Is there an SAP Solution for the Planning and Budgeting of Capital Assets?
A solution that provides planning, budgeting, and tracking for capital assets through the entire life cycle of each asset, from the initial request through the final disposal.
The solution needs to be able to run “scenarios.” A scenario contains equipment that may potentially be purchased. Scenario items are used to help determine cost, capacity, and cash flow feasibility.

Hi
What you suggested is the ideal approach...
However, if they say that the budget allocated to capital purposes (70%) applies to both capital projects and expenses and they would like to control it together, but have reports separately, it is not possible with standard SAP...
If they want to have just one IO for both cap and exp, You can suggest them a work around to capture CAPITAL or EXPENSE in a ref field (XREF1 in BSEG) and you can run KOB1 with XREF1 displayed in it....
In standard KOB1, XREF1 is not displayed, you have to use Exit COOMEP01 to include the fields you want... Add XREF1 to the Structure CI_RKPOS and write your code in the include ZXKAEPU01 of EXIT_SAPLKAEP_001
Without an identifier @ the time of booking the transaction in the system (Either by way of IO or a ref field), you wont be able to generate reports later on
Regards
Ajay M

Similar Messages

  • Tyre Manufacturing SAP Solution for production Planning PP-PI OR PP-Rep???

    Tyre manufacturing in SAP solution does it require to use PP-PI and/or PP-Repititive or PP-Descrete.Pl share if any one implemented SAP for tyre manufacturing with Process flow and which are the PP Components needs to be used.
    Thanks
    Ram

    Dear Girish,
    Thanks for the info and I think you are right,but some times if customer wants the answer from Consultant,what is best suggested or recomended ?? ,then it requires some expert judgement or based on previous experience,if you have any case study to share with me would be greatly appreciated.means which company uses what process ,are they benifitted from the solution if not what are the pain points and how are they managing it etc...
    Thanks
    Ram

