How to view man hours in MS Project 2013

I have created a sample project plan in MS Project 2013 with 3 resources. Some tasks are running in parallel while others are one after another. I am using standard calendar which is 8 hours a days, 40 hour a week.
How do I know man hours of my project plan? Is there some view available looking at which I can know the man hours of my project?

Hi,
assuming default settings, you should do two things:
Add column Work to your view
Display Project Summary task: tab Format, enable check box "Project Summary Task".
This will give you total of hours (Work) for your project in line 0.
Does that help?
Barbara

Similar Messages

  • How to view all approved timesheets in Project 2013

    Hi!
    How can I view all the approved timesheets in Project 2013? Do I need to build a report or is there a way to do this OOTB?
    Thanks!
    Best regards

    Hi Pedro, 
    You'll have to build a report for that. I'd suggest to start from one of the Excel Services sample report based on the timesheet OLAP cube. You'll easily be able to create a pivot table with timesheet per status, users, projects, periods, managers...
    SSRS is another path which requires development.
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • Project server 2013 how to check work hours per hour per project

    Hi all,
    I would like to know how to check the total work hours for a project per month. For examples, I want to know all the work hours for all resources spent for the project A in August. Any idea?
    Thanks,
    Anna

    Hi Anna,
    If you don't want to write queries, I'd suggest you to simply open the project unchecking the option "load resources summary assignments" and go to the task usage view. Then display the project summary task and choose the monthly timeframe ("view"
    tab) for the timephased part of the screen (right part).
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • How can I view less hours in iCal on my iPad

    On my Mac like in iCloud, I have the option in iCal to view 6 hours, which makes the space bigger and I can input more appointments at smaller time intervals. How can I do this on my iPad

    You can't.  You have to do that on your computer, then sync.
    However, if your email service provides web access, then use Safari to get there - then you can do whatever management tasks are generally allowed at that site, including adding folders.

  • How do i disable orientations for a specific view in my tab bar project without disabling for the other views?

    How do i disable orientations for a specific view in my tab bar project without disabling for the other views?
    Any suggestions?

    Note that you can also hide the tab bar completely with code in the userChrome.css file.
    Add code to the <b>userChrome.css</b> file below the default @namespace line.
    *http://kb.mozillazine.org/userChrome.css
    <pre><nowiki>@namespace url("http://www.mozilla.org/keymaster/gatekeeper/there.is.only.xul"); /* only needed once */
    #TabsToolbar { display: none !important; }
    </nowiki></pre>
    The customization files userChrome.css (user interface) and userContent.css (websites) are located in the <b>chrome</b> folder in the Firefox profile folder.
    *http://kb.mozillazine.org/Editing_configuration

  • How to view database performance in OEM back 8 hour

    Hello All,
    I have recently installed OEM 11g. Please can I know how to view the performance of the database back 8 hour as I can see the performance for an hour only on the performance page.
    Thanks.

    Yes, you can.
    For instance you can use the ADDM feature (via the Database Homepage --> Adivsor Central --> ADDM --> Run ADDM to analyze past performance
    Checkout:
    Oracle® Enterprise Manager Concepts
    *11g Release 11.1.0.1*
    http://download.oracle.com/docs/cd/E11857_01/em.111/e11982/database_management.htm#i1006971
    Regards
    Rob
    http://oemgc.wordpress.com

  • How do I view multiple images from different projects at the same time?

    Hello
    I've been trying to find the answer in the user manual, but no luck so far.
    I did find how to open 2 projects at once, but I can only see one image at a time in the viewer and I have to keep going back and forth between projects to compare images. (These are scans of old photos and I want to eliminate the ones that are poorer quality, so need to compare numerous images from 2 sets of scans)
    How can I view an image from one project at the same time as an image from another? I know that it can be done in the same project by apple-clicking the second, third etc image, but this doesn't work if the images are from different projects.
    Thank you
    Elizabeth

    Thank you again Tony
    I've now created an album, independent of the projects, and dragged test images into it and it does just the job I needed. Now i just need to keep my brain sorted with which ones are which while i'm working
    Elizabeth

