List of changes in the notification execution dates

Hi,
I want to generate a list of changes in the execution dates of the notification in t-code QM02. Table VIQMEL.
I want to know how many times the field 'required end date' has been changed in the 'execution' details of administration tab of the notification.
Please help....
Regards
Vrish

@ Priyanka & Sumit,
I have tried these standard options, but the changes in the date, viz how many times the notification was closed (after reopening) is not getting recorded here. It only shows the recent change date. I want a list of changes edited in that field.
For e.g.
Notification was closed on 01.08.2010,
but then again reopened on 03.09.2010, closed on 14.09.2010,
again reopened on 19.12.2010  & closed on 05.01.2011,
Then in this case I should get a list that the changes were done on 01.08.2010, 14.09.2010 & 05.01.2011.
Is it possible WITHOUT ABAP help?
Please reply,
Thanks in advance,
Regards
Vrish

Similar Messages

  • I performed a time machine backup without plugging my labtop into a power source. My computer died and all the settings were changed, ie the clock and date were changed back to 2001. So I tried to restore my computer using a previous time machine backup.

    I performed a time machine backup without plugging my labtop into a power source. My computer died and all the settings were changed, ie the clock and date were changed back to 2001. So I tried to restore my computer using a previous time machine backup. (which I now know was wrong). However, when time machine tried to restore it said there was not enough room to do a backup. It seems that it did a half backup because some essential  files such as system profiler are now missing. Can I undo this restore...? What can I do to fix this

    You need to do a full system restore, per Time Machine - Frequently Asked Question #14.
    If that sends a message, please note the exact wording.

  • How do I disable the notification "Transfer data to SD card - Internal storage is 75% full"?

    How do I disable the notification "Transfer data to SD card - Internal storage is 75% full"? after update to Lollipop

    Hi @rainbowgoblin I should use the File Commander app, you could read about it here:
    https://play.google.com/store/apps/details?id=com.mobisystems.fileman&hl=es_419 You can also set with the Android adb, to store apps in the SD Card intead of the internal memory. You should have ADB installed, the SDK up to date, and the USB debugging turned on from your device on the Developer Options.
    Then plug your Xperia to your computer and from a command prompt (you'll probably have to be in the folder where adb.exe is, most likely something like C:\Program Files (x86)\Android\android-sdk\platform-tools\adb.exe) run this command: adb shell pm setInstallLocation 2 (where 0 represents the internal storage and 2 represents the SD Card storage). To clear warnings about the available memory space on your device you can run: adb shell pm hide com.sonymobile.storagechecker I hope can be useful. Best Regards,

  • Function Module to find the Last Execution date of Back ground Job

    Hi,
    Is there any function module to find the <b>last execution date of back ground job</b>.
    So that I can transfer the data from SAP to Legacy system based on the document creation date should be in between last execution date and current date.
    thanks in advance.
    Eswar.

    Don't know of a function module, but you should be able to use the information in table TBTCO to get the last start date and time of the job you are interested in.

  • Has anyone else had issues with changing how the time and date look on the status menu in Mavericks?

    I'm trying to make it so the year displays, but haven't been able to figure out how to change that. I have the Day of the Week, Month, Day and Time only and I haven't been able to figure out how to do that in the Date & Time or the Language & Region Settings.

    There is no option in System Preferences. However, it may be possible to set it with a "defaults write" command.
    This page shows how to set the time and date format in the Terminal, but doesn't show whether you can add the year.
    http://apple.stackexchange.com/questions/75116/i-want-to-change-clock-from-12h-t o-24h-mode-via-terminal
    If you can find a description of Apple's date format code that includes the year, then it may be possible. Or not.
    I'm guessing Apple thinks only Time Travellers need to ask what year it is...

  • Table of list status changes of the production orders

    Dear.
    In which table the system store the list status changes of every production order ?
    Thanks.

    Hi,
    First go to CAUFV table input the production order get the object number
    Input this object number in JEST table and get the system status
    Input the system status in TJ02T table ,u will get the production order status

  • Changes to the ESS Personal Data iview

    Hi There
    With regard to the 'Personal Data' iview on ESS.
    I have a scenario where fields marked as REQUIRED are DISABLED.
    How do i enable them ?
    When trying to change the field configuration by previewing the Personal Data iview and then doing 'control + right click' on the relevant disabled field the changes DO NOT take effect.
    When changing an enabled field the change take effect.
    Any ideas as to what may be causing this ?
    Any advice with regard to resolving this issue will be appreciated.