  • SAP Solution for Mini steel plant with DRI Process

    Dear all,
    I am a metallurgist who spent couple of years in steel and process Industry and then moved to IT Consulting as SAP consultant / business analyst mainly working in the area of solution designing.
    Here i will like to describe SAP solution for Mini steel plant with DRI proces.
    u201CManufacture Productsu201D Description
    The series of operations performed upon material to convert it from the raw material or a semifinished state to a state of further completion. This includes the establishment and maintenance of a CAPEX plan, the planning, scheduling and execution of production activities, the dispositioning of produced goods, the maintenance of production data, the monitoring of production performance and the implementation of engineering changes.
    u201CManufacture Productsu201D Objectives
    M-010
    Compile 3-year CAPEX Budget     Establish the overall manufacturing goals and metrics that the organization will use to measure performance and progress towards objectives. These goals should be consistent with overall organizational strategy/value propositions. Develop long-term goals for production capabilities and manufacturing. These goals should align with the overall goals and objectives of the organization.
    M-050
    Perform Long Range Production Planning     u201CBudgetingu201D. Long range planning of production quantities based on planned available capacities and known or estimated customer demands. This process may include planning for different capacity and/or demand scenarios. Approved capital expenditures from the 3-year CAPEX budget may influence the budget. Range and frequency for budgeting is yearly.
    M-060
    Perform Medium Range Production Planning     Medium range planning of production quantities based on planned available capacities and known or estimated customer demands. This process may include planning for different capacity and/or demand scenarios.  Range and frequency for planning is quarterly.
    M-070
    Perform Short Range Production Planning     Short term planning of production quantities based on capacities and demands as previously planned in the longer terms, actual customer demand and actual capacities. The result from short range production planning will run into the operational plan for the current and following days.  Range and frequency for planning is monthly.
    M-080
    Schedule Production     This sub-process enables detailed scheduling by resources over the planning horizon. Planned orders that fulfill demands (Stock Transfer Requisitions, Sales Forecasts and Customer Orders defined by due-dates and due-quantities) come from the short range plan. This results in a feasible schedule, optimizing utilization of the production resources. It is based on production process constraints as well as labor resources in order to minimize production costs and also taking into account constraining raw materials availability.
    M-090
    Execute MRP     The purpose of this sub-process is to generate a Materials Requirements Plan (MRP) for all materials, which are produced or purchased. The MRP process involves looking at current material inventory, planned inbound material deliveries, requirements, lead times and stock levels to generate a detailed plan for future material requirements. The materials requirements will be generated with respect to the three planning horizons, short-term, medium-term, and long term. If an over stock of raw materials occurs as a result of a planning change production and marketing personnel will be informed. This would allow for the cancellations of any unneeded shipments.
    M-100
    Perform Setup / Changeover     Perform set-up and changeover activities on production equipment as necessary, to prepare for the production of specific materials/grades. Set-up and changeover activities will enable the production equipment to perform operations on materials, as per the specifications called out on the production order. Ensure time is allocated for first off inspection requirements after changeover.
    M-110
    Execute Production     Insure that the production plan is met by converting raw materials and component supplies into finished and semi-finished products. Batch/lot documentation will be created for individual production orders to provide traceability throughout the process. Each step of the production process is continuously monitored to identify mechanical, quality, and productivity issues and suggest solutions when problems arise. Data collection for performance and financial reporting enables management to take immediate action on manufacturing processes as well as conduct historical analysis.
    M-120
    Perform Quality Management     Quality management refers to the entire supply chain process. Process activities are related to the evaluation and inspection of key characteristics of semi-finished and finished materials. These evaluations are recorded and acted on based on the results. Report/manage internal quality problems or issues. Install and manage quality control systems to insure product quality. For supplier or subcontractor based issues this data should be used as a performance measure during the vendor evaluation process.
    M-130
    Manage Product Disposition     This process ensures those semi-finished and finished products that do not meet quality requirements, are prevented from being used and distributed in good finished product to customer, or released for the next step of the production process. A semi finished product is any material that needs to have another operation on line before being shipped to the customer. Finished goods are defined as any material that can be shipped to a customer; in house produced finished goods, subcontracted materials and trading goods. The information required to make decisions regarding disposition comes from the Quality Management system of each production facility. The first step ensures that raw material and returnable goods are dealt with in another subprocess. The reason for the goods not meeting quality standards is recorded along with the results of any investigation to find the cause of the fault. Information is sent to all other parties who need to know: order fulfillment, inventory management and shipping. The process ensures that the most appropriate action is taken to either dispose of, or rework the goods. Disposal or rework may be either through the original materials supplier or subcontractor, or Mittal Steel Point Lisas.
    M-140
    Maintain Product Related Data     u201CMaterial Master Maintenanceu201D. The Sub-Process 'Maintain Product Related Data' is the list of activities that identify the steps and decision points related to the request for and performance of additions, changes, and deletions to the Material Master file or files. This sub-process begins when a need to create, change or delete a material is identified and ends when the request is either actioned or refused. The sub-process is intended to cover all material types, including finished goods, raw materials, bills of materials, equipment and service, POS, Sundry Items etc. In fact, any product which the company wishes to inventory or purchase. A number of key strategic decisions, including a clear definition of when we issue a new material, will affect this sub-process.
    M-150
    Maintain Production Related Data     u201CMaster Data Maintenanceu201D. This subprocess identifies the activities related to requesting changes or additions to production related master data. Once a need for master data maintenance is identified, a request is submitted for approval. Data defining production capacities and performance standards (e.g. line efficiencies, material yields, etc.) require Corporate level approval prior to maintenance. Other data that is more specific to internal planning functions are maintained at the plant level. Maintenance requests are returned to the originator whether the request is approved or not to improve communication throughout the system. This subprocess may be triggered by: annual operations budgeting process process/production equipment upgrade or replacement change in facility work schedule (i.e. planned hours or days) change in personnel required to operate process/production equipment new products, formulations, or packaging.
    M-160
    Operations Execution Reporting     Gather manufacturing information at various points in the production process. Prepare management reports both at the detailed level for plant management and summary level for senior operations management. Reports will be available on-demand and will include - volume, efficiencies (mechanical, line, and labor), yields, downtime, asset utilization, environmental, safety, quality, and financial data. A major goal of this sub-process is to define a consistent method of calculating operations metrics. Some plants will use line information systems and PCSs to collect information. Not all plants are equipped with these systems and the where they do exist, the level of sophistication varies.
    M-170
    Manage Process Reliability     Optimize capacity by reducing process downtime and ensuring compliance to quality expectations by the reduction of rejects. Install tracking systems to measure line time utilization, quality results, process settings. Conduct root cause analysis, and use the data to develop and implement improved operating procedures.

