50% Hold on VAT (for Capital Asset procurement)

Hi Friend,
In my client place like Excise (50% Hold on Cenvat), they want to Hold 50% of VAT amount in the current year and by sub-sequent fiscal year begining they want to utilize it.
Is there any standart process in SAP?
Else any other way through which we can do the business process.
Regards,
nms

Answered

Similar Messages

  • Budgeting for capital Asset Procurrement

    Hi
    How can we set budgets in SAP for purchase of capital assets?
    Regards
    SM

    Hi
    You can use an Internal Order for Budgeting for capital asset purchases. In your purchase order make internal order as compulsory. there after for your Controlling area, create an internal order type and set up avaiability control for the same. Then create an internal order and assign a budget in KO22. Thereafter in purchase transaction give reference of this internal order. System would do a check for budget for asset procurement.
    Thanks & Regards
    Sanil K Bhandari

  • At times normal PR is prepared for capital item procurement. Due to this, a

    At times normal PR is prepared for capital item procurement. Due to this, a normal PO is made for capital item procurement

    Is this a general note or a question

  • 50% Credit in VAT for Capital Goods(Assets)

    Dear SAP MM Experts,
               My client need to take 50% VAT credit in the First year and remaining 50% in the next year for Assets(Capital Goods). Currently I have configured 50% Cenvat credit for Excise duty, it was working very well using J1ID.
    But for VAT, what configuration is necessary to take 50% VAT credit for Captial goods(Assets). Right now I use JVCD for taking 100% to VAT and JVCN to make it as inventory(Non Deductible).
    Please do the needful.
    Thank you.
    Regards,
    Baskar

    This is standard behavior of SAP. In case domestic purchase, we can avain 50% CENVAT on additional excise duty (AED).
    But in case of Import , we can avail 100% CENVAT for capital goods on additional customs duty (ADC).
    Understand the difference between ADC & AED.
    Try to convince client for the same. If he is not convinced, better write to SAP. Don't make changes related to subtransaction type 'IP'.

  • Setup for Down Payment made to the Vendor for Capital Assets(Otherthan AUC)

    Hello,
    Can any one explain how we can make down payments to vendors against capital assets and what setup is required for this.
    Plz advice.

    Hi,
    At the time of making down payment to vendor under capital assets purchase specify the purchase order number. For this vendor reconcialtion account and down payment special g/l symbol should assign first in OBYR.
    There u can choose the special gl indicators.
    Hope this is helpful, if yes assign points.
    Regards,
    Sankar

  • Purchase order for Capital Asset.

    Hello,
    How can I create the purchase orders for Capital Asstes?
    Narendra.

    Hi,
    You first need to create Asset Number in transaction AS01. This is normally done by finance people. Once you get the asset number, create purchase order in transaction ME21N, by selection account assignment as A - Asset. Enter other data such as material number, quantity, requirement date, price, tax code. In the account assignment tab at item level, enter the asset number you got while creating the asser in transaction AS01. Save the purchase order.
    Once you receive the material against this purchase order, the accounting entries will be done against the asset number.
    Hope this fulfills your query.
    Regards,
    Prashant

  • VAT for capital goods

    Hi Friends,
                                I have created a tax code with VAT for Captal goods JVCD. But in PO itself it's values is not getting. I have to activate this condition type ,I think. Can any body please convey, How to activate this condition type JVCD?
    Regards

    U r using TAXINN(i think)
    go to FV11 and maintain the condition record of JCVD.based on the access sequences ur having.
    that is the only way to get values in PO.
    regards,
    sujit

  • An SAP Solution for capital planning and Budgeting of Capital Assets?

    Is there an SAP Solution for the Planning and Budgeting of Capital Assets?
    A solution that provides planning, budgeting, and tracking for capital assets through the entire life cycle of each asset, from the initial request through the final disposal.
    The solution needs to be able to run “scenarios.” A scenario contains equipment that may potentially be purchased. Scenario items are used to help determine cost, capacity, and cash flow feasibility.