  • How to view baseline and updated project to show progress vs baseline

    I know how to assign a baseline to a project but I cannot figure out how to view both to show my client the progress since the baseline. Does anyone know how to do this? Please HELP.....
    FW

    Baseline management and reporting is a complex subject so I will start with basics not to confuse you.
    Assign the baseline as project baseline.
    Add a bar in gantt chart and select type project baseline, perhaps bar is already there and you need to just select it.
    Add a column Schedule %age complete and that is your baseline %age as of current data date.
    Note:
    Please make sure the baseline used for EV under project settings - calculations is project baseline to get the right Sch. %age.
    Jawad
    Novo Rail, Sydney

  • Project 2013 - entering work hours at a monthly level

    Hi all, 
    Any help with this 'hopefully small' problem will be hugely appreciated. It's not so much a problem, but
    me still being new to Project - sorry! As a summary of what I am working with:
    I have entered a list of tasks (all set to Manually Scheduled).
    I have entered a number of resources into the Resource List. 
    I have also assigned relevant resources to the tasks. 
    Using the Task Usage view, I would now like to begin entering Work hours for the resources assigned to the
    tasks. We are planning at a monthly level, so I know how many hours each resource is expecting to be spending on each task over each month. 
    I have set the Timescale of my Task Usage screen to a monthly scale, thinking that this would allow me to
    enter total hours for each month. As an example, one of the resources assigned to a task is set for 15 hours of Work in April. It all seems to look OK on input. 
    My problem is however, I would like the Start and Finish fields to reflect this, and span over the months
    in which the Task's resources will be doing work. It doesn't seem to pick up the month accurately. Although I have entered the 15 hours in the column labelled April, the Start and Finish dates have come out as 30/04/14 and 30/05/14 respectively. I was hoping
    the Start and Finish times of that row to be 01/04/14 and 30/04/14 respectively, but they are a month out of line, and has show the work to be happening over May, not April. Is there y way I can change this?
    I hope this makes sense as a question? Any help at all would be brilliant. Please do let me know if I've
    missed any detail and you need some more info. I'll also continue looking through the forums to check if this has already been asked. 
    p.s. I tried to upload an annotated image, but my account needs to be verified first. Do I need to do anything to request this? I didn't receive any usual 'verification' links in MS's email on opening this account.
    Thanks very much, 
    ac18

    Hi John, Julie,
    Thank you both very much for the help! Yes good spot, I did post it on both forums (http://www.msofficeforums.com/project/21190-project-2013-entering-work-hours-monthly-level.html) - it's been years since I've used forums of any kind, and it's great to see
    experts being active across multiple sites! 
    I have given both suggestions a try, but unfortunately am still not quite there yet. 
    John, although your tip seems to work OK, I think I was hoping to find a way for the Start and Finish times to automatically span across the Work hours I have entered. If I was to then enter another 5 hours, but this time for March, the Start-Finish dates
    should auto update to be 01/03/14 - 30/04/14. I understand now that this may require me to be on an Automatically Scheduled project? 
    Julie, your screen shot on the msofficeforums.com website is exactly what I am looking to achieve! I would like to enter month-level Work data, and that looks to be exactly that. I did try entering a zero in the month immediately after the last month that
    had hours in it, but Project seemed to simply ignore it, with no visible change to the dates. 
    I have done some further investigating, and there does seem to be something different happening with my Project version (it's Proj Prof 2013). I have access to another computer with Project 2010 installed on it, and this doesn't seem to cause an issue. Note,
    I did need to have set the tasks as Auto Scheduled. 
    Essentially, if I try and exactly replicate Julie's example on both versions with the following steps, I get slightly different results:
    Tasks set to Auto-Scheduled. 
    Set Project Start Date to 01/01/14
    Enter some resources. 
    Switch to Task Usage view. 
    Set the Timescales on the right hand side to: Bottom tier=Months, Middle tier=Quarters. 
    Enter a task. 
    Assign resources to the task. At this point, by default 8 hours worth of work appears for each assigned resource. In 2010, these hours appear in the January 14 column. But on my 2013 laptop however, these hours appear under the December 2013 column. Strange?
    Anyway, in both cases I clear these default hours by entering zeros in their places.
    I now enter 15 hours under April 2014 for one of the resources on the task.
    In 2010, the Start and Finish dates of the assigned resource's row update to 01/04/14 - 30/04/14.
    In 2013 however, the Start and Finish dates update to 30/04/14 - 30/05/14. 
    I have a feeling that this discrepancy is perhaps at the heart of my problem? Is there a setting with the application that I am not making?
    Thanks again, 
    Arjun