    Thank you for your prompt response. I'm assuming you are still proposing to use Sales order -> purchase order -> invoice verification -> Customer billing process flow. Is that correct?

  • Oracle Hyperion Planning and Budgetting

    We are planning to use the Oracle Hyperion Planning and Budgetting Product for our organization.And we are in the process of finding the best practice OR best suite Database software for Oracle Hyperion.
    Which database software product is best suite for Oracle Hyperion Planning and Budgetting?
    Our Source Systems
    Oracle E-Business Suite R12
    PeopleSoft Campus Solution
    Appreciate your commnets on this matter... Thanks

    Hi,
    you can try the following:
    Go to [http://service.sap.com/bosap-support] and navigate to Documention->Product Guides . Select SAP BPC and you should get the links to the related documentation.
    If you still get problems to access it, you must issue a message to SAP (service.sap.com/support) asking them to allow you accessing the documentation on SAP BPC.
    Regards,
    Stratos

  • Hyperion Planning and Budgeting

    Hi all,
              I want to know about the hyperion planning and budgeting. Please guide me in it...

    Hi,
    you can do the same work in SEM-BPS as with Hyperion.Only difference being the integrity of the various modules.As well the integrity of SEM with BW is much more powerfull and versatile than Hyperion with BW.Only reason being its a third party software. Hyperion is another BI tool independant of SAP BW. It is not the same tool than the BEx analyzer used only for querying BW data
    Suggestions:
    BW data could be reported from Hyperion by connecting the system with the right adapter; the other way around isn't possible (querying hyperion data via BW) except by setting the hyperion DB as a DB/UD Connect source system and having remote IProviders on-top of it.
    If you want ,you'll synchronize BW metadata in Hyperion and then create a report in Hyperion which will retrieve data from a BW query released for OLE/DB for OLAP (query properties/extended)
    now you can access any BW query / cube / multiprovider in BW
    Remember that hyperion has been bought by Oracle some months ago...
    http://www.hyperion.com/solutions/environment/sap.cfm
    Hope this helps,
    Regards
    CSM Reddy

  • Details abt Hyperion Planning and Budgeting

    Hi Experts,
    I want the entire details about Hyperion planning and budgeting for my project. I don't now anything about the Hyperion. I am in SAP BI. Please guide me in this matter...

    try this :
    http://download.oracle.com/docs/cd/E10530_01/welcome.html
    and http://download.oracle.com/docs/cd/E10530_01/doc/nav/portal_5.htm for manuals and
    http://edelivery.oracle.com/ for full access to software

  • Marketing planning and budgetting(costing)

    Hello CRM Experts,
    My client wants to implement marketing planning and budgetting (costing). They do not want to use SAP Project System.**
    *.How campaign can be replicated in SAP ECC and assigned to WBS element. Can you please provide your imput as early as possible.*
    Thank you very much in advance
    Eliz

    hi,  guy
    to achieve this, you need to implement the BPS in BW, and make the BPS and CRM integration.
    In standard, CRM Marketing is integrated with BPS,  you can login the CRM and open the BPS windows in Marketing object screen, fill your cost plan or trade plan or sale plan.
    For WBS elment, you need to activate the configuration in PS mode and middleware between CRM and ERP.
    If you don't need to use PS, maybe you can use Claim in CRM to manage the expense and cost in campaign.

  • Multiple currency planning and budgeting?

    Hi all
    We are having a requirement of planning and budgeting in same WBS with multiple currencies and also seeing reports in different currencies on single screen.
    Now has anybody explored this area and has anything to suggest.
    Thanks in anticipation
    Raman

