Disposition Area (MRP) in MM02 (BAPI_MATERIAL_SAVEDATA)

Hi All,
My mass upload program uses the FM BAPI_MATERIAL_SAVEDATA. Now I want to develope a mass upload program to create the disposition area of MRP.
Q:
Does someone know a FM or Global Class method that I can use for the mass upload program ??
Blacky.

Hi All,
Solved problem myself. I found/used the SAP Standard prog: RMMDDIBE
Further Info the FM:
MD_MRP_LEVEL_CREATE_DATA
MD_MRP_LEVEL_CHANGE_DATA
Blacky

Similar Messages

  • TCode to see List of Plant + MRP Areas + MRP Type

    Hi,
    Can anyone tell whether any TCode exists which gives List of Plant + MRP Areas + MRP Type for the List of Material Number Input.
    For eg:  MM60 will give list of materials with Plant and its MRP Type.
    But it wont give detailes of other MRP Areas under which the Material is maintained.
    Regards,
    Prathap

    Hi,
    MC47 will give the list only if some requirement is loaded for the material.
    Vishal - Table serves the purpose but i need Tcode only.
    Does anyone has idea on other possible TCodes.???
    Regards,
    Prathap

  • Add custom field in MRP area-MRP 2 in material master(MM01/MM02/MM03)

    Hi
    As per my requirementn we have to add one field in the Material master(MM01/MM02/Mm03). Mentioned path below.
    MM01/MM02)--> MRP1 tab --> in the MRP areas > click on MRP AREAS button>Pop will come with MRP AREA --> double click on entry > MRP area screen will appear> In MRP2 data tab> i've to add a new custom field. Program Name> SAPLMD_MGD1
    Screen --> 0040
    Is there any exit/customization which can be used to do this?
    i was unable to find a exit for the same.
    Thanks,
    Gauri

    Hi Gauri,
    See Note 44410 - Integrating cust.-specific fields in matl master, I think that it will help you
    Regards
    Eduardo

  • Material Master changes are not allowing (MM02)

    Dear All,
    we have done year end activities successfully for the 2010 fiscal year. we are following January to December. In 2011 January 9th date we have activated Material ledger. after that when we try to go to material master the system is giving this error.
    "Currency was not defined at production startup
    Message no. C+040
    Diagnosis
    You have set the material ledger to productive in valuatione area DEL1. Nevertheless, information about the currency settings at the time of production startup are missing.
    System Response
    The system cannot ensure data consistency, since it is not possible to compare the current currency settings with those made at production startup.
    Procedure
    1. Make sure that the currency settings have not been changed since material ledger production startup in valuation area DEL1.
    2. Inform your system administrator."
    Even when I try to create the new material master it is showing the same error.
    Could anybody guide me how to solve this.
    Thanks and regards,
    Mr.Rao

    Hi Mr Rao ,
    Your ML currency settings are incorrect .. which is causing the issue..
    A . Have you checked the following notes which give a detailed information about Material Ledger activation: 596558 Material ledger production startup 384145 Advice note on material ledger production startup 165844 Material ledger production startup Please, check attached note 596558, which provides recommendations on Material Ledger production startup: ...before ML activation .. i hope not ..
    B Always activate the material ledger for a complete company code and copy all currencies from FI. This is the only way to ensure the reconciliation with FI. c) In addition, it is recommended that you activate the material ledger for a complete company code because the invoice verification can neither store invoices that contain materials from plants the material ledgers of which are active nor more materials from plants the material ledger of which is not active. ... Please, consider that only transactions performed after the startup will be taken into account for the actual price calculation.
    C .Now to correct it .. you have to deactive ML and correct the currencies and then re-activate ML . Have a look into SAP  : Note 53947 - Changing currencies after production startup.  Now , are e the actual activities now posted and production is active .. if yes .. the deactivating ML is a pain.
    D .If the Material ledger is already set to u201CProductiveu201D, run the report SAPRCKMJX using SE38. This report should only be run in Development or Testing environment. It is not recommended to be used in Production. It may be used in case there is no activity in the plant (no stock, no movements have happened ever). SAP recommends use of their CO-PC development support for this (OSS Note 108374).
    Please revert back for any further clarifications
    Regards
    Sarada

