PS Experts,
Please guide me on the following case,
I have a customer project started 5 months ago with
RA Type (e) Revenue-Based Results Analysis
Profit Indicator (M) With Profit Realization
Actual cost incurred , No billing to customer
During the periods end closing through tcodes KKA2 & CJ88 the system performs WIP and posted in FI
This month my customer asks to change the Profit Indicator to be (Q) Percentage-of-Completion
I tried to do these changes and i made change in CJ20N in RA KEY and run KKA2 & CJ88 the result is that the system performs Sales in Excess but it keeps the old WIP and didn't delete them
My questions are
Is that right to change the valuation method in one project during its life
How does the system perform Sales in Excess/Bill in Excess while WIP( Work in progress) already performed and didn't automatically delete the WIP
Does it mean that a manual entry is needed to delete the WIP
Thanks
it is not a good practive to change RA method in the life cycle of its project
having said that if the change is relatively imple like changing Cost based POC to REv based POC then there would be no prblems as all the accruals and deferrals would readjust based on the new method
even with Q I would have assumed that this would be no issue - have you maintained the POC using statistical key figures??
if you need to do this with effect from previous month then you have to undo settlement and then recalculate RA and the settle again as explained by Paul
Similar Messages
-
Public Change Management indicator and mid-year reassignment in new GL
Dear experts,
I have two questions on documentation at help.sap.com
here http://help.sap.com/saphelp_erp60_sp/helpdata/en/b3/fa3a95ecd9465c82957992e30e1ff2/frameset.htm
it is said that:
1. "You can use the SAP document change interface to reassign original documents by setting the Public Change Management indicator when converting the worklist."
I run FMCT transaction and can not find this "Public Change Management" indicator. Where should I look for it?
2. "When you update in new General Ledger Accounting an FM account assignment that is to be reassigned, a mid-year reassignment is not possible"
Does this mean that I can not do a mid-year reassignment, if I use the new General Ledger Accounting?
Thank you in advance!
IrinaHi Irina, as I know this applies if the FM account assignment element is an split charateristic in the New GL, for example the Fund, if the fund accounting scenario is active.
best regards
César -
Transaction code to change group indicator & group number of a routine
Transaction code to change group indicator & group number of a routine
Post Author: paul.carpenter
CA Forum: Formula
Sorry for the ignorance. I did a little more playing, created a group summary count, then checked it against my record count per group.
All set now! -
Document Number series doesn't allow to change period indicator
Dear Experts,
We are facing a problem while going to change period indicator of any document numbering series from previous year to current financial year.
There is no problem creating new numbering series for new financial year. But while trying to change previous year period indicator series with current year It shows a error "Series in use" 3535-9.
We are running SAP B1 Verison 9.02.002 PL 10 Hotfix1
Any help please suggest.
SK
Note: Last Financial Year while we didn't face this problem in SAP 8.82.070.07.I have the same problem. You could solve it?
-
How to change Profit center in production order
Hi guys,
I have to change Profit center value in production order. Order has been created and released also. How to change, if i directly change system throwing error...Please suggest me in this case.
RGDS
DosThen Go to OBA5 enter the KO Application area
Add the 367 message and your user iD enter warning in online and Batch,
After that You can able to Change the profit center in Order with warning message in Order -
Mass Change Profit Centers on Open POs
The instance is ECC 6.0
We need to change profit centers on open POs. Is there a mass change or another systematic way of doing it?
Other question is that can we change the Profit Center on the POs where GR is done or it can be done only if the GR is not done?Hi,
Normally the profit center will be filled in material amster in sale view plant data or in the costing view of and which will get defaulted in the MIGO transaction.
Try changing the this field through MASS transaction.orthrough LSMW.
Regards, -
KE52 - Change profit centre - user exit
Hello,
I've searched high and low in transaction KE52 (change profit centre) for a user exit/badi/bte etc. and have found nothing. I need to validate that the 'Person Responsible' field is a valid SAP user. Please let me know if any of you have found a way of doing this - I'm not interested in z programs that find user exits etc.
Thanks
RichardHi Richard,
you could, instead of using a user-exit or BADI, use the field-exit of the domain VERAK (link to the data element) VERAPC.
I have not found any user-exit or BADI too.
Rgd
Frédéric -
Change Profit centers in all transactional data tables
Hello Experts,
I have been assigned to change Profit center MASKTOOLS to BRION in all transaction data tables.
Is there any standard SAP programs/reports that will help me do this?
How do I identify all tables were Profit center is stored?
Bearing in mind if I make changes directly in tables (example via Abap programs) BW will not recognise any changed documents and therefore not update BW accordingly.
Regards in advance SteveThanks Karthik T,
What about Internal orders, Sales orders, Service orders, Production orders, PA segments etc etc. etc..
I also have to think about orders with settlement rules which hold both profit center and profitablility segments which also hold profit centers.