    Hi Raman
    The following is the literature from SAP on the subject. You may find it useful.
    Planning and Budgeting in Any Currency
    Use
    International groups often use one uniform company code currency (group currency) in CO. However, it may be necessary to plan and budget in the respective local currency as the majority of costs will be incurred in the local currency. The local currency is usually the corresponding company code currency.
    Previously only budgeting of jobs (orders and projects) was possible in the local currency.
    From Release 4.70, you can also budget investement programs in the local currency. In addition, it is possible to plan investment programs, appropriation requests and jobs directly in the local currency.
    As was previously the case for orders and projects, plan and budget values for investment programs and appropriation requests are also saved in both the controlling area and local currencies defined in the master record of each object. If you change or re-specify the exchanged rates used, it is now possible to recalculate the values in the local currency using the values in the controlling area currency, and vice-versa.
    In reporting for IM, it is even possible to calculate evaluations in any report currency (plan, budget and assigned values). If the values are available in the specified report currency, they are issued unchanged. If they are not available, they are converted from the controlling area currency into the report currency.
    Effects on Existing Data
    Before Release 4.70, the plan values for appropriation requirements, were only saved in the controlling area currency. This was also the case if a local object currency was specified in the master record for the appropriation requirement. From Release 4.70, the plan values for appropriation requirements are always saved in the controlling area and local currencies. Therefore, you must adjust appropriation requests that were created in an earlier release and use a local currency that varies from the local object currency. The easiest way to do this is to use the program RAIMCRC2 to recalculate the plan values in the local object currency for appropriation requests whose plan values are in the controlling area currency (transaction IMCRC2, menu path: Financial Accounting  -> Investment Management -> Appropriation Requests -> Tools -> Recalculate Currency Plan for Appropriation Requests). Before you run the program, select the relevant option in the Process Control section of the initial screen.
    Effects on Customizing
    Adjustment of Planning and Budget Profiles
    To enable the planning of investment programs, appropriation requests and jobs in a transaction currency different to the controlling area currency, you must adjust the relevant planning profiles.
    To enable the budgeting of investment programs in a transaction currency different to the controlling area currency, you must adjust the relevant budget profiles.
    In the planning currency (or budgeting currency) section of the planning (or budget) profile, you must define the transaction currency in which planning (or budgeting) is to be executed:
    Only in the controlling area currency (default),
    Only in the object currency
    (= local currency defined in object master record ) or
    In a transaction currency chosen at the start of planning/budgeting
    (this option is not possible for appropriation requests).
    In the planning or budget profiles, you must also define the exchange rate types to be used for the conversion of total values that are not dependent on the fiscal year.
    To adjust the planning profiles, use the process steps:
    Maintain Planning Profiles  (investment programs)
    Maintain Planning Profile for Cost Planning (appropiation requests)
    To adjust the budgeting profiles, use the process steps:
    Define Budget Profiles for Investment Programs   (investment programs)
    Exchange Rate Types
    In the fiscal-year-dependent data of the CO planning versions, you must also define the exchange rate types to be used for conversion of plan values that are not dependent on the fiscal year.
    For conversion of fiscal-year-dependent budget values and fiscal-year-dependent plan values of appropriation request variants not yet assigned to a plan version, each exchange rate type is taken from the fiscal-year-dependent data of the CO planning versions 0.
    As the plan or budget values are stored in the transaction, controlling area, and local currencies, the exchange rates used must enable the conversion of the transaction currency into the controlling area and local currencies. Where necessary, the exchange rates used must be extended.
    To enter the exchange rate types, use the process step:
    Define Versions  (investment programs)
    Change Planning or Budget Currency
    If you always planned or budgeted existing investment programs/measures in the controlling area currency, it is not subsequently possible to change the planning or budget currency to the object currency in the planning or budget profiles. This conversion is not prevented in Customizing, but leads to an error when you next plan or budget existing investment programs/measures. Alternatively, you can convert the planning or budget currency into the transaction currency in the planning or budget profiles, and set the object currency indicator as default.
    A similar restriction does not exist for appropriation requests. You can change the planning currency in the planning profile at any time.
    Use the process step under "Adjust the Planning and Budgeting Profiles".
    Detailed Planning
    When you call up detailed planning from structure-based cost planning or revenue planning, the standard SAP planning profiles are used, to which the standard SAP planning layouts are assigned. These planning profiles cannot be changed in the planning transactions. Import the standard SAP planning layouts 1-401-IM, 1-402-IM, 1-403-IM, 1-701-IM,  1-702-IM and 1-703-IM using the transaction OKBF from client 000 in your client.
    To execute the import, choose the process step:
    Import Standard Planning Layouts.
    Reporting Currency for IM Reporting
    In IM reporting, if you want to be able to specify a reporting currency that is different to the controlling area and object currencies used in the investment program items or subordinate appropriation requests and measures, another exchange rate type is required for the due conversion of plan, budget, or values into the reporting currency. You define this exchange rate type in Customizing for the program type for the investment program to be reported ( Group Reporting).
    To enter additional reporting currencies, use the process step:
    Define Program Types  (investment programs)
    you may also refer the following link in SAP help on the subject
    [http://help.sap.com/saphelp_47x200/helpdata/en/86/98853478616434e10000009b38f83b/frameset.htm]
    Venu

