Dear all,
   For one of our work center the process time for 1 to 25 pcs is same i.e.45 min. For every next one pc to 25 pcs it is again 45 mins, i.e. for first 25 pcs it is 45 mins and for next 25 pcs that is 26 to 50, it is 45 mins more. Hw to map this in formulas for work centers.
  Also what is number of split parameter in work center? Is that operation split? Hw is it effective in scheduling. Kindly describe with an example.

While defining standard values in routing specify base quantity as 25 pc/ea/set as per  base unit of measure  and specify the formula in work center as follows
Capacitities:
Capacity category               001
     Setup formula               SAP005
     Processing formula          SAP006
Incase you have labor involved for that work center ADD NEW Capacity category in work Center as 002
Capacity category               002
     Teardown formula          SAP007
And in scheduling definr formule as
Setup formula               SAP001
     Processing formula          SAP002
DO not specify teardown formula if this work center capacity category is machine (001)
In costing view  Define COST CENTER and  Standard values  their activity types and formule
NUMBER OF SPLITS IN ROUTING IS DEFINED IF IN WORK CENTER NO OF INDIV. CAP. IS SPECIFIED ( No Of Indv. Cap. = Number of Splits)
pavan

Similar Messages

  • Working day formula that excludes weekends and holidays in WEBI

    Hi Guys,
    Can we calculate a working day formula that excludes weekends and holidays in WEBI OR in Universe?
    The universe I am working on is using stored procedures, so there are no joins or modelling done. Although there is a workday stored proc  that I can bring in the universe.
    I am just thinking if there is no modelling or joins done in the universe how will this help me in webi?
    Your suggestions will be very helpful.
    Thanks,
    Jitan

    One more suggestion I need from you  -
    I have a Work_Calendar_VW that has the following columns -
    Calendar_Date - 5/1/2014
    Calendar_Year - 2014
    Calendar_Month - 5
    Calendar_Day - 1
    Work_Day - 1
    Day_Type - WD (Work Day)  For Weekends this will be displayed as WE
    The columns have all dates for current year in SQL Server.
    I am going to pull this into the universe and create 2 derived tables to calculate MTD Day counts.
    Derived Table 1  - Calculate Yest Work Day... this will remove all the weekends and holidays and give me the last working day. This includes couple of case statments to check each day if it's a working day or weekend.
    For Work Day the above code will be 1 and for weekend 0
    Derived Table 2  - This will give me the count of working days in current month using the above view and Derived table 1 Below is the code  -
    SELECT COUNT(*)
    FROM Work_Calendar_VW
    WHERE [Work_Day] = 1 AND
       (Calendar_Date BETWEEN CAST(CONVERT(VARCHAR(25),MONTH(LastWoringkday()),101) + '/01/'
       + CONVERT(VARCHAR(25),YEAR(LastWoringkday()),101) AS DATE)
      AND LastWoringkday()).
    I cannot do joins because this universe has been built using stored proc and would like to implement this in BO universe.
    let me know if this is the right approach.
    Thanks,
    Jitan

  • About Work flows in detail

    Dear Friedns,
    Can anyone please tell me the Step by Step procedure of Creatinga New Work Flow.
    I know the concepts about Work flow and T-codes
    But I want to know what is to be done after what and why?
    Because it is very much confusing for me.
    Points will be rewarded without any doubt.
    Thanks in Advance,
    Satya.

    Hello satya,
    Work flow creation.
    Check it out.
    All the Best!!!
    Manoj.

  • Work center formulas

    Pls guide me how to create formulas for work center activities for setup etc. pls guide.

    Hi,
      Create Formula parameters in OP17 . Refer to the std. parameters SAP_01, SAP_02
      Create Work center formulas in OP21. Refer to the std. parameters SAP001, SAP002 , SAP003
      Create formulas based on the Business process.
      Hope you can proceed with this...
    -Thaila Shree

  • ABOUT WORK INTEGRATION

    HI
    CAN ANYBODY EXPLAIN ME IN DETAIL ABOUT WORK INTEGRATION BETWEEN SAP MM,QM & FI/CO MODULES?
    SHAMIT

    MM-FICO
    Materail type, Movement type and Valuation Area are the keypoints to decide account to which it has to post.
    In OBYC transaction (FI Configuration) the following will be available..
    Transaction event key, Chart of Accounts, Valuation Grouping Code, Valuation class, Account Modifier, GL Account(Debit/Credit)
    Movement type --> Valuation string and Account Modifier
    Valuation String -
    > Transaction event key of OBYC
    Material type -
    > Valuation Class of OBYC and which Chart of Accounts it belongs .
    Valuation -
    > Valuation Grouping Code of OBYC
    With the combination of all bold ones system will decide to which GL account it has to post..
    This is one area where MM and FI are integrated..

