Hi Experts
I want to change the reconciliation at the entry level. The account will be decided at the time of entry by a popup option in the entry screen.
Regards,
Jemes
Moderator: Please, avoid asking basic questions

Hi,
If you want this at only FI documents level then you can make settings in FS00 for the reconciliation accounts as ready for input.
But for this you will need to configure alternative reconciliation in the following path-
Financial Accounting (New) > Accounts Receivable and Accounts Payable > Business Transactions > Postings with Alternative Reconciliation Account
Regards
Milind Sonalkar

Similar Messages

  • What size SSD does the 13 inch 2012 entry-level MacBook Pro use?

    I want to upgrade my 2012 13" MacBook Pro to use an SSD. I know that MacBooks use 2.5 inch laptop drives, but what are the sizes that MacBooks support?
    12.5mm, 9mm or 7.5mm etc...?

    Most if not all SSDs are of the 9mm size and have a rubber bumper on them to make them taller, the 12.5 size. you can take the bumper system off most of them to make them fit into a 9mm space. But your Mac will take any size UP To 12.5mm. Not so for the optical bay.

  • Price change at the time of service entry

    Dear all,
    Please help me out to find how to change the price of service item at the time of service entry sheet. I am working on 4.6C and getting the price field not editable after accepting the items from the PO.
    Please respond with the prrocess how to change the prize at service entry level. also plz let me if any config is there.
    sachin

    Hi,
    Only if the price change indicator is set in the PO service item, the gross price      
    would be editable in the service entry sheets.  Please check in ML90 the setting of the required field selection keys to it.
    Please be informed that in case you use an unplanned scenario - with contract limits in the PO and selecting the services from the contract in ML81N - the indicator for allowing the price change in the SES must be selected on the limit tab in the PO item and also in the contract to the single service items. However you can not treat the contract service items separately - for example to get in one item the price changeable in another one not, this is unfortunately not possible ...  
    Regards,
    Edit

  • Changing the Reconciliation Account

    Dear All
    I have made a customer account and assigned Reconciliation Account 101 to it. Then some entries were made. It is also having some open items. Later on it was realized that wrong reconciliation was assigned. In the Customer Master Record, when I tried to change the Reconciliation to 102, I got a yellow warning mesasge which is as follows:
    Account has been posted to; hold balance sheet adjustment
    Message no. F2067
    Diagnosis
    The open item account in which you want to change the reconciliation account has been posted to.
    By changing the reconciliation account in the open item master record the proportionate values from the items open at the time of change are not posted to the new reconciliation account.
    Procedure
    On the balance sheet key date the open items from the old reconciliation account are allocated to the new reconciliation account using adjustment accounts. This allocation is carried out automatically when you create a sorted list of receivables and payables using report SAPF101.
    The postings necessary are only carried out for G/L accounts and are cancelled on the first day of the subsequent month (balance sheet adjustment posting).
    But on the contrary, when see the Customer  Reports, and give the New Reconcilaition 102, I am getting all the transaction as theyb were with the Old Reco Account 101. I also made some dummy entries for sales and payments.
    Please advice.
    Thanks & Regards
    Kanwaljit

    Hi,
    Sub ledger level you'll see all items.
    But GL level, you can't see all items.
    As you have posted few entries with old reconciliation account and remaining entries in new reconciliation account.
    Also you can use program "SAPF101" to transfer the old gl balance to new gl. Please check the documentation in this transaction for functionality.
    Rgds
    Murali. N

  • Changing the Reconciliation Account to Regular (Non Reconciliation) GL

    Hi there,
    We are on SAP ECC6.0.
    We need to change the Master Record of a Reconciliation Account by making it a Regular (that is NON Reconciliation) Account.
    The system is allowing us in doing this in certain cases and in some we are given the Error as:
    Modifications to reconciliation account not permitted
    Error Message # FH110
    We have already zero out the balance outstanding in all Vendors linked to this GL Account.
    Thanks
    Bob

    Hello,
    It is not the question of making the balance to zero. Though you might have brought the balance to ZERO, but still they are showing as open items only in your system. Until and unless they are cleared, you cannot change.
    After posting number of entries in the system, now try to change the reconciliation account to non-reconciliation account will have its own disadvantages and may affect adversely on your reporting. It suggested not to make any further changes. Make a new reconciliation and assigned the same to new customers or vendors or change the reconciliation account in the customer or vendor masters.
    Try to run F.5D
    Please recheck your configuration in OBBW.
    Regards,
    Ravi

  • How to change the order of the top level navigation?

    hello,
    i don't find where i can change the order of the top level navigation.
    help would be great because there is no documentation for this issue.
    greets daniel

    If you want to define the sequence of the entry points for display in the portal, you can prioritize the entry points. You define priorities for the entry points by assigning a cetain value to each of the entry points in  the SORT PRIORITY. You may only define values greater than 0 for the priorities  and lower than 100 (default value is 100.0). The smaller the value of the entry point, the further left it moves on the navigation bar. The entry points without a priority appear in any order.
    Hope that helps,
    Frank

  • [svn:bz-trunk] 20609: Change the default max object nest level from 1024 to 512.