  • Licensing Planning and Budgeting

    Hi all, i'm in a stuck!
    We are going to implement Hyperion Planning and Budgeting, the customer asked us about the licensing, and prices and all about this..,
    well, the cuestion is this, what components together with Planning are involved in the Hyperion Planning and Budgeting solution?
    I do this cuestion, because the customer asked me about the total cost of the product, and i need to know if there are more components around planning solution
    that need license to be used, and keep it in mind when i aseemble the total cost!.
    I hope you can help me.!
    Regards!

    Hi,
    I am not sure what version you are talking about. If you have a look at the EPM documentation there is a epm_licensing pdf that goes through the different licensing packages such as planning and explains what products and components are included.
    As for cost you will need to contact an Oracle account manager.
    Cheers
    John
    http://john-goodwin.blogspot.com/

  • Questions on Enterprise Planning and Budgeting

    Hi,
    First of all: this may be a very wrong place for posting these questions. However, I could not find a forum that seemed closer to the matter so I try it anyway.
    With EPB close to hitting the streets, some questions starting popping up - especially now that Oracle has recommended one of my customers - who is just starting out with Business Intelligence and are not E-Business Suite users - to embark on the EPB course.
    It is stated by Oracle that EPB - although it is an integrated component of the Oracle EBusiness Suite – can be used as stand-alone product. You can load data into interface tables. Questions:
    Does EPB work on its own Data Warehouse and if so, is this DWH also available to other OLAP tools for Analysis? Or should organizations doing Analysis and Reporting apart from EPB have a separate DWH for those OLAP queries?
    Does Oracle recommend loading data directly from operational sources into the FEM Interface Tables or does Oracle think it best for non-EBusiness Suite customers to set up a Data Warehouse independently of EPB and in a later stage implement processes to extract data from that DWH into the FEM Interface. Are the FEM Interfaces tables at the operational (fact) level or do they already have some sort of consolidation in them?
    Can Oracle somehow convince us that while EPB does not provide hooks for customization it will offer reports desired by non-EBusiness Suite customers with potentially very varied businesses? How much of EPB benefits are you missing out on if you do not have the E-Business Suite? What is EPB then giving you that with OWB and BI Beans/Discoverer you can not easily build yourself?
    The specific case of my customer: they have clear requirements for Management Information. Most of these are about analyzing histrical data (the classic slicing and dicing); forecasting and budgeting would be a nice to have in the longer run. They currently do not have a proper Data Warehouse. They have a consolidation point for some operational data. No dimensions have been defined, no data cleansing is performed and some data is not available at all. I am wondering whether EPB would be the proper tool for them to start with. Given their requirements as well as their lack of current experience with BI as well as the relative uncertain situation with regard to the data sources, I would feel more comfortable with a more down-to-earth approach: start designing a DWH and the processes to populate it as well as developing the most urgently needed reports. In that case, EPB would be brought in at a later stage – when the organization as well as the data management is ready for more advanced stuff.
    Is there anyone, especially from Oracle, who would care to comment? Also on my feeling that Oracle’s recommendation to use EPB is perhaps somewhat influenced by Oracle’s desire to build up references and experience with this brand new tool – that, as I understand it, is not even generally available – only a “controller release” is available right now.
    Thanks for anyone for your insights.
    best regards,
    Lucas

