Expected PO Receipts and scheduled out sales orders

Hi Guys:
in MRP Net requirements Calculation,
for Example  If want Consider Schedule out Sales orders( requested Delivery Date 02/02/2012) which is determined by planning horizon( 6 months 06/30/2012) , Since this sales order is within Planning Horizon it will consider for MRP Planning.
Is it the Same case with PO i.e Based upon the planning horizon PO will be included/excluded in planning?
Also if for example my PO is due from the Vendor one PO is due in 03/02/2012 and other PO is 09/15/2012?
Thanks
Kodali

Hi Venkat:
Expected PO receipts that fall within the planning horizon will be excluded or Included in the calculation?
I think it should be included otherwise you might be placing additional PO's to the vendor?
Thanks
Kodali

Similar Messages

  • Opening and closing stock with sales order and with out sales order

    hello,
    any body please help me my client want to check opening stock and and closing stock in areport.
    material contains batch and some material with sales order and some are with out sales order. my client is asking this in a single layout. please tell me isthere any teport or bapi or function module to get this report.
    this is very uregent. and layout is requesting like opening stock, production stock, sales stock and closing stock.
    please guide me to get this report.
    Thanks & Regads
    Bhakta

    Transaction MB5B
    For sales order related use specila stock as E and use radio button indicator in stock type
    For stock w/o sales order, use special stock indiactor as "space' and stock type valuated stock.
    to get a perticular month,opening stock/closing stock enter the start date/end date as month start and end date.
    See the o/p which will give the stock as required by you

  • How to disable forward scheduling in Sales order

    Hi SD Experts,
    Can you please provide the solutions for the below requirements.
    Requirement details are below:
    How to disable forward scheduling in sales orders....
    For My sales order type i already configured in customizing that delivery scheduling should only carry out backward scheduling.
    The results is tht no forward scheduling in carried out when material is i stock .. this is ok...
    But when there is no stock and ATP indiates an expected inward movemnt, the system ignores the indicator and carries out forward scheduling anyway.
    Is there any possibility to change this behaviour?
    Appreciate any help....
    Regards
    Sudheer

    Hi
    If you do not want the system to switch to forward scheduling automatically, you can specify per plant in Customizing for MRP, in the IMG activity Parameters for determining the basic dates that the system is to continue the backward scheduling calculation even if the resulting start date lies in the past.
    Thanks & Regards
    Bhaskar

  • Goods Receipt with respect to sales order

    hi,
        goods receipt with respect to sales order ,that sales order is prepared with reference to quotation
    erroer is
    Account assignment cannot be carried out because of different origin no.
    Message no. V1134
    Diagnosis
    The sales document to which you want to refer is based on sales document 20000005 and item 000010. Therefore, the settlement and possibly inventory management are carried out using the number of the preceding document.
    System Response
    This entry is not allowed.
    Procedure
    Enter the document and the item number of the preceding sales document

    Hi,
    Refer the sales quotation number for GR instead of the sales order number.
    Regards,
    Ravi Kumar C.

  • Sample bom creation and explosion in sales order

    hi,
         can any one help to create a simple bom with atleast one sub item for the bom and create a sales order in which the bom explodes ( i mean when u enter the main bom item it should list its sub items as its line item below it)...
    (also mention what item categories are to be taken care ... )
    rewards for sure
    thanks
    mmn