    Revision: 20609
    Revision: 20609
    Author:   [email protected]
    Date:     2011-03-04 10:23:41 -0800 (Fri, 04 Mar 2011)
    Log Message:
    Change the default max object nest level from 1024 to 512. A max object nest level of 512 should be more than enough for most applications which probably will not be sending deeply nested object graphs over the wire. For applications that are sending deeply nested object graphs over the wire and that bump up against this limit, the limit can be increased but you should also do testing to make sure that serializing/deserializing these deeply nested object graphs doesn't cause stack overflow errors. 
    Update documentation for the max object nest level setting to reflect the new default.
    Add documentation for the new max collection nest level setting.
    Modified Paths:
        blazeds/trunk/modules/core/src/flex/messaging/endpoints/AbstractEndpoint.java
        blazeds/trunk/resources/config/services-config.xml

    You should be able to get some more precise information from your Xorg logs, but I would bet it is related to the evdev driver. Some of the options in your xorg.conf no longer work with the latest version. For now you should be able to either map your mouse directly to the appropriate /dev/event* entry or change to the standard mouse driver, both of those methods should be in the wiki.
    You are supposed to be able to use the evdev driver without the input section of your xorg.conf by using dbus/hal autodetection, but AFAIK at the moment the xorg-server package still isn't compiled with hal support, so you would have to patch and rebuild the package.

  • How to change the Reconciliation Account of a Customer.

    Hi Everybody,
    I went through few posts from users regarding the change of Reconciliation Account in Customer Master, but nowhere the complete process of change of Reconciliation Account is explained. Can anyone throw some light on this and tell  the complete procedure of changing the Reconciliation Account in the customer Master.
    Thanks.

    Dear Himanshu,
    There is no specific process of changing the reconciliation account in customer master because it is not recommended and when you change the reconciliation account in the customer master then system will stop you at all. If you want to change then please follow steps mentioned below.
    1. Clear all the open of the customer whose reconciliation account you want to change. If open item exists and you change then this balance will lie forever in the trial balance which Accounting Standard will not allow.
    2. Once the customer balance does not exist then you can change reconciliation account.
    Another way to do is
    1. You create a copy of the customer you want to change the reconciliation account, put the new reconciliation account in the copied customer.
    2. Then you transfer all posting to the new customer so customer with old reconciliation account will be nil.
    If your profit center functionality is active and document splitting is not active with profit center characteristics then please avoid the second alternative
    Regards,
    Chintan Joshi.

  • Change the Reconciliation Account for the FI Document

    Hi,
    I like to change the reconciliation account of the line item in a FI Document, which will be created FROM MIRO or MIR6 trxn. I have tried the BTE - 00001120, I can modify the required field, but at the time of posting it's again fetching the default reconciliation account.
    Can any one plz suggest me the way to solve the problem? Please suggest.
    Thanks,
    Kuntal

    HI Kuntal,
    I'm facing same problem as yours.
    I posted a msg at this bulletin also, but the same, nobody answered me.
    Have you found any solutions yet? Kindly share to me if you have.
    Thanks a lot in advance!
    Best regards,
    Miao

  • Change the Reconciliation account

    Dear Friends,
    Can we change Reconciliation accounts in Customer/Vendor master records? If we can, so what about the old reconciliation account data or balance? How do we capture data from old reconciliation account to new reconciliation account?
    Explain in details......
    I appreciate your help.....

    Hi Teja,
    You can change the reconciliation Account in the Vendor or customer Master provided the field Status in your configuration allows changing the Reconciliation Account. Also, it is ideal that you change the reconciliation Account when the balance on the Reconciliation Account is Zero.
    If the Balance is not zero, then also you can change the reconciliation Account. In such a case you need to maintain a Clearing Account in Configuration and then execute the Transaction F101 with the check box "Change Rec Account" under the Parameters TAB in the transaction F110.
    This transaction will move the balance to the new reconciliation account,
    Regards
    Mahendra
    Assign points if it helps

  • Changing the "Reconciliation Account" in the master data of a Customer

    Hi All,
    I've to change the "Reconciliation Account" in the master data of a Customer. But this fiel has been made not modifiable.
    Could anyone tell how change this?
    Thanks,
    Gandalf

    Hi,
    In SPRO, change the field status for the customer account group to optional. Then you can change the reconciliation account of the customer.
    The Path -
    SPRO>>Financial Accounting (New)>>Accounts Receivable and Accounts Payable>>Customer Accounts>>Master Data>> Preparations for Creating Customer Master Data>>Define Account Groups with Screen Layout (Customers). Here select the account group for the customer and double click on the line. In this screen, double click on Company code data. Then change the field status in Account management for Reconciliation account.
    Hope this helps.
    Thanks and Regards,
    Anit

  • Unable to change requested delivery date in the sales order at item level.

