Cost in quotation from PS project

Hi everybody
In this scenario, i´m trying to see the cost from a project (wbs element) directly in the pricing procedure of the quotation to use it only as a reference for the sales price. I already assigned the position in the sales document to a wbs element and a DIP profile and i want to see that cost in condition type EK02.
The WBS element already has costs, the DIP configuration (and condition EK02 is assigned to the sales document) is also made but i can´t see the cost in the quotation.
Please can anybody tell me how i could make this scenario
Thank you
Regards
Rodolfo Gómez

Hi
Create a sales inquiry and account assign the WBS element of the project. Plan the costs in the activities or WBS elements. Use sales pricing trx DP81 to view the project costs in sales price basis view. You can create the quotation directly from the same trx. Once quotation is made you can add sales conditions and then create a final quotation. The sales order can be created with reference to the quotation.
Regards
Srikrishna

Similar Messages

  • Quotation from PS

    Dear friends,
                           What is the method to generate automatic Quotation from my cost planning i.e through Easy cost planning or Unit Costing.
    Thanks

    Hi Pravin,
    You can use DP81 (SAles Pricing) to create a Quotation from your project.
    Rgds
    Deepak

  • Proforma Invoice or Quotation from Project

    Hi Experts,
    My client requirement is like this:
    1. Receives request for procurement of goods/service from different user departments.
    2. Will send estimation to the user departments and will proceed further.
    I want to map like this through PS (SD module is not there):
    1. Receive requests
    2. Will create a simulation/plan project version
    3. Will generate the proforma invoice / quotation from the planned costs of this version.
    please let me know exact way to achieve the same.
    Satish

    Hi Satish,
    I am not quiet sure of what exactly is the requirement. It appears that the user department will send the PR to the estimator and  and  then the estimator will estimate the cost and send back to the User. Is your question related to the process of estimation and the way it has to be communicated back to the user?
    Can you please repharse your question for better understanding...Sinces the question is not very clear.
    If you want to Go for Sales Pricing thru projects.and create quotations..then SD module is required.
    Warm regards,
    Srinivas Potluri
    Edited by: Potluri Srinivas on Jul 23, 2011 3:35 PM

  • How to create Quotation from Ad hoc cost estimation of cProjects?

    Hi Guruu2019s
    Please help me in resolving the issue given below. I am able to get ad hoc cost estimation results in accounting screen, but not able to create a Quotation from Ad hoc cost estimation of cProjects.
    I am here with providing necessary steps to be followed. But these buttons are not available in my accounting screen.
    Prerequisites
    A reference quotation has been linked to the project under Structure  Object Links. An ad hoc cost estimate has been created for the project.
    Procedure
    1.     Choose the Accounting tab.
    2.     Choose link Ad Hoc Cost Estimate.
    3.     Enter client, user and password to log on to SAP ECC.
    The client, user and password must be entered if Single Sign On is not activated
    4.     On the Ad Hoc Cost Estimate screen, choose  .
    5.     On the Easy Cost Planning screen, choose  .
    6.     Choose  .
    7.     Choose Yes when you are prompted with u201CDo you really want to create the quotation?u201D
    8.     Write down the Quotation number :_______________
    9.     Choose  .
    Result
    Quotation in SAP ERP has been created.
    Please respond to this at the earliest. Points are given for your reply. I would be great if any one provides step by step procedure for IMG activities.  Thanks in advance.
    Thanks & Regards
    Suresh. J