  • MRP Area tables for MD06 information access like SQ01, DBM logical database

    We currently use SQ01 DBM logical database to access MD06 information (tables MDKP and MDTB).  The MRP results from the MRP Area are not showing in this query. This implies that the MRP area, MRP results are stored in other tables.
    I have reviewed tables (MDLV, MDMA, MDLG, DVER, MDIP) from a similiar thread.  However, they do not contain the MRP data (planned orders, stock, production orders ect) like in the DBM logical database.   This data access is very powerfull for exporting planning data for more robust analysis.
    Any help is much appreciated.
    Thank you

    Hi,
           Please try FM: 'AUFBAUEN_MDPSX_ANZEIGEN'.
        MD06 dame come many table.
    Example:
    (Plant level)
      icm61w-fabkl  =  wk_fabkl.                  :Factory calender
      imt61d-matnr  =  p_matnr.                    : Materials
      imt61d-werks  =  it_tbl-werks.            : Plant
    AUFBAUEN_MDPSX_ANZEIGEN 呼出
      CALL FUNCTION 'AUFBAUEN_MDPSX_ANZEIGEN'
        EXPORTING
          ecm61w      =  icm61w
          ecm61x      =  icm61x
          emt61d      =  imt61d
          et399d      =  it399d
          ECM61B      =
          ESFILT      =
        IMPORTING
          icm61m      =  wa_e_cm61m
          imdkp       =  wa_e_mdkp
          imdsta      =  wa_e_mdsta
        TABLES
          mdpsx       =  it_mdps
    regards,
       Gaito

  • Run MRP by MRP area - Tcode?

    Experts -
    How I can run MRP for MRP area? We have few MRP areas and assigned to many materials. MD01 is for plant level, I am looking for simmliar transaction (not background job) that can run MRP for MRP area.
    Thanks for your time-

    Hi Air, 
    Normally Planning of materials takes place on a plant level
    By usung MRP Areas - Specific storage locations can also be grouped together and planning takes place on that grouping area (MRP Area)
    Ex : Plant 3200/Sloc 50 & Plant 3200 /Sloc 51 is one MRP Area this is done in Configuration
    When activated materials can now be planned per MRP area and MRP runs can also be done on MRP area
    Consumption history will be kept on MRP area level
    i'm also forwarding a link which would be very helpful to you
    www.sap123.com/showthread.php?t=57
    In case if this information is found helpful do please do reward
    accordingly
    Thanks & Regards
    Pavan

  • Sap pp -MRP-area

    Hello SAP-Guruu2019s
    Pls tell me the Procedure/steps/Details to maintain MRP-area for a Vendor & also for a Sub-Contractor.
    Any comments welcome   & Thanks in advanc

