Cost plan for sim version

Hi experts
The business requirement is as follows:
1) Project schedule option-1 with work packages and costing plan ( L1 schedule)
2) Project schedule option-2 with different work packages and relevant costing plan (L2 schedule)
Clien requires both of these as drafts
The requirement can be met by creating sim_ver1 and sim_ver2  in transaction CJV1 (with out having operative version).
Subsequently the approved sim version will be used for creating operative version.
But is it possible to maintain cost plan for sim versions?
If no, please suggest best practice.
warm regards
ramSiva

You can only use network costing for simulation version. Other cost planning methods are not possible for simualtion version. Refer SAP Help

Similar Messages

  • Cost planning for a project

    Hi Experts,
    Can anybody tell is there is any t-code to mass change of the cost planning for a project. If there is a t-code please explain me the procedure how to do it.
    Thanks & Regards
    Raman T S

    You can budegt a project by:
    1. Transferring the values in the cost planning as budget.
    2. Entering the budget directly into the WBS element.
    PS STD cycle of creating Project is as follows:
    1. Creating the Project in the Project builder
    2. Using the relationships to link the activities
    3. Planning the output & duration of activities
    4. Sceduling the Project
    5. Planning Costs
    6. Allocating budget
    7. Releasing the Project for execution
    Choose Original Budget.
    In the Planned total column, you see the values copied from cost planning.
    Select the planned total column.
    Choose Edit ® Copy view.
    Percentage rate-100
    Overwrite- Select
    In the dialog box, enter the following data:
    The system copies the values from cost planning into the budget.
    Hope ur prob will be solved
    Regards,
    ANSAR

  • Cost Planning for vacant positions-

    Dear Experts:
    Can anyone tell me the best data collection method for Cost Planning for Vacant Positions.
    regards,
    Srikanth Reddy

    Yeah we do:
    Scenario is like this:
    Assume Business Planning is done at the begining of the Fiscal year.
    And Manpower Planning is also done at the same time for the fiscal year.
    Now, based on the MPP user would create Vacant Positions in OM.
    Periodicity of Cost Planning could be Yearly/ Quarterly/ Monthly.
    Whenever i create Vacant Position for Future Periods the system should calculate the Personnel Costs for the Vacant Positions for the same period.
    I just wanted to know, which method would be the best if anyone has done this before.
    regards,
    Srikanth Reddy

  • Cost Planning for networks in a CO plan version other than 0

    Hi,
    We have a specific requirement of getting the planned cost in terms of $ and hours on a network activity getting posted to some other CO version other than 0 in certain cases.
    It would be great if anyone could suggest a FM or a BAPI to achieve this end?
    Please reply if you need any clarification on the requirement
    Regards,
    Jibat

    In Cj30 you will get the CO version '000 , If you want to  your can copy cost planning values of your version V01 & V02 to
    Version 0  and do the budgeting  Because you actual will happen to 0 only so,  to compare your plan should  be there idealy.
    Apart from that network  cost planning can only be done in 0 version. And system give you option of copying the your preliminary plannning  to version 0.
    Virendra - Thanks for the explanation. It made my understanding better as well.
    With Regards
    Nitin P.
    Edited by: Nitin  Patoliya on Dec 3, 2009 12:50 PM

  • Trying to default a cost plan for PS from a CRM contract?

    I am trying to default a cost plan (akin to a budget maintained in IM) onto CJ40.
    This cost plan will be defaulted via a CRM table maintained especially for the appropriation/budget.
    Has anyone defaulted a cost plan onto CJ40 and if so how?
    Thanks in Advance,
    -SR

    Hi,
    The message is because your position has the historical record flag (HRP1000-HISTO) set to u2018Xu2019. From SAP help:
    Allows you to mark infotype records as historical records. Historical records are permanently stored on the database, so that you can report on the information at a later point in time.
    NOTE: You cannot change records once they are marked as historical. As a result, you should not mark records as historical unless you no longer require them for processing.
    Typically, the flag is set if a user has delimited an object through PP01. Youu2019d see the historical flag in the window that pops up.
    To remove the flag, execute report RHHISTO0, enter the relevant details in the selection and execute. The next screen ill show you which record has the flag set. Select that row and click u201Cremove historical recordu201D button on top. You should then be able to remove cost center from the position.
    Hope this helps.
    Donnie

  • Plans for Ubuntu version of ADE?

