    Make a select query to check with the custom table entries.
    If it fails , give an error message and exit from the screen.
    Hope this helps.
    Regards,
    Deepak Kori

  • Creation of Z reports for client adding two more column that is Purcahse order and delivery dates with Internal order wise

    HI Experts,
    Can any one help me to add two more column for standard report that is purchase order and delivery dates for Internal order wise.
    But here problem is when i checked with ABAP team they said there is no standard functional module to add two column.
    Please note below :
    Selection criteria is: 1) controlling area
                                  2) Fiscal Year
                                  3) From date and To date
                                  4) Plan Version
                                  5) Order Group.
    My client suggested : S_ALR_87012993 this tcode to run, but we suggested with S_ALR_87013019 as in this tcode we can get all the details
    That is required output fields, as it is showing all details but on yearly basis, he wants this to be period wise and also Abap team is not able to find standard functional module in the second tcode as well.
    Out Put fields to Pop up
    1) Orders.
    2) Budget
    3) Actual
    4) commitment
    5) Alloted
    6) Available
    These are two additional column
    7)Purchase order
    8) Delivery date.
    Require your help to know which all tables are included to extract above out put fields please help me.
    Thanks in Advance.
    Regards,
    Sudesh

    Hi Preeti,
    Thanks for reply, can you please let me know is there any other way to show the output fields.
    As my client is very specific to run the report on period wise, i also tried to execute the standard tcode S_ALR_87013019 and were we are getting all the required outputs to pop up but this is on year wise, but we can also check by period basis by clicking on order number and actual period basis where we can see period basis.
    Also one more question,what is the commitment table which is popping up in this, please advise.
    Thanks in advance.
    Regards,
    Sudesh

  • Purchase order document type wise park invoice creation authorization

    Dear Experts,
    at present our purchasing person is creating park invoice against all type of purchase order,we want to restrict him for certain purchase order type for creation of park invoice,is it possible what is procedure,please advice
    Regards,
    Shyam Shinde

    Shyam,
    As said by varma, if you looking for  FB60/FV50?then u need to search before you post.
    Thanks,
    Sri

  • Creation Vendor/cusotmer master location wise

    Hello,
    Client requires to create single vendor/customer code and then within that code, location wise data should be maintained
    (f or. e.g address, bank details, tax details etc.).
    So client have better control over vendor/customer bookings/ payment/ receipt, Better authorization, avoid creating multiple vendor codes.
    The same functionality is not available in SAP.  In SAP we need to create as many vendor codes as locations.
    The solution envisaged is as below:-
    Vendor code XXX01 party ABC. Location - Delhi/Mumbai/Chennai.
    And at of these location level further details should be maintained ( like address/bank/WHT etc.)
    Therefore at primary level the vendor/customer code should based on following parameters
    1. Company code
    2. Account Group
    3. Location.
    Can any body guide on the above issue.
    Thanks & Regards
    Mukesh Lunia
    deleted

    Not possible location wise.
    General data- client wise
    Company code data-Company code wise
    S.org/p.org-Sales/purchase organisation wise
    Rgds
    Murali. N

  • Restricted WBS during PO Creation : Department wise WBS to be allowed for PO Creation

    Dear SAP PS Members
    as per the SAP Standard anyone can choose the account assignment checked WBS for PR/PO Creation, however we are facing issues with this as end user may choose other department WBS out of understanding.which leads to reporting inconsistencies showing wrong picture of cost and assigned values.
    is there any way by which we can allow each department to use only their department WBS for Procurement (materials and services).
    that means SAP system shall control and avoid any transaction or postings on non relevant WBS's for the respective Department. ( other Dept. WBS)
    please provide the ideas or workable logic ! 
    Many Thanks
    Avinash Shelke

    How you are specifying that XXX-XX-X WBS is relevant to ABC department and so on? Are you using any custom field like 'Owner code' etc. to specify it?
    Through std. customizing its not possible but through development it can be done as follows:
    If you are maintaining department/owner code field n project structure for wbs then use this department-WBS field combination to validate it during PO, you need to maintain 'Department' field as a mandatory field in PO master (check whether it's custom field or std. in PO,i think it would be a custom one).
    Once department field appears in PO that validate it from 'department-WBS' combination of project structure (use these fields from table PRPS) and pop-up warning/error message accordingly. You would require stand. user-exit for it in PO search for it in MM forum.
    And if, you are not maintaining department/owner code field in WBS master then maintain it in a separate table (WBS->department) and validate in the same way as explained above.
    Thanks.

  • Shopping Cart Item wise PO or PR creation in backend system.

    HI Experts,
    I have one doubt in the shopping cart,can any one of you tell me the customizing setting for the same.
    Whenever we create shopping cart either PO or PR is created in backend system as per the requirement of client,there must be some customizing settings need to be done for the same.
    What is that customizing settings????reply for both PR as well as PO.
    Also when we have multiple line items in Shopping cart and if we want to create PO for one line item and PR for other line item in the back end system then how to change this setting for achieving item specific customizing?????
    Thanks in Advance,Please help.
    Thanks & Regards,
    Paresh Sojitra.

    Hi,
    1. Using Business Add-In BBP_CREATE_BE_RQ_NEW you can change all the data that is transferred to the backend system for generation of a requirement. This includes, for example, item data, account assignment data, and texts. You can access all the shopping cart data in the method FILL_RQ_INTERFACE for generation of the backend reservation via the BAPI BAPI_REQUISITION_CREATE
    2. Using the Business Add-In BBP_CREATE_BE_RS_NEW, you can change all the data that is transferred to the backend system for generation of a reservation. This includes header and item data.
    All the shopping cart data is available as input parameters.
    3. With Business Add-In BBP_CTR_BE_CREATE, you can replace or supplement existing contract data in SAP Enterprise Buyer with your own backend structures and tables. Enterprise Buyer calls this BAdI before it makes the RFC to the backend system to create a contract.
    For more details go through SE18 Badi documentation..
    Q Also in the the above case if i want to create Reservation for one item of shopping cart then what to do???????? and what to do for Contract creation in backend system????
    A. When you create SC for item, if the item was stock item in backend system automatically created reservation as mentioned in above settings.
    in classic scenario contracts are created in R/3 System.
    Thanks
    prasad.s

Maybe you are looking for

  • Condition colum in VA01 is in invisible mode, ie. gray color

    Hi expert, When I create VA01, I would like to change my price. But I am getting condition tab in gray color. If it white color only we can change the price and update any manual condition records. But I am getting only under condition tab in VA01 in

  • Safari is not loading anymore any webpage, other browser works fine

    A few days ago I changed router, and set a DHCP Manual ip for my devices on the new one. Now it's back on automatic as it used to be. I don't know why Safari is not working anymore, I am trying to open various pages but it won't load anything. This i

  • Dreamweaver CC Continues to Crash

    I have been subscribing to CC for nearly a year now and I have NEVER been able to use Dreamweaver CC without it crashing.  Adobe Technicians have blamed my computer, have blames it on my Fonts, Have blamed it on my coding.  They have told me to remov

  • Dreamweaver crashed by opening a PHP-File

    Since two days I can't oen any php-Files. If I will open a File with the extension .php Dreamweaver crashed. What can I do? I search for a soluten now more then one day. Regards Paul

  • How can I change GLOBAL1_CURR_CODE ?

    in DAC I set parameter $$GLOBAL1_CURR_CODE = EUR But when I run Execution Plan in the session log SIL_GlobalCurrencyGeneral_Update I see row: Severity Timestamp Node Thread Message Code Message INFO 4/20/2009 12:33:30 PM node01_OracleBI DIRECTOR VAR_