    The issue is when I create order with one material (linked to network and project is created automatically in the background), I am able to change (in change mode) req delivery date for an item, but when I create order with 2 materials (linked to network and project is created automatically in the background), I can not change (in change mode) the req delivery date of any item. Req delivery date is then copied from the header req delivery date.
    Is this a standard SAP functionality or a defect?

    Req del date is the date requested by customer and  can be changed at item level. Probably the confirmed date in the schedule line is derived from the network scheduling after ATP check. (ATP check is not activated in this case)
    I am able to change the req del date at item level if there is only one item (Linked to network) and not when there are two line items (Both are linked to 2 diff networks belonging to same project)
    I tried to change the date in the network, scheduled and saved but that didnt change the date in the sales order. On the contrary, if I run ATP check, netowrk dates get back to original dates derived from sales order.

  • How do I set the zoom at a particular level as the default to ensure pages are not too small and that i don't have to change the zoom for each page? in English

    How do I set the zoom at a particular level as the default to ensure pages are not too small and that i don't have to change the zoom for each page? in English
    == This happened ==
    Every time Firefox opened
    == From the beginning

    Some add-ons:
    Default FullZoom: https://addons.mozilla.org/en-US/firefox/addon/6965 (I use this one)
    No Squint: http://urandom.ca/nosquint/
    Also:
    http://support.mozilla.com/en-US/kb/Page+Zoom
    http://support.mozilla.com/en-US/kb/Text+Zoom
    http://kb.mozillazine.org/Browser.zoom.siteSpecific

  • Accounting for discounts given at the order entry level

    Hi,
    I'm Anil Wadhwa and I'm working for Amtrex Hitachi Appliances Ltd., Ahmedabad, India. we have implemented Oracle applications 11i and I'm part of the Order to Cash cycle specifically handling the OM Module.
    Initially I had the problem of using the discount feature available in Oracle Advanced Pricing and now I have got the solution for the problem.The problem I was trying to explore a feature whereby I was setting up a qualifier where I'm defining the Customer Class as 'DLR' which would be eligible for discount say @10%.
    I subsequently set up a modifier where I defined a modifier type discount @10% and attached it with predefined qualifier at both the header and line level.
    When I was trying the order entry the price which was defaulting from the attached price list was not getting reduced by 10%.
    Now this problem has been solved by giving a request from the 'Oracle Pricing Manager' called as Build Sourcing Rule.
    Now I want to know is there any way of accounting the discount given.
    Say my list price is 100 and i have given a discount of 10% and my selling price becomes 90.
    Then
    Debit Credit
    Customer 90 Sales account 100
    Discount 10
    How should I do the setup for discount and make sure that when the modifier gets applied whatever is the discount goes into the appropriate accounting setup.
    I will be obliged if somebody can guide me on this issue.
    Thanks & Regards,
    Anil Wadhwa
    [email protected]

    Anil,
    have you used any algorithms for ariving at discounts?
    Thanks
    AGK

  • When I set all the tracks in the latest Garageband to the same volume levels and save, when I open the file again they've changed back to a previous setting?

    I'm trying to mix a recording in the latest 2014 version of Garageband, but when I set all the tracks in the latest Garageband to the same volume levels and save, when I open the file again they've changed back to a previous setting? Does anyone know why it changes even after saving the file?
    Below is my iMac settings.

    Do you have a back up?
    If not you're into using file recovery software like  File Salvage - you can download a free trial and it will scan the disk for you and tell you with might be recoverable. Actual recovery will require that you purchase the app. There may be many files with the same or similar names. Always recover the largest file size.
    There are other such apps. Search on Macupdate or the App Store

Maybe you are looking for

  • Import Manager  Match Records question

    Hi I am following the below file https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/a0a9cee4-9cd1-2a10-62b6-ea2acb06a5a3 Till 5.2 I have done it successfully while proceeding through the match records i.e. In Import Manager, Match Re

  • Agent Determination Rule using Function Module

    Hi all, I am trying to create a custom agent determination rule using function module. But my rule is not getting invoked when the workflow is executed. I created a custom rule and linked my function module (with proper signature). FUNCTION 'ZRULEXXX

  • How to check which albums a photo is in

    You can check what playlists a song is in in iTunes - why not a similar application in iPhoto?

  • Read directories of an application server

    Hi i asked some question about this topic but i want to know at sure There is wat to Read directories of an application server? thanks

  • Playing IPOD Video / Picture Slideshow on TV?

    Hi All, I wanted to know if there was a way to play Video &/or Picture slideshows on my TV? Thanks...