How to transfer project cost of inventory to project

Hi, there
I created a Purchase Order with destination of inventory and associated with project and task. After approved, I received goods of the PO to a project loactor.
I don't know what to do next so that I can see cost of the receipt updated to the PSI.
My step:
1. run the cost processor
2. run the PRC: Transaction Import (Parameter:inventory)
3. run the Update Project Summary Amounts
But it doesn't work. It only works when I do the Miscellaneous issue to a project.
Edited by: 909822 on 2012-2-16 下午5:20

Hi
There is not special method.
You willl need to zero the amount / quantity on the original budget line and enter the required amount / quantity on the new GL period or new task or new project.
Dina

Similar Messages

  • How to Transfer Cost From an Internal Order to Another Internal Order

    Dear Sir,
    We had one Internal Order opened for Asset Under Commission (AUC) . We also had opened another Internal Order and cost were booked in this Internal Order also .
    Now , we want to transfer the complete cost from 2nd Internal Order to 1st Internal Order . During the Transfer , we want to maintain the same GLs (i.e in 2nd Order the GLs get credited and in 1st Order the same GLs must be Debited)
    Pl guide us , how to transfer the cost .
    Regards
    B Mittal

    You can do a regular FI posting debiting and crediting the same account, with a different internal order in each line item.

  • Transfer depreciation cost to COPA

    Hi COPA gurus,
    As i know, there is no way to assign assets to profit segment, and depreciation run is automatic, so how to transfer depreciation cost to COPA directly (not via cost center then allocation to profit segments)?
    Another point, business transactions to have Profit segment found automatically using substitution are only transactions from MM modules (price differences, revaluation, inventory differences). So Is substitution not able to apply with depreciation posting in this case?
    Could anyone show me, how does depreciation data transfer directly to COPA?
    Thanks so much,
    HuyenTT

    Dear Pradeep
    I have the similar issue.
    With the cost center in asset master, CO-PA document is not generated.
    Instead, Controlling document (CO object is CTR) is generated.
    Without the cost conter in asset master, CO-PA document and
    Controlling document(CO object CTR as statistics) is also generated.
    But, as you mentioned, even with the cost center in asset master,
    CO-PA and Controlling document should be generated, right?
    Customization I've done are
    - GGB1: Substitution
    - OKB9: Flag-on to "profitability segment" for the Depreciation cost element
    - OKC9: Activate 0_SCO10
    If I miss something, pls let me know.
    BR
    Y.Kaneko

  • Transfer actual costs from a Profit Center to another

    Hello,
    I need to know how to transfer actual costs from a profit center to another starting from a certain date, after having changed the corresponding profit center value in a Wbe.
    Thanks,
    Giovanna

    Your future postings are taken care to the new Profit Center. You only need to address the posting in Jan 2007 or probably until the period you changed the Profit center in the WBS.
    Since the value and number of transactions are likely to be limited in January 2007, you may want to use <b>9KE0</b> which is a direct posting to PCA. Identify the value that has gone to the old PCA for the period of Jan 2007, take that amount by cost element, use the same cost elements and amount and make the transfer posting. This is like a journal entry. Debit the old profit center and credit the new profit center with the same amount. This can be controlled by the minus signs to the amount.
    Caution; This practise may not be followed too often, the access to thist-code may be restricted to avoid frequent usage.
    For the history, you can take a download of the WBS with the amount you are going to transfer.

  • How to Transfer PPV to anthor project

    Hi,
    We are using standard cost method and PJM
    Item is received in Project locator for Project A. Cost collection program transfer the cost based on Std cost and PPV to Project A.
    Now the Item is transferted from Project A to Project B locator in inventory . Only the Std cost get transfered to Project B. The PPV is still remain in Project A.
    How to Transfer the PPV from Project A to Project B. (Project Transfer option in Exp inquiry is not allowed since the Source is Inventory).
    Thanks
    Govind

