Hello,
as far as I know the systems automatically creates elements when the cardinality is 1..1 or 1..n. Now I would like to know when exactly the system does this creation of initial elements.
One of my context nodes has a cardinality of 1...1. In some cases I can't set the attributes because there is no element. Therefore I want to have a better understanding of when the system creates initial elements.
Best regards, Hergen

Hi,
A context element is created automatically, if
- it is declared with cardinality 1..1 or 1..n and
- there is no supply function declared for this node.
If a supply function is declared, it has to make sure that the cardinality is fulfilled.
The creation of the first element is done at the same time as the supply function would be called, if there werde any.
This means: as soon as you access the element (e.g. by reading or writing any of it's attributes) the element is created.
So there should be no need for you to worry about the time, at which the element is created.
I assume that the element is not created, because you have declared a supply function.
Ciao, Regina

Similar Messages

  • Automatic creation of cost elements

    Dear All,
    The automtic creation of cost elements functionality is not working for some GL accounts in production. When new GL accounts are created, the same are not created as cost elements. All the standard settings viz 'selection of automatic creation' in controlling area configuration, creation of number ranges in OKB2 etc are in place. We posted in OSS and they are not able to find reasons why this is happening.
    Has anyone faced a situation like this? Please post your valuable thoughts and share your inputs. We currently have a log created by user on this and pending for quite sometime.
    Thanks in advance
    Venkatesh

    Hi,
    Yes. We do face problem like this often. We wriggle out by updating through manually when we are very nearer to go-live date. Otherwise, we can create an abap program and meet the deficiency.
    Trust this helps much!
    Cheers!

  • Automatic creation of WBES element using front end application

    Hi,
    i am looking at developing a front end tool where user will provide the required data and project name/wbes lement in the request. upon approval from project manager, sytem must creation requird WBE element in the requested project automatically. there will be multiple requests supplied to create wbes lements under the existing projects.
    for Eg. assume that there is a project AB11.00001 
    i have already have one 4th level wbes element like displayed below:
    AB11.00001
    AB11.00001.01
    AB11.00001.01.01
    AB11.00001.01.01.01
    AB11.00001.01.01.02
    AB11.00001.01.01.03
    now i would like to add new 3rd level and 4th level for above project as mentioned below:
    AB11.00001
    AB11.00001.01
    AB11.00001.01.01
    AB11.00001.01.01.01
    AB11.00001.01.01.02
    AB11.00001.01.01.03
    AB11.00001.01.02
    AB11.00001.01.02.01
    AB11.00001.01.02.02
    AB11.00001.01.02.03
    AB11.00001.01.03
    AB11.00001.01.03.01
    AB11.00001.01.03.02
    AB11.00001.01.03.03
    this must be done either using bapi or any other programme, i tried with bapi, but not able to solve, pls help me with best way of executing this auto application rather creating manually one by one using CJ20N. i am very sure we have finest ABAP'rs in this forum who will build this programme..
    thanks
    naveen lewis
    Edited by: naveennl on Aug 16, 2010 11:39 AM

    Hi Rifaee,
    appplogies for misunderstanding..
    i want only the clues how i can execute this using some of the available SAP functionalities.. ofcourse finest ABAP'rs only think out of the box to solve this and rest will usually answer it as not feasible.
    Edited by: naveennl on Aug 16, 2010 11:51 AM

  • Creation of cost elements automatically

    Hi,
    When I selected "manual creation of cost elements" in OB13, Then we can create a group of cost elements in OKB2 followed by OKB3 and SM35.
    Even I need to do same thing  I when I select " automatic creation of cost elements" ??
    I tried selecting " automatic creation of cost elements".  and I checked in KA03 whether it had created any cost element automatically. but it didnt created any thing...
    Please suggest..

