How to configure new cost center..

HI
my problem is untill now i used old cost center, to day onwards i want use new cost center... how to modify in my cost element in cost center.
i want to modify my old cost center and put new cost center.
Thank you.
Ashok kumar

hi Anil,
Check your settings in the Transaction code OKB9. In this transaction, default cost centers are maintained for each Company Code and Cost element.
Else you have defined default cost centers in your Cost Element. In such Case, use t-code KA02 and change the cost Center
If you satisfied with the reply then plese assign points.
Regards
Mahendra

Similar Messages

  • How to add new cost center to cycle segments

    Hello SAP Gurus,,
    How to add new cost center to cycle segments?
    needed badly and ASAP

    Hi
    Go to KSu2 and give the cycle name ad select the segment that you need to add cost center.
    If you are deal with cost cneter groups add new cost center to your cost center group KSH2.
    Kesh

  • How to use new cost center field, new profit center field, new account field?

    As I create a new change request of adding new GL account, or that of new cost center, or that of new profit center, I normally enter the new GL code GL01, or new cost center CC01 or profit center code PC01 in "General Data" section on the change requst screen,  these codes (GL01, CC01, PC01) are landed in ECC upon data replication.
    I do see there is another field called "New Account" of GL change request, or "New Cost Center" of CC change request, or "New Profit Center" of PC change requst all of which is under "Administrative Data" section. I have never used it. but I was wondering what the purpose it will serve and how should I use them.
    Please advise,
    Thanks,
    LUO.

    Hi Kiran,
    Thanks for the info. I don't quite understand though. could you tell me more about the usage of each? Why it is used when GL or CC or PC is blocked? Would the new cost center code entered replace old cost center master record?
    Thanks,
    LUO 

  • I would like to insert new cost center for the existing layout in BCS

    Hi,
    I would like to add cost center to existing layout.
    Currently we are loading data into BCS using flat file .
    In BCS we have current layout existed with below format.
    Header
    Controlling area
    Fiscal year
    Posting period
    Data Rows
    Company 
    Item
    Profit Center 
    Functional area 
    Trading partner 
    Period Value LC 
    Period Value GC
    Even we are getting flat file from R/3 as above format.
    Now our Business required cost center in BCS as their requirment and need to be bring from R/3 to BCS.
    In R/3 our ABAP people are working to bring the cost center from R/3 and made a flat file for us.
    In BCS we need to load the file which has new cost center,which was comming as per the new requirment.
    Please advise me how to add cost center in  Data Rows of BCS.So that it can accomidate new cost center which is comming from R/3.
    Please some advise me on this and answer would be appreated.

    Prasad,
    I knew how to add char to cube in BW.But i am not sure about BCS .
    - What's the difference in assigning the infoobject (CostCenter) to the infocube, doesn't matter if it's the basic (ordinary) or the BCS totals cube?
    I will follow as you said.
    - Taking the BW310 or SEM240 is very useful.
    Once it is done then what are the next steps need to do it.
    - What's done? What's the question?
    I am assigning points to you
    - I do not need the points assigned for nobody knows what. Feel free to unassign them.

  • How to change in cost center?

    Can some body please explain:
    How to change the depreciation expenditure charged from one cost center to another? Since the depreciation has been posted for the 2 months that have been closed, is it possible still to repost line items?
    To change the cost center thru KB61, is accounting document necessary?

    thanks for your reply!
    Actually the cost center is being changed from Aug onwards ,so the Depn posted to the old cost center for July needs to be reposted to the new cost center using KB61 taking the reference of accounting doc from KSB1 for the old cost center.
    But when i am using KB61 to repost the depn , system gives the error message " Transaction Repost CO Line item has been locked"
    ie July period is already closed.
    I do not have the authority to open the closed periods and repost. Is there is any other way?
    Also, once the reposting is done, Cost center can be changed for the assets thru AS02 so that system automatically posts the accumulated depn to the new cost center