    Hi,
    The ESS/MSS fields can be enabled/disabled from spro settings at the backend.
    Please check with HR consultant to see the status of that field.
    The pathmay be:
    >Personnel Management > personnel administration > own data > personal data
    Thanks
    Muthukumar

  • Map listener doesn't send the notification properly (data loss)

    I have a cache cluster of 60 storage nodes, it contains around 7 GB of data.
    I have attached a Map Listener to one of a cache in the cache cluster.
    Sometimes the update event received by the listener has both the New value (mapEvent.getNewValue()) and old value (mapEvent.getOldValue()) is NULL.
    I am expecting none of them to be Null.
    This happen infrequently and rarely. But the data is very critical so I can't afford data loss.
    Note : The data that was updated is present in the cache, its only the listener map event says its NULL.
    Can anyone suggest what could go wrong ? Why I am getting NULL value ?

    Hi,
    a listener is lite, if you used one of the addMapListener methods having the boolean flag fLite as third parameter to register it, and you passed true to that parameter.
    In all other cases it is a non-lite (heavy) listener which should always get the old and new values.
    You should use a lite listener if you are just interested on which entries changed, but not on the changed values itself. If you need the old and new values, then you should use a heavy listener. If your cached values are large and you want to spare with the amount of traffic, then starting with 3.4 you can use a MapEventTransformer to transmit only the relevant data from the old and new values and not the entire values.
    Btw, which version of Coherence do you use?
    Best regards,
    Robert

  • Can I speak with someone about making changes to the Family Base Data usage limit?

    Duplicate post - please visit:
    https://community.verizonwireless.com/thread/813039
    Message was edited by: Admin Moderator

    2Cool4School,
    The fundamental business practice for a telecommunication vender is to recognize and acknowledge system related errors. In this case, Verizon is liabile for systems errors that disadvantages it customers. After speaking with several Verizon employees, including supervisors, the systematic flaw inherent with their web based services and its possible error ratio has not been acknowledged. Furthermore, nothing is absolute and it is possible that this error was not cause due to any fault of my own. Thus, Verizon should understand their accountability in the matter. I guarantee that Ivan Seidenberg is interested in learning about this matter which could turn into a potential turn class-action lawsuit.
    Nigel
    << Comments edited to remove personal attacks and provocation >>
    Message was edited by: Verizon Moderator

  • Layout changes removes the data

    HI,
    We copied a standard program RIAUFK20, the program shows the ALV output . We changed only the fieldcatalog. The problem is when the program shows the output first time it shows the correct data what we added to the standard one. When user changes the layout and the screen refreshes it wipes out the data that we added to the report. How can it be prevented from being removed?
    Thanks in advance

    Sanjane:
    You will also need to modify the layout sets saved for that report; the existing layouts will not take into account your changes to the field catalog & data.
    If using ALV grid (function group SLVC_FULLSCREEN) have a look at function modules REUSE_ALV_GRID_LAYOUT_INFO_GET & REUSE_ALV_GRID_LAYOUT_INFO_SET. If using ALV list (function group SALV) have a look at function modules REUSE_ALV_LIST_LAYOUT_INFO_GET & REUSE_ALV_LIST_LAYOUT_INFO_SET. For all of these function modules, click on "Function Module Documentation" button to see the on-line documentation. You can also find documentation on help.sap.com.
    Regards,
    D.

  • Sending the Notification Data to Webmail ID.

    please help me.......
    My requirement is I want to send the Information to other user
    ok
    i can send informtaion through the SAP office mail if the user having SAP access
    But some of the user they Do not have the SAP user access.
    for this i want to inform SAme (some of the Notification information).

