Route determination for PO and Delivery

Hi Experts,
I would like to ask how to set up route fro deliveries and Stock transport orders.
Hope you can help me on this.
Thank you very much.
Regards,
Mylene

Working with Route Schedules
Use
Using a route schedule, you can control periodic customer deliveries of a particular shipping point to different ship-to parties (for example, customers or stores) in a certain sequence on a certain defined route. The planning is based on calendar weeks. The period unit is a day. Also, route schedules have a goods issue time.
The route schedule function supports the following processes:
Periodic deliveries from a shipping point to stores or customers are planned in advance on the basis of calendar weeks and weekdays, also without reference to particular deliveries.
You adapt the schedules in the specific cases to the planning. For example, you can plan a GI date for a Monday at 8 o’clock, without knowing the exact date or the delivery.
On the basis of this planning, deliveries that are to leave the warehouse at the same time are combined into groups. In Shipping you can thus distribute the workload by processing these groups.
Features
You can display all deliveries for a particular route schedule on a particular day, for a particular shipping point, and so on. In this way, for example, you can choose picking lists on the basis of route schedules.
You can create route schedules for the following documents:
Sales orders
Stock transfer orders
Deliveries that are based on sales orders, store orders, stock allocations, stock transfer orders, and deliveries without reference.
The route schedule is displayed in the header data of the delivery. For each delivery within the route, the system prints the expected date and the expected time of the delivery (on the basis of the local time at the original shipping point) on the delivery note; the goods issue date is used for the goods issue posting and the stock valuation.
In Customizing, you define for each shipping point, delivery type, stock transfer order, and order type whether or not route schedules are to be used.
You create the route schedules in the master data for shipping. Here you define the route schedule determination and the validity period for the route schedule and the itinerary.
As soon as the legs have been defined, you can branch to another screen to determine the actual itinerary, as well as the time (days/hours/minutes) required to get from one unloading point to the next. In this screen there is a field beside each leg. Here you can enter the number of the itinerary for the individual legs of the route. If, for example, you enter legs A and B, but assign itinerary number 2 and 1 to these, B is the first unloading point on this route. If you press Enter, the legs are displayed in the correct sequence.
At the same time it is possible to control the route schedule determination for each delivery type, stock transfer order, and order type. It is activated in the same manner as the repeated route determination. If the route schedule determination for a delivery is active, the system automatically attempts, during creation or change of a delivery, to determine a route schedule and records this in the delivery. Simultaneously, the scheduling is adjusted. All the deadlines, for example, the transportation planning time, the picking time, the loading time, the goods issue time, and the delivery time can change.
Deliveries with the same route schedule and the same date can be selected for the same picking run and the same goods issue. The same procedure can be used for printing delivery notes and freight lists, for the grouping of deliveries into shipments, and for confirmation of picking orders.
Deliveries that leave the warehouse at the same time, but are assigned to different routes and can therefore have different route schedules, can be combined together and processed through the creation of wave picks. The only condition is that all deliveries have the same goods issue time.
Route Schedule Determination
If exactly one route schedule is defined for a particular combination of requirements, then the system will use this.
For each combination of requirements for the route schedule determination, you can define several route schedules.
In the case of a delivery without a preceding document, the system determines the route schedule with the earliest delivery time at the ship-to party.
In the case of deliveries based on preceding documents (for example, stock transfer orders), the system searches for the route schedule that is nearest to the planned date/time of the delivery. The system uses the following search algorithm:
- If a route schedule exists for the specified time, this is assigned to the delivery.
- If there is no route schedule for the time specified, the system searches for the previous route schedule up to the GI time.
- If there is no route schedule from the GI time to the planned time, the system searches for the next route schedule in the future and assigns this to the delivery.
Requirements for Route Schedules
The route schedules are determined by the following conditions:
· Shipping point
Where are the goods coming from?
Ship-to party and unloading point
Where are the goods going to?
Shipping condition
How are the goods being shipped?
Transportation group
Which goods are shipped?
® For example, which type of goods?
Calendar week / year
When are the goods to be shipped?
If you do not explicitly enter the week and the year, the entry applies for each calendar week. If you enter a week and a year, the route schedule only applies for this week.
