HU process for GR from Process order

Dear Experts,
How handle Handling unit in process order GR,
Scenario: Processed bulk chemicals are packed in 20 KG bags (numbered bags), each bag contains unique number in packing.
Treaceability is based on the BAG numbers, Quality check for packed FG is carried out, rejections in any one of the bag will be removed and put in bocked stock.
I am thinking to use HU management.
please give me the steps to do this .
Thanks and regards
vinoth

Dear
can u use Class Characteristics by defining those charac wich may cause rejection , by this u can trace as well
if it suit to your scenario

Similar Messages

  • How can we call a task in process definition A from Process definition B

    Hi,
    Is that possible to call a task in process definition A from Process definition B?
    Thanks.

    Sure, as long as you can come up with the correct query to lookup the task key for the task you want to run.
    provIntf.addProcessTaskInstance(taskKey, processInstanceKey);
    -Kevin

  • Set new Required Field for MD14 and MD15 for conver from Planned order to P

    Dear all,
    I would like to set new required field (Purchasing Organization)  in T-CODE MD14 and MD15 for convert from Planned Order to PR. What's should I do?
    Please help, I 'm new for MRP.
    Best Regards,
    Kate

    Hi Kate,
    You are not on the right track; MD14 and 15 will choose the PLANNED ORDER population for the conversion. In planned orders there's NO PURCHASING ORGANIZATION DATA (normally)!
    So even if you managed to put the field on the screen, it will not do anything that makes sense.

  • Batch Processing for Workitem - Result Processing

    Hi All,
    I'm having problem in a workflow step.
    When the workflow step is execuetd i'm getting a step log as:
    Batch Processing for Workitem     Dialog work item created          14.05.2009 09:09:59                                   
    user01                    Execution started               18.05.2009 05:57:18                                   
    user01                    Work Item Processing Complete     18.05.2009 06:04:46 Functionality for Hi 000600113419 
    user01                    Terminating event received          18.05.2009 06:04:46 Functionality for Hi 000600113419 
    Batch Processing for Workitem     Result Processing               18.05.2009 06:04:46
    Can any one please let me know what code/program is executed in *Result Processing *

    I read this in the documentation:
    If necessary, the G/L account can also be set so that the tax code is not a required entry when posting transactions not relevant to tax
    How would I set this?? Or where is it done?

  • I know my Apple ID (an email and pass code) good,but really I forgot answers the security questions (2-questions) which verify my identity.I can not complete any purchase process for iTunes from another device for example (my personal computer)

    Hi,
    I know my Apple ID ( an email and pass code ) good, really
    I forgot answers the security questions,which verify my identity,
    So it is difficult to complete the purchase process for iTunes Store
    On my PC-FUJI'S,I use Windows Vista home premium as Operating
    System,so reset my secure questions and the answers of course,
    If you please.
    With my respect,
    A signature,
    Mahmoud Fouad El Deeb.

    Hello Mahmoud,
    The steps in the articles below will guide you in setting up your rescue email address and resetting your security questions:
    Rescue email address and how to reset Apple ID security questions
    http://support.apple.com/kb/HT5312
    Apple ID: All about Apple ID security questions
    http://support.apple.com/kb/HT5665
    If you continue to have issues, please contact our Account Security Team as outlined in this article:
    Apple ID: Contacting Apple for help with Apple ID account security
    http://support.apple.com/kb/HT5699
    Thank you for using Apple Support Communities.
    Best,
    Sheila M.

  • Blocked for payment from sales order

    Hi!
    Do you know to do to the FI document will come blocked from sales order?
    For example, I did a sale order with a client x. The payment terms of this client is setting to block the payment.
    So, when I did a sales order, and do all SD process, after billing it, on FBL5N the client document isn't blocked for payment.
    Do you know any way to block it from a sales order??
    Regards,
    Danielle.

    hai,
    A is also fine. If the payment terms is applicable for both customer as well as vendor, then the system will block for payment and in FBL5N also system will show with block indicator A.  Or
    Try to block in same FBL5N, select particular document, goto environment in menupath select change document and block it and then save. Again run FBL5N check the block indicator.
    There is no additional configuration is required apart from my first reply.
    govind.
    Message was edited by:
            govindaraj s

  • Restriction for items from Purchase Order based on Sale Order

    Hi !
           We create PO directly from Sale Order ( by ticking Option under Logistic tab, 'Purchase Order') for customer C01 (for eg).
    From the PO created, we post GRPO.
    Now our need is,
    Assume if 10 Qty is been ordered in such a way and been received (GRPO posted). it 'll add on to the stock account i.e will increase stock qty at our whse.
    is it possible to restrict these 10 qty of item from being sold to any other Customer other than whom hav ordered i.e if we create sale order for C02 the SBO should not take the items received from PO created based on Sales Order created for C01?
    Meera.

