LIV tolerance for price variance from PO to LIV

Hi Friends,
I am finding difficulty in setting up the tolerance key for price variance from PO value to invoice value. Suppose if PO price is $100 then system should allow upto $105 with out blocking means with percentage of 5%. If it exceeds 5% system should block the invoice.
Please suggest the tolerance key to use and if any other settings required.
Thanks...
Best Regards

Hi,
Following is the SAP help on the Tolerance settings for Invoice. Check the config and decide what is best for you (from your brief explanation it looks like AP and PP may be relevant fro your case)
===================
Set Tolerance Limits
    In this step, you specify the tolerance limits for each tolerance key
    for each company code.
    When processing an invoice, the R/3 System checks each item for
    variances between the invoice and the purchase order or goods receipt.
    The different types of variances are defined in tolerance keys.
    The system uses the following tolerance keys to check for variances:
    o   AN: Amount for item without order reference
        If you activate the item amount check, the system checks every line
        item in an invoice with no order reference against the absolute
        upper limit defined.
    o   AP: Amount for item with order reference
        If you activate the item amount check, the system checks specific
        line items in an invoice with order reference against the absolute
        upper limit defined. Which invoice items are checked depends on how
        you configure the item amount check.
    o   BD: Form small differences automatically
        The system checks the balance of the invoice against the absolute
        upper limit defined. If the upper limit is not exceeded, the system
        automatically creates a posting line called Expense/Income from
        Small Differences, making the balance zero and allowing the system
        to post the document.
    o   BR: Percentage OPUn variance (IR before GR)
        The system calculates the percentage variance between the following
        ratios: quantity invoiced in order price quantity units : quantity
        invoiced in order units and quantity ordered in order price quantity
        units : quantity ordered in order units. The system compares the
        variance with the upper and lower percentage tolerance limits.
    o   BW: Percentage OPUn variance (GR before IR)
        The system calculates the percentage variance between the following
        ratios: quantity invoiced in order price quantity units: quantity
        invoiced in order units and goods receipt quantity in order price
        quantity units : goods receipt quantity in order units. The system
    compares the variance with the upper and lower percentage limits
    defined.
o   DQ: Exceed amount: quantity variance
    If a goods receipt has been defined for an order item and a goods
    receipt has already been posted, the system multiplies the net order
    price by (quantity invoiced - (total quantity delivered - total
    quantity invoiced)).
    If no goods receipt has been defined, the system multiplies the net
    order price by (quantity invoiced - (quantity ordered - total
    quantity invoiced)).
    The system compares the outcome with the absolute upper and lower
    limits defined.
    This allows relatively high quantity variances for invoice items for
    small amounts, but only small quantity variances for invoice items
    for larger amounts.
    You can also configure percentage limits for the quantity variance
    check. In this case, the system calculates the percentage variance
    from the expected quantity, irrespective of the order price, and
    compares the outcome with the percentage limits configured.
    The system also carries out a quantity variance check for planned
    delivery costs.
o   DW: Quantity variance when GR quantity = zero
    If a goods receipt is defined for an order item but none has as yet
    been posted, the system multiplies the net order price by (quantity
    invoiced + total quantity invoiced so far).
    The system then compares the outcome with the absolute upper
    tolerance limit defined.
    If you have not maintained tolerance key DW for your company code,
    the system blocks an invoice for which no goods receipt has been
    posted yet. If you want to prevent this block, then set the
    tolerance limits for your company code for tolerance key DW to Do
    not check.
o   KW: Variance from condition value
    The system calculates the amount by which each delivery costs item
    varies from the product of quantity invoiced * planned delivery
    costs/ planned quantity. It compares the variance with the upper and
    lower limits defined (absolute limits and percentage limits).
o   LA: Amount of blanket purchase order