You can only use route schedules if you have maintained the working times and therefore at least one of the following times in minutes:
· Transportation planning time
· Pick/pack time
· Loading time
· Transit time
A route schedule can leave the warehouse exactly once in a week. If a route schedule runs several times, either on several days or several times a day, it must be copied to another route schedule.
Special schedules and public holiday weeks are possible.
Processing a Route Schedule
Implementation Options
Wholesale trade customers and stores can receive goods at regular intervals. These delivery rhythms have an influence on the workload in the warehouse. To help delivery planning, the route schedule serves as a tool for planning regular, repetitive customer deliveries on a particular route. At the time of planning, potential deliveries that have not yet been created are grouped in the route schedule. When the deliveries are created, the system can automatically determine a route schedule and assign it to the delivery. All deliveries with the same route schedule and the same date can be processed together in the shipping point. All these deliveries leave the shipping point together at a particular time. They are distributed along the same geographical route.
· Deliveries for route schedule MO10H leave the shipping on Mondays at 10:00 in the direction of Philadelphia.
· Deliveries for route schedule MO10M leave the shipping point on Mondays at 10:00 in the direction of Boston.
· Deliveries for route schedule MO10S leave the shipping point on Mondays at 10:00 in the direction of New York.
You can print picking lists for all deliveries that belong to route schedules MO10H - MO10S together.
Prerequisites
If you want to define route schedules, you must perform the following tasks:
- Activate the route determination
- Activate the delivery scheduling
- Activate the route schedule for your shipping point and make the following settings:
Transaction
Activity
Delivery
Route schedule determination for delivery type
Sales order
Route schedule determination for sales document type
Stock transfer order
Route schedule determination for delivery type
Set delivering plant and order type
Maintenance of the itinerary should be uniform for all the route schedules used. To ensure exact planning, maintain the itinerary for all the route schedules. If rough planning is sufficient in this case, you do not need to maintain the itinerary for a route schedule.
If you do not define any goods accepted times in the customer master for the unloading points of the ship-to party, the system assumes that the goods acceptance is possible at any time. The system determines the delivery time from the departure time in the route schedule plus the required traveling time to the ship-to party, as set in the itinerary (specific move time). This delivery time must be within the goods acceptance time of the unloading point of the ship-to party. If not, the respective route schedule is not determined during delivery creation.
For more information on route schedules, refer to the Implementation Guide (IMG) under Route Schedules.
Process Flow
Select the shipping point you are working for and enter the number of the route schedule.
Enter the data that defines the route schedule more exactly:
- Description of the route schedule
- Route
- Departure day (weekday)
- Departure time
You define the route schedule determination. When you create the delivery, the system can determine a route schedule on the basis of the following data:
- Shipping point
- Ship-to party
- Unloading point (if available)
- Shipping condition
- Transportation group
- (Optional) year/period
You enter this data (with the exception of the shipping point already entered in step 1).
You decide whether or not you wish to define the itinerary for this route schedule.
(Optional) You enter the itinerary and, if required, also the travelling time.
Creating a Route Schedule
Choose Logistics ® Logistics Execution ® Master data ® Transportation ® Routes ® Route schedule ® Create.
In the screen Create Route Schedule: Initial Screen, enter the shipping point and the number of the route schedule.
If you wish to use data from an existing route schedule as a reference, enter the respective shipping point and the number of that route schedule. If you also wish to copy the itinerary, check the Copy itinerary box.
Press ENTER .
The Create Route Schedule screen appears (here the system displays the number you just entered for the route schedule and the shipping point).
Enter the following data:
Description of the route schedule
The respective route
Departure day (weekday)
Departure time
In the Determine route schedule section, enter the following data:
Ship-to party
Unloading point (if available)
Shipping conditions
Transportation group
(Optional) Year/period
If you wish to define for this route schedule the itinerary according to which the individual ship-to parties are to be delivered to, choose Extras ® Itinerary.
The Create Itinerary screen appears.
Enter the itinerary and, if necessary, the travelling time.
When you determine the travelling time from one ship-to party to the next, you should include the wait time of the vehicle at the previous ship-to party.
If the same route is planned for several route schedules, define for each of these route schedules the same itinerary that should correspond to the stages and legs of the route.
Choose Goto ® Back.
You return to the Create Route Schedule screen.
In this screen, the Itinerary maintained field is now selected. If you wish to add other ship-to parties, you must also maintain the Itinerary for them.
Check your data and save your entries.
Reward if helpful...
Regards,
Diogo