    Dear Santosh Dharana,
    Good Question.  i can clarify you. this question
    1. when you select in ob13 create cost elements manually
    when your are using in obk2  we have to maintain here Acc from no. to Acc to no. ranges for Gl's and cost element categeory.
    after we can run batch in put in obk3 & SM 35 it's updated successfully.
    Note: After execute, *when you are try create another GL account with cost element we have to give cost element categeory by manually.
    2.when you select in ob13 create cost elementsAutomatically
    when your are using in obk2  we have to maintain here Acc from no. to Acc to no. ranges for Gl's and cost element categeory.
    after we can run batch in put in obk3 & SM 35 it's updated successfully.
    Note: After execute, when you are try create another GL account with cost element we don't have to give any cost element categeory here  system automatically give .
    Please try it.  i worked for this one
    Thanks & Regards
    shankar

  • Creation primary cost elements

    Primary cost elements can be generated in batch for creation, but then it seems to me it's all of them or nothing.
    Is this also possible for 1 year for instance or for a limited number of cost elements, via another transaction for instance.  MASS create?

    Hi Walter,
    First of all you have to select automatic creation of cost elements for your chart of account in OB13.
    Next in OKB2, you have to specify the cost element category for the range or single cost elemets.
    Next create batch input session in OKB3, here you can give from and to valid date.
    You have to execute the created batch input session in SM35.
    Rgds
    Murali. N

  • Creation of PL Element without it being a cost element

    Hi
    I have to asign two PL elements in T code 0KEK for transfer of material between two profit centers. The two elements should not be <b>cost elements</b> but they should be PL Elements to be used only in PCA.
    We have to create PL elements through FS00. But the system automatically creates a new cost element when i create a GL as a PL nature. Pls let me know how to create a PL element without it being a cost element.
    Regards
    Sanil Bhandari

    Hi Sanil
    IN OB13 
    Controlling integration tab
    select : Manual creation of cost element and create GL accts.
    Hope this works
    Best Regards
    Ashish Jain

  • IO automatic creation of plan settlement rule according to actual settlemen

    Hi guys,
    does anybody know, if it is possible to create mass wise plan settlement rules on internal orders according to actual settlement rule? Sounds like a normal requirement, but I did not find anything.
    Automatic creation of settlement rule seems only to work like (KSR1_ORC in customizing):
    01     No autom. calculation / manual maintenance
    02     Settlement to a profitability segment
    03     Settlement to a requesting cost center
    04     Settlement to a responsible cost center
    05     Settlement to sales order
    06     Settlement to a WBS element
    08     Settlement rule from assigned WBS element
    30     Settlement on Acct Assgnmnt from CRM or Errors
    31     Settlement on Acct Assgnment from CRM or on Event
    35     Settlement on Receiver from Accounting Indicator
    but nothing like "automatic on basis actual settlement rule"....
    Note: we can not use any of the above rules for plan, since also actual has to be entered manually.
    br
    Bjoern

    Hi
    See if you can use exit COOM0003 for auto creation of settlement rules.. Here you can write your own logic
    br, Ajay M

  • Manual/Autometic creation of cost elements in chart of accounts field

    Dear Friends,
    While creation of Chart of accounts (OB13) under  Controlling Integratiion tab
    thers is two options are there.
    1 manual creation of cost elements
    2 autometic creation of cost elements.
    While creation of cost elements if we select
    (MANUAL CREATION OF COST ELEMENTS) what will happen???
    (AUTOMETIC CREATION OF COST ELEMENTS) what will happen?
    What is the main difference between about two fields?
    Thanks in advance,
       Mallika

    Hi,
    MANUAL CREATION OF COST ELEMENTS -  Cost elements maintained manually. A push button is available for
    this purpose, with which you can go directly to the related cost
    element.
    AUTOMETIC CREATION OF COST ELEMENTS - Cost elements maintained automatically. When you save a new G/L
    account, the related cost element is automatically created. A prerequisite is that a default value for the cost element category
    has been set up for this cost element. If no default value is found, the system will not create a cost element.
    You can make default settings via :
    Cost Element accounting --> master data --> cost element --> automatic creation of primary and secondaru cost element --> make default settings
    Dhara.

