FS10N - Missing Material number during drilldown

Hello
In FS10N transaction, g/L Account display screen, when we drilldown on any of the field to see the material number, its missing from the layout. Also, some of the displayed in German Language.
I would appreciate your quick thoughts and help
SAP BI/ FICO Team

Hi,
Please go to the following path and add the field BSEG-MATNR -
SPRO -> FA (New) -> FA Basic settings -> Document -> Rules for changing document -> Document change rules, line item
On adding the field in this table, you will find the material number field being allowed for changes in FB02.
Cheers
Redoxcube

Similar Messages

  • Disable Customer-Material Number field during VL02n before post goods issue

    Hello SAP gurus,
    I would like to ask the possibility of disabling the field "Customer Material Number' during outbound delivery creation.
    As we would know, this field (LIPS-KDMAT) will only be disabled after post goods issue.
    Will it be possible to disable the field without having to post goods issue first?
    Thanks in advance.
    Jayson

    I think you can do with SHD0 screen variant, or else you need to go with userexit to make display field.

  • Change of material master during transfer between SRM and R/3

    Hi,
    I have a question for modifying material master data between R/3 and SRM.
    I would like to know if it is possible to change the material number during the transfer. The reason is:
    I have 2 R/3 backends and 1 SRM system. The material codes in the 2 R/3 systems are different but some materials having different numbers in R/3 are referring to the same material. I want to see such materials with the same material number. Is it possible to do this with Middleware plus some interruption in between? The "translation" should be bi-directional.
    Thanks

    Hi,
      No probs if the field is not replicated.No idea how to bring that through replication though.
      Coming to the Product Search...Although the number of such materials is less...You will have to modify the Product search which will take care of the  display of other products as well.
      The Std product search(<b>bbph_product</b>) uses the the search help exit "<b>BBP_F4IF_SHLP_EXIT_PRODUCT_GEN</b>".So you need to replace this one with your custom FM.
      In your custom FM,you will have to check for the HARMINIZED code field for all such materials and accordingly while selecting the Material select the HARMONIZED code as the Material number and in the Product search display that HARMONIZED code as the "PRODUCT ID". Also,you  will have to develop RFC enabled FM which will actually fetch all the Materials from the BAckend at runtime. Also are you displaying the Product List Plantwise?
      Pls give me ur mail ID where i can mail you the  sample code.
    BR,
    Disha.
    Pls reward points for helpful answers.

  • Material Number change during unpacking and packing using HU

    Dear Friends,
    Need your help for the below case.
    our client is importing and selling to the domestic and exports. This is typically a trading plant.
    The issue is when we unpack and repack using the HU, the material will be changed or not.
    As per some of the inputs, i heard it will change. Please confirm.
    If it changes how to avoid it.
    Thanks in advance.
    Regards
    Prabhu

    Depends on your design and how you want it to be, you can go either way.
    usually if you repack material  ( e.g. 200 kg drum repacked to 4 x 50 kg ) you have some labor costs and costs for the other packaging material.
    you can design your case with 2 materials , the trading good with 200kg  and a second material master for the trading good in 50 kg.
    here you would use a production order to produce the 50kg material, you would issue the 200kg material and issue 4 smaller empty drums and get 200 kg of the material in 50 kg drums
    This new material would then cost more than the 200 kg material since you added labor and empty drums.
    If you want only work with one material number, then you issue the 4 empty 50kg drums to a cost center and use the packing function in delivery.
    You will never be able to know how much material you have in 200kg drums and 50kg drums in stock this way, as this process is for transport packaging
    If you want show the accurate stock and value situation then I recommend to go with 2 materials

  • Material number is not populating in PO in tcode ME23N

    Hi,
    The material number is not populating in PO in transaction ME23N. The coloumns is displaying as blank and supressed(Gray).
    This problem occured during the upgradation from 4.6C to ECC6.0.
    We have checked the SPRO configuration for field selections and these are not having any problem.
    Data is updated in database tabes but it is not displayed in ME23N screen.
    Please advice.
    Thanks,
    Rakesh

    check OSS Note 492757 - ME21N/ME52N: You cannot set field selection for material
    maybe it helps to solve your issue