Similar Messages

  • Automatically route determination for Normal PO - Inbound delivery

    dear MM experts,
    we are successful route determination for STO & SO, now we wud like to know whether normal PO, route automatically determined or not.
    -while creating PO, we don't find the shipping tab, unlike in sto,
    or
    -while creating inbound delivery
    Please help in giving solution if any one as already implemented
    thanx in advance
    srihari

    Hi, did you solve it? I am having the same problem.

  • Route determination for subcontracting deliveries

    Folks,
    I am creating subcontracting PO's for subcontracting and after creation of the delivery, there is no route determined. I've maintained the transortation zone in the corresponding ship-to / customer master of the vendor, I have setup route determination, I've maintained transport relevancy for delivery type LB and item categroy LBN, though still no route is found.
    When I create a sales order for the same customer master record, the route does get found.
    any suggestions?
    MdZ

    Resolved: route determination for weight group had to be maintained as well.

  • Automatic route determination for sales order

    Defined
    Transportation Zone  sold to party -0000000002
    Shipping conditions -01
    Transportation group in Material master -0001
    Transportation zone ship to party - 0000000003
    Assignment made -
    Dep country zone -0000000002
    Dest country zone -0000000003
    Sc -01
    Transportaion group -0001
    route -zroad
    departure zone and destination zone is assigned to respective customer masters. and above assignment is made in IMG for route determination for order. But when i create the sales order route is not getting determined..i wnet to most of the threads in this form..but could not find a thread for route determination for sales order

    Aju Joseph
    -Do the shipping point detremination  in OVL2.
    -In Route Determination- Maintain Country & Transportation Zone For Shipping Point
    -Here you will find the Shipping point  whatever you have created in Enterprise Structure  which is in grey i.e you cannot change.
    -Just assign the departure zone which you have created in Transportation zone-000000002 to required shipping point & save it.
    --Raise the sales order & check the output
    Let me know if your problem is solved
    Regards
    Pradeep

  • Route determination for sales order returns

    Folks,
    I would need to have route determination for a sales order return (RE order). Currently a route is determined but this is the route for delivering to the customer. I've setup a new route for returns and maintained the determination. Despite above settings, the return route is not determined. Any suggestions?
    MdZ

    Folks,
    I would need to have route determination for a sales order return (RE order). Currently a route is determined but this is the route for delivering to the customer. I've setup a new route for returns and maintained the determination. Despite above settings, the return route is not determined. Any suggestions?
    MdZ

  • IDocs for Invioce and Delivery

    Hi all,
    I have to send the customer the Invoice and Delivery confirmation for that order placed by him through an IDoc in background job.
    We are going for a standard IDoc for invoice and Delivery also but how to fill the data into that standard IDoc.
    1.Do we have standard report like (BD12, BD14, BD10 etc.)
    2.Should we develop a report to fill the data into that Idoc.
    Please help me to find standard report or please help me to write code for that standard IDoc.
    Thank you all in advance,
    Regards,
    Shalem.

    Hi Shalem,
    You need to do the following activities.
    - Setup condition record (t/code <b>NACE</b>) for shipping (V2) and billing (V3).
    - Setup output type (t/code <b>NACT</b>) for shipping (V2) and billing (V3) with transmission medium <b>A</b> (ALE).
    - Setup procedures (t/code <b>NACZ</b>) for shipping (V2) and billing (V3) if required.
    - Once the above setup are done, for any creation of billing and shipping will create entries into table <b>NAST</b> (Message Status).
    - Then you can create IDoc using this standard program <b>RSNAST00</b>. Please ensure your ALE and IDoc configuration have been done such as BD64, WE20, WE21 and etc.
    Hope this will help.
    Regards,
    Ferry Lianto
    Please reward points if helpful.