    Hi MMn,
    Bill of materials (BOM)
    1. In the SAP System, you can use BOMs to represent different objects (such as materials, equipment, functional location BOMs, and documents) and to maintain object-specific data.
    2. Document BOM: A complex document may be made up of several documents, such as a program, technical drawings, papers, and photographs. These related information and documentation objects are grouped together as a unit using a document structure – a BOM for a document.
    3. Equipment BOMs are used to describe the structure of equipment and to assign spare parts to equipment for maintenance purposes. Bills of material for functional locations group together the elements of a technical structure, such as the functional unit of an entire plant.
    4. You work with order BOMs when you specially tailor the make-to-order production of your products to the requirements of your customers. In order to meet the customer requirements, sales order specific modifications to various assemblies are often required. Furthermore, assemblies are often specially constructed for a particular sales order.
    5. Before you can create a BOM for the component parts of an object, the object must have a valid master record in your system.
    6. A bill of material that you create for a material is known as a material BOM in the SAP System. A BOM explosion answers the question: What is the product made of? This question arises in various situations, such as when you want to:
    Determine material requirements for a product
    Look at the overall structure of a product in a design department
    See an overview of the parts and materials required
    Calculate the effects of changes to costs
    7. BOM is a collection of materials that make up a product. For example – computer, home theatre system. Material BOM is complex and is dependent on sales and distribution, material management or production planning.
    8. The most important rule is that the material type has to be a FINISHED PRODUCT (FERT) in order to categorise it as a BOM.
    9. BOM processing is divided into two different ways – either at the MAIN item level if the item is assembled or at the sub-item level (i.e. at the component level) if the material is not assembled.
    10. BOM is configured at the item category level (VOV7) and transaction code to create a BOM is CS01.
    11. In case of single level BOM, main item categories TAQ and TAP should represent single level BOM in VOV7 and in case of multi level BOM, the main item categories should represent multi level BOM.
    Main item level processing
    1. The material master records should have the item category group ERLA in the sales org.2 screen of the finished product. In this case, the associated sub items function only as text items, and thus are not relevant for delivery. This process ensures that pricing, inventory control and delivery processing is carried out the header level that is for the finished product only. This is mainly relevant to the assembled products.
    2. item category group – ERLA; main item category – TAQ (schedule line – CP) and sub item category – TAE (schedule line – CT)
    Sub-item level processing
    1. If the business prefers to have the sub-items be responsible for pricing, inventory control and delivery processing, the item category group should be LUMF on screen sales org.2 of the respective material master record. This ensures that subcomponents are relevant for processing. This is relevant to the products that are not assembled.
    2. item category group – LUMF; main item category – TAP (schedule line is CT), sub item category – TAN (schedule line is CP)
    Multi-level BOM
    In order to activate the multi-level BOM, structure scope in VOV7 has to be changed from single level explosion to multi level explosion.
    Try this and revert back fr clearifications
    Reward Points if helpful.
    Regards
    Srini

  • Check Credit and Stock on Sale Order

    Hi All
    Could you please tell me how to check Credit and Stock on Sale Order.
    Thank and Best Regard
    Thang

    How To Do Configuration For Credit Management
    Credit and risk management takes place in the credit control area. According to your corporate requirements, you can implement credit management that is centralized, decentralized, or somewhere in between. 
    An organizational unit that represents the area where customer credit is awarded and monitored.   This organizational unit can either be a single or several company codes, if credit control is performed across several company codes. One credit control area contains credit control information for each customer.
    For example, if your credit management is centralized, you can define one credit control area for all of your company codes. 
    If, on the other hand, your credit policy requires decentralized credit management, you can define credit control areas for each company code or each group of company codes. 
    Credit limits and credit exposure are managed at both credit control area and customer level.  You set up credit control areas and other data related to credit management in Customizing for Financial Accounting. The implementation guide is under Enterprise Structure -> Definition or Assignment -> Financial Accounting and then Maintain credit control area. You assign customers to specific credit control areas and specify the appropriate credit limits in the customer master record.
    Settings for determining the credit control area of a document.  The settings of items 1 - 4 are taken into account according to their priority.  The credit control area found is stored in field VBAK-KKBER.
    1. Transaction OB38
       Check which credit control area is assigned to the company code.
       Company code:
       Credit control area:
    2. Transaction OVFL
       Check which credit control area is assigned to the sales area.
       Sales area:
       Credit control area:
    3. Transaction XD02 or VD02
       Check which credit control area is assigned to the payer.
       Payer:
       Credit control area:
    4. Transaction SE37
       Is user exit EXIT_SAPV45K_001 being used?
    5. Transaction OBZK
       For the settings under items 2 - 4, field "All company codes" must be marked in Transaction
       OB45, or the credit control area must be entered under the relevant company code in table
       T001CM of the credit control areas allowed.
       Company code:
       Credit control areas allowed:
    6. Settings for the credit checks
    7. Transaction OVAK
       Which settings do exist for the sales document type used?
       Sales document:
       Check credit:
       Credit group:
    8. Transaction OVAD
       Which settings do exist for the delivery type used?
       Delivery type:
       Credit group for delivery:
       Credit group for goods issue:
    9. Transaction OB01
       Credit management/Change risk category
       Definition of the risk category for each credit control area. This risk category can be
       assigned to a credit account by using Transaction FD32.
    10. Transaction OVA8
        Here, the individual credit checks for key fields
        o credit control area
        o risk category
        o credit group are set. Take these key fields from the above settings and go to the detail
          screen. In particular, check whether fields "Reaction" and "Status/block" are set
          correctly. To carry out follow-up actions in case of a credit block, the credit check
          status must be set (field "Status/block").
    11. Transaction FD32
        Credit master data for the payer of the relevant document.
        Credit account:
        Credit limit:
        Risk category:
        Currency:
    12. Settings for updating the credit values Update of the credit values is required for the limit
        check (static or dynamic credit limit check).
    13. Transaction OVA7
        Update of the credit value is active for the corresponding item type if the check box is marked. This field corresponds to 
        field "Active receivable" in Transaction VOV7.
        Item type: 
        Active receivable:
    14. Transaction V/08, Pricing
        In the pricing procedure used for pricing, subtotal "A" must be entered in a line for
        determining the credit value (mark the pricing procedure and doubleclick on "Control").
        Usually, the net value plus taxes is used. This way the system is determined to use this
        subtotal for credit pricing. The credit price is stored in field VBAP-CMPRE and used for
        update and credit check.
        You can find the used pricing procedure of the order under "Item -> Condition -> Analysis".
        Pricing procedure:
        Line with subtotal = 'A':
    15. Transaction OB45
        Which update group (field "Update") do you use in the relevant credit control area? The
        default setting is "12". If you use another update group, check whether this is fine with
        you. If you open an OSS message, please tell us the alternative update group.
        Credit control area:
        Update:
    16. Transaction OMO1
        Which kind of update did you choose for structure S066? 
         In any case, "Synchronous update (1)" has to be chosen as the kind of update. 
         All other settings will lead to errors
    Regards
    Raja
    Edited by: ramanathan raja on Jul 25, 2008 4:37 PM