    Hi,
    Pls. find the following details regarding MRP Area :
    MRP Area
    Definition
    The MRP area represents an organizational unit for which material requirements planning is carried out independently.
    Basically, there are three types of MRP area:
    Plant MRP Area
    The plant MRP area initially contains the plant together with all its storage locations and stock with subcontractors.
    When you have defined MRP areas for storage locations and for subcontractors and you have assigned the materials, the plant MRP area is reduced by exactly this number of subcontractors and storage locations. This is because they are now to be planned separately.
    MRP Areas for Storage Locations
    You can define an MRP area that consists of a particular storage location, by creating an MRP area and assigning the storage location to it. Material requirements for this storage location are then planned separately from the rest of the plant.
    You can also group several storage locations into one MRP area, by creating an MRP area and assigning the storage locations to it. These storage locations are then planned together.
    A storage location of a plant may be assigned to only one MRP area.
    MRP Areas for Subcontractors
    You can also define an MRP area for each subcontractor.
    A subcontractor may be assigned to only one MRP area. An MRP area of the subcontractor type may also only contain one subcontractor.
    Use
    You can carry out MRP specifically for the determined MRP areas. This enables you to carry out differentiated material requirements planning. The requester can be, for example, the production on a particular assembly line or a subcontract order.
    The MRP area allows you to have specific control over the staging and procurement of important parts produced in-house and purchased parts for each shop floor area. You can, however, also plan the provision of components for the individual subcontractors.
    MRP areas of the storage location or subcontractor type are only suitable for:
    components that are planned and produced for stock
    finished products that are planned and produced for stock. By assigning a storage location in a sales order or by entering an MRP area when creating the planned independent requirements, you can define whether a material is planned in the plant MRP area or in the MRP area of the storage location.
    Finished products and important assemblies intended for make-to-order or engineer-to-order production are always planned in the plant MRP area.
    The planning run takes into account the planning with MRP areas as follows:
    If you do not enter a separate scope of planning, the system plans the whole plant, that is, all MRP areas in the plant, during the total planning run. If you want to carry out a total planning run for a particular MRP area only, you must specify the required MRP area in the scope of planning.
    During single-item, multi-level planning, the system plans the selected material in the MRP area entered. In addition, the system takes into account planning file entries from other MRP areas, for example, if the material is to be procured using stock transfer.
    During single-item, single-level planning, the system plans the selected material in the MRP area entered only.
    Structure
    You define the MRP areas in Customizing for MRP. You can thereby assign the following to an MRP area:
    one or more storage locations (example: you want to carry out planning for a particular assembly line and therefore assign a production storage location to the MRP area)
    a subcontractor.
    You assign the various MRP areas to the materials in the material master. For this, you create an MRP area segment for a material for every MRP area, in which it is used. In this MRP area segment, you can define MRP parameters such as, for example, the lot size or MRP type. This allows you to plan the material differently in the MRP area from how you plan it in the plant MRP area.
    MRP with MRP areas for the material is not activated until the material has been assigned to an MRP area. If you have not assigned a material to an MRP area, that is, you have not created an MRP area segment in the material master, the material will continue to be planned in the plant MRP area only. If you have assigned an MRP area to it, the system can plan it in the plant MRP area and in the assigned MRP area.
    Integration
    You can carry out material requirements planning for MRP areas using all MRP procedures and all lot-sizing procedures.
    You can also carry out an independent material forecast for MRP areas using your own parameters.
    The material consumption values are updated separately for each MRP area.
    A separate ATP check is carried out for each MRP area.
    If several storage locations belong to an MRP area, the system can also carry out a check at two levels, that is, at storage location level and at MRP area level.
    Example: Subcontractor
    You can also carry out planning for components to be provided in subcontracting using an MRP area by defining an MRP area for every subcontractor and assigning the components to be provided to the MRP area of the subcontractor. You therefore plan the requirements to be provided for these components for one subcontractor separately from all other requirements (see Planning for Components to be Provided in Subcontracting).
    Depending on the requirements situation, the system creates either stock transfer reservations from the plant to the stock of material provided of the subcontractor or it creates purchase requisitions within subcontracting/third-party order processing, according to the special procurement key settings.
    Implementing MRP Areas
    Implementation Options
    The main reason for you to implement MRP areas is if you would like to plan materials, which are required in different shop floor areas, storage locations or by subcontractors, separately from one another.
    As soon as you have activated materials requirements planning with MRP areas, this type of MRP is active at client level, that is, MRP will be carried out in this way in all plants.
    Material requirements planning with MRP areas cannot be reversed.
    Process Flow
    You can implement material requirements planning with MRP areas in three steps:
    You convert the existing planning file entries at plant level to planning file entries at MRP area level.
    During the conversion, the system creates a plant MRP area for every plant as a background job. This, however, will not affect your planning. The processes in material requirements planning and the planning results remain unaffected.
    The conversion is also useful even if you do not work with MRP areas, but still have to plan for several plants, as the new planning file improves system performance during the planning run.
    You activate MRP with MRP areas in Customizing for MRP. This causes the MRP area field to appear in the applications of MRP and in related areas. When you enter the plant number, the system automatically fills the field with the number of the plant MRP area. The number of the plant MRP area is the same as the plant number.
    This does not affect the planning run as the plant MRP area still corresponds to the present plant.
    You define an MRP area, for example, for a storage location. You then assign the materials that are to be planned for this storage location, by creating an MRP area segment in the material master.
    Materials requirement planning for this storage location is then carried out separately. The storage location stock is no longer included in the available stock of the plant MRP area. The receipt and issue elements of this storage location (MRP area) are also not taken into account in the plant MRP area. They are only taken into account in the MRP area of the storage location.
    If you have already worked with storage location MRP the system still carries out storage location MRP even after the activation of MRP areas. You need to decide in principle whether you want to continue using storage location MRP or whether you want to create MRP areas for the storage locations that are planned separately. It is not possible to simultaneously plan a material using storage location MRP and an MRP area for the same storage location.
    If you decide to use MRP areas, you should then try to convert all storage locations that are planned separately to MRP areas in one step. Before you assign the material to an MRP area, you must remove the MRP indicator, which is located in the material master at the storage location organizational level (view MRP 4) in the screen area Storage location MRP.
    Even if you have defined MRP areas in Customizing, the system plans the materials in the plant MRP area until you assign the MRP areas to the materials.
    Only the assignment of one or more MRP areas to a material, by creating MRP area segments in the material master, actually cause changes in the material requirements planning.
    Hope this helps.
    Regards,
    Tejas

