Error e-mailing a test plan

I select a test plan and then click 'Print or E-Mail Test Artifacts'. I select the defaults, Click Email, enter a username and I get TF400969: An error occurred attempting to send the email. Retry at a later time."
Using TFS 2013 Update 3. Screenshots below.

Hi Jamie,
Firstly, I don't think your issue is related to your TFS configuration with SMTP server, as you can send the test email correctly. And I don't think your issue is related to your IE settings either, as emailing query result works fine.
Could you please check the event viewer on your client machine to see if there is any error message useful?
By the way, I noticed that you set configuration to also email children suite and as well as links, attachments, and associated automation. How about you start from emailing a top level test plan without adding these attached files?
Thanks.
We are trying to better understand customer views on social support experience, so your participation in this interview project would be greatly appreciated if you have time. Thanks for helping make community forums a great place.
Click  to participate the survey.
Here's an update. I found this in the event viewer on the Application Tier server: 
TF53010: The following error has occurred in a Team Foundation component or extension:
Date (UTC): 3/24/2015 7:36:04 PM
Machine: xxxx
Application Domain: TfsJobAgent.exe
Assembly: Microsoft.TeamFoundation.Framework.Server, Version=12.0.0.0, Culture=neutral, PublicKeyToken=b03f5f7f11d50a3a; v4.0.30319
Service Host: 
Process Details:
  Process Name: TFSJobAgent
  Process Id: 6564
  Thread Id: 7640
  Account name: xxxx
Detailed Message: TF271001: An error occurred while attempting to send an email notification to the following address: providence. Further email notification errors that occur within the next five minutes might not be logged. Verify that the email notification
settings are correct in the Team Foundation Administration Console.
Exception Message: The specified string is not in the form required for an e-mail address. (type FormatException)
Exception Stack Trace:    at System.Net.Mail.MailAddressParser.ReadCfwsAndThrowIfIncomplete(String data, Int32 index)
   at System.Net.Mail.MailAddressParser.ParseAddress(String data, Boolean expectMultipleAddresses, Int32& index)
   at System.Net.Mail.MailAddressParser.ParseMultipleAddresses(String data)
   at System.Net.Mail.MailAddressCollection.ParseValue(String addresses)
   at Microsoft.TeamFoundation.JobService.Extensions.Core.NotificationJobExtension.SendEmail(TeamFoundationRequestContext requestContext, TeamFoundationNotification notification, TeamFoundationIdentity subscriber, TeamFoundationIdentity recipient)

Similar Messages

  • How to send a mail about the test plan status

    Hi
    I have finished the development of ecatt automation test cases.
    And I have integrated the ecatt  automation test cases into the test plan of TWB.
    I have scheduled a job in background to run the test plan.
    After the job has finished, I need to send a email to related users to tell them the status of each test cases in the test plan.
    Is there any way to implement it?
    Thanks a lot in advance!

    Hello,
    You can send mail with the status of the test catalog-
    specify a mail system to which Test Workbench test objects send messages to the people responsible
    Please refer the below link for more information:
    http://help.sap.com/saphelp_smehp1/helpdata/en/6a/88370a002911d2bd02080009b4534c/frameset.htm
    Regards,

  • Error when I clone a test plan

    Hi All
    I get the below error when I clone a test plan.
    I've no steps or attachments in the test case mentioned below. It helps to more than one test case
    clone operation encountered an error while processing test case 21428. Exclude this test case from the suites being cloned and retry the operation. Error details : Failed to parse xml in the UITest file attachment or TCM.Steps field. Make usre this data
    is valid and retry the opeartion
    Please let me know how to fix this issue?
    Thanks

    Hi Sathish,
    Base on the error message, it seems that there are something issue in test case 21428. I suggest that you could create a new test case that similar to test case 21428 and try again.
    Regards
    Starain
    We are trying to better understand customer views on social support experience, so your participation in this interview project would be greatly appreciated if you have time. Thanks for helping make community forums a great place.
    Click
    HERE to participate the survey.

  • Error during generate test plan

    I'm trying to generate a test plan in Microsoft test Manager 2013 but during the criation of the template always appears the same error.
    the error is "Application detected an unexpected fault
                       Running transformation: System.NullReferenceException: Object reference not set to an instance of an object.
                      atMicrosoft.VisualStudio.TextTemplating04F88A763EC75D0A56EFDCF2B8809A952EF3E8E3357BFF2D9D4011312F
                     1B1B7156AE7547C446AFAB5B0446F4365E959CE585F7E56BFF574A1A1FDA6152DD705D.
          GeneratedTextTransformation.TransformText() in c:\Users\2363\AppData\Local\Temp\testplan\TestPlanSection.tt:line 151"
    Some test cases are active, and i'm trying generate a documente too know what expect.
    Thank you foll the help you can give.