  • Output determination for PO and MIGO

    HI,
    Please provide me complete config of output determination for PO and MIGO.
    PO print out.
    GR, GI,TP, cancellation and return   print out
    Uts

    Hi,
    Please go through these steps you can get the GRN Printout
    1. Maintain the Printer Name in SPRO->Matl Mgmt->Inv Mgmt and Phy Inv->Print Control->Gen Settings->Printer Setting
    Enter the local printer where you want to print your Goods posting document
    2. Ensure that in SPRO->Matl Mgmt->Inv Mgmt and Phy Inv->Print Control->Gen Settings->Item Print Indicator, 1 stands for Matl Doc print out
    3. In SPRO->Matl Mgmt->Inv Mgmt and Phy Inv->Print Control->Gen Settings->Print Version, maintain Print Version 2
    4. In SPRO->Matl Mgmt->Inv Mgmt and Phy Inv->Print Control->Maintain Print Indicator for Goods Receipt/GI/Transfer Posting Documents
    Here for Particular mvt type 101,201,121,311 etcu2026 Maintain the Print item as 1--Material document printout
    5. In SPRO->Matl Mgmt->Inv Mgmt and Phy Inv->Output Determination->Maintain Output Types, for the Output types WE01, WE02 and WE03, ensure the following--
    Select the particular Output type then goto Details
    a. Default Values: Dispatch Time is 3 or 4 as per reqmt. and Transmission medium is 1
    b. Print Parameter is 7
    6. In SPRO->Matl Mgmt->Inv Mgmt and Phy Inv->Output Determination->Printer Det->Printer Determination by Plant/Str Loc, Maintain the Output device for all your Plants
    7. Go to MN21, for Tr Type WE, Print Version 3, maintain Print Item as 1.
    Now the settings are ready for Printing Material doc
    8. While doing MIGO, ensure that in General Tab, you get "3 Collective Slip" beside the Print Indicator and you tick mark the field.
    9. Now depending on the setting in 5a, the Matl doc is printed. If it is 3, you have to print it using MB90. If it is 4, it is printed immediately.

  • "Material is not the same for confirmation and delivery"

    Hello
    If this is not the right forum, my apologies. Direct me to the correct one if it is not ....
    Have been doing automated test development (HP's QTP) against SAP systems for over a year. I am not an application expert - very much a newbie when it comes to application knowledge but trying to gain some. I have "googled" the phase "Material is not the same for confirmation and delivery" and have not been able to find any references. What does this mean?
    I see this message for an iDoc using WE02. Have looked and looked but don't really know what I'm looking for.
    Clues?
    Thanks,
    DW

    DW,
    I have never seen that exact message, but I have seen similar ones.  Generically, the message probably means that you are attempting to perform a transaction against a document (perhaps a Purchase order?) and the Material number (Part Number) contained in the transaction is not the same as the Material number in the originating document in SAP.
    An example might be you have previously created a confirmation against a Purchase order, which now exists in SAP.  This Confirmation is for a specific Purchase order, item, and material.  Now, when you attempt to create an inbound delivery for the Confirmation, the material number contained in the new IDOC is different from the material number that was contained in the original Confirmation.
    I don't know what IDOC Message type you are having the problem with, but generically you can do some troubleshooting. Find the SAP Material number in the IDOC (MATNR probably).  Find the appropriate reference document number in the IDOC (confirmation number?  Purchase order number? or...?), and then manually review the document in SAP to ensure that the Material numbers are the same.
    If you are totally lost, you should really consult with an SAP App expert.  I am guessing that this is part of the Materials Management module, so you would be asking for an MM expert.
    Or, you can send more details, and we can try to help.
    What is the IDOC message type?
    What is the Message number of the error message?  Functionally, what is this IDOC trying to do, from a business perspective?
    Rgds,
    DB49