  • MRP areas--Component To be issues for different MRP areas

    Dear All
    I have this scenario for MRP areas--- MRP area 2000 and 3000..these areas are basically 2 separate physical production facitilties...One is main production plant and other is lab for making samples.... But they store the raw material stock seprately..stock for raw material for main production is in main warehouse 2000 and stock for samples lab in in their mini warehosuese 3000.
    Busniess wants to consume stock from main production warehosue when doing main production and to consume stock from samples warehosue when doing samples production. BUT header item is same and raw materials are also same. Means the same BOM.
    Example-- FG1 and it has RM1 and RM2 in BOM
    Kindly help to do settings\configuration somehow that when we do production in 2000, compoenent are comsumed from 2000 and when we do production in 3000, components from 3000.
    I extended FG on both MRP areas. even for RM1 anf RM2, i extended it on both MRP areas. So in MRP2 view prodcution stprage location is 2000 and with MRP area MRP 2 view production storage location is 3000.
    It did not work.
    Kindlt sugget

    Hi,
    What you need is a way to determine the proper issue storage location for the two cases.
    Since, as you say, the BOM is the same, you need to use production versions. In the definition of the production version you can control the issue storage location for the components of the order.
    All you need then is to choose the right production version for each case when you create the order.
    Regards,
    Mario

  • MRP Area Error

    Hi all
    I am uploading material master mrp area data using LSMW direct input method. The standard prog RMDATIND not showing the BERID field in the step field mapping. IEven table name MDMA is not sowing in structure step also. So that i am not able to mapp BERID field.
    Can u suggest right solution.
    Thanks
    Ganesh

    Hi prabu
    yes, that is fine. But i have load file only one and i want to update MRP area, MRP group through Standard program RMMDDIBE.
    If u said like i want to create onother program for MRP group only. But i dont want like that, i want to update both at a time.
    Please suggest me..
    Thanks
    GAnesh

  • MRP AREA CONFIG & PROCESS

    Hi PP Gurus,
    I want to know about the complete process of MRP Areas.
    1) Complete step by step process in terms of config. & front end in SAP.
    2) How to activae it for Plant, Storage location & vendor.
    3) Difference between above three & where they are exactly used.
    The person who helps will be awarded points = 10.Sure.
    Regards

