CORK error at process order Confirmation
Hi all
While Process order Confirmation (CORK) iam getting the following error
G/L account 499999 is not defined for chart of account 1000
Message no.F5507
I have run the same in Dev. Client
but unable to do in the quality client
i have checked in OBYB in both the clients
setting are same
plz.. provide the solution
thanx in advance
useful solution points will be awarded
Hi,
While confirming the Process Order, the following will be the effect in Accounting
FG Stock Account Dr.
To COGM Account
The followings are the possibilities in your quality client
1. whether you have defined the above account in Chart of Account and Company code segment level?
or
2. You should check it in OBYC > GBB > AUF (COGM account) and in BSX key (Stock account for Finished Inventory)
or
3. Whether it is blocked for posting or marked for deletion at Company Code level or Chart of Account level?
Regards,
Jigar
Similar Messages
-
Sales order stock error in Process order confirmation
Hello SAP Gurus,
In Make To order scnario while I do COR6 order confirmation it gives me Error that Sales order stock does not exist.
Can anyone suggest me which way I can remove the error?
What is the Transaction and movement to transfer stock to SALES ORDER?
Please reply...
Thanks & Regards,
Bhavik Dangi.Hi,
As per your mail, you can move the stock from normal stock to sales order stock through transaction MB1B with movement type 412 E. This route is generally follow if want to assign stocks manually to sales order stock otherwise if follow the PP route then system generates the stock against the sales order line item at the time of produciton confirmation and requirement type use in this are KSL, KE.
Rewards if it helps.
Regards
Goutham -
ABAP Programming Error when saving the Process Order confirmation in COR6N
Hello,
We have an issue related to Process Order confirmation using Tcode COR6N. When we enter all the inputs to confirm( Activity, yield and phase) and click on save it gives ABAP Programming Error (Exception condition "SEQ_NOT_FOUND" raised).
Any inputs in this regard, would be appreciated.Hello
I can observe that you have implemented the report ZOPSECRE and that an inconsistency was found.
This repor corrects inconsistent orders which do not have an operation or a sequence, or the two of them.
The report checks whether there is at least one operation or one sequence and creates both including status objects.
Therefore, you need to have the default valus for the operation generation defined on OPJG for this order type/plant.
BR
Caetano -
Process order confirmation error in COR6
Hi Gurus,
I am working as sap manual tester and facing below issue in Process order confirmation in t-code COR6.
Batch 456 for component 350515 does not satisfy BOM requirements
Message no. Z_MFG017
Need ur help.
Regards,
Imran
Edited by: imran.shek38 on Jan 25, 2011 7:16 AMHi,
Please check whether the Batch-Management checkbox is maintained for the component in the Material Master (MM02).
Also, check the Transaction MSC2N for this component and activate the checkbox for batch-managed item in the BOM.
Hope it helps.
Regards,
Kaushik -
Problem with creating Process order confirmation using BAPI
Hello,
While creating Process Order confirmation using BAPI_PROCORDCONF_CREATE_TT, material document is getting created. But a line item is inserted in the table AFRU without material document number. When it is created manually using the transaction COR6, the table is getting updated with material doc in the line item. Can anyone let me know what other attributes to be passed in order the update the same?
Thanks in Advance.
Regards, Senthil G.Hello , I am working with the same Bapi, can you please send me the code to fill the parameters, if I find the same error like you, I will send you the solution if I correct that.
Thanks for your help.
[email protected]
Guatemala, Cempro ADATSA -
Process order confirmation reversal
HI friends,
I am cancelling a process order confirmation using T-code CORS. The confirmation cancellation is happening, but the goods movements are not reversed. Help in resolving will be much appreciated.
Thanks in advance.
Warm regards
VivekHi All,
Sorry for the delay in response and thanks for your suggestions.
The backflushing is activated. I checked in COGI transaction for the concerned order. I got several entries with different error text. The error text is as follows
"You have no authorization for this transaction with movement type 102"
"You have no authorization for this transaction in plant XXXX"
"Deficit of SL Unrestricted-use 6,957 TO : 1030604 XXXX PL01"
Please let me know how to resolve these errors.