    Lucas
    Please note these are not official Oracle or my employers answers, just my interpretation. Hope this might help though.
    "Does EPB work on its own Data Warehouse and if so, is this DWH also available to other OLAP tools for Analysis? Or should organizations doing Analysis and Reporting apart from EPB have a separate DWH for those OLAP queries?"
    EPB has it's own EPF schema, which it shares with Oracle's other CPM applications, but it's not a traditional warehouse schema arranged as a star schema, you're not supposed to load data directly into it, and it's really designed for storing data that needs to be loaded into AWs for analysis. You'll therefore still need to build your own warehouse schema, and then load data (through the interface tables) into the EPF schema for use with EPB.
    "Does Oracle recommend loading data directly from operational sources into the FEM Interface Tables or does Oracle think it best for non-EBusiness Suite customers to set up a Data Warehouse independently of EPB and in a later stage implement processes to extract data from that DWH into the FEM Interface. Are the FEM Interfaces tables at the operational (fact) level or do they already have some sort of consolidation in them?"
    It depends. Data can be loaded directly into the EPF (new name for FEM) schema, but you'll probably want to cleanse and transform it first, most probably in a data warehouse. The data that goes into the EPF schema is at transaction level, and EPB will perform any aggregations as it loads data into it's AW. Of course data in the form of balances - that goes into the EPF balances table - will be to an extent already summarised (or at least snapshotted) but the twenty user data tables are just regular fact tables, with the granularity set to whatever you require.
    "Can Oracle somehow convince us that while EPB does not provide hooks for customization it will offer reports desired by non-EBusiness Suite customers with potentially very varied businesses? How much of EPB benefits are you missing out on if you do not have the E-Business Suite? What is EPB then giving you that with OWB and BI Beans/Discoverer you can not easily build yourself?"
    Too early to see really, especially as no-one apart from Oracle has done an EPB implementation yet. With regard to the question about what EPB gives you that OWB and BI Beans don't already give you, I think the relevant bit is "you cannot easily build yourself". EPB is an application, not a toolset, and it'll appeal to those people that want to buy a supported planning and budgeting application from Oracle, that integrates with e-Business Suite and doesn't require them to build everything from the ground upwards. With OFA and OSA you could have course build a similar application yourself, using Visual Basic or Express Objects and Express Server, but for most people buying it from Oracle was a more sensible solution.
    "The specific case of my customer: they have clear requirements for Management Information. Most of these are about analyzing historical data (the classic slicing and dicing); forecasting and budgeting would be a nice to have in the longer run. They currently do not have a proper Data Warehouse. They have a consolidation point for some operational data. No dimensions have been defined, no data cleansing is performed and some data is not available at all. I am wondering whether EPB would be the proper tool for them to start with. Given their requirements as well as their lack of current experience with BI as well as the relative uncertain situation with regard to the data sources, I would feel more comfortable with a more down-to-earth approach: start designing a DWH and the processes to populate it as well as developing the most urgently needed reports. In that case, EPB would be brought in at a later stage – when the organization as well as the data management is ready for more advanced stuff."
    Yes, I'd agree with this approach. EPB isn't the place to start integrating and consolidating data, and the EPF schema isn't where you'd want to store your complete data warehouse. You could of course, using the twenty data tables and the user defined dimension tables, but you'd pretty much be limited to querying via EPB (the schema isn't really suitable for querying directly using tools such as Discoverer) and the AW that EPB creates wouldn't be suitable/supported/documented for use by regular OLAP API tools such as Drake or the BI Beans. If it was down to me, I'd build the warehouse as normal, using OWB or any other ETL tool, create my dimensional model as normal, then take selected data out and put it in the EPF schema, and then carry out my planning & budgeting using EPB. I'd then still run Discoverer / Discoverer "Drake", or BI Beans or any other ad-hoc query tool against my warehouse schema for the warehouse "power users", and use EPB as the application for my finance and planning department,

  • Integration HP Planning and Budgeting to Oracle eBS.

    hey guys,
    i am very new to Hyperion and i want to know how to integrate Hyperion Planning and Budgeting to Oracle eBS.
    thanks and regards,
    Rahul.

    Hello,
    Unfortunately there is no prebuilt package that makes "Planning the source for OracleEBS". Right now the ERPi software you are looking at will only control budgetting information. You can review the current compliance of the software by doing a review of the documentation under the chapter "Data Write-back Rules".
    If you are looking to source pure data from Planning into OracleEBS then a custom solution will need to be developed and maintained outside of the Hyperion software .... or built to plug into the Hyperion Software (like ODI).
    Thank you,

  • Report Internal Order needed - showing Plan and Budget Values?

