Hi,
The table which contains the document assignment is DRAD table. Where you have to pass your equipment number or Functional location in Object Key field DRAD-OBJKY along with this object as DRAD-DOKOB. In case of equipment the entry in *DRAD-DOKOB as EQUI and in case functional location it will be IFLOT.
This is how you can find out attached documents based on document type per equipment or Functional location.
Hope it is help ful.
Regards,
N.Nagaraju

Similar Messages

  • Document Linking BPEL 2.0 - partly working

    According to the BPEL 2.0 specifications you can use import statements to link xml schemas or wsdls. This seems to work during design time. When you build/deploy the project only the last import is used. All preceeding imports are skipped or not noticed. So when I put these two imports in the bpel code:
    <import namespace="http://www.ao-services.nl/pas/tasks" location="xsd/pas-task-proxy.xsd" importType="http://www.w3.org/2001/XMLSchema" />
    <import namespace="http://www.ao-services.nl/PAS/processes/local" location="xsd/bpel-local-types.xsd" importType="http://www.w3.org/2001/XMLSchema" />
    I get the following error, because ns14:PasTaskPayload is part of the first import
    error: in SubCommunicatieAfhandelen.bpel(138): "element" is set to "ns14:PasTaskPayload" on this <bpel:variable> but it cannot be resolved (check value of "element", imports, WSDLs or XSDs).
    In reverse order:
    <import namespace="http://www.ao-services.nl/PAS/processes/local" location="xsd/bpel-local-types.xsd" importType="http://www.w3.org/2001/XMLSchema" />
    <import namespace="http://www.ao-services.nl/pas/tasks" location="xsd/pas-task-proxy.xsd" importType="http://www.w3.org/2001/XMLSchema" />
    I get the error
    error: in SubCommunicatieAfhandelen.bpel(137): "element" is set to "ns12:DocGenParameters" on this <bpel:variable> but it cannot be resolved (check value of "element", imports, WSDLs or XSDs).
    Looks like a bug as it should be possible according to the OASIS Bpel 2.0 specs to have multiple imports. Or am I missing something?

    unfortunately not. that throws the selection failure fault...
    Exception is thrown because the from-spec at line 188 is evaluated to multiple nodes
    <details>
    <from-spec>
    <from>$networkNodesOutputVariable.ExecutionNetworkNodeCollection/ns6:ExecutionNetworkNode/ns6:executionNetworkNodeUid[$nodeCounter]</from>
    </from-spec>
    <variable>
    <message>networkNodesOutputVariable</message>
    </variable>
    <fault>
    <bpelFault>
    <faultType>0</faultType>
    <selectionFailure/>
    </bpelFault>
    </fault>
    </details>

  • Documents attached to Work Order

    Hi all,
    I have a functional spec that says: "Validate if one or more documents have been attached to the work order through Services For Object Functionality"..
    How can I check this? Is there any table that relates work order and documents?
    Thanks!
    Nicolas.

    Hi,
    Use the FM BDS_GOS_CONNECTIONS_GET for the same.
    CLASSNAME: BUS2007
    OBJKEY: 12 digit order no.(prefix zeros in ur order no.)
    Thanks
    Sunil
    Edited by: sunil gupta on Jul 5, 2011 10:52 AM

  • Multiple notifications linked to work order

    Hi sap gurus,
    How can we link multiple notifications in PM Work order
    Regards,
    Krishna

    Greetings Krishna,
    You can use the "Objects" tab in the Order view (IW32 t-code) to assign multiple Notifications to an Order.
    Please note a Notification can only be assigned to 1 Order at a time (therefore it is a N:1 relationship between Notifications and Orders).

  • Work Order Reporting using I_BEGRP as a selection criteria

    Hello all,
    I am having a small problem regarding the authorization object I_BEGRP, which appears at general data informed tab at equipment level. The situation is as described below:
    Our client has several subcontractors working with Maintenance Work Orders in the system, and in order to control that each subcontractor does only access to their own data (equipment, work orders, etc.) different authorization group has been used to assign each of the equipment.
    Problem is now when the client needs to be able to know the list of MWO per subcontractor.
    The need is clear: for a user that is not restricted by this authorization group, it cannot be usedas a selection criteria to obtain a list of WO of a certain subcontractor.
    I have seen that it can be shown in the equipment standard report IH08, but only as exit data, but not as entry selection criteria, but neither for MWO (IW39) nor for notifications (IW29) it can be used as an entry selection criteria.
    Can someone help me with this issue? is the only solution to make a custom development, and to copy program RIAUFK20 in order to allow this field as an input?
    Thank you very much for your help.
    BR,
    Francesc.

