Blanket Purchase Order and the Framework Order

hi Gurus,
I wanted to know the following.
What is the difference between Blanket Purchase Order and the Framework Order.
Thanks.

Hi,
Framework order is also known as Blanket PO.....which we use for the procurement of Low value Material with Long term planning....It is used as Mini Contract....
Blanket Order:
Used for long validity period and with the provided value limit. By its name u201Cblanketu201D which covers to required long time? We use doc type FO(for long period) and item cat. B(for value limit).Goods receipts or the entry and acceptance of services performed are not necessary in the case of a blanket PO and limit items. The invoices are posted directly with reference to the purchase order, provided that the specified value limit is not exceeded. But manual entry of invoiced amount and invoiced quantity is required during LIV process.
Example: Procurement of stationary items.
Frame work order:
Framework order (FO) is a document type which is provided by the standerd SAP.
It can be used for the consumable material ( Which is having low value & where making GR is not of worth like C category item.) & called as blanket PO. Here we need to mntion the validity period & target value or quantity as a restriction as well as need to mention item category as a "b".
Also it can be used for the procurement of extarnal services (Item category "D" ). Here we need to do the entry of services which have been performed & need to accept the same whereas in blanket PO, GR is not required.
At the end i would tel u that Framework order is the document type which can be used as blanket Po & procurement of services.
Regards
KK

Similar Messages

  • What is the diffrence between a blanket PO and a Framework order?

    What is the diffrence between a blanket PO and a Framework order?

    Hi
    You have to use document type Frame work order for Blanket PO.
    You can use blanket purchase orders to procure consumable materials or services for which it is not worth creating a separate purchase order for each procurement transaction. 
    Blanket purchase orders are usually valid for a longer period of time. You can directly post the invoices for the materials and services procured for this blanket purchase order.
    Raju

  • Purchase orders and their open order quantity with their due dates.

    hi friends
    i need to build  a query  where i can see the purchase orders and their open order quantity and their respective due delivery dates.i have never done  this.
    ME2M serves my requirement  upto little but i cannot see the delivery dates in that report.
    please help mein finding the steps involved in building the query.
    Thanks
    Alahari

    Use the table EKPO and EKKO
    adhoc querry is a tool in which we can create report
    to get report we have to use three t. codes
    1.sq03-->is for to create user group
    2.sq02--.is for infoset Querry
    3.Sq01-->for exact querry
    try with these codes or revert with ur response
    follow the link for query creation
    First check this link,
    SAP Query Creation
    SAP Query -A Reporting Tool for Functional Consultants(Part 2)
    SAP Query 1
    SAP Query -A Reporting Tool for Functional Consultants (Part 1)
    Always after going to SQ02 or SQ01 T Code ,first click on Environment in the menu ->Query Areas-->
    Standard Area Client specific and then start creating the Infoset or else the query.
    Still if you are not satisfied means,please revert back.

  • Purchase orders and their open order quantity with their due delivery date

    hi friends
    i need to build a query where i can see the purchase orders and their open order quantity and their respective due delivery dates.i have never done this.
    ME2M serves my requirement upto little but i cannot see the delivery dates in that report.
    please help mein finding the steps involved in building the query.
    Thanks
    Alahari

    Deliver date is available in table EKET field EINDT.
    Use table : EKKO ,EKPO, EKET.

  • Uploading Purchase Order Against the Sales Order through DTW

    Hi Experts,
    I searched the forum but could not see anything regarding this.
    Can I upload Purchase Orders against the Sales Orders using DTW upload facility? Manually we do it through the Logistics Tab in Sales Order.
    Thank you in advance.
    Kind Regards,
    IC

    Hi,
    You can use the BaseType, BaseEntry and BaseLine columns for this in the row level template (DLN1):
    BaseType: it's the Object Type of base document (ORDR.ObjType) which is '17' in case of Sales Order
    BaseEntry: it's the Document Entry of the base document (ORDR.DocEntry)
    BaseLine: it's the row number of the line in the base document (RDR1.LineNum)
    If you import your Delivery Notes with this info, the link to the Sales Order will be updated just as if you used Copy To in SAP.
    Regards,
    Nat

  • Badi for purchase requisition and stock transfer order

    Hi,
    Could anybody please tell the BADI to update the item details (dates etc) in the 'Purchase requisition' and stock transfer orders.
    I could find ME_PROCESS_REQ etc but could not locate the methods to modify the item level data.
    Thanks & regards,
    Ravish

    Hi,
    You can use the same badi which you found out.
    ME_PROCESS_REQ.
    In that there is a method process_item.
    There you can get the line items of the PR.
    Then in the POST method you can do the stock transfer .
    In the check method also you can check the entire process of PR.
    With Regards,
    Sumodh.P

  • How to avoid purchase req and stock transport order to take part in MRP.