    Hi
    What you suggested is the ideal approach...
    However, if they say that the budget allocated to capital purposes (70%) applies to both capital projects and expenses and they would like to control it together, but have reports separately, it is not possible with standard SAP...
    If they want to have just one IO for both cap and exp, You can suggest them a work around to capture CAPITAL or EXPENSE in a ref field (XREF1 in BSEG) and you can run KOB1 with XREF1 displayed in it....
    In standard KOB1, XREF1 is not displayed, you have to use Exit COOMEP01 to include the fields you want... Add XREF1 to the Structure CI_RKPOS and write your code in the include ZXKAEPU01 of EXIT_SAPLKAEP_001
    Without an identifier @ the time of booking the transaction in the system (Either by way of IO or a ref field), you wont be able to generate reports later on
    Regards
    Ajay M

  • Depreciation run for legacy assets

    Hello,
    This is the first depreciation run in SAP for the month of April 2007.
    System is posting depreciation for those assets procured during the year i.e purchased in April but not posting for legacy assets i.e assets uploaded from legacy.
    Regards
    Sreekanth

    Hi Murali,
    Our Fiscal year is betyween April and March. Depreciation for legacy assets has been uploaded till the month of March 2007.Planned depreciation is getting displayed in the asset explorer under Fiscal year start column.
    Hope u were looking for this info.
    Regards
    Sreekanth

  • Excise Invoice Cycle for capital goods

    Hello,
    Can someone enlist the complete CIN config settings & J1ID settings for capital goods procurement.
    Regards
    Mahesh

    Hello,
    Can someone enlist the complete CIN config settings & J1ID settings for capital goods procurement.
    Regards
    Mahesh

  • Creation of Assets for Capital Investment Measure

    Hi,
    Can some please tell me how to create an Asset for Capital Investment Measure.

    Hi,
    First you have to create master data using asset class AuC.
    You have define asset class for Capital Investment Measure (AuC class) in t-code : OAOA. And still in the same t-code (OAOA), you choose "investment Measure" in box "Status of Auc".
    If you choose "Investment Measure", the assets under construction in this asset class can be created solely in relation to capital investment measures (internal orders or WBS elements).  So you cannot create and post in Asset Accounting directly (Example post using t-code : F-90).
    If you use WBS Elements then you can post to the asset for Cap Invest Measure using t-code : CJ8G or CJ88.
    Hope it can help.

  • Capital Goods(Asset) Procurement

    Hi all,
    I have a scenario where company is procuring an asset and the vendor from which the company is procuring the Asset is sending that Asset in different parts like for a whole machinery the vendor is dismantling at its end and then assemble inside the client premisis but sending in different shipements
    Now requirement is In the PO there is only one line item with Asset code, GR is to be done for all the Dismantled parts and for that parts material master is not maintained, on some of the dismantled parts excise entry is required.
    When is Asset is assembled i have to show the GR entry for complete asset and have to update my RG23C register for both Part1 and Part2 entry.
    How to map such a scenario??
    Regards
    Akshit

    Dear ,
    I feel u want to take the Credit for the Parts material.
    In J1IEX  use the option without PO & take the credit.
    In this u don't ahve to create the material code,by using material Description of u can take the credit.
    Pi. use this .
    Biswajit

  • Business Process for Refurbishment of Capital Asset in SAP PM

    Dear All ,
    Please explain me best practice for Refurbishment of Capital asset created as Equipment in SAP PM.The Current Standard process of SAP is for spares/equipment not categoried as Capital asset .
    Regards,
    Basant Kumar

    Dear Chinta,
    Sorry I can't give you any documentation, but let me give you a little explanation about refurbishment.
    Refurbishment is a process to repair our  repairable spare part, then return that spare part back to the equipment, or to warehouse.
    1. Warehouse make a good receipt 'other' for the repairable spare part, (spare part is received at warehouse)
    2. Make a refurbishment order (IW81). We can repair the sparepart by our technician, or by external service
    3. Make a good issue to refurbishment order
    4. Repair faulty spare
    5. Perform good receipt with reference to refurbishment order.
    6. Order close
    Hope this can help.
    Regards