    Hi,
    the only workaround I can think of is to use suitable search help for equipment. So the process would be to run IW29, open search help for equipment that allows you to specify authorization group (I think Equipment by Equipment list should work), then select all equipments from the auth. group and then run IW29 restricted by equipments. It's not nice but it allows you to select all orders that have equipments assigned to some specific authorization group. Otherwise you need to enhance standard reports to allow authorization group as one of the select options.
    Cheers

  • Printing Attachments along with Work Order

    Hi Friends,
    My client has a requirement that the attach a external document (DOC, PDF, XLS) to a work order and wants this document to print automatically along with work order printing.
    How to set this in SAP?

    Nilesh,
    Can you please tell how this issue was resolved for the benefit of others as well. We currently have a requirements where we need to print attachments along with a WO.
    Thanks in advance.
    Mahesh.

  • Digital signature for work order processing

    Hi,
    Have anybody implemented digital signature for work order processing? Can you throw some lights,  what are the steps involved?
    Requirement is when work order reach certain status, like on order release, on partial confirmation, on final confirmation or on Technical completion, digital signature needs to be captured. This is a regulatory requirement.
    I read some threads that explains digital signature can be assigned to plant and order type combination, but i couldn't find this specifc config step, we are using ECC 6.0. Is anything needs to be activated before I can see these configuration steps.
    With ABAP help I was able link digital signature tool to work order, but was wondering if this can be achieved through configuration as mentioned in some of the threads.
    Also I have another requirement, like if you are doing a mass TECO using IW38 transaction, capture digital signature once and the same should be applied for all the selected work orders. Otherwise you have to enter your password as many time as the number of work order selected.
    Jaison

    Hi,
    Some information on operation sign-off available in [help|http://help.sap.com/erp2005_ehp_03/helpdata/EN/da/49d9c433ff4985b2484b7b911123cf/frameset.htm]
    -Paul

  • Automatic printing of a document linked to an Equipment

    Good day SAP Experts,
    I have a question which I hope there is a simple answer to within SAP.
    I have created some documents that are stored in a seperate pc and are linked to SAP PM equipments. (Transaction CV01N)
    I can follow the link from the equipment back to the document, open and view/change this document and also when the document is open, I can print it.
    So far so good, now is the tricky bit,  I create a PM work order for this Equipment, I can see there is a document linked to the equipment, so I want this documnet to be printed automatically when I release and print the work order.
    To put it simply, my request is similar to having received an email with an attachment, I want the attachment to be printed in full when I request the email to printed.
    In  the customising of DMS I have found :
    Application Type
    This key controls the processing of original application files with applications in document info records.
    Use
    For authorization purposes, you can define the following settings for each application, depending on the data carrier type:
    1 - Display
    2 - Change
    3 - Print
    But I cannot get option 3 to work or am I misunderstanding the use of "3-Print"
    Any help or guidance greatly appreciated.
    Leslie

    Hi Leslie
    The print function in workstation applications won't automatically print the documents attached to an equipment. This function is designed to allow you to print using the print button in a SAP DIR or from CV04N, not for automated printing when a work order is released. This would require either an ABAP enhancement or a product like Seal.
    The problem with linking a document to an equipment and printing it is that the equipment could have any documents linked including photos and numerous procedures or work instructions designed for different tasks. Unless all documents are relevant for all tasks, you could easily find yourself in a position where you end up printing 5 documents you don't need every time you release an order. This is the reason that the best technical solution is rather to link the document as a product resource tool to a maintenance order or task list. This indicates in SAP that the document is a tool required for that specific maintenance order or task and you can select different documents for different tasks and the order in which the documents should be used because without this the results could have serious safety impacts. I.e. ensure that the person follows the tag out procedure before trying to do another task on the equipment.
    Regards,
    Athol

  • On Work Order using Object lists for equip u can manually create Notifi

    On a maintenance Work Order using Object lists for equipment you can manually create a notification for each line item.
    We want to automate this process to do this when we save the document.
    Any ideau2019s on how to do this?
    Does a user exit exist for this?

