Grouping, Pegging and Distribution (GPD) when run MRP for PS

Dear all,
As you know, MRP is a core of Planning Process. So when you run MRP for PS, SAP can't check stock in general stock and project stock at the same time. Now, my client have accept to run MRP base on project stock. But there are some problem when they give me requirement and actually situation in their company. One of them as below:
They have 3 WBS element (WBS 1, WBS 2, WBS 3) and they use the same material A. Their requirement is they want to run MRP to plan material for 3 WBS.
Solution 1: use MD51 and run MRP for Project definition and each of WBS element have respective project stock, the system will generate some of planned order for each oder reservation. After that, I will convert all of planned order to PR => PO => Good Receipt for each WBS element. When run MD04, I can see the stock for each project stock for respective WBS element.
Ok, I will talk about the limited of this solution. I suppose after complete technical for all of order reservation in WBS 1 and in project stock of WBS 1 have 3 material A not be use. But in WBS 2 is missing 3 material A. So when I run MRP again for WBS 2 by tcode MD51, the system will generate new planned order for this missing material A. This is not logic because I have enough material A for reservation in WBS 1. So I suggest my client that you should transfer material A from WBS 2 to WBS 1, they agree with me if they don't have many WBS element. But they have about 300 WBS element and they can't do transfer posting between many many WBS element. This solution 1 is not be accept.
Solution 2: I use GPD for this requirement. Firstly I will group WBS 1, WBS 2 and WBS 3 into WBS group. So use tcode MD04, I can see only WBS group and all of order reservation in each WBS 1, 2, 3 be showed on MD04 table. When I run MRP, the system will generate planned order for them. After that, I will conver all to PR => PO => Good receipt to WBS group. And in MD04 table, I can see project stock for WBS group. I begin transfer material from WBS group to each WBS 1, 2, 3. When all of order reservation in WBS 1 is technical complete, the material in WBS 1 have 3 material A not be use. And in WBS 2, I have a new order reservation and it be assigned 4 material A. At this time, project stock on WBS group is 0 but in WBS 1 is 3. But when I run MRP by tcode MD51, the system generate planned order with amount is 4. I wonder that why SAP does not check all material on all WBS element in WBS group to suggest a planned order with amount is 1. If SAP can solve this problem, my client will be accept this solution.
Hoping you support me.
Thanks, Regards
Hoai Vu

Hi Ahmed Rifaee
Thanks for your reply, I will talk about process in SAP.
So, I have 2 WBS element, that's simple because my project is have about 200 WBS element.
WBS1 have 2 order reservation for each actvity and material A0001 be use in 2 order reservation.
Order Reservation 1 needs 3  A0001
Order Reservation 2 needs 5  A0001
WBS2 have 1 order reservation for each activity and material A0001 be use in it
Order Reservation 3 needs 4  A0001
1.)     If I don't group 2 WBS1 and WBS2 to one WBS group, SAP will have 2 project stock for each WBS. and when I run MRP, WBS1 and WBS2 run independent base on current project stock at each WBS. So, although project stock WBS1 is run out of A0001 while A0001 still exist A0001 in project stock WBS2, SAP still generat planned order for missing part A0001 in project stock WBS1.
2.)     If I use GPD by group WBS1 and WBS2, I can solve this problem easy because they will use only one project stock for WBS group. Ok, after I good receipt A0001 into project stock, I'm sure that I have enough A0001 for 2 WBS1 and WBS2. But I can trace which reservation be ordered to delivery to them exactly. I try to use tcode MD09 to trace from Purchase order to Order reservation but I have just to trace in case PO have not been good receipted. I wonder that Pegging can help me in this case (PO have been good receipted).
Can you give me any idea for these problem
Thanks, Regards
Hoai Vu

Similar Messages

  • No planned order created when run MRP for Sale Order

    As I have told on the subject. My problem is system does not generate planned order for components in BOM
    Some more information is: requirement class in SO is 043
    I have choose "2" in tab MRP 4 for individual/collective and all component and finish product have MRP type is PD and Strategy is 20 - make to order
    Please help me to solve this
    Thanks

    Hi Hoai Vu,
    Please check in OPPQ plant parameters in SPRO weather you maintained for the plant conversions of planned order to production order.
    SPRO-> Production> material requirement planning> plant parameters--> carry out plant parameters or over all maintenance of plant parameters (OPPQ)
    Then check the for the material did you maintained the work scheduling view or not.
    I hope helps you any queries please revert me back.
    Regards,
    Madhu.G

  • Ignore the number of schedule lines in sale order item when run MRP

    Dear All,
    I have a problem when I create production order (discrete manufacturing)
    When I create a sale order with one sale order item and 3 schedule lines for this sale order item.
    After that, I run MRP for this sale order, what I get is 3 planned orders for 3 schedule lines. It means that I will have 3 production orders for 1 sale order item.
    I want  create one production order for one sale order item whatever the number of schedule lines in sale order item.
    I think I have to config in MRP. Please help me.
    Thanks in advance