    Hi,
    How do you generate test plan in MTM, please provide the detail steps. Do you clone test plan in MTM? What’s the version of your TFS?
    # Copying and cloning test suites and test cases (Clone a test plan and its test case section)
    https://msdn.microsoft.com/en-us/library/hh543843.aspx#sectionToggle3
    On the other hand, please try to clean TFS cache and try again. (Delete the cache folder, which path like C:\Users\[user name]\AppData\Local\Microsoft\Team Foundation\5.0)
    Regards
    Starain
    We are trying to better understand customer views on social support experience, so your participation in this interview project would be greatly appreciated if you have time. Thanks for helping make community forums a great place.
    Click
    HERE to participate the survey.

  • Send an e-mail after creat Test Plan STBW_2

    Hi All,
    I am working Solman 7.0 and creating Test Plan from STWB_2. But as we know is "standard" to send e-mails to resources are assigned each activity inside test plan as information about version 7 - EHP1.
    I've hust check out configuration in STBW_SET and is ok too. Maybe there are other customizing necessary to active this e-mails.
    Regards,
    Warlei Figueiredo.

    Warlei,
    See the SAP Note 1348140 - E-mail notification in test sequence does not work.
    Good luck!
    Best regards,
    Jacques.

  • Error message when I calling planning layout in the STS

    Dear
    I'm trying to use Status and Tracking System with BPS ( SEM 4.0 SP10,  BW 3.5 SP14 ).
    But I got some error messages when I calling planning layout in the STS screen..
    I designed 2 lower unit(A,B) and 1 upper unit(C) for the test. and using Bottom-up work-flow.  
    I did
    1. Create Planning Area in the BPS0 ( also Level, Package, Layout ..)
    2. Created Web Interface in the Web Interface Builder using the upper BPS Layout .
    3. Customizing STS
        - Create Sub Plan & Session
        - Asssign Hierarchy to Sub Plan
        - Determine attribute for created planning session ( Bottom-up, Auto mail )
        - Define Header characteristics for planning session to contains the planning package completely.
        - Determine Date, Person Responsible and Layout.
    4. Send Start mail
    5. Open STS Web Start Screen ( using B Unit responsible user .) 
    When he click "Open Planning" icon in the screen the following error messages were happened...
    I've no idea for that because I didn't use any variables or offset settings.        
    I guess that comes from header settings for the planning session because when I deleted the header settings for the planning sessions, I could see the planning layout.
    but I could not use lock processing in the STS.
    Could you tell me what's happening to me?
      [ Following error message ]
    Correct the data on variables and offset in character string "? 
    Message Number  UPC_FW092 
    Long Text  Diagnosis
    Character string "", which contains data on the variables and offset, has an invalid format, and cannot be converted.
    Procedure
    Correct the character string, so that it has the correct format. A correct entry on variable and offset has the following form:
    <VARIABLE_NAME> [{ + | - } OFFSET]
    Examples:
    VAR0
    VAR1+1
    VAR2 - 2.
    Also check whether the variable, that you want to use is available in the planning area.

    Hello,
    this seems to be a bug. The error message should include a variable name between ''. Since there is none, the function that raises the error was not called correctly.
    It's not likely that this is related to STS since STS does not use variables at all. It's probably a problem with the layout. If you can't resolve it, please open a message to SAP Support.
    Regards
    Marc
    SAP NetWeaver RIG

  • Test Plan template

    Hi
    I'm new to ABAP development. I have completed few objects in ABAP environment. I would like to have a test plan template to maintain documentation.
    Could anyone provide the same?
    Thanks
    sapien