Warm Regards
Vivek -
Set loss quantity to a fixed percentage in Process Order Confirmation - C0R6N
Hi Experts,
How it is fixed the loss qty percentage at the time of process order confirmation.
I want to set the loss quantity to a certain percentage when compared to the Total Process order quantity.
For Example:
If the Total processed quantity = 100
Yield Quantity = 20.
Loss = 80.
This kind of scenario should not happen, since Loss quantity is very much higher that the yield quantity. I want to set the loss quantity to a particular percentage ( say 20-30 %) of the total processed quantity so that the yield quantity will be higher than the loss quantity by a substantial amount. Are there any possibilities of doing this through configuration. If not what are the other options?
NB: Scrap quantity is not maintained at the time of process order confirmation.
Regards,
Umapathy.Hi Umapathy,
Yield and Scrap are user entry fields where you can have restriction on entered qty by changing under delivery and over delivery to error through OPK4 config as shown below. Agree that any qty can be entered in any field (Yield or Scrap)
OR
You can define the operation scrap. Read the below doc for more details.
http://scn.sap.com/docs/DOC-52834
OR
Another option is to use exit and write your logic based on input yield and loss.
Thanks & Regards,
Ramagiri -
Loss % in process order confirmation
Dear all,
During process order confirmation,loss should not to take above 10%.
It should be within 10%.
Kindly let me know hat customization to be done for this scenario
Regards
RajasekaranHi,
In the confirmation parameters in OPK4 in the checks option in the under delivery maintain error when quantity falls below under delivery tolerance and in the material master in work scheduling view in tolerance data maintain under Underdely tol as percentage and check...
Thanks
Kumar -
OPK4 Process Order Confirmation parameter
Dear All,
In process order confirmation i want do a configuration like
Operation 10
Phase 20 0010(supr.ope)
Phase 30 0010(supr.ope)
Operation 40
Phase 50 0040(supr.ope)
now I maintained a relationship between 50 & 30 like "30 is predecessor of 50"
I required during confirmation if confirmed quantity of phase 30 is 50 and now if I go for phase 50 confirmation system should not allowed confirmed quantity >50 of previous confirmed operation 30
for that i have done setting in OPK4 like
Checks
Operation sequence " E Error when operation sequence is not adhere to"
but system is allowed to do a confirmation more than 50 qty of operation 30
so what is the meaning of operation sequence check in PPPI
Regards,
Murari Shah
Edited by: murarisap1986 on Apr 6, 2011 7:50 AMDear Murari shah,
"E Error when operation sequence is not adhere to" This is to avoid the operation confirmation if it's not in sequence.
For example,assume there are 5 operations in an order,directly i can't confirm the operation 0050 unless it's prior operation is
confirmed.So the system checks whether the prior operation is first confirmed,if not the system proposes an error.
So for this reason, we can make the necessary seetings in OPK4 for plant and order type combination.
check and revert.
Regards
Mangalraj.S -
Restriction during process order confirmation
Hi,
I want one validation during process order confirmation (mile stone) through t code COR6N if resource capacity & shift intervals not maintained ( t code CRC2) then process order should not confirmed & there should be error message. Plz advice how it is possible through customization.
regards,
sps.Dear shukla,
Check with this User Exit,
CONFPI02 Process order confirmation: Customer spec. input checks 1
CONFPI03 Process order conf.: Cust. spec. check after op. selection
CONFPI04 Process order conf.: Customer specific input checks 2
CONFPI05 Process order conf.: Cust. spec. enhancements when saving
If the above is not working then check with this BADI
WORKORDER_CONFIRM at the time of saving,
Regards
S Mangalraj -
PROCESS ORDER CONFIRM DURING UD
Hello Experts:
Here's my question concerning a customization in QM issuing UD.
Std. results recording has been completed and valuated:
UD is customized to require user to confirm all operations including QM operations have been Process Order Confirmed. This is o4 inprocess manufacturing.
When attempting to enter UD, error pops up indicating QM Operation XXXX has not been confirmed, do so to complete UD.