  • MRP-Delivery Schedule for Sales order is not updating in Production order

    Dear Experts,
    I have created Sales order and maintained delivery scheduling, Then Run MRP through MD50,
    We received Planned order then through this we have converted to Prodcution order.
    When we observe the delivery schedule for sales order under assignment Tab in Produciton order which is showing zero instead showing line item of Delivery schedule.
    I am able to see Sales order and Line item but i am not abel to get any delivery schedule line item.
    Please suggest where settings are missing.
    Thanks in advance
    Regards
    Don

    Dear Experts,
    Please provide me solution.
    after Running MD50 transaction against Sales order.
    If I maintained different Scheduling Line Item for First Line item of Sales order.
    The Respective Scheduling Lines should update against Each Production order which has converted from Planned order.
    Thanks in advance.
    Regards
    DON

  • Find the user exit while creation and change of sales order

    Hi Team
    Below mentioned requirement , in which user exit i have to put below logic while creaion and change of sales order?
    u2022     The logic for the user exit to explode should consider the following assumptions and validations
    o     Customer master to have the entry at KNVV-KVGR1
    o     Material master to have the entry at MVKE
    o     UoM in the Sales order item (VBAP- VRKME) should be = Pallets PAL or tonnes (TES)
    o     Should have more than one line item or number of line items with UoM PAL or tonnes TES should be > 1
    for example :-->
    Product A with Scales mentioned below
    Product A     Quantity / Scale     UoM     Price(£)
         0-10     PAL/TES     20
         11- 20     PAL/TES     10
         21- 30     PAL/TES     5
         31-40     PAL/TES     2.5
         >41     PAL/TES     
    Product B with Scales mentioned below
    Product B     Quantity / Scale     UoM     Price(£)
         0-15     PAL/TES     25
         16-20     PAL/TES     20
         21- 30     PAL/TES     15
         31-40     PAL/TES     10
         > 41     PAL/TES     5
    u2022     Product A (qty 10PAL) + Product B (qty 15 pal) ordered in a single order with 2 line items.
    u2022     The expected results should be
    o     Product A qty 10 + B qty 15 added = 25Pal
    o     The system user exit should add the total number of pallets on the order line items and point towards the respective scales, so in this example prices against each line item should be the respective price against 25 Pal = 5£ for product A per pal and £15 for product B.
    Thanks in Advance.
    Puneet.

    Hi Team
    Below mentioned requirement , in which user exit i have to put below logic while creaion and change of sales order?
    u2022 The logic for the user exit to explode should consider the following assumptions and validations
    o Customer master to have the entry at KNVV-KVGR1
    o Material master to have the entry at MVKE
    o UoM in the Sales order item (VBAP- VRKME) should be = Pallets PAL or tonnes (TES)
    o Should have more than one line item or number of line items with UoM PAL or tonnes TES should be > 1
    for example :-->
    Product A with Scales mentioned below
    Product A Quantity / Scale UoM Price(£)
    0-10 PAL/TES 20
    11- 20 PAL/TES 10
    21- 30 PAL/TES 5
    31-40 PAL/TES 2.5
    >41 PAL/TES
    Product B with Scales mentioned below
    Product B Quantity / Scale UoM Price(£)
    0-15 PAL/TES 25
    16-20 PAL/TES 20
    21- 30 PAL/TES 15
    31-40 PAL/TES 10
    41 PAL/TES 5
    u2022 Product A (qty 10PAL) + Product B (qty 15 pal) ordered in a single order with 2 line items.
    u2022 The expected results should be
    o Product A qty 10 + B qty 15 added = 25Pal
    o The system user exit should add the total number of pallets on the order line items and point towards the respective scales, so in this example prices against each line item should be the respective price against 25 Pal = 5£ for product A per pal and £15 for product B.
    Thanks in Advance.
    Puneet.