    Please suggest how to avoid purchase req and stock transport order to take part in MRP.

    hi,
    check the settings for the MRP type...there you need to show which doc will be taken into considerations...
    SPRO >> MM >> CBP...
    Under CBP check for the MRP settings where it is placed(check under master data settings)...and check for the indicator for PR's and STO's release orders under tab "Additional external req. in the reorder point planning"..
    Regards
    Priyanka.P

  • Sales order and return sales order in the same field

    Hi Everybody,
        I have sales sales order and return sales order in the same field ,how can i separate these two orders in the report.
    Your suggestions are appreciated
    Warm Regards
    Shreya

    Both are sales documents and should be separated by document type....i assume that all the documents are sotrd in the same infocube and if you have tha document type characteristic you can separated them directly in a report
    Regards

  • Link India Localization with Blanket Purchase Agreements and Releases

    Could anyone highlight on how India Localization Taxes be linked with Blanket Purchase Agreements and Blanket Releases?
    Any additional Setups required?
    Shubhendu Chakraborty
    Kolkata.INDIA.

    Only Amount Agreed field on header level can control the checks on the blanket purchase order.

  • Procurement cycle in third party order and stock transport order.

    please provide me in steps the procurement cycle in third party order and stock transport order.

    Hi,
    STO Process: -
    1.Create a vendor for the company code of receiving plant, using account group :0007 using T-Code XK01.
    2. Assign this vendor to Delivering plant
    Go to XK02 >Purchasing view>Extras>Add. Purchasing data>Plant
    3. Create internal customer with the sales area of the vendor. Go To XD01
    4. In Pricing procedure determination relevant to STO, assign document Pricing Procedure and customer pricing procedure appropriate for STO to get the pricing in the invoice.
    5. Maintain condition records for the relevant pricing condition.
    6. Some more setting for STO: Go to MM> Purchasing > Purchase Order > Set up STO > define shipping data for plants > Go to Receiving plant >assign customer here & Supplying SA (for billing) to Receiving plant here
    7. Go to MM > Purchasing > Purchase Order > Set up STO > define shipping data for plants > Go to Supplying plant and assign the sales area of receiving plant.
    8. Go to MM > Purchasing > Purchase Order > Set up STO > assign delivery Type & Checking rule
    Assign the delivery type to document type. In this case, Delivery type NLCC is assigned to Document type NB
    9. Go to MM> Purchasing > Purchase Order > Set up STO > Assign document Type, One step Procedure, Under delivery tolerance
    Assign the document type NB to supplying plant and receiving plant
    10. After all settings , Create the STO using T-Code:ME21N and maintain pricing conditions of freight and Save.
    11. Create Delivery :VL10G
    Click on the Background Button after selecting line item
    A message is flashed : See log for information> next Click on Log for delivery creation Button >click on line item>click on document button to get Delivery document No
    12. Picking, PGI:VL02N
    13. Billing:VF01
    Save the document and its done
    14. J1IIN - Outgoing Excise Invoice
    15. MIGO - Goods Receipt against outbound Delivery
    16. J1IEX - Capture & Post Excise Invoice
    Pricing configuration for STO: -
    In SPRO > MM > Purchasing > Conditions > Define Price Determination Process > Define Schema Determination > Determine Schema for Stock Transport Orders > Here assign Calculation Schema "RM2000" i.e. Stock Transfer Document to Schema Grp Pur. Org, STO Type (For e.g. UB) and Supplying Plant.
    Calculation Schema "RM2000" has condition type P101 which will pick up the MAP of supplying plant automatically during creation of STO in ME21N ("Conditions" Tab).
    You can create new freight / delivery cost conditions in M/06 and assign in pricing procedure "RM2000" in M/08 and also assign the Accrual Key to this and do the Account Determination for this Accrual Key in OBYC
    At the time of PGI, following accounting entry will get generated;
    Stock A/c - Dr - 110 INR (Receiving Plant)
    Stock A/c - Cr - 100 INR (Supplying Plant)
    Freight Clearing A/c - Cr - 10 INR (Supplying Plant)
    Third Party Process Flow: -
    1) MM01 - General Item category Group should be BANS in basic view of material master.
    2) VA01 - Creation of sales order with VA01 transaction in SD module
    3) When sales order is created system automatically creates a PR for the material with item category as "S"--> Third Party Item
    4) ME21N - Directly PO with item category as "S" and delivery address as customer address
    5) MIGO - Statistical GR by MM ( When it is made goods are received and delivered)
    6) MIRO - Invoice by MM for vendor
    7) VF01 - Billing by SD on Customers

  • Different product hierarchy in sales order and in service order

    Dear experts,
    In VA03, I notice that
    - under Line Item > Sales B, there is a field Product Hierarchy
    - under Line Item > Account assignment, there is a field Order. From here, it links to a service order. In the service order, I can see a field Product Hierarchy too.
    I would like to know if there is an implication when the field Product Hierarchy in sales order and in service order are different. Is it possible that this will cause an inconsistency?
    Usually these two fields have the same value, since the value in sales order is copied from service order. However, in my case, the product hierarchy is changed/updated in service order, but not in sales order.