Please explain the steps to execute P.Order confirmation via the COR transactions.
Appreciate.
VerrozGo to CO11N
Enter process order and Operation xxxx in respected field and save the transaction. Do for all unconfirmed operation or for which you getting error message.
You will be able to UD. -
Goods Issue- Process Order Confirmation
Hi,
During Process order confirmation, in Goods Movement tab the BOM components with qty are displayed. But some components OTHER than BOM items ISSUED for the process order is not displayed in the goods movement tab. Why?
Is there any additional configuation to be done?
Thanks....
JK
Edited by: J K on Apr 15, 2008 6:04 AMHi
As said by Mr sateesh,
If u r doing confirmation phase/operation wise(COR6), then the material assign to phase/operation is only seen according to phase/operation wise.so have to check in which phase u have confirm the component quanity.
or
If u confirm the process order collectively(CORK), then their must missing in OPK4 (confirmation Parameter) of All component tick at Goods Movement.
Kindly check the same & coem back if their is any other issue
Parminder -
In-process inspection...how to stop the process order confirmation?
Hi...i'm making an in-process inspection and i want to stop the movement to the next phase or the process order confirmation, until the usage decision is made...how can i make this ?
Dear,
You can do this with OPK4 setting here slect your plant and process order type go in details here change the setting to
Results Rec. (QM) = Error message if no inspection result exist.
Regards,
R.Brahmankar -
Process order confirmation without 101mvt type
our client is a process industry.client need during process order confirmation Background 101 not happen.
Step : 1 Process order create
Step : 2 Goods issue The material -261
Step: 3 Process order confirmation (No 101)
Step: 4 Goods Receive (MIGO) 101 happen
Following Steps Process only,
cork-only activity confirmation only,after Activity confirm GR will Happen , how to configure in the system,any user exit or sap note there in the sense tell me?
Thanks For AdvanceHi Thiyaharaajan,
For Goods issue i believe you are using MB1A/MIGO. You also use backflush to automatically issue the material during confirmation.. For this maintain Backflush - 1 in material master MRP 2 view.
Also during confirmation for doing Auto GR (101 movement type) you need to assign the control key ticked with Auto Goods Receipt for Last operation/phase of Master Recipe.
Thanks & Regards,
Ramagiri -
BAPI For Process Order Confirmation
Hi,
For Process Order Confirmation we are using the following tcode. COR6N. in the t-code we are include a new field (Shift Field) with help of CONFPP07. and we made the field as mandatory also. in cor6n it is working fine.
now we are using the bapi for same Process Order Confirmation. here the new field is not available. we want to include the new ( Shift ) Field also. we are using the following
BAPI Fm: BAPI_PROCORDCONF_CREATE_TT .
Regards
SathisBAPI_PRODORDCONF_CREATE_TT to confirm a production Order
Erwan
Maybe you are looking for
-
I recently was working on a project in Logic Pro 9.1.1, saved the project and put my macbook to sleep. When i return, my mac wont turn on for the first 10-15 minutes sitting on the blank screen with the rotating circle. When it finally loads through
-
Reporting Tab is not showing in SCSM 2012 SP1 Console
I'm working with SCSM 2012 SP1. But after installing data ware house only "DataWareHouse" tab appares no "Reporting" tab. And it shows below MSG: And only the below reporting management pack are available in the Data Ware House >> Management pack are
-
How do I fix my problem with Artist and Sort Artist?
I have all my songs sorted by Artist and because I have songs that feature other artists I use the sort artist field. In itunes it all looks fine but when I sync it with my iPod Nano 5th Gen one of the artists names comes up as the artist for all son
-
Hi Experts, I am facing a problem in opening an attachment in WD abap. Actually i need to open an attachment from my WD abap screen , as like standard does . Standard is using call dialog 'SO_DOCUMENT_VIEW_MANAGER' and passing some values in it, a
-
Photoshop CS4 crashes when open .NEF
Hey, I have a roaming profile network system at work. All my software is current and up to date. When I log into the local administrator everything works fine of course and i can open .NEF files in photoshop, but when I log into one of the roaming pr