  • How to configure route in sales order and delivery

    Hi friends,
    Can any one explain about Route determiantion steps. It has to take the route automatically in sales order and delivery also.
    i have configured
    shipping condition, transportation group, transportation zone, plant, shipping point determination, actual route by proposalroute.
    Apart from this what are the remaining steps, but it is not picking  in sales order and delivery.
    please any one send the steps for route determination. its very urgent for me.
    Thanks & regards
    Raju

    hi,
    Route is determined
    1.Country of Departure & Departure Zone taken from Shipping Point
    2.Country of Destination & receiving Zone from Ship to party
    3.Shipping condition from CMR
    4.Transportation Group from MMR
    5.Weight Group which is optional.
    Check the above.
    Route is determined in delivery.
    ASHA

  • User exit -Item Category Determination for a Home Delivery Shipping Condn

    Hi All
    1.     A Standard Order is created in ECC and if the shipping condition is HOME DELIVERY the default site that gets determined will be a HUB and if it is an UPS shipping condition the default site that gets determined is the PDC
    2.     The default Item category determined for the delivery relevant items (Box1 and Box2) will be “ZSNP” which is fine if the Shipping condition is UPS and the site is PDC.
    3.     However if the Shipping condition is HOME DELIVERY and the site is a HUB then the “ZSNP”  Item Category has to be flipped to “ZTBB” which then will determine the correct Schedule line category “ZB” and triggers the IPO process. This in turn auto creates a purchase requisition on the PDC when the Sales Order is saved
    plz help
    thnx
    rohit

    Hi Lawrence Tam,
             If you are going to create a new item category usage to determine an item category, you need to add a new line in transaction VOV4 for the new combination of sales document type + Item Cat. group + usage + high leve item cat. to determine the item category.
    Thanks in advance,
    Mariano.

  • RFC For Order and Delivery creation in SD from CRM - text not getting copie

    Hi
    I am trying to find out how the order and delivery is created in R3 if I create a return order in CRM, as we have one issue in which the text is not being copied to delivery??
    Thanks in advance
    Sameer

    Please check if you have any custom code/user exit in ECC which uses transaction code (VA01 , VA02 or VA05 etc) prior to invoking credit checks. 
    Orders created via CRM will not have transaction code set (SY-TCODE).

  • Account determination for project stock delivery (for movement type 281Q)

    Hello
    We are trying to carry out delivery for project stock (CNS0) using  movement type 281Q.
    We notice that there is no account modifier availalbe for this scenario resulting in error during PGI. However, we can do PGI after changing the config of account determination without account modifier.
    Since working without an account modifier is not acceptable for various business reasons, we must have an account modifier defined. We are wondering why SAP has not provided a standard solution for dealing with project stock delivery.
    Can any one please suggest how to deal this situation.
    Thanks and warm regards,
    Jagadeeesh

    We have business requirement as stated below:
    We need to procure materials for specific Projects but also want to track the stock for the Project by value in the invnetory. In other words, the encumbrance of the procurement needs to take place against the Project but we want to be able to take it into inventory as a valuated stock and issue to the WBS whenever it is required.
    Is this possible?  What we know is that as soon as we give reference of the WBS for the Procurement, it gets expensed to the Project and we cannot value manage in inventory.
    The reason for this requirement is there is a long time between when the item is procured and when it is used for the project. Till such time we have to track the Project items in the inventory as any other stock but its still tagged for the project and encumbrance would need to have happened
    Any ideas on how to deal with this will be appreciated
    Thanks
    Noornie

  • Letter of credit  maintenance for order and delivery documents

    Hi Friends,
    As there are three places where we can maintain Letter of Credit ( Financial documents) data.as
    1. Order Header data
    2. Order Item data
    3. Delivery Header data
    What is the importance of all these and ideally where shd maintain ?
    kindly guide
    Shailesh