  • Regarding new cost center

    HI
    my problem is untill now i used old cost center, to day onwards i want use new cost center... how to modify in my cost element in cost center.
    i want to modify my old cost center and put new cost center.
    Thank you.
    Ashok kumar

    hi Anil,
    Check your settings in the Transaction code OKB9. In this transaction, default cost centers are maintained for each Company Code and Cost element.
    Else you have defined default cost centers in your Cost Element. In such Case, use t-code KA02 and change the cost Center
    If you satisfied with the reply then plese assign points.
    Regards
    Mahendra

  • How to delete a cost center hierarchy

    Hi all,
            We are having a issue regarding the cost centers. The cost centers have been assigned wrong cost center numbers. Now the client wants a set of new cost center numbers to be used in the system. In order for that to be done I thought may be if I can change the cost center hierarchy that has been assigned to the controlling area in OKKP transaction we can assign new cost centers to the new hierarchy and solve the problem.
              But the system does not allow us to assign a different cost center hierarchy from the already existing one when cost centers are assigned to it.
    My issue is how to delete the cost center hierarchy.
    If that is not possible how can we remove the cost centers assigned to the cost center hierarchy ( is this possible)
    Last question can we delete the transaction data posted to cost centers.
    Points will be assigned to all the replies.
    Thanks,
    Sarada

    Hello Sarada,
    If the requirement is to track new cost centers only going forward, then you may need to create new Cost Centers, block old cost centers. Create a new node in the hierarchy saying "Old-do not use".
    If the requirement is to have the history transactions reflect the new cost centers as well, then you will need to undertake a project for SLO (System Landscape Optimization) which will replace this data at table level. This is a major project in itself and the programs are proprietary to SAP.
    Hope this helps.

  • How to configure new account assignment group of material

    dear expert
    how to configure new account assignmnet group of material
    vicky

    how to configure new account assignmnet group of material
    Probably, the question should have been how to create Account Assignment Group for a material.
    Go to IMG SD => Basic Functions => Account Assignment/Costing => Revenue Account Determination => Check Master Data Relevant for Account Asignment.
    There select Materials : Account Assignment Groups and create as per the requirement and save.  Now you can see the same while creating the material master.
    thanks
    G. Lakshmipathi

  • To find out recently new cost center

    Hi all,
    I have a problem that I had updated one request new data(it's like 200904 transaction data) to cube,
    while the inexistent cost center in master data is added(0Costcenter).
        The problem arise,how could i find out which new cost center is added to 0costcenter,because I
    need to listed those new cost center to user.
        Thanks.

    in the maintain master data screen for cost center give all the attributes a restriction to initial value.
    once you get cost centers search with them in the infocube and take out final list from there.
    or you write a abap report to check cost centers which have all fields initial and get it in a file.
    data: itab type standard table of /Bi0/pcostcenter with header line,
            itab2 type standard table of /Bi0/pcostcenter with header line
    select * from /Bi0/pcostcenter
    into table itab
    where objvers = 'A'.
    loop at itab.
    if itab-BUS_AREA is initial.
      if itab-0COMP_CODE is initial.
    .... keep checking for all the attributes.
         .... if all atributes are initial
          append itab to itab2
      endif.
    endif.
    endloop.
    CALL FUNCTION 'GUI_DOWNLOAD'
    EXPORTING
    filename = <give file name here>
    write_field_separator = space
    TABLES
    data_tab = iout
    EXCEPTIONS
    file_write_error = 1
    no_batch = 2
    gui_refuse_filetransfer = 3
    invalid_type = 4
    no_authority = 5
    unknown_error = 6
    header_not_allowed = 7
    separator_not_allowed = 8
    filesize_not_allowed = 9
    header_too_long = 10
    dp_error_create = 11
    dp_error_send = 12
    dp_error_write = 13
    unknown_dp_error = 14
    access_denied = 15
    dp_out_of_memory = 16
    disk_full = 17
    dp_timeout = 18
    file_not_found = 19
    dataprovider_exception = 20
    control_flush_error = 21
    OTHERS = 22.
    you will get all cost centers which doesn't has any attribute

  • How to create New Work Center

    Dear Experts
                      How to create New Work Center?, what are all the inforamtions  need while creating workcenter.
    Regards
    Rajakarthik