  • Use material number with profile serial number in SRM

    Hello,
    I created a material number in the back-end and I transfered it to the
    SRM.
    After creating and approving the PO with that material number, I tried to
    create a confirmation in the SRM and I got the error message:
    "Maintain serial numbers for total quantity".
    I do not have an a suitable field in the SRM.
    Please advice.
    Best Regards
    Eyal Weinreb
    HP

    check it up in ECC.
    even if you do MIGO, you will get same erro message.
    Note 1278707 - BAPI_GOODSMVT_CREATE: Message M7 175 during goods receipt
    You are using BAPI_GOODSMVT_CREATE to perform a goods receipt posting for a subcontracting purchase order where the materials being received are serial number managed. The BAPI incorrectly returns the error message M7 175 (Maintain serial numbers for total quantity) even though the correct number of serial numbers are being passed over in the parameter table GOODSMVT_SERIALNUMBER. This error also occurs when the serial numbers should be automatically created during the goods receipt posting (controlled by the field SERIALNO_AUTO_NUMBERASSIGNMENT in the table GOODSMVT_ITEM).
    Note 1337306 - Goods receipt for stock transport order with serial numbers
    In transaction MIGO, you post a goods receipt for stock transport orders for a material with serial number requirement and the system issues error message M7 175: "Maintain serial numbers for total quantity". On the "Serial Numbers" tab page, all you are told is that the item is not relevant for serial numbers. You are therefore unable to maintain serial numbers, even though there is a serial number requirement for this transaction/event. You can post the goods receipt in transaction MB01.
    IEN                    166     Maintain serial numbers for total quantity
    M7                     175     Maintain serial numbers for total quantity

  • To fill in the material number with item category u201CBu201D for Framework Order.

    The use of framework orders (also referred to as blanket purchase orders)  enables you to procure a variety of materials or services from a vendor up to a predefined maximum value (the value limit).
    Instead of a specific delivery date, you specify a validity period for the order.
    Goods receipts or the entry and acceptance of services performed are not necessary in the case of a framework PO and limit items.
    The invoices are posted directly with reference to the purchase order, provided that the specified value limit is not exceeded. When the value limit of the PO is reached, or the validity period is exceeded, the system issues a warning message. It is possible to book the invoices, but these are blocked for payment.
    During the phase of service performance, the cumulative u201Cactual" values (for the services actually performed) are continually updated in the underlying purchase. This enables you to monitor the progress of a procurement project on an ongoing basis. By comparing the "actual" value with the total value, you can always obtain an overview of the degree to which a budget for unplanned services or materials has been exhausted (i.e. see whether predefined limits have been reached or nearly reached).
    So with the Framework Order type (FO) and item category u201CBu201D you get the error that it is not allowed to fill in the material number with item category u201CBu201D.
    Please suggest me the possible solution to fill in the material number with item category u201CBu201D for Framework Order.
    Best Regards,
    Harisha

    The Framework order type is specialy defined for lesser value procurements (ex: stationeries, cleaning services ....) which are all not worthy to create Material Master at all.
    If you are very sure to fill the Material number, then proceed with some other document type.
    In what circumstances you want to put material number in FO order?
    Karthi.

  • Material Number Truncated in ALV to Excel Download

    Hi Guru,
    I have a ALV program report. It has about 18 columns, but for some strange reason, when we download this report to an ALV the 3rd column which host the material number as the last digit missing/truncated.
    For example if we have a material number in SAP ALV Grid as 1234567, when we download this the excel, what we get in excel is 123456. with the last number missing.
    What is the best solution to fix this issue.
    Thanks for you help in advance.

    Hi Keshav,
    Previously I faced the same situation, like in ALV grid I was displaying the material nos with output length as 15. Since in the Grid display you can readjust the columns, So after displaying we just expanded in the grid and try to download the same in excel. But at that time the ALV was downloading with material number field length as 15 ( What I set in my field catalog). Even when I saw the print priview I saw only the length it is showing as 15.  After changing the output length as 18 in field cat  I got the correct download.
    (Here I am assuming that the question is raised for  ALV grid display since no where it is mentioned the type of ALV).
    Sorry it was mentioned in the question itself
    Regards
    Shiba
    Edited by: Shiba Prasad Dutta on Feb 22, 2010 2:41 PM

  • Changing material number when Process Order is released

    Hello,
    We have a scenario in which the material number of a process order may need to be changed after the process order is released.  We will have both in process and post production inspection types assigned to this order, and both inspection lots are created at process order release.  We also will have a batch number created at process order release. 
    When recording test results in the inspection lot before a process order has been confirmed, the users may identify that the material number should be different.  We would like a way to be able to either change the material number in the process order (and inspection lots).  We know this involves a lot of updates (master data changes to the existing process order and inspection lots).  Currently, there is no way to transfer information to a new material number without receiving product in and performing a usage decision in the post production inspection lot to transfer to a new material number. 
    The client has implemented all modules, except PP (which we are in the process of now).  We know that Variant Configuration would have been the right solution for this, but this is not an option since MM is already implemented. 
    If you have any suggestions, please reply. 
    Thanks in advance.