    Meera,
    Which version of SBO are you using 2005 or 2007?
    I don't think Serial numbers can help in this scenario.  There is no hard allocation or blocking possible using Serial numbers.
    This is the Work around I am thinking about.
    Set the items to be Batch Managed - On Every Transaction
    When performing Goods Receipt, enter the Sales Order Number as the Batch Number
    When creating the delivery, using SBO_SP_TransactionNotification we can easily check the Batch of the Item being selected and verify it with the BaseRef of Delivery lines to match with Sales Order number.
    If the numbers don't match we can warn user with message, "The items batch reserved for Sales Order xyz"
    Even if you make a mistake when entering the batch number same as Sales Order number when doing a goods receipt. It can still be traced and blocked during delivery.
    Hint: The Batch table records the Goods Receipt transaction along with the BaseDocument number, Base Ref, etc
    If you decide to go this route, I could help you further.
    Let me know
    Suda

  • Workflow for Delivery from Sales Order Creation

    Hi All,
    I am new to SAP workflow.  There is a requirement to create a delivery through VL04 (in background) based on the Shipping Point of the approved Sales Order.  How can this be done?  I am assuming that I should be using BUS2032 for the Sales Order and BUS2015 for the Delivery. 
    The first step should be to send an email that gives the user two options (Approve and Reject) once a Sales Order is saved.  However, I am unsure of how to pass parameters to VL04 and submit the program.
    For example, if the order is approved the Shipping Point will be passed to VL04 and run in background to create the delivery.  How can you determine the Shipping Point from BUS2032?  I did not see any attribute for this within the BOR.  Also, how do you create the step to submit that Shipping Point to transaction VL04 in background? 
    Any help you can give would be greatly appreciated.  Thanks.
    John

    Hello,
    You could try using a BDC with VL04 but first preference would be to see if there are any BAPI functions (search for BAPI) that can do this.
    If BUS2032 doesn't have an attribute that you want (eg shipping point) then sub-delegate to ZBUS2032 and add the attribute, it's straightforward. You just have to know how to determine the value programmatically.
    regards
    Rick Bakker
    hanabi technology

  • Business process for Service related Sales Order

    Dear Sir,
    We have a business scenarion as per following:
    A Customer has given an Order for providing a Service related to repairing of a Machine at customer site .  To repair the machine , we have to send our engineer at customer site and also need to engage an outside expert .  The expense related to travelling of our engineer and engaging of outside expert (by a route of service purchase order)  also need to be booked against the customer service order . Finally a Service Invoice will be raised to customer .  We also need to know the expense/income against the rendered service  (in reference of customer service order) .
    We are not aware of the steps to be followed as per the SAP recommended practices for such a scenarion  and request SAP experts to kindly guide us  about the  steps to be followed .
    We will be highly greatful to you for the kind help pl .
    With thanks and Regards
    Sonia Agarwal

    Oh... It would be a long story.. I m trying to explain and hope it help..
    I m not sure if you can change configuration or not.. If you can, please try below way..
    1, Check/config requirement class: spro->SD->Basic function->ATP and transfer requirement->Define requirement classes.. You can use 039 or create your own one with reference to 039.. Please kindly take note that all the CO parameter should be correctly set.. i.e. account assignment, settlement profile, RA key....
    2, Check/config requirement type: spro->SD->Basic function->ATP and transfer requirement->Define requirement types.. You can use 'SE' which is linked to '039' or you can create your own one linked to the requirement class defined by you..
    3, Make sure your sales order item can determine this requirement type.. For this purpose, you have 2 ways..
       i.. Determine by sales order item category..spro->SD->Basic function->ATP and transfer requirement->Determination Of Requirement Types Using Transaction.. Under this configration, you can establish the link between sales order item category and requirement type..
       ii.. Or you can determine the requirement type by material master.. spro->Production->Production planning->Demand management->Planned Independent Requirement->Planning Strategy->Define Strategy & Define Strategy group.. You can create a new strategy by assigning the requirement type and then assign your strategy to a new strategy group and finally maintain the strategy group into your service material MRP3 view..
    Roughly, after above configurations, the service sales process can work... The front-end opreation steps might include..
    1, Create a sales order..
    2, Issue material consumption.. MIGO/MB1A via movement type 231..
    3, FI posting or CO cost assignment..
    4, External service purchasing (Please take note that you need input a correct account assignment in your purchasing order)
    5, Billing creation.
    6, Result analysis (tcode:KKA3, a step in month end process)
    7, Sales order settlement (tcode:VA88, a step in month end process)