  • Netherlands Working Hours Formula

    Hi Group,
    I need to overwrite a fast formula for Netherlands. This is what oracle has provided without give any explanation what is the type of the formula where to attach the formula. Please if any one has any input please share. I am stuck with this
    Netherlands Working Hours Formula
    Oracle HRMS enables you to derive the weekly working hours to appear on the Central
    Bureau of Statistics (CBS) file. You define a FastFormula with the name
    NL_WEEKLY_WORKING_HOURS, to return a parameter called Working_Hours with
    a value for weekly working hours in the format 99.99. The formula code uses any
    database items or balances to obtain a value for the weekly working hours.
    Note: If you do not define a FastFormula, the application draws the
    working hours from the Individual Working Hours held on the
    assignment.
    Thanks,
    Nitin Singh

    Hussein,
    I know how to write a formula it is this particular formula i need to overwrite. Oracle has not provide where to attach it or what type of formula is that the only thing which they wrote in the article u have mentioned is
    Netherlands Working Hours Formula
    Oracle HRMS enables you to derive the weekly working hours to appear on the Central
    Bureau of Statistics (CBS) file. You define a FastFormula with the name
    NL_WEEKLY_WORKING_HOURS, to return a parameter called Working_Hours with
    a value for weekly working hours in the format 99.99. The formula code uses any
    database items or balances to obtain a value for the weekly working hours.
    Note: If you do not define a FastFormula, the application draws the
    working hours from the Individual Working Hours held on the
    assignment.
    This is just partial information. What should be the type of formula where it need to be attached. Oracle has not provided with that at all.
    Thanks,
    Nitin Singh

  • Can i speak with someone online about working at apple

    Can i speak to someone about working at Apple, i have a long story.

    -> https://www.apple.com/jobs/us/

  • Working days formula and Crystal 7 - is it possible?

    Post Author: Tim F
    CA Forum: Formula
    Hi folks,
    Really hope someone can help, I'm struggling with writing a report that needs to show the difference between two dates in working days. I've found the same formula posted here several times but cannot get it to return a logical value in my report. I'm wondering if that might be because I'm using an older version of Crystal? The formula in question is this one:
    //Main formulaWhileReadingRecords;Local DateVar Start := ({PPV_COMPLAINTSEH.DTRECD});   Local DateVar End := ({PPV_COMPLAINTSEH.ACTCMPLTD}); Local NumberVar Weeks; Local NumberVar Days; Local Numbervar Hol;DateVar Array Holidays;
    Weeks:= (Truncate (End - dayofWeek(End) + 1 - (Start - dayofWeek(Start) + 1)) /7 ) * 5;Days := DayOfWeek(End) - DayOfWeek(Start) + 1 + (if DayOfWeek(Start) = 1 then -1 else 0)  + (if DayOfWeek(End) = 7 then -1 else 0);  
    Local NumberVar i;For i := 1 to Count (Holidays)do (if DayOfWeek ( Holidays[i] ) in 2 to 6 and      Holidays[i] in start to end then Hol:=Hol+1 );
    Has anyone come across an alternative way of doing this, or have any ideas why this formula is not working in my report? Any advice would be much appreciated,
    Regards,
    Tim

    Post Author: Charliy
    CA Forum: Formula
    You set up a Running Total.  Drag the filed you want Summed, Select Sum as the operation if that is not the default.
    Just below that you weill see Radio Buttons that say For Every Record, On Change of Group, On Change of Field, Use a Formula, etc - click the one that says Use a Formula.  The Blue Bos to its right will turn Red, click on it, this is where you put your formula: NOT(DATEPART('w',{table.date}) IN [6,7])
    Save that, then just decide if you want it reset on a Change of Group, or Never (Grand Total).  Give it a name and put it on your report.