    Dear,
    The interface between the R/3 functions and the SAP Business Workflow is realized using object technology. In this workflow scenario, the system processes the following objects:
    Objects     What You Should Know:
    Task group TG20000015     The task group contains all the workflow objects, which belong to the workflow scenarios for maintenance notifications.
    Business object BUS2038
    (maintenance notification)     A maintenance notification corresponds to business object type BUS2038. A maintenance notification is identified by the notification number (key field).
    You can find the attributes, methods and events for business object BUS2038 in the Business Object Repository of the R/3 System.
    Standard tasks:
    •     TS20000545
    (process new notification)
    •     TS20000544
    (notification is processed)
    •     TS20000546
    (complete notification)     These are single-step tasks, which refer to an object method. This task is assigned to the people or departments that are authorized to process the object.
    Workflow template WS20000317     This template contains the definitions of the workflow task for this workflow scenario. You can use this workflow template to notify the people responsible that a maintenance notification has been created. The triggering events for this workflow template are CREATED and INPROCESSAGAIN.
    Standard role AC00000171     This is the standard role for maintenance notifications.
    The role resolution (defined in the standard role definition) is used to determine who is responsible for the processing of a maintenance notification.
      Process for Workflow Template WS20000317 
    Purpose
    The workflow template for this process is started when you create a new maintenance notification.
    Process Flow
    1.     The system triggers one of the following events for business object BUS2038 (maintenance notification):
    o     CREATED (maintenance notification created)
    o     INPROCESSAGAIN (maintenance notification in process again)
    2.     The triggering event starts the workflow template WS2000317 and the linked process as described in the following graphic.
    The standard tasks in this process are valid from Release 4.6.
      Preparation and Customizing (PM-WOC-MN) 
    Use
    The application-specific Customizing settings, which you must make to process this workflow template, are described here.
    Prerequisites
    All the general Customizing settings, which are required for the SAP Business Workflow component to be used, have been made.
    Activities
    Make the following settings in Customizing:
    1.     Set up the organizational structure and thereby determine your organizational units:
    Basis &#61614; Business Management &#61614; SAP Business Workflow &#61614; Edit Organizational Structure
    2.     Assign the organizational units to the standard tasks:
    Plant Maintenance and Customer Service &#61614; Maintenance and Service Processing &#61614; Notifications &#61614; Set Workflow for Maintenance Notifications &#61614; Assign Agents to Tasks
    3.     Activate the link between triggering event (CREATED, INPROCESSAGAIN) and workflow template WS20000317:
    Plant Maintenance and Customer Service &#61614; Maintenance and Service Processing &#61614; Notifications &#61614; Set Workflow for Maintenance Notifications &#61614; Activate Event Linkage
    For step three, make sure that you activate the event linkage for the workflow template and not for the standard task.
    For more information, see the Implementation Guide.
      Operation and Link to Application Functions (PM-WOC-MN) 
    Use
    This workflow is used to inform the people or departments responsible automatically that a series of tasks must be executed in the following order:
    1.     Processing of a newly created maintenance notification (notification status Outstanding)
    2.     Processing of a maintenance notification with outstanding tasks (notification status In process)
    3.     Completion of a maintenance notification (status of all tasks Completed)
    The person(s) or department(s) responsible receive a mail (work item) in their inbox informing them of the tasks to be performed.
    Activities
    System Activities
    If a maintenance notification is created or put in process again, then the SAP Business Workflow automatically ensures that:
    1.     The workflow-triggering event CREATED or INPROCESSAGAIN is generated
    2.     The workflow template WS20000317 is started
    3.     A work item is sent to the work center for the person(s) or department(s) responsible
    User Activities
    As the person responsible for a work item, you have the following options:
    Options     What You Should Know:
    Processing a work item as a workflow     To see the work item, choose Office &#61614; Inbox. You have the following processing options:
    •     You can process the work item by double clicking on it. The transaction for changing a maintenance notification appears.
    •     You can call up another screen for the work item, to obtain an overview of outstanding and completed tasks.
    •     You can set a work item for resubmission as a reminder to process it later.
    •     You can navigate from the maintenance notification to the workflow log, to define who has performed which activities.
    •     You can receive a work item using another mail system client (for example, Lotus Notes™ or MS Outlook™).
    Processing a maintenance notification manually using a worklist     If you process a maintenance notification manually (outside of the workflow), all the changes to the notification are also considered in the workflow process.