    Hi,
    In addition to the above post, you need to identify that:
    1. Whether you need separate activity types and cost center for the newly created work center. These details are entered in the Costing View of the Work Center.
    If these are required then use KL01 to create new activity, KP26 to define the activity price.
    If required create cost element using T Code KA01 and Cost Center using KS01.
    Take help from the CO guy on this.
    2. Also  you need to ask the concerned about the operating times for the wor center. That is Start time and End time of WC. It is used for capacity evaluation and scheduling of the orders. It is maintained in the capacity view (Bottom left Button in the view).
    this view will also contain the details regarding the calendar, to be assigned to the work center, if needed. Collect details for this requirement. Also you can assign a different calendar to WC apart from factory calendar.
    3. Find out whether this WC will be operating in shifts or not. Accordingly maintain the details.
    Hope it is useful for you.
    Revert for clarifications
    Regards,
    Rohit.

  • New Cost Center trigger

    I need sample code to implement a trigger so that when a new cost center (dept) value to the accounting flexfield is added, then it fires off and creates the corresponding row in the fnd_shorthand_flex_aliases table
    Does any one know how to create it?
    Thanks,
    Chiru

    Hi All,
    I create a trigger to insert data into the fnd_shorthand_flex_aliases table, if a new flex_value is created in the fnd_flex_values and fnd_flex_values_tl.
    However, I am getting the error:
    ORA-04091: table fnd_flex_values is mutating, trigger/function may not see it.
    More than likely it is due to the fact that I am trying to query the table fnd_flex_values to insert into the fnd_shorthand_flex_aliases table, while inserting into it at the same time.
    Does any one know how to get around this?
    Thanks,
    Chiru

  • New Cost Center

    Dear All,
    Scenario :
    New cost center or new location or new office has built by organization , how to handle this scenario without interference with existing database entries ?
    Is the following option is correct ?
    To create new database and punching entries in that database for new location or new branch.

    Hi
    Thats purely ur managment policy and decisson based.
    See as u said by defining numbering series, Diff G/L acc, Cost Centre,whse we can achive simply, finally management  will get consoldiated P&L as well Profit Centre wise also for all Profit centre wise...
    If they want to maintain different DB then that also ok, finally there is no option for consildaation the P&L,TB without Some addons....so this factor u have to look when u r going for different DB for same Business process.
    Some Companies will have lot of constraints like this branch sales details, customers and their details should not be shown to other branches but to achive this in default B1 it is tough to achive...so u have to think in multiple angle which is best.
    Cheers
    Giri

  • How to find the cost center group from cycle/ segment in CO module?

    Hi All,
    I need to fetch the list of cost centers in the cost center group against the cycle.
    Is there any table which will store the list of cost centers against the cycle?
    or else, what I was thinking is use of BAPI BAPI_COSTCENTERGROUP_GETDETAIL, which will give me the list of cost centers,
    but we need to pass the controlling area + cost center grp to fetch the cost centers from BAPI, I have controlling area with me but not the cost center grp name, only I have Cycle info lke cycle name, segment name, seq number. so how to find the cost center grp name from the cycle name?
    Regards,
    Mrunal

    FM: RK_AL_CYCLE_READ
    CHECK TABLE: T811K

  • How to delete the Cost center line item data

    How to delete the cost center line item data of particular cost center and only one cost center is exisiting for that company code.
    Is there any way to delete the line items in that cost center.
    Can data archiving & deleting can help us..........
    does it have any effect over other cost center data....
    any input needed.........
    regards
    rajesh

    Hi,
    i found 2 reports for you:
    1) CO_TOTAL_WRI - Archiving CO Totals Records   
    2) RKCOITW1     - Archiving CO Line Items: Write Program        
    from 2) is a linlk to customize archiv-parameters
    -> start it with transaction se38 / sa38
    A.

  • How to determine the cost center

    Dear experts:
    Could you give me some suggestions about how to determine the cost center depending on the different
    storage location when we use the t-cdoe MI07
    Thanks in advance.
    Rong

    Hello experts!!!
    how have you resolved this issue???
    I have the same situation, and i dont know how to manage this.
    Thank you very much in advance.
    Best regards,
    M. Cecilia Vacatello.

Maybe you are looking for