  • Remove Reason For Rejection From Sales Order Using BAPI_SALESORDER_CHANGE

    Hi
    I have a sales order and would like to remove the rejection reason.
    I am trying to use BAPI_SALESORDER_CHANGE with the following code:
    (0000xxxxxxx  is my material #. i just removed the actual #).
    MOVE: '0000050106' TO SALESDOCUMENT.
    MOVE: 'U' TO T_HEADER_INX-UPDATEFLAG.
    MOVE:                        30 to t_order_item_in-ITM_NUMBER,
                                      ' ' to t_order_item_in-REASON_REJ,
          '0000000000xxxxxxxx' to t_order_item_in-material.
    APPEND t_order_item_in.
    MOVE: 'U' TO t_order_item_inx-updateflag.
    MOVE: 'X' to t_order_item_inx-REASON_REJ,
               'X' TO t_order_item_inx-material.
    CALL FUNCTION 'BAPI_SALESORDER_CHANGE'
      EXPORTING
        salesdocument              = SALESDOCUMENT
        order_header_inx           = T_HEADER_INX
      tables
        RETURN                     = T_RETURN
        ORDER_ITEM_IN              = T_ORDER_ITEM_IN
        ORDER_ITEM_INX             = T_ORDER_ITEM_INX
    WAIT UP TO 5 SECONDS.
    CALL FUNCTION 'BAPI_TRANSACTION_COMMIT'
    EXPORTING
      WAIT          = 'X'
    IMPORTING
       RETURN        = t_return
    WAIT UP TO 5 SECONDS.
    can anybody help?
    the BAPI returns success messages saying the item was processed successfully but the reason code is still there.
    However, if i pass in any other reason code like 02 or 06, it works!.
    thanks.

    Thanks for your help. =)
    I also realized that I forgot to add the SO Item # into the T_ORDER_ITEM_INX-ITM_NUMBER fields.
    But now it works.

  • New TCode for retention from purchase order

    Hi
    I am in SAP Ecc6.0 with EHP3. There is a new TCode in SAP for downpayment - ME2DP. For using this tCode, we have to give downpayment category in payment processing tab in purchase order.
    Then we excute ME2DP. Similarly there is a Retention field in payment processing tab in purchase order. But i want to know the tCode where i can execute retention (as there is ME2DP for downpayment)
    Edited by: Deepak Agrawal on May 12, 2010 3:18 PM

    Meera,
    Which version of SBO are you using 2005 or 2007?
    I don't think Serial numbers can help in this scenario.  There is no hard allocation or blocking possible using Serial numbers.
    This is the Work around I am thinking about.
    Set the items to be Batch Managed - On Every Transaction
    When performing Goods Receipt, enter the Sales Order Number as the Batch Number
    When creating the delivery, using SBO_SP_TransactionNotification we can easily check the Batch of the Item being selected and verify it with the BaseRef of Delivery lines to match with Sales Order number.
    If the numbers don't match we can warn user with message, "The items batch reserved for Sales Order xyz"
    Even if you make a mistake when entering the batch number same as Sales Order number when doing a goods receipt. It can still be traced and blocked during delivery.
    Hint: The Batch table records the Goods Receipt transaction along with the BaseDocument number, Base Ref, etc
    If you decide to go this route, I could help you further.
    Let me know
    Suda

  • Automatic Transfer Order for GR from External vendor and from Process Order

    Hi Expert
    We need to implement the logic for automatic transfer order,
    the Idea when we Receive the Goods from Vendor and while posting goods via Migo we want that the system create automatically the TO.
    the same approach to be implemented for GR from Process Order we need that the system create TO directly to the right Bin
    Your support is higly recommanded
    Olfa

    Many thanks for your support
    I made what you illustrated in your previous message for the Mvt type 501:
    There is a pop up screen which displayed asking me to create TO for Material Document
    Please find attached the related screens
    And please note that the Material Master was updated accordingly
    Please note
    Please correct me if I made a wrong step
    Regards

  • Sales Order Processing for "Services"

    Dear SD Gurus,
    Our Client is providing some services to our regular customers and they want to follow sales process for services.
    Process should be -
    Create Sales Order, Then create Billing document w.r.t. Sales Order. (delivery is not required)
    Kindly help
    Edited by: sagar g on Jul 28, 2009 9:11 AM

    Kindly do the following Settings :-
    1. Create Sales Order Type in VOV8 and maintain Order Related Billing only with Billing Type as F1.
    2. Use item Category as TAD
    3. Assign Item category in VOV4 with Sales Order Type + LEIS = TAD
    4. Maintain the Same Item Category group in Material Master.
    Also maintain the Copy Control Settings between Sales Order type & Billing Type.
    Best Regards,
    Ankur
    Edited by: Ankur Agrawal on Jul 28, 2009 1:08 PM

  • Down payment process for Poland, new business process or not ?