    Hai
    Check the following
    Test Plan
    Prepared By           Preparation Date     
    Project          Initial Testing Date     
    Object:          Last Changed Date     
    Object Type     Report
    Predecessors     None
    Successors      None
    Sno     Particulars     Y/N
    1     Is the functionality of the object in accordance with Technical specification provided?     Y
    2     If there are changes in functionality suggested by onsite thru mail / phone till the completion of coding for the object. (Deferring the Tech spec)  mention the changes clearly as below.     N
    S. No     Date     Mail/Phone     Change description
    3     Please mention the final functionality of the object to be tested after final changes.
    Test Cases
    Test Case No.     Test Case Description     Expected Results     If Not Applicable Specify Date
    1.     Check for the data population in the internal tables     As per the spec     Applicable
    2.     Check for the input validations     As per the spec     Applicable
    3.     Check whether the required fields are selected from the tables     As per the spec     Applicable
    4.     Check whether the output format is according to the required format     As per the spec     Applicable
    Y2K Test     Check for date handling for compliance with year 2000. Ensure that test cases are prepared to handle date validation and manipulation of dates.
    Check whether 4 digits variable is used for YEAR in case YEAR is taken as separate variable. Emphasize on declaring date variable referring to SY-DATUM           
    Time spent for preparing Test Plan (Hrs.)     1 hr
    Total Number of Test Cases Applicable     4
    Regards
    Sreeni

  • Transport of Test Plan / Test Packages

    Dear all,
    We intend to transport a test plan with all test packages from the development Solution Manager to the productive Solution Manager because in the productive Solution Manager no configuration is allowed.
    We are using the Solution Manager functionality to execute manual testing in the following way:
    On SOLAR02 the project 'FOUNDATION' is stored. The project 'FOUNDATION' has been migrated from a outstanding sandbox Solution Manager system to all three Solution Manager Systems: DEV, TEST and PROD. Test scripts have been uploaded on the 'test cases' tab of the respective business process branch.
    In the development Solution Manager SMD a test plan has been generated using the uploaded test scripts mentioned above.
    On the quality assurance Solution Manager the same project 'FOUNDATION' is stored and the same test scripts are uploaded on the same branches.
    When the test plan is transported (using the recommended STWB_2 transport functionality) from the development SM to the quality assurance SM there are two issues.
    1. The transported test plan cannot be edited / regenerated anymore. An error message "The specified structure does not exist" is displayed. Message number is SOLAR056.
    2. The transported packages can be assigned to users but no notes can be added to the test cases. The error message is: "Unable to find template". Message number is SOFFICEINTEGRATION231.
    It seems that the transported test plan cannot retrieve the underlying project structure, even it is identical to the project structure of the development SM.
    This problem is urgent to us, as the test phase is starting next week.
    Thank you very much for your support.
    Best Regards,
    Marc Reinhardt

    Hello Marc,
    We have experienced similar problems. A transport of the test plan and copies of the test plans have resulted in us loosing status values and test notes. 
    I was informed it had to do with the fact the information is stored in the GUI. How I don't know, I am not a technical person.
    I was wondering if you may have encountered the similar problems I have had above and found ways around it.
    You can reach me at [email protected] as well.

  • Test plans

    Hi friends , I am new to SAP testing and have been given a scenario to write test plan and cases.
    the scenario is like this . there are two output types configured in Nace : Z123 and Z456.
    Z123 : Sends an email  with the invoice doc as PDF attached to a mail to the AR team for checking.
    Z456 : After checking they send the same invoice as PDF to the customer of the invoice  through VF33  transaction .
    can some one tell where to find the Customer for an invoice?
    Can any one suggest what are the possible test plans /cases  that can come up in this scenario?

    If this is related to some sort of financial module or system, then perhaps it's better to move this thread to one of the EBS or Peoplesoft forums.

  • How to prepare the UNIT test plan

    Hi ALL
    can any body tell me how to prepare a unit test plan

    Use the following colums in preparing unit Test data.
    1. Sr.No.
    2.Test Condition.
    3.Expected Results
    4.Description/Instruction for the test execution.
    5.TestData used for the test.
    6.Actual Result.
    7.Pass/Fail.
    For a login Screen. Unit Test plan wud b.
    1.  1
    2.   User Presses Login Button.
    3.   Data shud be validated.
    4.  As soon as the user enter the fields in the login screen,the data shud be validated and If entered data is correct proceed to the next screen, else popup an error.
    5. User:kiran, Pwd:***
    6. Entered incorrect data,but proceeded to the new screen.
    7. FAIL.