I am still hoping there is SAP standard reports that can help identify and change
Steve D -
Change profit center for accounting document on item line
HI
I need to change profit center for accounting document on item line, for that purpose I have used user-exit EXIT_SAPLV60B_004, but my new profit center gets latly overwritten in FM CO_DOCUMENT_CHECK (which is called from FM AC_DOCUMENT_CREATE). It gets overwritten from COBL. Is there any way to solve this?HI,
possible reasons are :
In GR document profit center pulled from PO Material :
If you have ordered with material code, must check profit center assigned into material by mm03/Plant Data2
If you have ordered without material code, than check cost center assigned Profit center by 1KE4 -
Changing Profit Centre in IW32 of a Work Order
Hi Gurus,
I am trying to change a Profit centre in a Work Order via IW32 as Profit Centre is greyed out.I know it has to done via changing the Functional Location.But although i have changed Function Location still Profit Centre remains unchanged..
Is there any way to change Profit Centres in WOs?
Also please let me know are there restrictions on WOs status for changing Profit centres?
please help me its very urgent.....hi
The system proposes the profit center in the cost center belonging to the responsible work center. You can overwrite this, however.
If you change the responsible work center in the order, the system does not automatically overwrite the profit center on the additional data header screen. If required, change this manually.
You can change the profit center in the order, provided that no actual data exists for the order yet
regards
thyagarajan -
Change profit centre in material master
Dear all,
How to change profit centre in material master with stock(opening balance - 561 stock ?
What are implications of changing profit centre in material master ?
JeyakanthanIn standard SAP it is possible to change the profit center at any time.
However this will create inconsistencies in your profit center accounting. Hence you should issue all stock first to a cost center with 201 movement, then change the profit center, then get the material back with 202 movement.
You need to make MM335 message an error message in OMT4 to allow a change only if there is no stock
If you dont follow this way, then you create inconsistencies in profit center accounting.
Because...you received your stock without profit center (actually it is a certain default profit center), if you then change the PC in your material, then each issue will be posted to the new PC, while it never had a receipt. -
Changing Profit Center in Partially Delevered Sales Order
Dear Experts,
Can anybody tell me how we can Change Profit Center in Partially Delivered Sales Order?. in Standard, System allows to change PC in open sales Order without any subsequent documents.
There is business requirement to change PC in all Open Sales Orders.
br,
vgl.Try this.
Go to MASS, Key in Object Type BUS2032, select Table MASSVBAP and click on "Fields". There select the field "MASSVBAP-PRCTR" and execute.
Next paste those open sale orders and again execute. There maintain the required Profit Center on top cell and click Carry out mass change.
thanks
G. Lakshmipathi -
Changing Profit Center in PartiallyDelevered Sales Order
Dear Experts,
Can anybody tell me how we can Change Profit Center in Partially Delivered Sales Order?. in Standard, System allows to change PC in open sales Order without any subsequent documents.
There is business requirement to change PC in all Open Sales Orders.
br,
vgl.Hi,
I think note 580216 should solve your problem. Please read this note carefully
regards
Waman -
Change Profit Centre in Cost centre
Hello Experts,
I have to change profit centre in cost center (postings have been done on cost centre), how can I do ?
Thanks in advance.
Regards,
CatherineHi,
Once you post transaction to the Cost Center, we can not change Business Area or Profit Center assignment for the same Fiscal Year.
System will allow changes for the subsequent Fiscal Years though.
You cannot really reduce the number of Cost Centers. However we can restrict the validity period though. You can delete the Cost Center validity for the dates that do not have transaction with in the same Fiscal year as well.
Hope this helps
Regards,
Som -
Change profit center assignment in cost center
Hi All,
We have around 20 cost centers and assigned to 10 different profit centers.From 01/01/2011,we would like to change Profit center assignment in cost centers.
all cost centers postings should post to old profit centers till 12/31/2010 and from 01/01/2011,postings should go to new profit centers.
What is the best way to achieve this?any help is appreciated.
Thanks,
AnushaHi Ajay,
Thanks for your reply.profit center changes are working with analysis period changes.
i have one more issue here,i can't change hierarchy in cost center and getting errors..
Message no. KS042
Diagnosis
Field Hierarchy Area to be changed must be unique for the entire interval. You selected a change interval which does not include the entire period. Any change in the field would result in an inconsistency.
I have try to change time depended field in configuration.system is not allowing for field "KHINR" in OKEG TC.
any help is appreciated...
Thanks,
Anusha
Maybe you are looking for
-
Using javascript to make a text box invisible by clicking a radiobutton
hi my radiobuttons are for a persons title eg Mr Miss Mrs Ms and value 5 is for other. when i click other i want a text box to appear that a user can write in, and if the user changes their mind after writing in the box i want the text box to disappe
-
i have to read an excel sheet from the application server into an internal table that i hv created.can you help me to write select query &read dataset statement? suppose the internal table name is T_a and it has fields f1 to f7 which are all present
-
When I open Outlook the window doesn't open with the program
When I click on the Outlook icon the program opens at the top of the screen, but the window showing my messages, inbox, etc is not opening up automatically and when I open it up using the MESSAGE VIEWER option under the Window option it lists all my
-
Third party ships goods. Automatic GR in our company?
Hi, We have a PO. The PO idoc is send to the vendor (orders05). The vendor sends an confirmation Idoc back (ordrssp). Then then vendor sends the goods directly to the end customer. Can I post an automatic goods receipt? We do not check or the custome
-
Problem when installing, Need help.
Ok well I just downloaded the trial of Adobe After Effect CS4 and click on the .EXE and picked a spot for it to extract to which was my C drive My Documents and I made a folder called Adobe and put it there now all seemed to be working no errors unti