    Hello,
    I want to create a report (Report Writer/Painter) which shows for example in one column the planned values and in another column the budget value of an order group.
    I know the standard reports S_ALR_87012993 - Orders: Actual/Plan/Variance and the other standard report S_ALR_87013019 - List: Budget/Actual/Commitments.
    My question: Is it possible at all to have these both values plan and budget by order/order group in one report? - Or it is not possbile because these values are stored in different tables and different libraries?
    If it is possible with Report Writer, I would be very glad - if not, is there any other chance (e.g. individual programmed report)?
    For any comments or hints thank you in advance.
    Regards,
    VCG

    HI,
    both are report painter reports for libraries 6O1 and 6O2 which are based on reporting tables CCSS and RWCOOM.
    Try to find all value fields that you need in 6O2 / RWCOOM as this is the "big brother" of 6O1/ CCSS.
    Best regards, Christian

  • Enterprise Planning and Budgeting

    Dear All
    Does the Module enterprise planning and budgeting provides controlling functionality similar to encumbrance accounting in GL, or any other control functionality on transactions like Requisition/PO/Invoice  Item Wise...?

    Oracle Hyperion Planning, including PBCS, does not include built in functionality for pre-expenditures (a.k.a. encumbrances) or most other accounting controls you would find in PeopleSoft / Fusion Financials.  However, you can build this type of functionality into your Planning application. 
    For example, you could use the Version dimension in Planning (or create a seperate dimension for this purpose) to contain children members which would hold multiple entry types:
    Version
         + Approved
         + Encumbrances
         + Adjustments
    Version would equal Approved + Encumbrances + Adjustments.  Then you could create a Business Rule to do the following: 1) Approved = Approved + Encumbrances 2) Clear Encumbrances.  You could build the security in Planning to control who can input into "Approved" and who can run the Business Rule.  You could even use the Hyperion Planning workflow capabilities to incorporate work-flow controls into this process. 
    Hyperion Planning, and PBCS, provides the flexibility to build most financial processes and controls, but it is certainly not out-of-the-box functionality.
    Hope this helps.
    Jason Wells       

  • BW Datasource for Internal Order and Budget

    Hi Gurus,
    I would like to ask what datasource I can use for FICO specifically for Internal Orders and Budget. I have looked at all the datasources under the CO node but i can't seem to find a datasource that has the details for the Internal Order and for the Budget.
    Thanks in advance
    - Kit

    Hi,
          Check these datasources once.
    0CO_OM_OPA_8-- Orders: Budget Line Items 
    0CO_OM_OPA_2 --Orders: Budget 
    Refer this link as well.
    http://help.sap.com/saphelp_nw70/helpdata/EN/43/de43fcf6e2154bbbbcecbc63cdf287/frameset.htm
    Regards
    Karthik

  • Workforce Planning in Planning and Budgeting Cloud Servie

    Hi Experts,
    Does Oracle Planning and Budgeting Cloud Service (PBCS) have Pre-build modules Workforce Planning, Capital Asset Planning and Project Finance Planning.
    According to my understanding PBCS doesn't have any pre-build modules. I am not sure whether recently it has been added or not, so I wanted to double check.
    Thanks in Advance.
    Regards
    SKH

    PBCS still does not offer other planning modules like Workforce plnning/Capex etc.
    you can see more info at https://docs.oracle.com/cloud/latest/pbcs_common/CSPGS/apes02.html
    Regards,
    Sunil

Maybe you are looking for

  • How to pop up a new browser window to point to an external site

    Please help. we want to popup an new browser window when click on a button and the new window is pointing to an external web site. I can make it work to point to an external site in the same window. But that is not we want to. I do see some old posti

  • How to change a setting in the Java Control Panel with command line

    Hi, I am trying to figure out how to change a setting in the Java Control Panel with command line or with a script. I want to enable "Use SSL 2.0 compatible ClientHello format" I can't seem to find any documentation on how to change settings in the J

  • Exchange 2013 SP1 Installation Errors I Cannot Resolve

    Good Afternoon All - Note:  I updated this post an hour after posting.  Still no solution, but please see updated info at end of this post) I'm trying to introduce Exchange into an existing, small environment.  The server I'm trying to install it ont

  • AP Journal Import Error

    Hi all, While running process to import journal error occured. Description of error are as below: 1) User run ACCOUNTS PAYABLE JOURNAL ENTRY EXCEPTION REPORT, run completed with no error. 2) The follow up auto run of JOURNAL IMPORT EXECUTION REPORT w

  • 4 system landscape - ChaRM

    We are implementing ChaRM in Solution Manager with 4 system landscape.Our requirement is : Client need staging between quality system & production system. Dev ---> Quality - > Staging - > Production system. My query is : Once we create this staging s