    Hi
    I understand you want to allocate all cost incurred on project A to project B. If you setup the allocation rule to do that, each run of the allocation process will generate one expenditure item on the target project.
    Therefore, you can have only one expenditure type for such expenditure item.
    If you want to keep the list of expenditure types of project A so cost will be transfered to identical expenditure types in project B, you might consider setting up multiple allocation rules.
    You need to setup allocations source by resource list, where the resource list is defined by expenditure types. The summarization process will summarize the total amount of each expenditure type on project A. You will need to setup each allocation rule for an individual expenditure type (resource) in project A. Foe each such allocation rule you set the target expenditure type to equal the source expenditure type. Be sure to have all you expenditure types with an additional expenditure type class of miscellaneous.
    Dina

  • How to run "Transfer Invoice Variance to Inventory Valuation"

    Hi friends,
    Im using oracle 11i. we have purchasing, inventory, AP, GL. Pls give me navigation path of running Transfer Invoice Variance to Inventory Valuation concurrent program. i have created an invoice with some addition cost (freight) that is not included in Purchase order. i have run "Transfer payalbes to general ledger" and posted those journals. I need to run Transfer Invoice Variance to Inventory Valuation program so that item costs get re-averaged. how can i do that? pls provide me the exact path including responsibility name.
    Thanks in advance.
    LISAN

    Hi,
    You can also refer to:
    Oracle Cost Management User's Guide
    http://download.oracle.com/docs/cd/B25516_18/current/acrobat/115cstug.pdf
    Thanks,
    Hussein

  • How to Re-classify cost from Project to Cost Center.

    There is a Project X   -  Its owner is Cost Center YYYYY.
    There is pressure to close Project X
    but we have commitments to the amount 4 milllion.
    We were thinking if there is a way to compensate this 4 million to Cost Center  YYYYY..., and close the project and then use Cost Center YYYYY as the cost object for our PO's / Commitments...
    I don't understand the Cost Center Budgeting Philosophy
    can anyone give suggestions, how re-classification, re-valuation, or transfers, can be made in SAP.
    Regards,
    Edited by: Owais Bin Abdul Aziz on Dec 6, 2011 6:04 PM

    Hi
    You can close project but before closing project transfer actual costs sitting on it to some other cost center.
    What do you mean by compensation to CC YYYY?. Please elaborate with more details.
    Regards,
    PSR

  • How to derive/generate Revenue only wth Project costing?Burdening possible?

    Hello Experts / Dina,
    I am doing a implementation to customer where only Project costing is in scope and customer wanted to derive / generate revenue for few of the revenue generated project using oracle project costing. Currently this customer is using legacy external application to enter manual journal for revenue.
    So can you please provide me workaround to achieve only revenue generation using oracle project costing?
    I have one workaround but wanted to validate from you all experts. Plz help me...
    1. Enabling budening on same expenditure item I can generate revenue using burden schedule and setup total burden cost db and cost cr account in auto accounting so that burdent Cost Crd account will be a reveue account and burden Cost dbt account will be UBR a/c. and then transfer the burden cost to GL as revenue vs UBR.
    This work around is thorotical and dont know what is implication of burden mulitpliers. If I used this workaorund then revenue (burden cost) amount is depend upon the expenditure orgnization multiplier and not on job based or employee based. How to solve this problem?
    I think there is possibility to drive the burden multiplier based on expenditure types..if taken that approch then end up in creating lot of expenditure type for each multiplier.
    So please help with workaround or someother method.
    Thanks

    Hi Dina,
    First of all many many thanks for posting your answer on this question.
    1. > I tried using total burden schedule approch to generate revenue but I think there is problem to restrict the accounting for the expenditur items which should not be burden ( need not to be generate revenue). As Total burdening approch creates burden accounting as raw cost though burden mulitplier is not specified ( system takes as value 0) :(
    2.> Then I tried a approch of using create & distribute burdening method ( burdening on separate expenditure item) - This works fine and generate burden accounting ( revenue a/c -& UBR). And provides a restriction of generating revenue on selected expenditure items based on burden schedule schedule (multiplier as 0 not specified). On Expenditre Inquiry also can reports a revenue after querying on Expenditure Type Class as "Burden Transactions". You can also reverse items and reverse costing / burdening ( reveneu ) with normal standard process.
    3.> If I wanted to use borrowed and Lent processing then I guess it will be easy. But only problem is I can't keep Project Org as Resource Org. Then there is pain in defining lot of resource organization and project organization ( I m not sure customer will agree :() . Also after referring the Project API guide I am still confuse about 2 diff extention doing same thing.
    a.> Transfer Price Determination Extension b.> Transfer Price Override Extension . Can you please explain what is difference between both of them and wat is purpose for both of them?
    Also In case i don't used the extension then I will be left only using Transfer price % ( 100% + ) to derive my revenue price? rght? Also I am not sure how can customer will have restrictions on the expenditure items which should not generate revenue? ( By defining another transfer price schedule on the selected TASKS with rule as transfer price % 0? )
    and I hope by using borrowed and lent processing I can do adjustments ( like reversing of revenue ) as standard way?
    Please guide.
    Thanks a ton !!!
    Cheers,
    :-)