  • Different weights (man hours, material, costs) of/within different WBS sections

    Hi there,
    I am using Microsoft Project Standard 2010.
    Within some elements of my schedule I would like to weight by man-hours, within some by material and within some others again by cost.
    Also I would like to manually adjust the the weighting on the highest level of my schedule manually. E.g. WBS 01 20%, WBS 02 30% and so on.
    By now I have only found out about how to weight by "Work"; putting in man-hours and then using the weighted %Work Complete.
    But how about the other above mentioned weightings?
    Thanks in advance!

    hkd66,
    For work type resources the Work field is essentially man-hours and it sounds like you figured that out. For material resources, the metric is defined by the material label and the standard rate per the material label (e.g. "bricks" at $1.00/brick). Weighting
    by cost is something you must "back" into via the quantity. Cost type resources are of course direct cost entries. Is that what you mean by "some others"?
    Now the question comes, what exactly is your intent with regard to adjusting the weight at the highest level? Are you trying to set up the initial plan to achieve a certain man-hour and cost budget, or are you trying to achieve something else?
    Although it may appear that you can "weight" your schedule's man-hours by entering a value in the % Work Complete field at summary level, that is not the intent of that field, nor the best use for it. You will not be able to do a similar thing with the cost
    field. Summary lines are intended for summarizing the data of the subtasks under them, not for rolling data down to subtasks.
    We need to better understand what you are trying to accomplish (i.e. you end goal), before we can give you much guidance.
    John

  • How to find next number range for project definition in tcode CJ20N

    Hai Experts,
          Please help me 'How to find next number range for project definition in tcode "CJ20N". I was trying in function module NUMBER_GET_NEXT. Is it right function module? If its right what input i need to give for this tcode and for the field project definition?
    Note: I searched in forum before posting, but couldn't find the solution.
    Thanks
    Regards,
    Prabu S.

    Hi,
    For project defination internal number is assigned by system.
    When you saves's project then system allocate one number to project defination, you can view it,
    SE11 >>> table  PROJ >> Click on contents >>> execute,
    here you will get your project defination & number is assigned to project defination.
    kapil

  • No scrolling when viewing man pages with Gnome terminal?

    Hi all,
    I have just installed Oracle Solaris 11 on x86. For a long time I've used Solaris 9 on SPARC. I like the new OS, but I'm having a problem viewing man pages with Gnome terminal. When I view a long man page, e.g., "man newfs", I don't get a functional scroll bar on the right hand side of the window. And although the space bar works to advance the page, when I reach the end, it doesn't return to the command prompt. It just beeps, prints "END", and I can only exit by closing the window. Can anyone tell me how to fix this? Suggestions would be much appreciated.
    Many thanks,
    Chris Tidy

    It does sound like you're using "less" instead of more. When you see the "(END)" prompt you can simply type "q" and it will exit back to the command line prompt making it unnecessary to close the window. See the "less" manual page for more detail on the less command. Under Solaris 9 the paging was done with the "more" command. If you set the PAGER environment variiable to "more" the man page will use more and revert to the behavior you'd be used to with Solaris 9. Less erases the text you've already read when you type that final "q" which is a behavior I don't like. I didn't bother to determine if there is a way to fix that with less, I just went back to more. The choice between "more" and "less" is a personal preference.