  • What happens in the back ground when you schedule a Sales Order?

    Gurus,
    What happens in the back ground when you schedule a Sales Order?
    Assemble to Order scenario.
    Edited by: 792050 on May 17, 2011 3:24 AM
    Edited by: 792050 on May 17, 2011 3:24 AM

    If I merge libraries and then back the merged libraries up onto an external drive or DVD, do I just back up the libraries themselves, or do I also back up the original files?
    If you're running a Managed Library, then backing up the Library also backs up the original files.
    I ask because my HDD is getting pretty full. I want to reduce the amount of stuff on it, and the iPhoto libraries are the biggest single consumer of space at the moment (Nearly 100GB).
    1. Quit iPhoto
    2. Copy the iPhoto Library from your Pictures Folder to the External Disk.
    3. Hold down the option (or alt) key while launching iPhoto. From the resulting menu select 'Choose Library' and navigate to the new location. From that point on this will be the default location of your library.
    4. Test the library and when you're sure all is well, trash the one on your internal HD to free up space.
    Regards
    TD
    P.s. If you're running a Managed library, then it's the default setting, and iPhoto copies files into the iPhoto Library when Importing
    If you're running a Referenced Library, then you made a change at iPhoto -> Preferences -> Advanced and iPhoto is NOT copying the files into the iPhoto Library when importing.

  • User Exit and BADI for Sales Order

    Dear Experts,
                        please give me available user exits and BADI for sales order .i want to take the data from sales order at the time of sales order posting .

    Hi,
    In debugging you can find some Enhancement Spots where you can implement your code. This lets you ignore the need for access key, but its a time consuming process spotting out the exact enhancement point.
    Regards
    Karthik D

  • Add 2 buttons Release and Reject on Sales Order CRMD_BUS2000115 application

    Hi Experts,
    My Requirement is to add 2 button 'Release' and 'Reject' for Sales Order CRMD_BUS2000115 aplicaiotn using PCUI.
    Also provide the functionality...as
    1.Click On Release will change the status of seleceted order as "Released" i.e. to remove the Billing/Dleivery Blocks...And SAVE it.
    2. For "Reject"  change status as Rejected and Save it using standard "SAVE'' button.
    Can anybody would explain how should i proceed and where i have to code ??
    Or Source code or sample code?
    Can I call BAPI_TRANSACTION_COMMIT aftre changing it ??
    Thanks in Advance,
    Arjun Pawar.

    Hi Experts,
    I have added 2 buttons 'Release' and 'Reject' for Sales Order CRMD_BUS2000115 aplication using PCUI which provides the functionality...as
    1.Click On Release will change the status of seleceted order as "Released" i.e. to remove the Billing/Dleivery Blocks...And SAVE it. 2. For "Reject" change status as Rejected and Save it using "CRM_ORDER_SAVE" api followed COMMIT work. Functionality is working fine.
    But <b>I'm getting an error / explorer error " An error has occurred in this script page" ( the Error is : 'CAT Params' is undefined ) is coming as soon as query/click on "GO", carried out after the action performed like "Release/Reject"</b> on the sales order approval screen.
    Please, can anyone give an idea @ the cause of error ?? whether it is frame error ?? or else???
    And How to resolve it???
    Thanks,
    Arjun

  • Difference between Valuated and Non valuated Sale order stock

    Hi All,
    Can anybody tell me the difference between the above said subject with the steps involved in each scenario.
    That is valuated sale order stock and Non valuated sale order stock in Product cost by Sale Order.
    With Journal entries at each step and whether any WIP or variances at Production order level and sale order level and all the financial entries related to them
    Thanks in Advance,
    Ravi Kumar