        The system determines the number of days by which the invoice is
        outside the planned time interval. If the posting date of the
        invoice is before the validity period, the system calculates the
        number of days between the posting date and the start of the
        validity period. If the posting date of the invoice is after the
        validity period, the system calculates the number of days between
        the posting date and the end of the validity period. The system
        compares the number of days with the with the absolute upper limit
        defined.
    o   PP: Price variance
        The system determines by how much each invoice item varies from the
        product of quantity invoiced * order price. It then compares the
        variance with the upper and lower limits defined (absolute limits
        and percentage limits).
        When posting a subsequent debit/credit, the system first checks if a
        price check has been defined for subsequent debits/credits. If so,
        the system calculates the difference between (value of subsequent
        debit/credit + value invoiced so far) / quantity invoiced so far *
        quantity to be debited/credited and the product of the quantity to
        be debited/credited * order price and compares this with the upper
        and lower tolerance limits (absolute limits and percentage limits).
    o   PS: Price variance: estimated price
        If the price in an order item is marked as an estimated price, for
        this item, the system calculates the difference between the invoice
        value and the product of quantity invoiced * order price and
        compares the variance with the upper and lower tolerance limits
        defined (absolute limits and percentage limits).
        When posting a subsequent debit/credit, the system first checks
        whether a price check has been defined for subsequent
        debits/credits, If so, the system calculates the difference between
        (value of subsequent debit/credit + value invoiced so far) /
        quantity invoiced so far * quantity to be debited/credited and the
        product quantity to be debited/credited * order price. It then
        compares the variance with the upper and lower tolerance limits
        defined (absolute limits and percentage limits).
    o   ST: Date variance (value x days)
        The system calculates for each item the product of amount *
        (scheduled delivery date - date invoice entered) and compares this
        product with the absolute upper limit defined. This allows
        relatively high schedule variances for invoice items for small
        amounts, but only small schedule variances for invoice items for
        large amounts.
    o   VP: Moving average price variance
        When a stock posting line is created as a result of an invoice item,
        the system calculates the new moving average price that results from
        the posting. It compares the percentage variance of the new moving
        average price to the old price using the percentage tolerance limits
        defined.
    Variances are allowed within predefined tolerance limits. If a variance
    exceeds a tolerance limit, however, the system issues a message
    informing the user. If an upper limit (except with BD and VP) is
    exceeded, the invoice is blocked for payment when you post it. You must
    then release the invoice in a separate step. If the tolerance limit for
    BD is breached, the system cannot post the invoice.
    Note that if you set all limits for a tolerance key to Do not check, the
    system does not check that tolerance limit. Therefore any variance would
    be accepted. This does not make sense particularly in the case of the
    tolerance key Form small differences automatically.
    Activities
    Configure the tolerance limits for the individual tolerance keys.
                 Lower limit             Upper limit
                 Absolute    Percentage  Absolute    Percentage
     AN          -           -           X           -
     AP          -           -           X           -
     BD          X           -           X           -
     BR          -           X           -           X
     BW          -           X           -           X
     DQ          -           -           X           -
     DW          -           -           X           -
     KW          X           X           X           X
     LA          -           -           X           X
     LD          X           -           X           -
     PP          X           X           X           X
     PS          X           X           X           X
     ST          -           -           X           -
     VP          -           X           -           X
===============================================
Best Regards,
Siva