    Dear
    Check in OPPQ then look in Master data Availability Check & strategy for material also check whether u have maintained strategy for same material and see did u extended sales views for other material
    As u said 3 schedule lines for this sale order item check whether u have extended sales views for next material
    With Regards
    Pushpalas

  • Best MRP type and strategy to run MRP for component using PIR and forecast

    Hi Experts,
      I want to run MRP for Component parts. I need to run MRP based on Planned independent requirements and Forecast Data.
    Which is the best suited MRP type and strategy.
    Please help to share bestpractices if any. thank you.
    Rayudu

    Hi,
    is the components you are talking are Semi finished materials or Raw materials and Packing materials which are procured from vendors ???....
    It is not a good idea to maintain planning strategy for Components which are part of BOM...these materials are automatically planned when the header materials of these components are planned....
    If these components are not part of any BOM then you can try the option of using forecast based planning.. MRP type  VV and maintain the forecasting view in the material master
    You can also explore the option of consumption based planning like manual or automatic reorder point planning...
    Thanks
    Kumar

  • Running mrp for a particular group of amterials

    How do we run mrp for a particular group of materials.not for the whole plant.like running mrp to mrp group.

    Hi,
    You also have three other choices:
    1. MPS vs MRP for splitting into two sets of materials, e.g. daily MPS for manufactured material and weekly MRP for purchased material.
    2. Running Single Item, Multi-level MPS (MD41) or MRP (MD02) for a product group
    3. Develop an ABAP using your selection criteria (based on view MA61V?) that makes calls to FUNCTION BAPI_MATERIAL_PLANNING.
    Regards
    Alex Dixon

  • Is there a way to increase the font size in the sidebar of Mac mail and the Finder when running OS 10.6.8?

    Is there a way to increase the font size in the sidebar of Mac mail and the Finder when running OS 10.6.8?

    The only way to increase the size of the onscreen text in the Finder Menu Bar and in the Side bar in Finder Windows is to change the screen resolution in the OS X Preferences Pane under the Displays icon.
    What Mac and screen size are you using?

  • Run MRP for multi Plant

    Dear all
    I want to ask you about running MRP for multi plant based on SAP ECC EHP4.
    I have a situation as below:
    I have 2 plant are 1000 and 2000. In plant 1000, I create a production order in plant 1000. The component is store in both of plant 1000 & 2000.
    So, when I run MRP. Does system will check stock from both plant 1000 & 2000?
    Because my company is keeping raw material in 2 plant, and there are one plant have been used for production.
    I want you confirm that Does SAP ECC EHP4 can run MRP for multi plant and the system will check stock on multi Plant?
    Thanks

    Hello,
    The scope of planning is used to control whether the total planning run is executed on a multi-plant level
    several plants
    one MRP area
    several MRP areas
    a combination of plants and MRP areas.
    Here the planning will cover all the material which is relevant for planning in all the above given areas.
    You can carry out the total planning run for the scope of planning online or in background mode. The planning run, however, must always be started with parallel processing.
    Hope it helps. Please revert back.
    Alok Tiwari

  • Running MRP for finised product material

    i have a material BOM (finished product material and it consist of some raw material) those materials have MRP
    when i run MRP for this BOM i want to generate PR for the raw materials and a production order for the finised product material
    Please i want all the steps for these senario

    Nehad,
    You need to create PIR(Demand) for the finshed product for the MRP to trigger Planned order for the Finished product and Dependent requirments/PR for the Raw materials.
    1. Use transaction MD61 to enter demand for the finished product with respect to the plant and requirement type "LSF" if it was strategy "10" or "BSF" for strategy "11". You can check the planning strategy used for the finished product using transaction "MM03" in the MRP3 view... if no strategy is assigned you can still use "LSF" requirement type.
    2. Now run MRP using "MD02", you should get planned order for the finished materail and PR for raw material. Please note the MRP type for both the materails should be "PD" you can check this in "MM03" - MRP1 view of the materails.
    Regards,
    Prasobh

  • Using MD50 to run MRP for Sale Order

    Dear all,
    I have some problem when using MD50 with Mill Product Industry.
    When SAP system not activate Mill Product yet. I used transaction code MD50 to run MRP for Sale Order, the system have generated planned order for multilevel. But when SAP system have activated Mill Product, I used transaction code MD50 to run MRP for Sale Order, the system only generate planned order for single level. I think that we have to configure something based on Mill Product Industry. So can you help me for this
    Thanks, Regards

    Hi,
    Check with following links which may help you resolve your issue :
    http://www.sap.com/sme/whysap/industries/millproducts/index.epx
    http://help.sap.com/saphelp_di471/helpdata/en/4e/1796374b088e5ce10000009b38f8cf/frameset.htm
    http://help.sap.com/content/documentation/industry/docu_is_mill.htm
    Regards,
    Tejas

  • How to run MRP for Bulk Material without using LTP

    Hi, how can I run MRP for BULK material without using LTP.
    Thanks in advance
    BK