    Hi Shail,
    Thans for your inputs,
    But I wanted to know it in more detail. In what scenarios they are used with financial entries in both the cases.
    I will give you my scenario. It goes like this,
    My client is in pipe coating business, who receives pipes from customers and does only coating work(which is considered as service) and despatches it to the customer. this process is carried on the basis of work order(Sale order).
    Now Production order is created and work is done on that with reference to Sale order for that particular customer.
    So the pipe which my client receives should be non valuated stock as it will not be a raw material to them and the cost incurred on it is booked on production order like chemicals as raw material consumption, activity cost etc.
    now in this scenario just tell me how and at which stage FI entries get generated at Production order and Sale order level, and also at wat level Standard cost estimate should be created i,e at production order level or sale order level(sale order cost estimate).
    Will there be any entries at goods isssue and GR against production order. If no then how the COGM account will get hit.
    Please tell me this scenario in both cases Valuated sale order stock and Non valuated sale order stock with financial entries in Sale order costing.
    Thanks & Regards,
    Ravi Kumar

  • BAPI - Goods receipt and then create transfer order for a production order

    Hello Everyone
    We need to do goods receipt and then create transfer order for a production order (Material for WM scenario)
    We are using BAPI 'BAPI_GOODSMVT_CREATE'
          i_items-orderid = wa_afpo-aufnr .
          i_items-order_itno = wa_afpo-posnr.
          i_items-mvt_ind = 'F'.
          i_items-stge_loc   = wa_afpo-lgort.
         i_items-stge_type = '901'. "wf_styp.
         i_items-stge_bin = wf_sbin.
          i_items-entry_qnt  = wf_qty.
          i_items-entry_uom = wa_afpo-meins.
          i_items-entry_uom_iso = wa_afpo-meins.
          i_items-batch      = wa_zmobtag-charg.
          i_items-move_type  = '101'.
          i_items-move_reas  = wl_3131.
    We are passing i_items (like line of goodsmvt_item) along with other parameters to BAPI and its creating material document and Transfer order automatically. Problem is the TO created is showing destination storage bin as default storage bin( from material master).
    The field goodsmvt_item-stge_bin is just changing the Source bin details. There is no field for bin in the BAPI so that we can change the Destination storage bin as per our requirement.
    My requirement : Creating material doc and then TO. Material should move to specified storage bin.
    Please let me know any alternate way( No BDC) so that my requirement is achieved.
    Regards
    Swetabh

    Hi ,
    can u check these fields ,
    STGE_TYPE_PC     UBTYP     CHAR     3     0     Storage type for transfer posting
    STGE_BIN_PC     UBPLA     CHAR     10     0     Storage bin for transfer posting
    Regards
    Prabhu

  • I've just imported photos that are misdated and appear out of order in my events. How can I correct the dates on these events so they appear properly?

    I've just imported photos that are misdated and appear out of order in my events. How can I correct the dates on these events so they appear properly?

    The one iin the Photos ➙ Adjust Date and Time menu option:
    checkbox below:

  • How to include both items and service on Sales Orders

    Hello experts,
    I have a client who wants to include extra handling charges such as gift wrapping charges on their sales order in addition to regular items that is on the sales order.
    If I create the sales order as a Item/Service Type ='Service'. I can select the correct G/L account for this Sales Order. But if I create the sales order as a Item/Service Type ='Item', then I can only select items and not the sales order.
    The client wants to include both the items and service in the sales order. Is there a way to do this in SAP B1?
    Michael

    Hello Michael,
    I think you may create Service type items to include both by Item Type documents.
    Thanks,
    Gordon

Maybe you are looking for

  • Why is Noise Reduction only available with some raw files

    I  have been going through my CRW, CR, and CR2 raw files and have noticed that some, when opened in ACR, do not allow me to adjust all the parameters in Noise Reduction.  I thought it might be ISO related, but with a group of identically created raw

  • Setting up context sensitive help for WebHelp in web application.

    Hi, I'm working on a help system for a web application. It will include context sensitive help triggered by an icon on the screen, and the Topic will open in an iframe with a set size. The developer has already set up the iframe that pops up when the

  • Jspx tag warning, on first element of jspx, on ALL pages of app.!!

    Hello All, I am getting the below posted warning on the FIRST TAG ON JSPX, RIGHT AFTER JSP:ROOT ELEMENT, FOR ALL JSPX PAGES OF THE APPLICATION!!! No grammar available for namespace http://java.sun.com/jsf/core, contents fo element view cannot be vali

  • I cant open some pdf files

    I just cant successfully open some PDF files(preview default) occasionally on the new Macbook Air, left with all blank contents, whereas, there is no problem in other PCs, I have no idea at all, need solutions ASAP, thanks.

  • How to split iPhoto library

    my library is too big.  What is the easiest way to split? Has to be simple to access.