  • How to write utp(unit test plan)

    how to write utp(unit test plan)

    Hi,
      Steps to be followed for UTP.
    UTP : Unit Test Plan. Testing the program by the developer who developed the program is termed as Unit Test Plan.
    Two aspects are to be considered in UTP.
    1. Black Box Testing
    2. White Box Testing.
    1. Black Box Testing : The program is executed to view the output.
    2. White Box Testing : The code is checked for performance tuning and syntax errors.
    Follow below mentioned steps.
    <b>Black Box Testing</b>
    1. Cover all the test scenarios in the test plan. Test plan is usually prepared at the time of Techincal Spec preparation, by the testing team. Make sure that all the scenarios mentioned in the test plan are coverd in UTP.
    2. Execute your code for positive and negative test. Postive tests - to execute the code and check if the program works as per expected. Negative Test - Execute code to know if the code is working in scenarios in which it is not supposed to work. The code should work only in the mentioned scenarios and not in all cases.
    <b>White Box Testing.</b>
    1. Check the Select statments in your code. Check if any redundant fields are being fetched by the select statements.
    2. Check If there is any redundant code in the program.
    3. Check whether the code adheres to the Coding standards of your client or your company.
    4. Check if all the variables are cleared appropriately.
    5. Optimize the code by following the performance tuning procedures.
    <b>Using tools provided by SAP</b>
    1. Check your program using <b>EXTENDED PROGRAM CHECK</b>.
    2. Use SQL Trace to estimate the performace and the response of the each statement in the code. If changes are required, mention the same in UTP.
    3. Use Runtime Analyser and Code Inspector to test your code.
    4. Paste the screen shots of all the tests in the UTP document. This gives a clear picture of the tests conducted on the program.
    All the above steps are to be mentioned in UTP.
    Regards,
    Vara

  • Job help to regenerate the test plan after test case addition in solar02

    Hi,
    Any job help to regenerate the test plan after the test case addition in the solar02?
    It is very hard to regenerate in the test plan in test plan management, need to select the test case manually every time.
    Rg,
    Karthik

    Hello,
    You can send mail with the status of the test catalog-
    specify a mail system to which Test Workbench test objects send messages to the people responsible
    Please refer the below link for more information:
    http://help.sap.com/saphelp_smehp1/helpdata/en/6a/88370a002911d2bd02080009b4534c/frameset.htm
    Regards,

  • Reg: Test Sequences in Test Plan Management

    Hi Guru's
       I do created the Test plan and Created Test Packages and also assigned Testers to that package
            I do also created a Sequences for the testers
                           But it allows the tester to change the status  whose in Sequence 2  before the tester whose in sequence 1 is not yet ended the test.
             It give just an information
    Previous test case not yet finished
    Message no. AGSTWB000
    I wanna make it as an error- It should not allow the tester in sequence 2 to change the status until tester of sequence is completed / ended the test.
    Help me to guide this issue
    Thanks in advance
    Regards
    Anandh

    Hi,
    is there any solution?
    Is it possible within a test sequence that Tester No.2 can NOT edit his test case before Tester No.1 has finished the previous test case?
    Any idea?
    Thanks and best regards,
    Marco

  • Test plan for upgrading the support packs

    Dear friends,
    We are going to upgrade the BI system with SP18.
    Please let me know the impact system will be facing with this upgrade and the test plan to take care after the upgrade.
    With Regards
    Neetu
    Edited by: Siegfried Szameitat on Oct 29, 2008 8:48 AM