    Does Adobe have plans to port their Digital Editions software to Ubuntu?
    This support for Ubuntu would be essential for those who own ebooks. Ubuntu users are currently unable to read their ebooks that are only compatible with ADE (i.e. to read Google Play ebooks offline).
    I wish that ADE becomes available to all popular desktop platforms (i.e. Windows, iOS and Linux) so that everyone can read their DRM protected ebooks.
    Hat Adobe irgendwelche Pläne, Digital Editions nach Ubuntu zu migrieren?
    Diese Unterstützung für Ubuntu wäre sehr wichtig für die, die Ebooks haben. Ubuntu Benutzer können derzeit keine Ebooks lesen, die nur mit ADE kompatibel sind (z.B. Google Play Ebooks offline lesen).
    Ich wünsche, dass ADE für alle populäre Desktop Plattformen zur Verfügung steht (z.B. Windows, iOS, und Linux) damit jeder deren Ebooks mit DRM lesen kann.
    Schönen Tag noch.

    Thank you for your quick reply!
    I then read this tutorial for setting up ADE in Wine:
    http://robert.penz.name/440/howto-install-adobe-digital-editions-on-ubuntu-12-04-and-use-i t-with-an-e-book-reader/
    I don't have an e-reader, but double clicking on the ascm file opened it in ADE under Wine. Then it downloaded a protected PDF in my home directory for offline use. ADE for Windows ran surprisingly fast on Ubuntu 12.10, and it opened up all the notes/bookmarks and pages. I haven't found a problem with it yet other than trying to open the ascm file from within the ADE interface.
    Thanks again.

  • How to add "Cost Plan Version" and "Planned Cost" into CNE5 report?

    Hi,
    I would like to display Cost Plan Version(VERSN) and Planned Cost in the CNE5 report.
    How to retrieve Planned Cost that based on the Cost Plan Version ?
    Appreciate helps. Thanks.
    Regards,
    See Mun

    Plan versions:   A plan version is created in accounting and stores different cost plans for a project, such as an "optimistic" and a "pessimistic" plan.
    Now coming to plan version 0 is verson where actaul cost is updated in your organisation.
    Plan version 1 is used for the planning...
    How to see the  same in CJE5 is suggested by Virendra..
    However there is no filed name planned cost  in report but the name of the filed is Proj.cost sched.000
    with which you can achieve your result.
    path is run txn CJE5>give your Project no.> F8> in new screen> F5-->in new Window scroll down in the  right side for the Proj.cost sched.000 filed > with select take the same to left side>Enter--> values will displyed for this field in your report.
    similarly you can use the other fields as well... take help of F4, to know the meaning of fileds.
    Regards
    Nitin
    Edited by: Nitin  Patoliya on Jan 17, 2009 11:18 AM

  • Cost Planning Details not reflecting in new version

    Dear Experts,
                        .  We created the 'NEW' version . But we want to copy cost planning from u201C0u201D version to u201C1u201D version. For
    this we are executing u201CCJ9BSu201D t-code but after executing this, only cost
    are getting copied. Detail Planning is not getting copied.Kindly look into the matter and helpful solutions are

    Dear Experts,
    . We created the 'NEW' version . But we want to copy cost planning from u201C0u201D version to u201C1u201D version. For
    this we are executing u201CCJ9BSu201D t-code but after executing this, only cost
    are getting copied. Detail Planning is not getting copied.Kindly look into the matter and helpful solutions are.
    i.e
    1 I planned material costs in .Cj40 > Primary Cost > Edit >Detailed Planning >Change
       Here we maintain material cost, service cost, BPO etc
    2.When we copy the version from '0' to new version which i have created copying the 1 version.Or say '0' version to '1' version then material cost is not reflecting in new version cost planning after CJ9BS.

  • Clarification on Cost planning version

    Hi Gurus,
    I need a clarification... as per the client's business requirements, cost planning is to be executed in various versions before it is finally approved. As of now it is decided to copy  this into zero version (approved version). What will happen if components & services are assigned to network when real execution starts ?
    Let me give an example, Unit cost planning is executed for $1000. This cost plan is copied into zero version. when the user start executing the project, they assigned components & service in the network amounting to $800. As system takes this planning directly to zero version, will the total planned cost will become  $1800 ? If so, should i not take the approved cost plan into zero version instead to copy into some other version and only use Plan 1/Plan 2/ Actual Report to see the comparison ?
    Whether my understanding is correct ?
    Regards,
    Vinodh

    Hi Vinod,
    Goto OPSV ( Define Order Value Updating for Orders for Projects ), remove the Check box "addit" for Order category - 20.
    You can copy the Planned cost from other versions to active version - "0" but you can keep order settings to avoid appending planned cost to WBS Element Level. So, even though user do network costing, network planned cost not appended to WBS Element. Hence your initial approved planned cost remains same and you can see in all reports.
    Hope this clears you !!
    Br,
    Hari.