    Hi Suresh,
    maybe you find the following link also useful:
    [http://help.sap.com/saphelp_ppm400/helpdata/en/index.htm]
    Navigation: Collaboration Projects -> Accounting Integration -> Preliminary Costing and Quotation Creation -> Ad Hoc Cost Estimate for cProjects  or Sales Pricing for cProjects
    From the page:
    The cost planning function is executed by Easy Cost Planning (ECP). The cost estimate is always created at project level and is always single-level. The organizational data relevant to costing (controlling area, company code, and master cost center for the derivation of the activity type under which the allocation is reported) is derived from the HR organizational unit specified in the project definition. The costs are calculated based on the rates for the resource, project role, or task. For more information, see Costing Logic.
    The revenues are calculated automatically if you have selected the option Use Cost/Revenue Rates from cProjects or Use Sales Pricing in SAP ERP as the revenue calculation type for the project type that you are using for the project. You make this selection in Customizing for Collaboration Projects, by choosing Connection to External Systems -> Accounting Integration -> Make General Settings. With the last option, the revenues are calculated with the dynamic item processor (DIP). For more information, see Sales Pricing for cProjects. Then you can also call up sales pricing from within the ad hoc cost estimate.
    You can archive the ad hoc cost estimate in SAP ECC (archiving object CO_ECP) if the project has the status To Be Archived.
    Technically, the ad hoc cost estimate is saved in SAP ECC with reference to the cProjects project number. When the project is transferred, it is recosted and the cost estimate stored for the account assignment object.
    Hoping this helps...
    Best regards,
    Thomas

  • Can we Trasfer the cost from Cacital Project to Indirect Project?

    Dear Experts,
    Can we Transfer the cost from Capital Project to Indirect Projects? and If we can Transfer what are the Limitations are there to do so?
    Thanks & Regards
    Bharath
    Edited by: 983186 on Feb 15, 2013 9:35 PM

    Hi
    Any expenditure item charged to any project could be transfered to another project, assuming the Transaction Source does not restrict the adjustment in PJC.
    When you select the expenditure item to transfer, the system creates a negative EI in the original project and another related EI in the target project.
    Distributing those transactions will credit the CIP account on the capital project and debit the expense account on the indirect project.
    Dina

  • Project cost to Quotation

    Hi
    i am using dip profile to transfer  project cost to Quotation  in that i can able to transfer all the activity cost but i can't able to transfer  the general activity cost.Please give valuable input to me.
    regards
    Raj

    the general cost activity is planned against a cost element - this would be a default entry in your network profile.
    In the DIP profile you need to set up the characterisitic - cost element - like activity type (which is working for you)
    Then set up a DIEN material and use the cost element as a source
    This way your cost activity will be covered

  • Create quotation from DP81

    Hello Experts,
    I run DP81for creating quotation from the sales pricing which comes from the planned cost of my project.
    Dynamic items are created based on the activity type. Eg: Junior consultant - 100 hrs - $10000,
    Senior Consultant-100hrs-$20000
    When I convert the dynamic items to quotation, each dynamic items are converted to each quotation line item.
    I dont want this to happen because I am going to send quotation to my customer as services. Eg: Line item 1 - Implementation service - $30,000. I want all the dynamic items aggregated to one quotation line item.
    How to do this? I have tried with "individual quantity not checked". I have selected Activity type as the characteristics.
    Any thoughts would be great for me.
    Regards
    Srinivasan Desingh

    Hello all,
    To achieve this,
    1. Check the check box - 'Product' in the DIP profile characteristics.
    2. Configure the pricing in the item category of the service level material as statistical.
    This will aggregate all the dynamic items into your Service level material in the sales order/contract and shows the value in the service level material.
    Regards
    Srinivasan Desingh

  • Can we have Cost of Manufactuirng sent to Projects while Inventory issue of these items to be through Sales Order Shipping. Can we do that?