    Hello,
    I'm a little bit confused about implementation down payment process for Poland.
    The OSS-notes 818079 and 1007635 describe a solution for this.
    How do I have to implement the correct down payment process for Poland ? Do I have to create an extra business process with new sales order type, new billing type, separate calculation procedure, new output type and so on ?
    Or is it possible to use existing business processes in sales and distribution for down payment processes ?
    Thanks in advance
    Holger

    hi,
    Check the process for down payment processing
    The following Customizing settings have to be made for down payment processing:
    Settings for the billing plan - To activate the billing plan function, maintain the materials, for which you wish to process down payments, with item category group 0005 (milestone billing). This gives the item type TAO via item type determination. The item type TAO calls up the billing plan function.
    You need to implement the following activities in the billing plan for down payments:
    Maintain deadline category - This determines the billing rule (percentage or value down payment) for the down payment request. The system assigns billing type FAZ (payment request) defined in the standard system with billing category P. (For the billing type FAZ there is the cancellation billing document type FAS in the standard system).
    Maintain the deadline proposal - Use the down payments that are due for the proposed deadlines.
    Maintaining a Pricing Procedure with the Condition Type AZWR:
    In the standard system the condition type AZWR is delivered for the down payment value already provided but which has not yet been calculated. You must include this condition type in the relevant pricing procedure before output tax.
    Enter condition 2 (item with pricing) and the calculation formula 48 (down payment clearing value must not be bigger than the item value) for the condition type AZWR.
    Before the condition AZWR you can create a subtotal with the base value calculation formula 2 (net value). If the condition AZWR is changed manually, you can get information on the original system proposal from the subtotal.
    Maintain the printing indicator - The pricing procedure can not be marked as a transaction-specific pricing procedure (field Spec.proc.) The condition type AZWR has the calculation type B (fixed amount) and the condition category E (down payment request / clearing).
    Maintaining the Billing Document - In the standard system there is the billing type FAZ (down payment request) and the billing type FAS for canceling . The down payment is controlled using the billing category P of the billing type. A billing type becomes a down payment request when the billing category P is assigned. You have to maintain blocking reason 02 (complete confirmation missing) for the billing documents and assign it to billing type FAZ.
    Copying control - Copying requirement 20 must be entered in copying control at item level for the down payment request. In the standard system the order type TA for copying control is set up according to the billing type FAZ for the item category TAO.
    Copying requirement 23 must be entered in copying control at item level for down payment clearing. In the standard system the order type TA for copying control is set up according to the billing type F2 for the item category TAO.
    Financial Accounting settings - A prerequisite for down payment processing is that the account is assigned to the underlying sales document. To do this, change the field status settings in Customizing as follows:
    Set reconciliation accounts (transaction OBXR) - For the `received down payments' and `down payment requests' from
    the G/L accounts you have selected, you should assign the field status definition G031.
    Maintain accounting configuration (transaction OBXB) - For the down payments (posting key ANZ in the standard system) and the output tax clearing (posting key MVA in the standard system), you must maintain the posting key.
    You must also carry out a G/L account number assignment for the tax account.
    Maintain the posting key (transaction OB41) - For posting key 19, set the sales order as an optional field !!!
    Maintain the field status definition (transaction OB14) - For field status variant 0001, field status group G031, set the
    sales order as an optional field !!!
    Assign the company code to the field status variants (transaction OBC5)
    chandu

  • Looking to stop sending IDOC if output has been already processed for PO

    Hi,
    I am using the Message type ORDERS to trigger the IDOC for the purchase order based on the output type. But my requirment is that if the output is already processed for a  specfic purchase order then it should not allow to process the output again for that purchase order. So i am writing a logic in user exit that if NAST table entry is already exist and proccessed for the output type for specfic purchase order then i want to stop sending the idoc.  As NAST entries doesn't contains any segment data due to that i am unable to set the ALE filter in BD64 transtaction .So could you please anyone give me any suggestion how can i stop sending the IDOC if output has been already proceessed  so that it will helpful for me.
    Thanks in advance for your help .
    Regards,
    Kiran

    >
    divyesh vasani wrote:
    > Hi Shabarish,
    > Thanks for your reply.
    > I was working on solution proposed by  NALLAM GUNA RANJAN.
    > But as you and Jai mentioned, but I think Maintain Order At Runtime option is available with Interface determination not with Receiver determination.
    > In my case, From same Input file(from which Text file is generated) mail report has to be generated but after creation of text file only.
    >
    > Thanks
    > Best Regards,
    > Divyesh
    1. In case you intend to use maintain runtime then use a single receiver and add multiple inbound interfaces. This is the easiest solution
    2. use a BPM. use send steps in serial. First send step should be File (request for acknowledgment) and then followed by send step for mail.
    Do not go for scripts etc unless no other solution persists since maintenance and support in the future will always be an issue.
    let me know if u still have issues.