  • Problem with combination of two working query formulas

    Hey guys,
    I have a problem in building a formula correctly with the BEx formula logic. I am sure, you can help me with this.
    Right now I have four columns in my query. The first column (Actual) displays actual amounts either in local (10) or reporting (25) currency type depending on the optional selection either in the variable screen or in the free characteristics filter. The second column (Actual with Budget exch. rate) always shows the actual amounts with the budget exchange rate of the reporting currency. The third column (Budget) is build in the same way as the first column, but shows budget amount data. In the fourth column (Variance) the variance between budget and actual data should be calculated, but here lies the problem:
    The formula should differentiate the chosen columns for the calculation depending on what currency type is selected either from the optional variable selection before the query is executed or from the free characteristics filter. So if I select currency type 10 it should calculate the variance by subtracting the budget column from the first column, but if I select currency type 25 it should subtract the budget columng from the second column.
    I have implemented a formula which works already, but not for both selection possibilities (variable screen or free characteristics filter). Either the formula works when I input a currency type in the variable selection screen or when I select a filter value in the free characteristics filter. However, I need to combine both formulas in one working formula so that the user can choose if he wants to filter the currency already in the variable screen in the beginning or in the filter after query execution. Here are the two formulas which I need to get combined into one formula:
    Used Variables:
    VScreen_Selection --> value from the key of the optional Currency Type Variable from the Variable Selection Screen
    Filter_Selection: --> value from the key of the InfoObject Currency Type
    Formula for Variable Screen Selection:
    (VScreen_Selection == 10) * (Budget - Actual) + (VScreen_Selection == 25) * (Budget - Actual with Budget exch. rate)
    Formula for Free Characteristics Filter Selection:
    (Filter_Selection == 10) * (Budget - Actual) + (Filter_Selection == 25) * (Budget - Actual with Budget exch. rate)
    Can you help me to combine both Formulas? I can't believe that this is too difficult. Many Thanks in advance.
    Best Greets,
    Norbert

    Hello.
    Did you try this:
    Formula 1: Hidden
    (VScreen_Selection == 10) * (Budget - Actual) + (VScreen_Selection == 25) * (Budget - Actual with Budget exch. rate)
    Formula 2: Hidden
    (Filter_Selection == 10) * (Budget - Actual) + (Filter_Selection == 25) * (Budget - Actual with Budget exch. rate)
    Formula 3:
    (Filter_Selection <> 10) * (Filter_Selection <> 25) *Formula 1 +
    (VScreen_Selection <> 10) * (VScreen_Selection <> 25)*Formula 2

  • Why do in-line conditiona​l expression​s work in Formula Node but not in 'Eval Formula Node.vi'?

    'Eval Formula Node.vi' and a standard Formula node seem identical in most respects in terms of their functionality, however I'm stumped by the case of inline conditional expressions. 
    I'd like to read in a string in the syntax "(expr)?(expr)expr)" from a text file and recieve the output as a double.
    The subVI seemed like the perfect tool since I was already using it to interpret a number of other calculations within the text file, however in this case the behavior is not as expected.
    Has anyone else ever tried this? is there a different syntax needed between the two tools?
    Are there other features of the Formula Note not replicated by this VI?  (so I can avoid them in future)?
    For simplicity I've attached a little demo of the behavior.
    I am currently working in 2010, which I know is getting on in years.
    If the behavior is improved in later versions, that may be a good excuse to upgrade :-) 
    Thanks,
    Elaine R.
    Attachments:
    Conditional Formula Node demo.vi ‏13 KB

    .aCe. wrote:
    Eval formula Node does not do any conditional expressions as far as I am aware.
    That is right. It's a rather dirty hacked VI library to do some formula evalution and has many limitations in comparison to the Formula Node including no support for conditional operator as well as some others. In addition it can also error on some more complex bracketed expressions.
    It is an old example VI that was never revisited and probably never will be as writing a new one from scratch would be easier. But considering that the Formula Node and Mathscript and other possibilities exist, this is not likely going to happen soon.
    Rolf Kalbermatter
    CIT Engineering Netherlands
    a division of Test & Measurement Solutions

  • Alerts not working when formula is in the cell

    I am having a problem where my alerts are not working in the preview mode.  They work fine when I hard code the alert range.  But I need the alert to change under differnt conditions and I am using an IF statement
    the formula is simple
    =IF('TXF Inputs'!D27=3, C34/2, C34)
    output is either 0.375 or 0.375/2 = 0.1875
    if i hardcode the cell with either of these values the alert works, but it does not work with the formula.  The confusing part is that I have other alerts that have IF statements in them and they all work.
    They also work fine in the main screen, ie it shows yellow if my default values =0.1875, but then when I preview or publish they don't work
    bw

    Can u give us the details like which component you are using for alerts.