  • Changing To New AT&T Data Plan, Breaks Voice Mail

    Sorry, but I'm posting this in several iPhone Hardware Discussions, since I think it applies to all versions of iPhones.
    I'm also sorry if this has been posted before, but I'm not looking for help or answers, I'm providing them.
    I have been on the $30 per month unlimited data plan with AT&T. Today I decided to change to one of the lower cost, lower monthly data rate plans. I called up AT&T and they made the change.
    What I didn't realize is that making this change broke my voice mail. Well, more specifically, it broke the voice mail on all 5 phones in our Family Plan.
    By breaking voice mail I mean that people can no longer leave you voice mail messages. If they call you, they will get the standard message that this person does not have a voice mail box and you cannot leave them a message.
    Unfortunately, you don't realize it's broke. Since no one can leave you a voice mail, you don't get any voice mail notifications. AT&T doesn't send you a message stating that they just broke your voice mail. Your voice mail is broke and you don't know it.
    It was my wife who figured it out. She had several missed call notifications, but no voice mail notifications, which seemed odd. When she clicked on the voice mail icon, she was prompted to Set Up Your Voice Mail. There was no list of her existing voice mail messages. Just a button to click to start the set up process. Which she did. She was asked to enter her PIN and record an outgoing message, even though she had done this the first time she set up her voice mail. She entered both her PIN and outgoing prompt. But when she clicked Save she got an error message stating that she could not set up voice mail. Her voice mail needed to be set up, but it wouldn't let her. There was no suggestion in the prompt telling her what to do or why it was suddenly broken.
    So, I called AT&T. The person I spoke said I needed to power down the phone, which I did. After powering the phone back up, voice mail was still broke. I was then transferred to AT&T tech support. That person told me power down the phone. Which I did, but with some skepticism. After powering the phone back up I was told to go back into voice mail, which was still asking me to set up my voice mail. I followed the prompts and entered my PIN and recorded my greeting. This time it worked. Not only did I get voice working again, but I could see all the old voice mails I had. Unfortunately, I cannot get any voice mail messages during the several hours it was broken because none could be recorded.
    Technical support person did fix the problem. However, I had to contact all family members and we had to go through this same procedure (power off, wait, power on, re-enter a new PIN and greeting) for each and every phone. This took somewhere close to an hour of my time.
    The AT&T technical support person explained to me that since I changed my data plan (from unlimited to 200 MB) new "configuration" data needed to be sent to the phone. To get this data to your phone, you have to turn the phone off so they can send the data. Then you have to renter all your voice mail data.
    Incredible.
    So, as I said, I'm not looking for help or answers. But I thought posting what I went through might be helpful to anyone else who might change their data plan.
    Changing data plans = Broken voice mail .... Which requires a long phone call to technical support and reentering your voice mail data.
    Sheesh.

    I've been a cell phone user since the early days of analog cellular. Back in the days of brick phones, of which I was a user.
    I've been a customer of of Cellular One, Ameritech, Verizon, T Mobile, Cingular and AT&T.
    I've never experienced loosing my voice mail as I did today.
    I considered my voice mail broken since I could not access my visual voice mail on my phone, I could not reset my voice mail on my phone (following the prompts on my phone) and no one could leave me a voice mail message if they called me. I called AT&T customer support and they could not get my voice mail working. I'm not sure what more could be broken, but I would classify my voice mail as broken.
    You may find it acceptable to have your voice mail broken (or perhaps cut off) if you change your data plan, but I don't think that's acceptable.
    I don't see how I made a major change to my account. I didn't make any changes to the types of data I can send or receive. The only change I made was to opt for a lower cost plan that delivers all the same data. That change resulted in all 5 members of my family plan to loose their voice mail.
    You may be correct that all this needed was for it to be reset. But, I can't reset it. The customer service person could not reset it. It took the tech support person to be able to reset it. All of which was about an hour on the phone.
    I don't think this experience should be typical. Maybe it isn't. Maybe for some strange reason, in my circumstance something more went wrong. But, that's not what AT&T told me. They told me what I experienced is typical.
    So, I thought I would post this for people that might experience this issue, or think about changing their data plan so that they would know what to do.
    But, perhaps I was wrong in using this Discussion site to post what I thought might be helpful.
    I'm sorry. I will (as I told a previous poster) delete this post. As soon I as I figure out how.