    Hi,
    Pls. find the following details regarding MRP Area :
    MRP Area
    Definition
    The MRP area represents an organizational unit for which material requirements planning is carried out independently.
    Basically, there are three types of MRP area:
    Plant MRP Area
    The plant MRP area initially contains the plant together with all its storage locations and stock with subcontractors.
    When you have defined MRP areas for storage locations and for subcontractors and you have assigned the materials, the plant MRP area is reduced by exactly this number of subcontractors and storage locations. This is because they are now to be planned separately.
    MRP Areas for Storage Locations
    You can define an MRP area that consists of a particular storage location, by creating an MRP area and assigning the storage location to it. Material requirements for this storage location are then planned separately from the rest of the plant.
    You can also group several storage locations into one MRP area, by creating an MRP area and assigning the storage locations to it. These storage locations are then planned together.
    A storage location of a plant may be assigned to only one MRP area.
    MRP Areas for Subcontractors
    You can also define an MRP area for each subcontractor.
    A subcontractor may be assigned to only one MRP area. An MRP area of the subcontractor type may also only contain one subcontractor.
    Use
    You can carry out MRP specifically for the determined MRP areas. This enables you to carry out differentiated material requirements planning. The requester can be, for example, the production on a particular assembly line or a subcontract order.
    The MRP area allows you to have specific control over the staging and procurement of important parts produced in-house and purchased parts for each shop floor area. You can, however, also plan the provision of components for the individual subcontractors.
    MRP areas of the storage location or subcontractor type are only suitable for:
    components that are planned and produced for stock
    finished products that are planned and produced for stock. By assigning a storage location in a sales order or by entering an MRP area when creating the planned independent requirements, you can define whether a material is planned in the plant MRP area or in the MRP area of the storage location.
    Finished products and important assemblies intended for make-to-order or engineer-to-order production are always planned in the plant MRP area.
    The planning run takes into account the planning with MRP areas as follows:
    If you do not enter a separate scope of planning, the system plans the whole plant, that is, all MRP areas in the plant, during the total planning run. If you want to carry out a total planning run for a particular MRP area only, you must specify the required MRP area in the scope of planning.
    During single-item, multi-level planning, the system plans the selected material in the MRP area entered. In addition, the system takes into account planning file entries from other MRP areas, for example, if the material is to be procured using stock transfer.
    During single-item, single-level planning, the system plans the selected material in the MRP area entered only.
    Structure
    You define the MRP areas in Customizing for MRP. You can thereby assign the following to an MRP area:
    one or more storage locations (example: you want to carry out planning for a particular assembly line and therefore assign a production storage location to the MRP area)
    a subcontractor.
    You assign the various MRP areas to the materials in the material master. For this, you create an MRP area segment for a material for every MRP area, in which it is used. In this MRP area segment, you can define MRP parameters such as, for example, the lot size or MRP type. This allows you to plan the material differently in the MRP area from how you plan it in the plant MRP area.
    MRP with MRP areas for the material is not activated until the material has been assigned to an MRP area. If you have not assigned a material to an MRP area, that is, you have not created an MRP area segment in the material master, the material will continue to be planned in the plant MRP area only. If you have assigned an MRP area to it, the system can plan it in the plant MRP area and in the assigned MRP area.
    Integration
    You can carry out material requirements planning for MRP areas using all MRP procedures and all lot-sizing procedures.
    You can also carry out an independent material forecast for MRP areas using your own parameters.
    The material consumption values are updated separately for each MRP area.
    A separate ATP check is carried out for each MRP area.
    If several storage locations belong to an MRP area, the system can also carry out a check at two levels, that is, at storage location level and at MRP area level.
    Example: Subcontractor
    You can also carry out planning for components to be provided in subcontracting using an MRP area by defining an MRP area for every subcontractor and assigning the components to be provided to the MRP area of the subcontractor. You therefore plan the requirements to be provided for these components for one subcontractor separately from all other requirements (see Planning for Components to be Provided in Subcontracting).
    Depending on the requirements situation, the system creates either stock transfer reservations from the plant to the stock of material provided of the subcontractor or it creates purchase requisitions within subcontracting/third-party order processing, according to the special procurement key settings.
    Implementing MRP Areas
    Implementation Options
    The main reason for you to implement MRP areas is if you would like to plan materials, which are required in different shop floor areas, storage locations or by subcontractors, separately from one another.
    As soon as you have activated materials requirements planning with MRP areas, this type of MRP is active at client level, that is, MRP will be carried out in this way in all plants.
    Material requirements planning with MRP areas cannot be reversed.
    Process Flow
    You can implement material requirements planning with MRP areas in three steps:
    You convert the existing planning file entries at plant level to planning file entries at MRP area level.
    During the conversion, the system creates a plant MRP area for every plant as a background job. This, however, will not affect your planning. The processes in material requirements planning and the planning results remain unaffected.
    The conversion is also useful even if you do not work with MRP areas, but still have to plan for several plants, as the new planning file improves system performance during the planning run.
    You activate MRP with MRP areas in Customizing for MRP. This causes the MRP area field to appear in the applications of MRP and in related areas. When you enter the plant number, the system automatically fills the field with the number of the plant MRP area. The number of the plant MRP area is the same as the plant number.
    This does not affect the planning run as the plant MRP area still corresponds to the present plant.
    You define an MRP area, for example, for a storage location. You then assign the materials that are to be planned for this storage location, by creating an MRP area segment in the material master.
    Materials requirement planning for this storage location is then carried out separately. The storage location stock is no longer included in the available stock of the plant MRP area. The receipt and issue elements of this storage location (MRP area) are also not taken into account in the plant MRP area. They are only taken into account in the MRP area of the storage location.
    If you have already worked with storage location MRP the system still carries out storage location MRP even after the activation of MRP areas. You need to decide in principle whether you want to continue using storage location MRP or whether you want to create MRP areas for the storage locations that are planned separately. It is not possible to simultaneously plan a material using storage location MRP and an MRP area for the same storage location.
    If you decide to use MRP areas, you should then try to convert all storage locations that are planned separately to MRP areas in one step. Before you assign the material to an MRP area, you must remove the MRP indicator, which is located in the material master at the storage location organizational level (view MRP 4) in the screen area Storage location MRP.
    Even if you have defined MRP areas in Customizing, the system plans the materials in the plant MRP area until you assign the MRP areas to the materials.
    Only the assignment of one or more MRP areas to a material, by creating MRP area segments in the material master, actually cause changes in the material requirements planning.
    Hope this helps.
    Regards,
    Tejas
    Edited by: Tejas  Pujara on Nov 7, 2008 12:02 PM