    Hi:
    Check with Tcode: IBIP - Plant maintenace batch input utility tool.
    Hope, it may help!
    Thanks,
    Murali.

  • DMS: Object Links for Work Order

    Hello All,
    I would like to attach and checkin originals to a work order thru CV01N/CV02N transaction. But, there is no specific tab for work oder. How do I acheive this?
    what configuaration and development has to be done?
    Any kind of help is highly appreciated.
    Thanks,
    Chandra

    Hi,
    If you need only a tab to be seen in the CV01N/CV02N Tcodes, then there is a config settings,
    Document Mangement--> Control Data->Define Document Types (under that select your document type to which this attachment is required) > Define object links> select the production order (PORDER---Object & Screen # 0251)
    then you can see the production order tab in the DIR,
    OR
    As per my understanding of your requirement is:
    When you attach a Original in DIR then it should be visible in the Production order also.
    To achieve this you need to build a relation b/w Material Master & DIR (particular document type), so when a order is created then DIR with original will also get attached automatically so that you view, or through EWB also it can viewed & edited.
    Hope i have understand correctly.
    Regards
    Rehman

  • Linking Contract Master to Work Orders & Materials

    Hello,
    I'm researching the possibility of linking (tying) stock to a Service Order (in a Work Order) and/or Sales Orders before it arrived on the PO. This is for provisioning stock to customers. Is there any possibility that this could be done via Projects in SAP? 
    A colleague thinks there is a way to create a project (transaction code CJ01 or CJ27) and link it to a Purchase Order in project.  If the project was a reference document, could it be done as an example?  He also believes that there are special transaction codes for moving stock between normal stock and project stock (Special stock) such as 281Q and 412Q as examples. 
    Also, Transaction code MBBS appears to be an overview of the project to show valuated sales order and project stock? Project stock was referred to as a type of special stock?
    As an end user, I am not familiar enough with SAP to know about this project area but thought this might give you a starting point. However, I've been exploring some of the functionalities to come up with a
    solution.
    Thanks in advance.

    Hi
    You can use the BAPI - BAPI_ALM_ORDER_MAINTAIN to maintain orders.
    Given below few order related tables
    AUFK     -Production order headers
    AFIH     -Maintenance order header
    AUFM     -Goods movement for prod. order
    AFKO     -Order header data PP orders
    AFPO     -Order item
    RESB     -Order componenten
    AFVC     -Order operations
    AFVV     -Quantities/dates/values in the operation
    AFVU     -User fields of the operation
    AFFL     -Work order sequence
    AFFH     -PRT assignment data for the work order(routing)
    JSTO     -Status profile
    JEST     -Object status
    AFRU     -Order completion confirmations
    This may help you.
    Thanks & Regards,
    Govind.

  • Add new document link not working in upgraded sharepoint 2013?

    Hello there,
    Upgraded SharePoint team sites from 2010 to 2013. add new document link not working for shared document in upgraded sharepoint 2013?. it is specially not working on machine where Office web apps set up with this sharePoint server and it
    is working fine with environment  Office web apps not configured with Sharepoint.
    Looking resoluion /suggestion, thanks in advance.
    Regards,
    Sushil