    Hi,
    it will helps hopeful,
    Upgradation steps:
    1) Convert Data Classes of InfoCubes. Set up a new data class as described in SAP OSS Note 46272. 
    2) Pay attention to the naming convention. Execute the RSDG_DATCLS_ASSIGN report. 
    3) Run the report RSUPGRCHECK to activate objects. 
    4) Upgrading ABAP and JAVA in parallel may cause issues. If there is no custom development on J2EE instance, it is recommended to drop the J2EE instance and re-install the latest J2EE instance after the upgrade. 
    5) Apply SAP OSS Note 917999 if you include the Support Patch 6 with the upgrade or you will get the error at PARCONV_UPG phase. When you upgrade to a product containing Basis 700, the phase PARCONV_UPG terminates. You included Basis Support Packages up to package level 6 (SAPKB70006) in the upgrade. The job RDDGENBB_n terminates with the error RAISE_EXCEPTION. In addition to this, the syslog contains the short dump TSV_TNEW_PAGE_ALLOC_FAILED. The program SDB2FORA terminates in the statement "LOOP AT stmt_tab". An endless loop occurs when the system creates the database table QCM8TATOPGA. 
    6) Apply the OSS note 917999 if you get the following error during PARCONV_UPG phase: PARCONV_UPG terminates with TSV_TNEW_PAGE_ALLOG_FAILED
    Critical OSS Notes:
    819655 u2013 Add. Info: Upgrade to SAP NW 2004s ABAP Oracle
    820062 - Oracle Database 10g: Patchsets/Patches for 10.1.0 
    839574 u2013 Oracle database 10g: Stopping the CSS services ocssd.bin 
    830576 u2013 Parameter recommendations for Oracle 10g 
    868681 u2013 Oracle Database 10g: Database Release Check 
    836517 u2013 Oracle Database 10g: Environment for SAP Upgrade 
    853507 u2013 Usage Type BI for SAP Netwaevers 2004s 
    847019 - BI_CONT 7.02: Installation and Upgrade Information 
    818322 u2013 Add. Info: Upgrade to SAP NW 2004s ABAP 
    813658 - Repairs for upgrades to products based on SAP NW 2004s AS 
    855382 u2013 Upgrade to SAP SEM 6.0 
    852008 u2013 Release restrictions for SAP Netweaver 2004s 
    884678 - System info shows older release than the deployed one 
    558197 u2013 Upgrade hangs in PARCONV_UPG 
    632429 u2013 The upgrade strategy for the add-on BI_CONT 
    632429 - The upgrade strategy for the add-on FINBASIS 
    570810 - The upgrade strategy for the add-on PI_BASIS 
    632429 - The upgrade strategy for the add-on SEM-BW 
    069455 - The upgrade strategy for the add-on ST-A/PI 
    606041 - The upgrade strategy for the add-on ST-PI 
    632429 - The upgrade strategy for the add-on WP-PI
    Post upgrade Steps :-
    1. Read the Post Installation Steps documented in BW Component Upgrade Guide 
    2. Apply the following SAP OSS Notes 47019 - BI_CONT 7.02: Installation and Upgrade 558197 - upgrade hangs in PARCONV_UPG, XPRAS_UPG, SHADOW_IMPORT_UPG2 836517 u2013 Oracle Database 10g: Environment for SAP Upgrade 
    3. Install the J2EE instance as Add-in to ABAP for BI 7.0 and apply the Support Patch that equivalent to ABAP Support Patch.
    4. Run SGEN to recompile programs. 
    5. Install the Kernel Patch. 
    6. Missing Variants - (also part of test script) look at the RSRVARIANT table in SE16. If it is empty, then you will definitely need to run RSR_VARIANT_XPRA program - RSR_VARINT_XPRA OSS -953346 and 960206 1003481 
    7. Trouble Shootauthorizations 820183 - New authorization concept in BI               
    Regards,
    Deva Reddy

  • Test Plan Progress report parameter

    I'm trying to use the Test Plan Progress report but the Test Plan field is always empty therefore I cannot render the report.
    The TFS is 2013 update 4 and I tried also with the report downloaded from MSF for Agile Software Development 2013.4 template. The cube is processed with no errors.
    Any ideas?

    Looking further I noticed that the MDX query that is populating the report parameter is not returning any data.
    Could this be a breaking change for the report from the last TFS update?
    Below is the query generated by the report:
    WITH
    MEMBER [Measures].[ParameterCaption] AS
    IIF([Test Plan].[Test Plan Name].CURRENTMEMBER IS [Test Plan].[Test Plan Name].[All],
    "All (No Filter)",
    [Test Plan].[Test Plan Name].CurrentMember.Member_Caption
    MEMBER [Measures].[ParameterValue] AS
    [Test Plan].[Test Plan ID].CurrentMember.UniqueName
    SELECT
    [Measures].[Point Count Trend],
    [Measures].[ParameterValue],
    [Measures].[ParameterCaption]
    } ON COLUMNS,
    ([Test Plan].[Test Plan ID].[All], [Test Plan].[Test Plan Name].[All]) +
    Extract(
    [Test Plan].[Test Plan ID].[All],
    [Test Plan].[Test Plan Name].[All],
    [Team Project].[Project Node GUID].[All],
    [Test Case].[Area Hierarchy].[All],
    [Test Plan].[Iteration Hierarchy].[All]
    ) +
    Filter(
    CrossJoin(
    [Test Plan].[Test Plan ID].[Test Plan ID],
    [Test Plan].[Test Plan Name].[Test Plan Name],
    StrToMember("[Team Project].[Project Node GUID].&[{4dad3f77-6199-41eb-af5a-a95f93b6af18}]"),
    StrToSet("[Test Case].[Area Hierarchy].[All]"),
    StrToSet("[Test Plan].[Iteration Hierarchy].[All]")
    [Measures].[Point Count Trend]
    [Test Plan].[Test Plan ID], [Test Plan].[Test Plan Name]
    } ON ROWS
    FROM [Team System]

Maybe you are looking for