    Hi,
    We have document pricing procedure maintained at two levels for Sales order or Billing type.
    The pricing procedure is determined based on SAles Area Customer pricing procedureDocument Pricing procedure+pricing procedure.
    Example :For Sales Document type the document pricing rpocedure will be A and for billing type 'B"
    Sales Area1A+Pricing procedure A
    Sales Area1B+Pricing procedure B
    Now A will be maintained in VOV8 and B will be maintained in VOFA.So two pricing procedures.
    Regards,

  • What to do with the Sales Order once the Production Order is TECO?

    Hi everybody,
    What to do after a Production Order is confirmed, GI, GR, and the Production Order is Technically Complete?
    In MD04, I can still see the Sales Order, and I can see also the line with CSTOCK (Customer Stock).
    What to do now to complete the scenario?
    Thanks in advance,
    Rudy.

    Thank you!
    But I get the following message in VL01N:
    "No schedule lines due for delivery up to the selected date "
    What does it mean exacly?
    I have a Confirmed Production Order.
    I have a quantity in CSTOCK.
    So, what is missing here?
    Thanks in advance!
    Rudy

  • To create a stock transport order and third party order

    please explain steps to create a stock transport order and third party order with transaction code what are the pre-requisite. related to MM?

    First you need a supplying plant. stock ready to transfer for a matetrial which should be created/extended at both the suppling and receiving plants.
    The order type is UB
    rest of the things are Pur org, Pur Grp, Company Code etc...
    The most important part is Vender has been replaced by supplying plant.

  • Authority check for sales order and stock transport order

    In my code i have a requirement to enter sales order and Stock transport order. However i want that a WM resource should not be allowed to enter sales order and an SD resouce should not be allowed to enter stock tranpsort order. Please suggest.

    Hi,
    Another way to solve this is create a Z table with field user name and Resource type and compare the user id ( sy-uname) with the Z table and allow accordingly.
    In production environment controlling authorization in this approch is much easier.
    Hope this helps.
    Regards
    Bikas

  • WHAT IS SALES ORDER -OENSALES ORDER AND CLOSE SALES ORDER

    HI....
    WHAT IS SALES ORDER -OENSALES ORDER AND CLOSE SALES ORDER
    WHAT IS MB1C AND  MB1B TCODES

    Hi
    If the sales order is made with a Qty of 10 items in it , if the all 10 items are delivered to customer then that is called as Closed Sales order
    Means if Sales order Qty (vbap-kwmeng) = Delivery qty (lips-lfimg) then that is losed other wise out of 10 qty 5 are supllied and 5 are yet to be supplied then that is open sales order
    MB1C = Goods receipt for others
    MB1B = Transfer Posting for Material Moving
    Regards
    Anji

Maybe you are looking for

  • Can't sync new iPhone 4 with iTunes without it locking up iTunes

    Got my new iPhone 4 last Friday. They tell me I need to register it and sync it. Didn't get around to trying that until yesterday. Tried most of the day and night last night, using iTunes 9.whatever it was. Kept on locking up iTunes. Tried deleting i

  • IPod can't be updated...not enough space hold selected playlists

    My nano will not update automatically any more. Yes, there is enough space but the newest iTunes refuses to see it. Also, the only sure way to get songs out of nano is to delete it manually. Even unchecking them does not work. I regret upgrading to t

  • Trigger based on data load from sqlldr

    I am trying to trigger an event based on when data is loaded to a table. This load is done via sqlldr with the following: LOAD DATA TRUNCATE INTO TABLE cushis FIELDS TERMINATED BY "|" (chdiv_id, chdiv_no, chcust , period_no , csaln , csupv , DOC , DO

  • I need to substitute the default font (times roman) in my editable form fields with a san serif...

    I am making a PDF with editable form fields out of InDesign CS6. When I make the interactive PDF, the font, Helvetica Neue  is being substituted with the default font, Times Roman. The client has provided me with last years PDF which has a nice San S

  • Ichat not supported on my macmini intel?

    hi all..i tried to get ichat working on my macmini intel core duo 1.66....it starts and takes quite a while to login ( it eventually does after 2-3 minutes waiting for login), but under video/audio settings it says: your computer doesn't support vide