    Hi Prasobh,
    The exact scenario is as follows:
    1. A semi finished good will be used as a component to produce the finished good.
    2. This semi finished good will have treatments added to it, and quality inspection will be performed as treatments are added. 
    3. Inspections will occur several times as treatments are added.  If during one of these inspections, material is out of spec, and the blend should be transferred to another material number, we need to be able to change to another material number.  To have a customization where material number is changed in all of the relevant PP and QM tables seems risky. 
    This is why we can't really use material classification.  We also do not have the option to use VC bc the MM module is already implemented. 
    Thanks.

  • Purchase order from production order !!  (Missing material no)

    Hi,
    This purchase order is created directly from production order.( My problem is the material number is no where shown on PO. but when I print it (print preview) i can see the material number along with the Production order number. I am writing a new report and need material no.
    Interesting thing is, even when the Material no is missing. I can see the short txt for material as 'Galvanise'.
    Pls help me in finding the material number.(item wise)
    Thanks & Regards
    Hrishi

    Hi
    1. Check table EKPO, if material number is stored against said PO,
    2. Check ME23N, ME23N, ME22, ME23 screens are u able to see material no. in any of T-code.
    If one of T-code not showing material number, it is sort of bug in system
    Regards,
    NNK
    PS:Award points for useful ans

  • Validation of vendor material number in IDOC_INPUT_INVOIC_MRM

    Hi folks,
    Scenario: Inbound EDI vendor invoices received as IDOCs.
    I'm using Logistics Invoice Verification process code INVL to receive and post vendor invoices on to the ERP2004 release of R/3.
    I have purchasing info records setup with the vendor material number.
    When I process an inbound vendor invoice, I can put in a customer material number i.e. a material number existing in material master in E1EDP19-IDTNR with qualifier E1EDP19-QUALF = 001.  When I do this, R/3 checks that the material number is valid and refuses to post an invoice if the material number is invalid - this is good.
    This means that the EDI program parameters with the 'Check Material Number' enabled is working as expected.
    Now when I only have a vendor material number i.e. E1EDP19-QUALF = 002 an E1EDP19-IDTNR = vendor part number, R/3 posts the invoice even if the vendor part number is invalid - IDOC_INPUT_INVOIC_MRM does not seem to be validating the vendor part number.  The document posts whether I use a valid vendor part number or an invalid one - what am I missing?
    Satish

    I can answer by words of Axel Angeli - top level SAP R/3 consultant and R/3 cross-application development coach, the author of classic book "SAP R/3 Guide to EDI, ALE and Interfaces":
    "SAP R/3 delivers a serious of predefined EDI programs. Many project administrators see them as standards which should not be manipulated or modified. The truth is, that these IDoc processing functions are recommendations and example routines, which can be replaced by own routines in customizing."
    and
    "SAP R/3 is delivered with a series of predefined IDoc types and corresponding handler function modules.
    Some of the handler programs have been designed with user-exits where a developer can implement some data post-processing or add additional information to an IDoc.
    You must always see those programs as examples for IDoc handling. If the programs already do what you want, it is just fine. But you should never stick to those programs too long, if you need different data to be sent."
    So now you can feel free to customize
    Regards,
    Maxim.

  • "Settings for material number conversion not found" occurs when ...