  • Project Cost Transfer

    We have a project where we have the manufacturing cost incurred and sent to GL. Now the client wants this cost to be transferred to another project. What are the methods by which this can be achieved?
    Regards,
    Karthik

    Hi
    The inventory expenditures in Oracle Projects cannot be adjusted. Therefore you may either do the change in original module or use a workaround.
    Assuming you are working with Project Manufacturing , you could transfer the items from the original project locator to the new project. Use Project-Transfer transaction type.
    Alternatively enter a preapproved Miscellaneous expenditure item to debit the new project and a negative one to credit the original project. This method you can easily move the summarized amount of all cost between projects, however, there is no link to the original expenditures.
    Dina

  • How to transfer the stock form Project stock to Sale order stock

    Hi
    How to transfer the stock form Project stock to Sale order stock
    I tried to do this with movement type 413Q
    System is giving me error
    Valuated project stock not allowed with customer stock.
    Message no. KI346
    How to do this
    Thanks
    NK

    You can use Mov Type 412-Q
    412     Q     Transfer posting project to own - reversal
    Thanks
    Rajesh

  • How to Capture Multiple Cost centres and Business Unit information in a project?

    Dear Experts,
    With the help of UDA functionality in project super responsibility, I have captured Cost centre and Business unit information and this info will be used/reflected in CC and BU segments of all transactions gets recorded against that project.
    Now, our user wish to have multiple cost centres and business units to be tracked in the same one project. How is this feasible? Below example describes my requirement in a summary, please advise.
    An Indirect project is created when a defect on a machine reported from client's customer and all subsequent activities (purchases, travel to customer site to analyse and troubleshoot, purchases for any in-house analysis etc..involves costs spending internally) in resolving that defect/project involves 6 to 7 different departments (Sales, Tech Support, Quality team etc.,who actually work/travel and spend costs against project until defect resolution). And, each of the above departments will have 1 dedicated owner (project owners) to manage that project and each of these 6 or 7 owners owners will have their own cost centres (eg: 2345 - Sales team) against which they wish to see their transactions (travel, purchases during defect resolution) globally.
    So, all I want to know is how can I make one single project to accommodate multiple cost centresand business unit information to be assigned using UDA? Please let me know if I am not clear.
    Regards
    Venkat

    I think you should use the expenditure organization on the transaction itself to derive the CC/BU. Have AA lookups and define AA rules where you look at a Exp Org to BU or Cost Center to derive accounting.

  • How to find the difference between Project costs & Cost center costs?

    Hi all,
    Can you please explain me ? What is project Cost & Cost center cost and which are the tables having those fields of project cost & cost center Costs? And how to find the difference between their costs ? And please give me the functional Idea about it?
    Thanking you all in Advance...
    Regards,
    Chandru

    Hi,
    goto table COSP:
    1) object-no. beginning with 'KS' refer to cost-centre
       example: 'KSKOKA4711'
       with KS, KOKA = controlling area and 4711 = cost centre
    2) OBJNR beginning with 'PR' refer to projects / WBS-element
       example PR00001234
    Message was edited by: Andreas Mann

  • How to settle project costs to AUC

    Dear Experts,
    Please teach us how to settle project costs to AUC.
    Your response is very much appreciated.

    Refer below link
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/2a/f9f56e493111d182b70000e829fbfe/frameset.htm
    Venkat

  • How to transfer Avid XPress project on PC to Premiere CS4 on laptop?