  • Automatic creation of the Cost Object Owners in WorkFlow

    Hello Experts,
    Business requirement background is
         SREQ Contact person just enter cost object and submit for approval.In all cost object cases he can save the service order and submit. After SREQ FRA reviewer approval, before workflow  notification mail is sent to  cost object owner, system will check if the user exist in X92 system or not. If user is not exist, based on GDDB id, automatically the user will get created in X92.
    And The solution will be as follows:
    1). Once the SREQ FRA reviewer approves the SO, then the notification mail be send to the Cost Object Owner
    2). Here system should check GDDB ID of the Cost Object Owner, is it exist in X92 system or not.
    3). If GDDB ID is not there in X92 system, then on the basis of the GDDB ID, the system should automatically create the SAP user ID for the CO Owner and an email is to be send to the CO Owner for the approval of the SO along with the user id details.
    4). If GDDB ID exists in X92, the SO will be submitted for further approvals.
    How to Customize the steps 2 & 3 that i mentioned in the solution?
    Any help form experts will be appreciated and rewarded
    Thanks in advance....
    Regards
    Satya
    Edited by: gsnreddy on Mar 24, 2011 2:14 PM

    Hi,
    You have to do two settings:
    a) for chart of account switch the flag for automatic creation (OB13)
    b) maitain the logic for defining of cost element category (OKB2)
    Regards,
    Eli

  • Automatic Creation of PO by workflow once PR is released.

    Hi All,
    Can anybody explain the details steps for creation of workflow template if PR is released then automatic creation of PO needs to be created with reference to PR.?
    Thanks,
    Ravi

    You can take a look at standard Workflow WS20000075(PO). Regarding your requirement most probably you need to do some configuration. In SRM this is possible once a Shopping Cart is completed it can be converted to a PO.
    Thanks
    Arghadip

  • Automatic creation of rfq against pr reference?

    dear mm experts,
    i would like to know whether std sap - mm allows automatic creation of rfq against pr reference.
    i have a requirement user creates prs for materials, and rfq have to have to generated/created automatically after pr is saved. is this possible with std sap spro settings
    pl help
    thanks in advance
    srihari

    If you refer the same document on the following link you see that RFQ is not automatically
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/75/ee1fa755c811d189900000e8322d00/frameset.htm
    What does their mean automatically is
    using the assign and process you can create RFQ. but not like Auto PO using Me59n
    Creating RFQs
    To create RFQs, you must generate a basic list via Requisition ® Follow-on functions ® Assign + process.
    From the basic list, you can flag a requisition for RFQ processing. Select a requisition and choose Edit ® Flag for RFQ ® With vendor or Without vendor.
    Choose Goto ® Assignment overview to access the assignment overview screen. Position the cursor on the text Flagged for RFQ processing and choose Edit ® Process assignment.
    A dialog box for the creation of RFQs appears.
    Enter the deadline for submission of quotations and check other relevant data, such as the purchasing organization.
    When you press ENTER, you will obtain an overview of the purchase requisitions that have been flagged for RFQ processing.
    Select the items that are to be adopted in the RFQ.
    Adopt the selected items in the RFQ.
    u2013 If you wish to change the selected items before adopting them, choose Edit ® Selections ® Adopt + details. The relevant item detail screens will then appear, allowing you to make the desired changes.
    u2013 To adopt the selected items without changes, choose Edit ® Selections ® Adopt.
    The item overview for the RFQ to be created is displayed with the adopted items.
    If you have flagged the requisition for RFQ processing without a vendor, or if you wish to issue RFQs to another vendor, assign the RFQ to a vendor and save the document.
    Repeat this process for each vendor to whom the RFQ is to be issued.
    For more information on the creation of RFQs, refer to the section Creating RFQs.

  • How to switch off automatic creation of the business partner?

    Hello!
    Advise please why in erp after creation of the customer automatically form business partner? How to switch off automatic creation of the business partner? It very much disturbs, because business partner are created from crm. Because of automatic creation business partners are duplicated.