  • MRP Areas & shipments out of

    Once I create an MRP area what is the best practice around making shipments in SD "from" the MRP area and not the plant it resides in itself?
    Also if product is made within the plant iself the MRP area resides in vs outside STO ... what is the best practice on "transfering" the product from the plant to the MRP area (MRP area resides within the same plant).
    Tim

    Thankyou.
    One last quesiton ... we are concerned about consuming "forecast" against the MRP area stock .... management is still asking how are sales orders to be entered "against" the MRP area so that forecast in demand plan is consumed?
    As it sounds the order entry is as normal eg by sold to, material, date, etc. and only real difference is that when you create your delivery and pick you retrieve stock from the MRP area location eg 1002 which decrements stock from it.
    As far as movements, it sounds like you can use location to location transfer postings to move stock between the plant locations and the MRP area location inside the plant and special procurement keys to move UB or NB Stock transports to the plant and then transfer to the MRP area.
    Your thoughts or guidance are appreciated as we've never used MRP areas and can't find much info on these areas anywhere.
    Tim

  • Mrp groups & mrp areas

    Hi, wht is the difference bet mrp groups and mrp areas. if we have 4 different final products (ea consists of around 300 parts- bom) what will be prefered to use for mrp run?

    Hi All,
    For you case :
    You can maintain the MRP group for your finish product. But not for all the components of the final products also. because MRP group is based on the Material Type
    even the Mrp area you cannot used.
    Better use the normal MRP run per the plant parameters.
    1. Main Difference b/w MRP group and MRP area :
    MRP group :
    1.  The MRP group is an organizational object that can be used to allocate special control parameters for planning to a group of materials.
    2. You can maintain MRP groups if planning control per plant is not precise enough for your requirements and you want to allocate certain material groups different control parameters from the plant parameters.
    MRP area :
    1. The MRP area represents an organizational unit which carries out materials requirements planning independently
    2. An MRP area can include one or several storage locations of a plant or stock with a subcontractor

  • MRP profile

    Hi,
    In MM02> MRP1 Tab>MRP areas
    On MRP area level the content of the fields (marked as default value in the MPR profile) is updated with the value out of the
    MRP profile.
    does it mean all default fields are overwritten to the material master data?
    is there any means to change some fields, for example, MRP controller remains the initial value in the material master data even using MRP profile updating?
    Thanks.
    Wang Jiayi