  • F-47 for assets procurement before closing year

    Dear Friends,
    Please advise, is it possible to do asset transaction for the new year before closing or carrying out the year end activities.
    our situation is FY Jan to Dec. We have not carried our year end activitites yet for year 2009, but now we need to do new asset transactions for year 2010 like we want to make F-47, F-48 for new asset.
    Please reply ASAP.
    Thanks.
    Sunil.

    Sunil
    You can allow advance payments by activating / ticking the Special G/L in OB41 for posting keys 70 & 75
    Test it first, if you want.
    Rgds
    Zubin

  • ED Configuration for Capital goods

    Hi Gurus,
    I have a problem in calculation of Excise duty with respect to capital goods.
    Our client wants to Create a new tax code ......though which they can claim the .....Input of 50%  Excise duty this year and 50% next year,( for that he want to update two different GL accounts for these percentages)  and 4% VAT on it.
    EX:
    The new tax code for 12.36% of excise duty + 4% VAT, required in a single tax code. (This 12.36% ED -- 50% this year and 50% next yr)
      Required for the following scenario
    Suppose Base AMC valve is          Rs.10000/-
    12.36% of Excise duty which is     Rs.1236/-
    4% of vat on Rs.11236/- which is    Rs.898.88/-
    Total amount including taxes Rs.10000 + 1236 + 898.88 = 12134.88
    As the client is not using CIN, how to configure this scenario.  We are on ECC 6.0
    Thanks in adv,
    Sri SAP

    Hi,
    1. for Capital Goods, first in J1ID miantain in material and chapter id maintain that material code with Assets.
    2. In Create PO with Account assigment as Assets.
    3. In SPRO, while maintaing specify Excise accounts per Excise TT as
    CAPE          CR Credit     ONHOLD CENVAT on hold account
    CAPE          DR Debit     ONHOLD CENVAT on hold account
    CAPE          DR Debit     RG23AT1 RG 23 AT1 Account
    CAPE          DR Debit     RG23BED RG 23 BED account
    CAPE          DR Debit     RG23ECS RG 23 ECS Account
    4.  Now in  PART2, RG23C Register type is updated for Capital Goods
    5. The Excise Posting Entries must be like
    During Excise Invoice Credit            
                                        Cenvat Account           Dr.       (50%)
                                        Cenvat On-hold           Dr.       (50%)
                                        Cenvat Clearing                      Cr.
    6.  Check the Balance Credit Capital Asset T Code J2I8
    Hope help u !
    Regards,
    Pardeep Malik

Maybe you are looking for

  • Ssrs 2008 r2 report dataset call a stored procedure

    I am modifying an existing SSRS 2008 r2 report. In a dataset that already exists within the ssrs 2008 r2 report I need execute a stored procedure called StudentData and pass 3 parameter values to the stored procedure. The stored procedure will then r

  • Changing line color on XY plot

    This should be something really simple. I simple created a property node, set the active plot, and set the plot.color. What happens to some plots is the points change to my specified color and other stays as my background plot color which is white. I

  • Ical alarm default

    Is there anyway to get ical to set the default alarm setting to 1 hour everytime I create a new event? Currently 15 minutes is the choice every single time.

  • I have two partitions and want to choose which to login to. Cannot remember the key combination to hold on power up

    I have two partitions and want to choose which to login to. Cannot remember the key combination to hold on power up

  • Nexus 5020 Switch Profile Error

    Hi There, I have 2 x 5020s peered together with a switch profile. Somehow the switch-profile configurations have gone out of sync. 1st 5020 switch-profile  : xxxx Start-time: 889959 usecs after Tue Aug  9 12:25:47 2011 End-time: 453948 usecs after Tu