    Hi,
    I have the following problem: I have an Avid Xpress sytem on a PC and Premiere Pro CS4 on a laptop. I have a project on the PC that I would like to edit while travelling with the laptop - and I'm trying to work out how to transfer the project from one to the other (via an external hard drive).
    I noticed that Premiere in the latest update supports AAF files, but when I export the Avid project as AAF, Premiere can read the info in the AAF file but somehow it does not recognise the associated OMF (media) files (i.e. it imports the AAF and then asks where a given OMF file is, but when you tell it, it says that the file format is not supported).
    I read somewhere that an alternative would be via quicktime reference files - but the problem I see there is that if I want to transfer the media files to another drive, the quicktime reference file has no means of knowing where they are (or rather will think that they are still at the old place, because it does not ask for any location)?
    Another thing may be that the original Avid OMF files might not be quite the right format for Premiere - there is also an option to export to OMF 1.0, but I'm not sure if that would help.
    Any suggestions and help regarding transferring the project from one system to the other would be appreciated! Many thanks!

    Um ... by basically re-doing the project ... as there's SO much added to CC since the CS6 version, the tools have changed, the available effects have changed, the underlying code has changed ... there's just so much that CC can do that can't be done in the old CS6 version.
    You can try exporting an XML and importing that into CS6 ... sometimes that works better than others, it hath been stated. This is sort of like trying to put a modern engine with all the computer controlled gizmos & pollution controls & fuel injection and designed to work with a 5-speed auto transmission into a 1965 Chevelle. With the older 3-speed manual tranny. How do you do it? Rebuild everything ... both the engine & the car. Lot of work.
    Neil

  • How we can do  transfer for cost estimates between plants?

    Dear Gurus,
    We have 2 plants. Suppose, Plant A and plant B.
    Production is performed at the plant A. There are all quantity structure from PP: BOMs, routines.
    But goods receipt and sale occur at the plant B. There are no quantity structure.
    Now, we have calculated cost estimates for plant A and we need to transfer that cost estimate with cost components split  to the plant B.
    How we can do that?
    Thank you,
    With best regards,
    Kamila.

    Hi Ajay,
    I have done according with your message following.
    ke40-
    http://imageshack.us/photo/my-images/545/ke40.jpg/
    http://imageshack.us/photo/my-images/153/ke40gr.jpg/
    http://imageshack.us/photo/my-images/69/ke40lg.jpg/
    http://imageshack.us/photo/my-images/268/ke40pc.jpg/
    kepc
    http://imageshack.us/photo/my-images/12/kepc1.jpg/
    http://imageshack.us/photo/my-images/716/kepc2.jpg/
    http://imageshack.us/photo/my-images/217/kepc3.jpg/
    Unfortunately, there are still no cost component split in CO-PA.
    Did I miss something?
    With best regards,
    Kamila.

Maybe you are looking for

  • Can running Macbook Pro in Clamshell Mode cause problems for Macbook Display?

    Hi, I recently got a new monitor (Dell U2711) and it is stunning when running at full resolution through a mini displayport to displayport adapter. However, i ran my MBP in Clamshell Mode and after rebooting (without the display this time) i had horr

  • Ipod shuffle not detected in Windows 7 64 bit SP1

    OS - Windows 7 64 bit SP1 Itunes version - 10.5.3.3 Ipod is detected as USB Mass Storage device under Device Manager and as IPOD under the category Unspecified device in Device and Printers. It does not get detected in Itunes and also does not show u

  • All Agents Greyed Out or Not Monitored

    Hello, I am running SCOM 2012 R2.  All of my clients were re-imaged (Over 500) during the summer.  Each image that was created had the SCOM 2012 R2 Agent installed.  The images were installed on all of my clients.  Now, most of the clients are listed

  • Graphic Problem

    I have Macpro Quadcore 2.93 With NVIDIA GeForce GT 120, With a dell U2711 connected to it, and I cant get it to work properly in max resolution 2560*1440, I can switch to the resolution but its all blurry. Max Resolution I get is 1920*1080. I guess t

  • How to restirct datepicker in OAF

    dear friedns? how to restict datepicker validation in OAF? Thanks krish Edited by: user5425941 on May 19, 2011 3:26 AM