  • Exception agreegation not working on Formula cumulative work

    Hi Guys,
    I have an issue with exception aggregation when I am trying to aggregate the values of Formula cumulative work.
    How we can aggregate the value of formula.
    formula is:    (finish date <= start date)* work.
    where finish date and start date both are formula variable with replacement path.

    Hi Anshu,
    I have tied this option also but it did not working.
    please see below output of the report.  Please see I am getting unique record based on the activity.   please help.

  • About Work progress on Forms 6i

    Dear Ainath,
    Thanks for your useful information about the work progress on forms 6i.
    The code you sent is run successfully.
    With regards to your code, How should I associate this with the task which will run on my forms 6i.
    I wanted that when the task begins on my forms 6i, it display the progress bar implicitly and when the task ended successfully the progress bar will also ended implicitly.
    And if the task on my forms fails , the progress bar also terminated.
    Could you plz also suggest me about that?if possible.
    Thanks
    David

    Does HOST('touch me'); create a file called 'me' in your working directory? Have you tried the command independently in UNIX as the same UNIX user? The results of these two tests may offer clues.

  • Work centre formula?

    Hi
         what are the impacts of formula we used SAP0,SAP008,SAP004 in creating maintenance work centre.If we do not use these
         formula what will be the impact.
    regards
    sanjay

    Hi,
    Formula SAP008,SAP004 are used in plant maintenance,customer service & Project network kind of scenarios.
    kapil
    Edited by: Kapildev Farakte on Dec 22, 2009 5:35 AM

  • Does unsigned 32-bit arithmetic work in formula nodes?

    I am trying to generate some 32-bit patterns to control my instrument under test. The easiest way to assemble these patterns seems to be to put the bits together in a formula node by shifting and OR'ing. All of my LabView variables are defined to be U32, and the corresponding variables in the formula node are uInt32.
    The problem is that whenever I assign a "1" to the most significant bit of a variable, the entire value is coerced to zero. What is happening? what might I be doing wrong? I checked all of the obvious things, such as incorrect data definition, etc. I tried putting together the pattern in various orders, and I narrowed the assignment down to its simplest form. However, I still cannot get a value of 1 into the most significant bit of the U32.
    Is there a way around this problem?
    Thanks,

    Well I seem to have recreated your problem using the formula node (either that or we're both not doing something right).. Look at "out1".
    The logical shift function works fine of course.
    Message Edited by Bill@NGC on 07-30-2007 08:42 PM
    “A child of five could understand this. Send someone to fetch a child of five.”
    ― Groucho Marx
    Attachments:
    shift fp.png ‏219 KB
    shift bd.png ‏206 KB

Maybe you are looking for

  • EDI_DC40 Segment Issue

    Hi Experts, Scenario JMS -- XI -- IDOC I have tested the interface and found it works fine.  As disabled EDI_DC40 segment in mapping and checked Apply Control record Values from Payload  in the Receiver IDOC communication Channel. Since I have develo

  • Mail Preferences Dialogue Box

    I don't appear to be getting the correct dialogue box when I click on "Mail", "Preferences". A dialogue box that is titled "Accounts" appears. I know looking at a friends Mac, he gets an entirely different box. We both appear to have the same version

  • RemotePortletCommunicationError

    Hi while consuming the producer page,i'm getting the below exception. Can i confirm that producer is up when wsdl url is displaying? What mi8 be the issue? Log: <HTTPClientTransport> <invoke> A request to the producer URL "http://adcdaa03.us.oracle.c

  • Patches Update

    Hi all, We've upgraded B1 2007B patches.  I've installed PL06 in server.  One of my client PC is showing an error called, 'Another version of this product is already installed. Installation of this version cannot continue'. In addition to the above c

  • Desktop icon duplicates itself in my safe file dialog

    This is something that's been puzzling me for a while. Every once in a while my Desktop icon duplicates itself in my safe file dialog. I don't know when this happens, but I'm unable to remove them and it keeps growing and growing. Can anyone help me