    Hi,
    Process Of Letter of Credit for Imports
    1. The Clearing agent ask for amount, the person who receive the product will give Letter of Authority to Clearing Agent. The clearing agent move to bank and take check.
    For this purpose, we just issue LA.
    2. Prepare Purchase for the Vendor from whom we are going to receive the product. There may be 2 or more Vendors.
    1. Product cost to be transferred to Vendor A
    2. Freight or Other Charges to Vendor B
    3. Customs Duty and Others to Vendor C
    Tcode : Me21n
    3. First We have to pay Customs Duty to Commissioner of Customs after LA issued.
    Entry : Customs Clearing a/c Dr
    Cess on Custom a/c Dr
    CVD Clearing a/c Dr
    Cess on CVD a/c Dr
    Special CVD a/c Dr
    Vendor C a/c Cr.
    T-code :MIRO or YMIROOTH
    4. Cenvat credit for the product will be taken by person who handling Excise in that company
    Entry : Cenvat Clearing a/c Cr.
    RG23A Part II a/c Dr.
    5. Clearing of Cenvat Credit
    Entry : Cenvat Clearing a/c Dr.
    CVD clearing a/c Cr.
    Cess on CVD a/c Cr.
    Special CVD a/c Cr.
    6. After Bank payment they will transfter to us
    Entry : Vendor a/c - Dr.
    Bank a/c - Cr.
    Give ur mail id.. i will send the doc. its not easy to make u understand that concept.
    Regards
    Srikanthraj

  • House Bank Determination for Customer and Vendors.

    HI,
    We have two House Banks namely BOAAR and BOAAP one is for Paying Customers from BOAAR and another is for paying Vendors BOAAP. Now how will this House Banks are determined when F110 is done. that means, when paying system should pay VEndors from ONLY BOAAP and Customer should be paid from BOAAR.
    Currency: USD
    Payment Method: Check,
    How to handle this in SAP.

    HI Sravan,
    Thanks for quick reply, Yes this is one option, and the other option is editing the propasal and choosing the right bank,
    Is there any other alternative other than maintaining the House Bank details in Masters Records?
    Spandana
    Any more suggestions!
    Edited by: Spandana on Mar 31, 2011 6:35 PM

  • Resolving error for determination for agents and buffering

    Hi,
    Can u please let me know how to resolve buffering error and agent determination error, by which way and what tcode are there for it if any ?
    One more question is there how to test workflow and how to restart it with issues?
    Thanks
    Parag

    Hi parag ,
    how to resolve buffering error -
    To resolve buffering errors 
    1) Use Synchronize Runtime Buffer  ( SWU_OBUF)
    Always refresh the runtime buffer when you have made a change in a task definition or after transporting
    new workflows  or versions of workflows that are to be used on the day of tranport .
    2) use the refresh organizational environment option in Business workplace ( SBWP)  or in start workflow  function ( SWUS) .This refreshes buffers for current user id .
    agent determination error
    to solve agent determination errors ,you can take help from following tcodes -
    swi1_rule  - Execute rules for work items
    swi2_adm1  -  Execute work items without agents
    swia - Execute work items without agent check
    how to test workflow and how to restart it with issues
    SWPR - workflow restart after error
    swi2_diag -Diagnosis of workflow with errors
    SWPC  -  continue workflow after system crash
    SWUD - workflow diagnosis
    swus - test workflow
    hope this helps.
    Thanks,
    sahiba

Maybe you are looking for

  • Help! My Lacie won't mount!

    Help! Help anybody out there can help. I have recently bought a LaCie 1TB Rikibi External HD. It has been great so far and I have filled it with approx. 700GB. I have two partitions, one with 10GB (Windows) and one with appr. 990GB Then a couple of w

  • Tcode SQVI post any security threat in production system ?

    hi, my user is requesting to use tcode sqvi in production, but authorisation team do not allow as the tcode will allow user to do query across. is SQVI a security critical tcode that we should not let user have in Production system ? comment and advi

  • Java 2 Programmer's Certification Exam...

    Hi there ppl, i was just wondering if employers are really that bothered about exactly how much you scored on your java 2 cert programmer's exam? If so, then what is considered a decent score or percentage? Thanks. (ps. got my exam tomorrow so i'm in

  • Dynamic file access

    I need to know how to access relative files in a directory so I can place them (or the file names) in a list within my flash application. My goal is to allow the user to download new XML files to a directory and have flash search the directory for ne

  • What is that? Safari 7.0.5 freezes because of this "gkbisd"

    I noticed my safari hangs/freezes for about 1 min and I noticed that I get these logs in Console while this happens: 2014-07-10 9:28:52.230 AM gkbisd[158]: Unable to collect cdhash for /System/Library/Frameworks/Quartz.framework/Versions/A/Frameworks