    Hi,
    I have made the following customizing settings to activate customer integration with business partner, but the problem is when I create a BP with a role (FI-Customer) the customer is not created automatically.
    1. Set BP Role Category for Direction BP to Customer
    Roles: FLCU00 - Business Partner FI Customer (FS: BP)
    FLCU01 - Business Partner Customer (FS: BP)
    2. Defined the Number assignment for Direction BP to customer
    4. Customer account group and numbering is also defined.
    3. Created a BP with BP Role FLCU00, I can see the Customer - General Data tab, but no customer was automatically generated by the system.
    Kindly let me know if any customizing I have missed.
    Regards
    Ameya

  • Functional module for automatic creation of pur requisition & pur order

    hello,
    what is the functional module for automatic creation of puchase requisition and automatic creation of purchase order which we will assign in action box in service order processing management.
    please let me know as early as possible
    regards,
    rajesh kumar raju

    Hi,
             Please check with following.
    IDOC_INPUT_ACC_PURCHASE_REQUI
    IDOC_INPUT_ACC_PURCHASE_ORDER
    /ISDFPS/OR_PURCHASE_ORDER_CR
    BS01_PURCHASE_DOCUMENT_CREATE
    CO_MP_CREATE_PURCHASE_ORDER
    Thanks & Regards
    Sadhu Kishore

  • Stop Automatic creation and confirmation of Transafer Order for a doc type

    Hello All,
    There is a requirement that I need to stop Automatic creation and confirmation of Transafer Order for a particular document type.
    The issue is that sometimes the cycle goes upto creation of Invoice automatically but sometimes this does not happen. More over the user wants that the transafer order needs to be confirmed manually.
    Can u please provide the .steps involved for thie case.
    Thanks
    Chandrashekhar

    Dear Steve,
    Thanks a lot for giving reply with what I need to do, but I am unable to see result.
    I have down configuration like below even though system not processing Auto TO creation. Can you explain me if I have down any mistake below.
    Click on ‘Assign’ button,
    Press on ‘New entries’
    WhN = ‘900’
    Reference Movement Type = ‘101’
    Movement indicator = ‘B’
    Movement type for Whse Mgmt = ‘101’
    TR create Transfer Requirement = ‘X’
    Immed.TO Creation
    Mail confirmation for background processing = ‘01’.
    GR date = ‘2’

  • Automatic Creation and Confirmation of Warehouse Task in EWM 5.1

    Hello,
    We want an automatic creation and confirmation of the warehouse task in EWM 5.1 on the based of a delivery type and warehouse number.
    The scenario goes in this way... As soon as the inbound delivery is created/replicated in EWM, the creation and confimartion of warehouse request, warehouse task and warehouse order (all the transactions) should be called automatically. And the goods receipt should be posted.
    Can someone throw more light on the customizing/BADI/enhancements etc required??
    Thanks and Regards..

    Hi koen,
    I tried with the FM that you suggested...
    But somehow with the process type 'stock removal' gives an error...
    Is that that this FM will help to create a pick task for a particular outbound delivery--Tcode:/SCWM/TODLV_TO.
    how will this FM take the outbound delivery as an input?or it will be on the corresponding sales order number and item number as input?
    Being new EWM i require help on this..about how to go about creating the pick task for an outbound delivery which wil be equal to the warehouse request.
    Thanks in advance,
    Rashmi.

Maybe you are looking for

  • JDev doesn't recognise my EJB3 beans as beans

    It thinks they're PoJos. The beans are developed from its own CMP Bean producing wizard. I've about 15 other beans in this package generated in the same way and it recognises those as EJB Persistent Entity beans... The problem is that now when I try

  • Keychain won't remember passwords

    after upgrading to SL the keychain no longer wants to remember any passwords. this is effecting ALL passwords, both online and off. The ones already in the keychain do not work anymore. Any assistance is much appreciated Thanks

  • Looping login screen in Crystal Reports for Visual Studio 2008

    Hello, I am using Visual Studio 2008 with the Crystal Reports Basic for Visual Studio 2008. Visual Studio and the Crystal Reports Basic Runtime for Visual Studio 2008 (x64) are installed on both the development and production boxes.  I am using Cryst

  • How to wait until setPage(number) is finished

    SR 3-8311228061 When calling getStrings, found I need to iterate the pages of the doc/xls/etc However Autovue Support tells me that setPage() is asynchronous I asked how to wait until setPage() is complete, they suggested I post the question here Not

  • How do you retrieve lost notes

    How do I retrieve deleted notes on my Apple devices?