    Dear Wang Jiayi,
    Profile are provided to simplyfy the data maintainace, in every bussiness for similar material type or objects we have many common things , which will be similar in 90 % cases, so to create this kind of materials we can have all similar fields grouped together in MRP profile which are MRP relevant , the fields which are valid for 100 % materils will be default and fix, the fields which are valid for 50% or so will be default but will not be fix so that you can change them while creating material in MM01 or MM02.
    so when ever you will attach MRP profile all the default will be copied , if defaults are not fix you can change them while creation or Change mode.
    But if you change profile and expect system not to change the default set by earlier MRP profile , its not possible.
    you need to go ahead with some work around , Create MRP profile with all default values which can be valid for 90 %, like the profile Z002 which will have all other fields other then MRP controller , maintain manually MRP controller in creation MM01 or in MM02.
    If data size is larger , use LSMW or BDC to upload this data.
    Check out and revert.
    Hope it helps you.
    Regards
    Ritesh

  • Multi-level mrp run

    lets say i have a FG which has a bom that consists of a Semi-FG (SF1) and a Packaging material. This SF1 also has a bom which consists of a Raw mat.(RM1) and another Semi-FG(SF2). SF2 has yet another bom, which consists of 3 more raw materials - RM2, RM3, RM4.
    my question is that whenever i execute an mrp run, why is it that requirements are only captured for the FG, the SF1, and the PM. a PIR for the FG has been created, set for 3 mos. the FG has a strategy group 40, while everything else has strategy 10 (make to stock)?

    Hi raf ,
    Please check with  MRP type & Porcurement Type for all semi finished materials at MRP view (MM02).
    MRP type=PD & Proc Type= E
    I assume stock of all  semi material is zero. With above condition if u run MRP for Fert (F1)Material with PIR at MD02, both dependent req and procurement proposal will be created for Semi finished material.
    u can see the planning result at MD04
    Please check and come back
    Regards
    Pradeep

  • Items below to phantom items are not available in ASCP workbenck.

    Hi Experts,
    I came up one issue on ASCP, consider following BOM. Assume that all below items are MRP planned , all items supply qty is zero,
    FG ( finished good, WIP supply type - Push)
    |-> PH ( Phantom, WIP Supply type - Phantom)
    |-> P (Purchase item, WIP Supply type - Push)
    Now I have entered forecast against FG. After running data collection and plan, I can see forecast for FG. It is suggesting work order for FG but not suggesting purchase order for P part. While going in detail, I found that BOM data is successfully imported from source instance by data collection. But in plan, I can not see any child part for FG.. either PH or P. And this will be reason of not creating planned order for P. So can you please help me to find out reason behind this behavior.

    Hi Dipak,
    Check the value for profile option MRP: Explode Demand Through Phantom Component. It should be set to yes for planning to recognize the requirements for the components below the phantom.
    Prabhu Chepuri.

Maybe you are looking for

  • How can I get passed the set up page?

    I used Time machine from my old computer and used the external hard drive to plug in my new pro. I'm not sure if I just had a lot to put on the pro that it is taking so long, but it's been sitting on the "Thank You. Your Mac is set up and ready to us

  • Running a VM from an exFAT drive

    I use a windows 7-x64 box at work, on which i hv my linux VM running on VMware player 3. How can I use the same VM on a mac. Right now I'm running it on an NTFS external HDD which is perfect for windows. However, I need to use it on my mac (Snow Leop

  • Hpe 150 freezes. hp assistants says Smart Drive error. Common issue?

    HPE-150f seems like the hard drive is going out. Is this common with these TB drives? Which do i use to replace it? After only one year? Wow. How do i reinstall? I have no CD?

  • How to view JDBC drivers installed?

    Hi, How could I see in XI which JDBC drivers are currently installed on the system. I have an XI user with, if I don't go wrong, all the privilegies, but no access to the installed OS. Thanks in adv. for your suggestions. Cheers, greg

  • Best Practices for UI Elements in a Class

    Hi, I am quite new to Flash. I am making a class called "Slice" in the file "Slice.as" which is bound to a symbol called "Slice" which is defined in my main .fla file. I have used the visual tools in Adobe Flash CS4 to design the symbol. The "Slice"