  • Program execution date record or log

    Hi:
      We've been requested by Development team, to discover if there is any report or program or log that trace the date and/or time that a program has been executed.
      I guess that there is not exactly a report like these, but if anyone can give us an idea of how to get these information, we will apprecciate it.
              Thanks a lot, abrahamdelgadov

    Abraham,
    Certain information pertaining to your requirement are available in Table REPOSRC.
    Try REPOSRC in SE11.
    Other way is
    Check the system log. Use the transaction ST03 and click on Performance database (Push button). Hit the target system and select period (you want to analyse ...this is system log and you may not be able to read if the last execution date of the transaction is more than 90 days..not sure how it is configured in your system) and click on "Transaction Profile".
    This holds the complete list of Programs / transaction codes executed during last three months. Only painful thing is, we need to browse the list to nail down to the requirement.
    Vinodh Balakrishnan

  • How to track the Last Execution of a Custom Program

    Hi all,
    I want to know the last execution date of a Cutom Z program. Kindly tell me as where do we see the same. Is there any table where this is being saved.

    Hello Nikesh,
    EXIT_SAPLS38E_001 is related to the user exits for the ABAP editor (Please read the documentation for details)
    EXIT_SAPLSABE_010 is triggered everytime the report is started, i mean before INITIALIZATION (i laymans terms before selection-screen is displayed).
    Please have a look @ [How to find First Program run in the Current Month in Foreground?|How to find First Program run in the Current Month in Foreground?]. You can very well implement this methodology as well
    BR,
    Suhas
    Edited by: Suhas Saha on Jan 15, 2010 2:11 PM

  • Does the inbound delivery date get updated in the Purchase Order?

    Dear Experts,
    Here is the use case, The original delivery date in the purchase order is 01.11.2011. Accordingly, the supplier sends an ASN to my client against the PO with the same delivery date. However, now, store keeper of my client wants to receive the stock on 03.11.2011.
    1) Can the store keeper/ goods recipient change the delivery date in the corresponding inbound delivery document to 03.11.2011?
    2) Will the change of the intended delivery date be notified back to the supplier who has triggered the ASN?
    3) Will the new delivery date be updated back in the purchase order?
    Point 3 is particularly important for the client from vendor evaluation point of view as any delay from the client side should not affect the vendor performance for ontime delivery.
    Thanks in advance,
    Ranjan
    Ranjan Sutradhar

    for point 2 not the dates wont be sent back to supplier untill unless you have any logic writen for that and if there is a Interface designed for it and I dont there will be any since ASN is sent from Vendor and if you are changing the dates in ASN .
    for point 3 no its not going to change the delivery date in PO at item level but at the item detial level in PO history tab the scheduled date and delivery date as per ASN will be mentioned
    its better you run the case in system and check it....this wont take much time

Maybe you are looking for

  • [SOLVED]How to add multiple gateways in Arch

    Hi, can someone please advise how to add multiple gateway address for multiple interfaces. In my case I have two wired LAN cards. I use Arch network daemon to manage my NIC's. I know in Gentoo it could be done through : 'gateway_ethX=( "default gw xx

  • How to disable search help for material key?

    Hi Expert, I have a input field of matarial number in the screen, and the search help is always shown with the field although I do not want it. I want the customer to enter the material number manually without using the search help. What should I do

  • Bootvar and boot command

    Hi all,  I have recently upgrade our Failover Active/Standby ASA software. Everything works flawlessly. Except I have the following question regarding the boot and bootvar command.  After the upgrade, both devices come with the new IOS image. However

  • Error when installing issue in Content Viewer

    Hi, I have a strange error in my Content Viewer. When downloading it stalls and a message says "Could not install issue, relaunch app and download your purchase again" (my translation from swedish). It sometimes stalls when downloading and sometimes

  • Text symbol in script

    Hi All, I am using a standard symbol in script.Insert>symbol>standard symbol,whether these symbols are speific to the program or will be available globally.i meant to ask if i use a standard symbole 'cp_prod' can i use the same in another form for di