    After I run an initial load data into the InfoCube 0PUR_C01, I want to check the InfoCube Content by the following path:
    RSA1 -> pick up the InfoCube 0PUR_C01, right click it and select Manage -> Get to Content tab -> Click InfoCube Content button -> Deselect all selection, only tick the 1st column checkbox next to 0Material, then hit enter, get a small window titled as "Cancel" with a red STOP msg sysing "Settings for material number conversion not found" with an "Exit" button and a question mark button, click Exit button leads to SAP Easy Access screen, if clicking the question mark button, another window pops up with the msg showed above, click Technical Information button causes the original window short dump and the short dump msg shows below in between two dashed lines:
    Runtime Errors         RPERF_ILLEGAL_STATEMENT
    Date and Time          11/28/2005 14:43:13
    ShrtText
        Statement "CALL SCREEN" is not allowed in this form.
    What happened?
        Error in ABAP application program.
        The current ABAP program "SAPLSHL2" had to be terminated because on
        statements could not be executed.
        This is probably due to an error in the ABAP program.
    Error analysis
        There is probably an error in the program
        "SAPLSHL2".
        The program was probably called in a conversion exit
        or in a field exit. These are implemented by
        function modules called CONVERSION_EXIT_xxxxx_INPUT/OUTPUT or
        USER_EXIT_xxxxx_INPUT.
        Conversion exits are triggered during screen field transports or
        WRITE statements, field exits during field transports from the
        screen to the ABAP/4 program.
        In this connection, the following ABAP/4 statements are not allowed:
        -  CALL SCREEN
        -  CALL DIALOG
        -  CALL TRANSACTION
        -  SUBMIT
        -  MESSAGE W... and MESSAGE I...
        -  COMMIT WORK, ROLLBACK WORK
        -  COMMUNICATION RECEIVE
        -  STOP
        -  REJECT
        -  EXIT FROM STEP-LOOP
        Moreover, conversion exits for output conversion
        (implemented by function modules called
        CONVERSION_EXIT_xxxxx_OUTPUT) do not allow
        -  MESSAGE E...
        to be used.
    Trigger Location of Runtime Error
    Program                                 SAPLSHL2
    Include                                 LSHL2F19
    Row                                     3
    Module type                             (FORM)
    Module Name                             TECHNISCHE_INFO5
    rce Code Extract
    e  SourceCde
    1 ***INCLUDE LSHL2F19 .
    2 form technische_info5.
    >>   call screen 1900 starting at 5  8.
    4 endform.
    5
    6 &----
    7 *&      Form  SHRINK_VALUES
    8 &----
    9 *       text                                                           *
    10 ----
    11 *  -->  p1        text
    12 *  <--  p2        text
    13 ----
    14 form shrink_values.
    15
    16   loop at dynpselect.
    17     clear checktable.
    18     if dynpvaluetab-lowvalue ne space and dynpvaluetab-lowvalue na '*'.
    19       move 'EQ' to checktable-op.
    20       move dynpvaluetab-lowvalue to checktable-low_value.
    21       append checktable.
    22     endif.
    What could cause the problem by selecting only 0Material when checking the InfoCube 0PUR_C01 content?  What does that mean by this STOP msg "Settings for material number conversion not found"?
    Thanks

    Hi Kevin,
    Set the length of 0MATERIAL and change conversion to alpha:
    Re: Error Installing 0MATERIAL from Business Content
    Best regards,
    Eugene

  • ERP - SD Sales orders with billing plan (material number change appear)

    Sales and Distribution.
    Regarding sales orders with billing plan.
    We create the sales order and create billing plan at header or item level.
    We issue down payment request(s) upon receipt of sales order.
    Often during the life time of the sales order one or more of the material numbers are changed after the down payment request(s) has been issued and paid by the client.
    Our issue is that prior to changing the material number in the sales order we have to reverse the payment(s), reverse the down payment request(s) and after the material number change re-issue the down payment request(s) and register the payment again.
    We wish to find a solution avoiding all the reversals.
    If you have a similar situation please inform how to handle material number change in the sales orders with billing plan.
    Best regards
    Lise

    Dear Consultor SD ,
    There is no setting to create the invoice based on schedule line.
    What you can possibly do is create multiple deliveries based on the schedule line and
    then invoice the individual deliveries.
    If you want system to split the deliveries based on schedule line, then you will have to include Schedule line also
    in the COMBINATION REQUIREMENT in VTLA.
    Thanks & Regards,
    Hegal K Charles

  • Need to enter rack number during GR

    Hi,
    Is there any way to put rack/shelf number during GR using MIGO?
    As per my knowledge we need WM for that. another way is through batch management, classification button will come during GR(if classification tab has been maintained in material master).
    Any other option to solve this besides to these two method?
    thanks,
    sheetal

    Is this the Business req??
    If so, if u do not consider it for the reporting purpose.. You can use the text field of the MIGO for this purpose.
    Hope it will help u.

  • Material Number In Sales Order in Change Mode

    Hi All,
        Following is my scenario.
    During creation of sales order I am taking two line items in sales order that is in sales order there are two line items.
    One item is finished product and other item is the semi finished product. Whenever I am saving the sale order Finished product material number is in change mode but the semi finished material number become in display mode.
    My question is how to make the semi-finished material number in change mode?. Any configuration.
    I can use screen variant. But one material number is coming in change mode but other is coming in grey mode.
    Note : there is no subsequent document exists.
    Regards
    Sridhar

    hi
    pls check any variant configaration is been maintained for that semi finished product
    regards
    senya
    Edited by: senya_1111 on Jul 31, 2009 1:59 PM