    I want to send the cost of manufactured items to a Project/Task .
    Still I want to issue these items from inventory using a Sales Order (Sales Shipping).
    Billing shall be from the Project.
    Can we do the above cycle?
    In another scenario, what if I want to bill from the Sales Order?Dina Rotem@

    Hi,
    You will have to enable project manufacturing if you want to collect manufacturing cost on a project. Once you create a project, add this project to a project manufacturing organization through a PJM responsibility. Once you associate project and PJM org you will be able to put the PJM organization in the sales order line created on a Project sales order in Oracle OM. Also, mention the project number in that sales order.
    Once this sales order is shipped, run the cost collection program and it will bring in the manufacturing costs to project.
    Hope it helps
    Regards
    Kaushal

  • Cost of material charged to project but qty remains in stock

    Dear Gurus,
    I have a scenario, we have project systems PS. We have valuated projects and valuated project stock. Once project is over and if we have material left over, then my client want to charge the cost of the material to the project but he want to keep the stock at zero value in inventory, and issues it next time on zero value.
    I have tried to transfer material using 415 Q, but system does not allow to transfer materaial from valuated project to non-valuated project.
    kindly suggest any solution.

    Dear,
    my client wants to charge the leftover material cost to project but want to keep the qty in stock, so this is why we have a nonvalauted project. otherwise my client projects are valuated. i have not find any solution to charge the cost of material to project from project stock and keep the stock in inventory on zero value. and next time when this leftover is issued it will be issued on zero value.
    hope u have a solution.
    Edited by: Johi Kapoor on Nov 10, 2011 11:57 AM

  • REQUIREMENT TO STOP BALANCE SHEET ACCOUNTS FROM ACCEPTING PROJECT AT JOURNAL CREATION OR ANY FINANCIAL DOCUMENT CREATION.

    Dear Gurus,
    I have a requirement from my client to stop balance sheet account from accepting project at financial document creation or journal entry because this process distrupt the profit and loss account report or transaction report by project as balance sheet items are not expected to be part of this report.
    Kindly advise on the way to achieve this to enable fulfill requirement and deliver excellence service.
    Kind regards,

    Hi Nagarajan,
    Thank you for your response.
    My sample is whenever an entry is raised to be posted to a balance sheet account such account should not allow user to post but only in revenue and expense account. E.g. A Stock account should not allow project assignment but a cost of sales, expenses or sales revenue accounts should only accept project assignment.
    Only P&L items should allow project assignments.
    I hope this is clear is enough.
    Regards,

  • Purchasing from Marketing project

    Hi Gurus,
    Regarding purchasing from marketing project, we have the following issues:
    1. We need to create a purchase requisition in ERP from a campaign in CRM. For Cost Posting, Internal Order in SAP-ERP are needed, instead of a WBS element. Is there a way to impute to an Internal Order instead of a WBS element?
    2. In addition, is there an option in customizing to indicate the purchase type document (Purchase Requisition Type or PO Type)that we want to use in ERP?
    Thank you for your help!
    Andrea Figueroa

    Hello Guys,
    SAP answered us and they have said that unfortunately currently it is neither possible to use an Internal Order number, nor is it possible to assign the Purchase Requisition Type (NB is always used).
    They recommended to use Badi CRM_MKTPL_PURCHASE, method CHANGE_HEADER_DATA to adapt the header data.
    Hope this help everyone,
    Andrea F.

  • How can I move an original Version from one Project to another Project?

    How can I move an original Version from one Project to another Project?

    From the Aperture User Manual:
    To move an image into a different project
    Drag the image [from the Browser] into another project in the Library inspector.

  • Importing clips from iMovie project (they keep ending up in the trash)

    I have never tried to import other clips from another iMovie project before and I just tried it yesterday. This is what I did:
    -I went into the other project and clicked on each individual clip from that project that I wanted (one at a time).
    -I copied that clip and then saved it to the desktop
    -From there I copied those clips to my external drive (which holds the new project that I am working on
    -I then opened up the new project in iMovie
    -I went to File<Import
    -I selected the clips that I had copied over to the external drive
    -I imported them
    -They all showed up fine, they played fine and I was able to edit them and put them into the time line as well
    The problem I face though is after I save the project and exit, the next time I open the project, each of those clips are missing and have been placed in the trash
    What am I doing wrong?
    Thanks ahead of time for your help!