  • Network costing stored in CO version 1 or 2

    Hi All,
    Can we use the CO version 1 or 2 for network cost planning otherthan 0 and how?
    I want to store the network cost planning in CO Version 1 or 2 and not in version 0.
    Regards
    Muzmail

    Hi Amit.Amerash,
    Actually the problem with my client is that they are planning materials/services to the project from time to time.There is no single time material planning so it will create problem while running RA because system will post wrong COS to the project.
    So i was thinking that if possible to store network costing in version 1 and i can do manual cost planning in 0 for system to post exact COS .otherwise i have to tick off the addititive indicator for order cat 20 in OPSV.
    I want to see both network cost planning and manual cost planning in the system.
    Regards
    Muzamil

  • Easy Cost Planning & Project Stock

    Dear Experts,
    I am using Easy cost planning for WBS cost planning and Project definition control data tab page has Valuated Project stock selected.My costing model had an external procurement material for which I generated PR & PO thru Execution services.But the account assignment in my PR & PO was P with the corresponding WBS as account assignment and not Q.
    I have two question regarding this,
    1) Does it mean that while using ECP, Project stock concept will not work?
    2)How can we get the pop up of procurement type options(like Res + PR for WBS element) while generating PR through execution services?

    Hi,
    I am replying again because in my last answer there was some typing mistake.
    Hi,
    I tried your scenario is my system.
    whenever i am changing P to Q in Config in SPRO,It is giving an error that "The selected account assignment category is not supported" that means it is not meant for Q but i double click for object type PR WBS Element and changed Acct Assgmt Cat to Q then system allowed me to save.
    The i create a PR and WBSE is coming in the Account Assignement ,then i converted PR to PO and then i recived goods as project stock.when i issued the material in ECP it is not issuing from Project stock because 221 Q is not present in Config for SPRO so it is issuing from Normal stock so special stock from ECP is not supported.
    But you can manually issue the material to the WBSE in MIGO/MB1A by 221 Q.
    Hope it is clear.
    Muzamil

  • Easy Cost Planning -Costing has already been completed. No changes possible

    Hi,
    I am in Easy Cost Planning tool and i would like to remove some items or add in some items.
    The system is giving a message that "Costing has already been completed. No changes possible"
    May i know where did we complete the costing(Transaction code?) such that no changes are possible on East Cost Planning tool anymore?
    Thank you.

    Hi,
    Check the Costing Model in CKCM and do changes as per your requirement.
    Now Use this costing Model in CJ20N while cost planning for wbse. you can change cost plan here also as per wbse specific requirement.
    regards,
    Hari

  • Product Cost Planning

    We are embarking on production planning & I need to know best course for financials/product costing.  Would the AC505 Product Cost Planning Course be suitable for a business who is about to embark on production planning .  We are in manufacturing, and we will be using lots of components (BOMs) and process orders etc.

    Hello Higgins:
    There are 3 product costing courses:
    AC505 - focus on product cost planning. for example, from BOM, routing to estimated / simulated cost.
    AC520 - focus on ACTUAL cost scenario ,for example , make-to-stock , make -to order, sales, service, periodic
    AC530 - focus on special module Material Ledger , for industries to get the actual cost (more precise)
    so I understand that you start on Planning, so AC505 is the right course.
    But I recommend to attend AC520 as well to understand the actual cost flow . so you can compare plan and actual together.
    and if you like the most accurate cost , and implement ML (material ledger) - AC530 is another one.
    Hope this help.
    BR,
    Manthana

  • Is it Possible to do easy cost planning in network and acitivity level

    Hi,
    Is it possible to do easy cost planning in network and acitivity level
    Rgds
    Purna.M

    Dear Sanjeev,
    ECP not possible at Network or activities but it is not like that as you saying " any of cost planning not possible at activity level as per sap standard."
    It is possible to do Network Cost Planning, for that you have to make the settings required for to determining the plan costs in networks.
    In networks/activities the plan costs are:
    Calculated automatically on the basis of the defined price and quantity structures
    Planned using unit costings for general costs activities or material components
    for this make the setting in config of PS node Project System -> Cost -> Planned Costs -> Automatic Costing in Networks/Activities.
    Rgds
    Rajesh

  • Element wise Cost planning

    Dear all,
    i need to arrive planning cost at component level, lets put like this, i created a WBS under, one external service under, one BOM. I am exploding the BOM component in Project & i am getting the total planned cost for the BOM along with the component, but i need at component level Plan cost. Is it possible to arrive plan cost for the component in BOM ?
    Looking for the further co-ordination
    Kumar

    sorry mukesh ,
    I thought you want to do cost planning  for perticular component..... ( i unerstood wrongly....)
    i think you want planned cost at component level........
    it is not possible... miximum you can get at activity level........
    since all componets you are attaching to activities.....
    one thing you can get cost by cost elements.... in cost element report.... wher you can find cost by cost elements like ....  RM .... Finished good, semu finished ( depend on valuation class in mterial master....)
    Venkatesh