  • How to view the Users in the Portal Activity Report

    Hello,
    Can anyone tell me how to view the Report of users who have logged in a specific time. For Example I would like to view the users who have logged in between 9.00 am and 9.15 am. Is it possible to view mentioning the country name?
    Please explain me in detail how to view the Report.
    Thnx in Advance
    cheers,
    Murali

    hi,
    You can certainly do it for hourly basis but i am not sure whether it could be done quarter an hour basis. Also The portal nodes within a cluster can be in different time zones, yet the activity data from all nodes are aggregated together and reported together. To enable the reporting of hourly data from different time zones, portal activity reports display hourly data based on the GMT time zone.
    Do see the documentation
    http://help.sap.com/saphelp_nw04/helpdata/en/fb/144120ea5b4e9c9385d493a578d6c9/frameset.htm
    Weblog :Portal SP9: Portal Activity Report
    Regards,
    Ganesh N

  • How to view pdf, xls files generated by using JasperExport

    I am using Weblogic Server 8.1 to deploy my project. I have some pdf, xls files that generated by JasperExport. Code: <br>
    Map parameters = new HashMap(); <br>parameters.put("donvi",DVi); String ConnectionURL ="jdbc:oracle:thin:@localhost:1521:qltb"; <br>Class.forName("oracle.jdbc.driver.OracleDriver"); <br>Connection jdbcConnection = DriverManager.getConnection(ConnectionURL,"qltb","qltb12345");<br> jasperReport = JasperCompileManager.compileReport("C:\\baocao.jrxml"); <br>jasperPrint = JasperFillManager.fillReport(jasperReport,parameters,jdbcConnection);<br> //JasperViewer.viewReport(jasperPrint); <br>JasperExportManager.exportReportToPdfFile(jasperPrint, "report.pdf");<br>
    report.pdf is exported to folder <br> C:\bea\user_projects\domains\cems ( cems is name of domain) . <br> But I dont know how to view this file or write relative path of this file For example : in test.jsp page I write Report 1 But it doesnt work.

    Install IronTrack SQL as described in the following link
    http://www.irongrid.com/documentation/irontracksql/install.html#install_oracle9iAS

  • How do I embed fonts into Captivate projects?

    This question came up in May 2006 but was never really
    answered. I'd like to know how to embed fonts into my Captivate
    projects so that the output looks the same on all computers. While
    the text animations are fine, the Text Caption fields are the ones
    that seem to have fonts that go walkies on other computers. I know
    you can embed fonts in PDFs. Why not in Captivate (unless I'm
    missing something in 2.0).

    First, a tip for the forums: If you use the URL tags, your
    post won't require horizontal scrolling - sorry, but I use Firefox
    and entering a long URL totally blows my ability to smoothly read
    the post ... you can manually add a text link by using the "L" tag
    as shown below (I've put spaces in to avoid this being turned into
    another text link)
    [ L = Your Text]
    http://www.yourdomain.com [ /
    L ]
    Back to your issue, Charinos. I'm glad you did find the URL,
    but that thread and your problem are not even in the same world.
    That thread deals with fonts in text-entry boxes (boxes for
    end-user text-entry), and you are talking about text-captions, an
    entirely different object.
    In fact, if you make changes and save those changes to a
    text-caption, then publish the project, the fonts in your text
    captions will remain stable and are not dependent on the fonts
    installed on the end-viewer's machine. The reason is that when the
    SWF is compiled, the text captions are converted to images and so
    long as the file is viewed as intended in the HTML document - at
    the proper size - the stretching you describe cannot take place.
    I'm not saying you are seeing things, but if my understandings of
    the Captivate machine are correct, what you are saying is happening
    cannot
    be happening. Something else is going on, like a failure to
    save changes, use of non-conforming text-caption boxes with a
    resultant loss of margins, or something.
    Sorry I'm not more help. I can't duplicate what you are
    seeing but I hope someone else can help you out - I may still be
    misunderstanding your issue.

Maybe you are looking for