    It sounds like something may be preventing iMovie from properly saving the project on the external drive. The drive format may be wrong, or third-party software might be causing conflicts. More here:
    http://discussions.apple.com/message.jspa?messageID=1852869#1852869
    Another possibility is that you are opening the wrong project file saved inside the iMovie 5 project. If your project was originally an iMovie 4 project converted to iMovie 5 that's an easy mistake to make. More here:
    http://discussions.apple.com/click.jspa?searchID=-1&messageID=1971832
    Note that the copy/export/import routine you used can be simplified enormously. iMovie 5 lets us Copy and Paste clips much more simply. To copy clips from Project A to Project B, open Project A, select all the clips you want copied to Project B, choose Edit > Copy, open Project B, move the playhead where you want to place the clips, and Paste. iMovie will import all the files that support those clips from Project A to Project B. Note that it imports the entire file for the clip, not just the clip itself. That's so the clip inherits all the non-destructive editing features it had in Project A.
    To avoid Project B becoming unnecessarily large, it's important to Copy and Paste all the clips you want together. If you copy two clips at the same time that share the same file iMovie imports their source file just one time. But if you Copy and Paste two clips that share the same source file separately, iMovie imports the same file twice.
    Karl

  • Copying a single file from one project to another????

    Hello,
    New to Mac from a PC, tried search with no results. I have a single image I would like to display in 2 separate projects in Aperture. (As I will be writing to a disc and print later). How do I copy the image from Project A to Project B, making is available to both??? Thanks in advance!

    There are two different ways to do this.
    The first way is literally exactly what you are asking for but may not be what you really want. You can copy the image (and corresponding master) by holding down the option key while dragging the image from one project to the other - make sure the drop target is the actual little yellow project box and not something inside the project box. When you do this there will be two completely separate copies that have nothing to do with each other. If you make an adjustment to one the other will not change, if you delete one master the other will still be there.
    The second way may be what you actually want - if you create any type of album within or even outside of a project you can drag any images from any project into it - no copies are made but the image will "show up" in that album no matter what project it happens to live in. This is usually a better way to group images together from multiple projects no matter what the purpose.
    Here are some more details:
    [Aperture organization|http://photo.rwboyer.com/2008/07/apple-aperture-21-organization>
    RB

  • Using Webi to generate report from Microsoft Project?

    Does anyone know if there a way to create a Webi report from Microsoft Project?  Can put me in the right direction towards accomplishing this task?

    Hi,
    For this use Microsoft .Net with Integration of Business Intelligence(BI/BOBJ). Select web I reports with Crystal Reports generation and use in the .Net Project.
    All the Best
    Madhu.....

Maybe you are looking for

  • How to import external table, which exist in export dump file.

    My export dump file has one external table. While i stated importing into my developement instance , I am getting the error "ORA-00911: invalid character". The original definition of the extenal table is as given below CREATE TABLE EXT_TABLE_EV02_PRI

  • Best Practice for the database owner of an SAP database.

    We recently had a user account removed from our SAP system when this person left the agency.  The account was associated with the SAP database (he created the database a couple of years ago).  I'd like to change the owner of the database to <domain>\

  • PROBLEM WHIT IDVD 08!!!!!!!!!! HELP ME PLEASE

    I can't running idvd 08, when i clik on idvd icon, idvd open and close immediatly what is the problem ???

  • Using iCloud with my iPod touch

    I can't update the operating system on my iPod touch so that I can use iCloud.  It appears to keep downloading the new version to iTunes on my desktop computer but never seems to transfer to iPod.  Can anyone help with that?

  • Passing multiple parameters to an Oracle procedure

    I'm having trouble passing multiple parameters to a stored procedure in Crystal Reports 2008 (12.2.0.290). I'm using an OLE DB (ADO) connection to an Oracle 10g database. I have created a stored procedure that has 3 parameters (in out sys_refcursor,