    Hi,
    Use trasnsaction code OPPQ and goto BOM Explosion and selection depends on
    Field selected
    No dependent requirements are created for informational purposes for bulk material items in the plant selected. This can improve system performance.
    Field not selected
    Dependent requirements are created for bulk material items in the plant selected. These dependent requirements are displayed in the planned order for informational purposes only. They are not considered in the net requirements calculation; that is, they are not included in material requirements planning (MRP) and are not displayed in the stock/requirements list
    Reg,
    Deepak.
    Edited by: deepak k b on Nov 11, 2008 6:56 AM

  • Run MRP for production order/maintenance order has been release

    Hi all,
    please tell me how to configure for running mrp for production order/maintenance order has been release. as you know, i want production order has not release will not appear in MD04. I think that is the way for running mrp will not take care about this production order has not release
    Thanks all

    Hi Hoai,
    It is impossible to exclude production order from net requirement calculation in MRP run. You may take a look at the online documentation under the PP-MRP area.
    Material Requirements Planning (PP-MRP)
       Planning Process
         Net Requirements Calculation
           Net Requirements Calculation for MRP
    But there is a way to temporarily exclude production order from MRP. That is you can set the 'delivery completed' indicator in 'Goods receipt' Tab in in production order. Please note that this order will not appear in MD04. Actually to some degree, this order could be considered as completed because ticking the indicator could set status 'DLV' for the order. But you still can execute confirmation, goods issue and goods receipt activities. This way is just a workaround. You may
    consider it.
    Or maybe you can consider the useage of BADI: MD_CHANGE_MRP_DATA to change the MRP run data to see if this could fulfill your requirement.
    Regards,
    Rachel

  • Run mrp for specific material

    i want to run mrp for specific material (not for all the plant materials) in background in scheduled intervals............what can i do?

    Dear,
    You need to go for enhancement M61X0001 with function al modules EXIT_SAPLM61C_001 and EXIT_SAPMM61X_001
    Please refer my reply from this link,
    [MRP run for Specific Material|Re: Excluding materials from mrp run]
    Regards,
    R.Brahmankar

  • I am updating iphoto 9.1 to 9.3 and every time when I clicked for update aps store asked to open it in the account where you purchased. I am using the same account and its available in the purchased item of this account. Can someone resolve this problem.

    I am updating iphoto 9.1 to 9.3 and every time when I clicked for update aps store asked to open it in the account where you purchased. I am using the same account and its available in the purchased item of this account. But in my purchased item library it indicates that you update iPhoto. I am not sure which account the aps store asking. Can someone resolve this problem.

    Contact App Store support. They're the folks who can help with Account issues.
    Regards
    TD

  • How to run MRP for BOM as well as ROL items

    We have only one plant. I  want to run MRP for BOM items as well as ROL items.  MRP can be  run plant wise thru tcode MD01.  I want to run mrp for only ROL items.
    Please suggest
    Regards,
    ( Rajneesh Gulati )
    Edited by: Rajneesh  Gulati on Jun 20, 2008 11:33 AM

    As I understand for Quartz, I think you should create a security subject for it in your code. I guess the background tasks in Quartz work in separate threads. It is not recommended in EJB application. you can use EJB timer service instead.
    -Albert

  • [svn:fx-trunk] 5473: Fix for bug around handling of constraints during and after effects were run , both for old and new effects.

    Revision: 5473
    Author: [email protected]
    Date: 2009-03-20 16:02:58 -0700 (Fri, 20 Mar 2009)
    Log Message:
    Fix for bug around handling of constraints during and after effects were run, both for old and new effects. Fix was to correctly record and handle styles that were set or not set in either state and to temporarily set width/height values for the duration of an effect if we disabled the relevant styles that affect width/height.
    QE Notes: None
    Doc Notes: None
    Bugs: SDK-17809
    Reviewer: Jason
    Testing: checkintests, Mustella Effects, ListDataEffects
    Ticket Links:
    http://bugs.adobe.com/jira/browse/SDK-17809
    Modified Paths:
    flex/sdk/trunk/frameworks/projects/flex4/src/mx/effects/effectClasses/FxAnimateInstance.a s
    flex/sdk/trunk/frameworks/projects/framework/src/mx/effects/Effect.as

    Revision: 5473
    Author: [email protected]
    Date: 2009-03-20 16:02:58 -0700 (Fri, 20 Mar 2009)
    Log Message:
    Fix for bug around handling of constraints during and after effects were run, both for old and new effects. Fix was to correctly record and handle styles that were set or not set in either state and to temporarily set width/height values for the duration of an effect if we disabled the relevant styles that affect width/height.
    QE Notes: None
    Doc Notes: None
    Bugs: SDK-17809
    Reviewer: Jason
    Testing: checkintests, Mustella Effects, ListDataEffects
    Ticket Links:
    http://bugs.adobe.com/jira/browse/SDK-17809
    Modified Paths:
    flex/sdk/trunk/frameworks/projects/flex4/src/mx/effects/effectClasses/FxAnimateInstance.a s
    flex/sdk/trunk/frameworks/projects/framework/src/mx/effects/Effect.as

Maybe you are looking for