    Hi  Sushil,
    According to your description, my understanding is that the add new document link was not working on machine where Office web apps set up with this SharePoint server after you upgraded SharePoint team sites
    from 2010 to 2013.
    For your issue, it can be caused by integrating Office Web Apps with upgraded SharePoint Site.
    Firstly please make sure claims-based authentication is used by the SharePoint web application that is used to create the new document. Only web applications that use claims-based authentication can open
    files in Office Web Apps. To determine the authentication provider for a web application, follow these steps:
    1.In SharePoint 2013 Central Administration, click Manage web applications.
    2.Select the web application that you want to check, and click Authentication Providers on the ribbon.
    The authentication provider must be displayed as Claims Based Authentication for Office Web Apps to work correctly with the web application. To resolve this issue, you can delete the web application and recreate
    it using claims-based authentication, or you can change the authentication method of the web application.
    Secondly, make sure the WOPI zones match on the SharePoint 2013 and the Office Web Apps Server farm.
    To do this, run the following command on the SharePoint Server:
    Get-SPWopiZone
    The result will be one of the following:.
    internal-https
    internal-http
    external-https
    external-http
    Next, run the following command on the SharePoint Server.
    Get-SPWOPIBinding
    In the output, look for WopiZone: zone. If the results from Get-SPWopiZone don’t match the zone that is returned by Get-SPWOPIBinding, run the Set-SPWOPIZone -Zone cmdlet on the SharePoint Server to change
    the WOPI zone to match the result from Get-SPWOPIBinding.
    If not work, you can try to disconnect SharePoint 2013 from Office Web Apps Server and re-configure Office Web Apps for SharePoint 2013.
    For more information, please refer to the article:
    http://technet.microsoft.com/en-us/library/ff431687(v=office.15).aspx
    Best Regards,
    Eric
    Eric Tao
    TechNet Community Support

  • I have an iMac(Intel) Desktop computer.  I cannot print anything as it is telling me that it is "offline" How do I start it working again?  My Lexmark Printer is in working order as I have just photocopied a document successfully.

    I have an iMac (Intel) Desktop computer.   It will not send a message to my Lexmark printer because it says  "offline".   My Lexmark printer is in working order as I have just successfully photocopied a document on it. 

    That message means that the computer cannot see the printer on its network.
    Is the printer directly connected to the computer with a USB cable, or is it a network printer (either wireless, or wired to the router with an Ethernet cable)?
    Matt

  • Document attachment to work order

    HI all,
    While I am trying to attache a document through *Services for Object* in maintenance work order Create attachment is not getting populated.
    I need to attach one docuement ( picture) to this work order perticularly which was saved on my desk top.
    Could any body suggest pls
    Regards,
    Srinivas Kasina

    Hi,
    Have a look at this thread
    Attaching of documents to work orders
    Check for OSS notes in Support Portal for Object Services under PM-WOC-MO Application area.
    Regards,
    Maheswaran.

  • Hi, my apple ID verification email does not contain the link for me to click in order to verify my account. Re-submitting has not worked, what can i do to verify/activate my account

    Hi, my apple ID verification email does not contain the link for me to click in order to verify my account. Re-submitting has not worked, what can i do to verify/activate my account in order to access Icloud?

    If you want to change your iCloud ID or password on your phone go to Settings>iCloud and tap Delete Account, then sign back in with your updated information.  Note: this only deletes the account and any synced data from your phone, not from iCloud.  Provided you are signing back into the same account and not changing accounts it will be synced back to your device when you sign back in.

Maybe you are looking for

  • Can i use an app on my iMac on a shared account? if so how do i use it on the shared account?

    My wife has purchased Angry Birds Space on an her account on the same computer and we share the itunes but i was wondering if we coupld share apps as well. If anyone could help it would be much appreciated! thank you

  • International call not generating..

    HI all, I am facing call dropping for international call . When I starts dialing 900 it is giving bust tome and disconnecting. Confirming here call restriction for extensions are international and FXo line having international capability. Please see

  • Tabs and Breadcrumbs Disappearing! Please help

    Hi, I am currently using APEX 4.2. Every time I view a page which is a member of a standard tab, all the tabs and breadcrumbs disappear and I don't know why. They're all part of the same tab set, and related parent tabs, and all the pages have the sa

  • Got the problem with the desktop

    I wanna have the empty desktop , I know how to hide the dock but the problem is i couldn't get ride of the icon of Macintosh HD and Untitled or the icon of the application when i run an application such Adium icon. I want those icon don't appear on m

  • Sprint's new 'iPhone For Life' plan

    Here's the deal: $100 flat fee per month for 20GB shared data PLUS: $20/month iPhone 6 16GB $25/month iPhone 6 64Gb or 6+ 16GB $30/month iPhone 6 128GB or 6+ 64GB $35/month iPhone 6+ 128GB The kids and wife get the 16GB; I get the 128GB making my mon