Similar Messages

  • Set Tolerance Limits for Price Variance for PR missing from SPRO

    I'm looking into setting up tolerance limits for price variance at the PR level. But when i navigate here:
    SPRO > Materials Management > Purchasing > Purch.requisition > Set Tolerance Limits for Price Variance
    I'm not seeing that available in SPRO. It's available for PO's but not PR's. We want to be able to set tolerances on the PR to be applied to the PO for non stock items (material master). Please advise

    Hi,
       There is no standard configuration option to set the tolerance limit at PR level. You may set the tolerance limit for PO and control the price change. If you want the same functionality at PR level, then you have to go for development. Please check whether the BAdI: ME_PROCESS_REQ_CUST can fulfill your requirement. You may set the tolerance limit in OLME - PO - Set Tolerance Limits for Price Variance itself and write the logic in the BAdI to check the price variance in PR based on the same configuration (table T169G and similar).
       You may check the similar thread: PR VS PO Price Tolerance
    Regards,
    AKPT

  • Set Tolerance Limits for Price Variance when PO-based Purch.Requisition

    We must garanty that Price from Purch.Requisition will be the same at PO.
    IF some variance occur a error messag must be sent to user and PO could not be saved.
    I found at customzing under SPRO > Materials Management > Purchasing > Purch.requisition > Set Tolerance Limits for Price Variance .
    Reading the help of customizing it mean the system consists what we need..
    I have created tolerance limit NB, and set limits for all checks as 0,01.
    When I will activate messages as recommended on help no messages 601 and 602 have the text that guide us to correctly setting.
    The help mention that after create tolerance limit we must set this tolerance by document type..but I didn’t find this field at customzing
    Does anyone can help me ?
    See the help on customizing below…
    Set Tolerance Limits for Price Variance
    In this step, you can define percentage-based and value-based (absolute) tolerance limits for price variances between purchase orders and purchase requisitions. Variance types are mapped out in the SAP system by tolerance keys.
    You define the tolerance limits for each tolerance key and assign your tolerance key to the document types for purchase requisitions. The tolerance limit then applies for all documents of this document type.
    When processing a purchase order, the system checks whether the unit price of a purchase order item differs from the unit price of a purchase requisition item. If you have configured, activated and defined tolerance limits in document types, variances are permitted in the tolerance limits. If the variance exceeds the tolerance limit, the system issues a warning. If you have defined a percentage-based and a value-based absolute tolerance limit, the strictest of the two variances will apply for this check.
    Note
    You can determine whether the system messages (601 and 602) appear as warnings or error messages in step "Define Attributes of System Messages".
    To do this, go to the Materials Management IMG and choose Purchasing -> Environment Data -> Define Attributes of System Messages.
    Requirements
    The tolerance key must be defined in step Define Tolerance Key.
    Activities
    1. Define tolerance limits for each tolerance key.
    2. Define the tolerance key in step Define Document Types.
    Thx  and best regards,
    Ale

    HI
    SET   TOLERANCE  LIMITS  FOR PURCHASE  REQUISITION  UNDER THE  DEFINE  DOCUMENTS   FOR PR
    AFTER  SETTING  TOLERANCE  LIMITS  WHILE  CREATING  PURCHASE  U  WILL   GET  BASED ON  TOLERANCE  LIMITS  THERE   FOUR   WAYS  TO  SET  TOLERANCE  LITS 
    1
    ABSOLUTE VALUE
    2
    PERCANTAGE
    3
    TOTAL  PO  VALUE
    4
    QUANITY  BASED  PRICE  PER  UNIT
    OK  BYE

  • Tolerance Limit for Price Variance (Purchase Order)

    Hello,
    Business Case :
    Final users require a specific tolerance limit rate for Price variance in Freight services POs.
    We have a current rate set up at Company level
    --> standard customizing (MM / Purchasing / Purchase order / Set tolerance limit for Price variance)
    Do you know any way to set up diffferent tolerance limit depending on the purchasing flow ? Vendor level for example ?
    thanks for your time.
    regards,

    Thanks for your reply.
    What do you mean by "syestem look for noramal quantity variance from info record" ?
    P.I.R only conatins under and over delivery tolerance, but nothing related to price variance between GR and Invoice.
    I'm looking for a customizing in order to have a Tolerance limit for Price variance at another level than Company.
    At vendor level for example ?
    Do you confirm there is no standard customizing ?
    Any user exit available ?
    thanks
    regards

  • Tolerance for price confirmation

    1.The tolerance for price confirmation is not restrictive enough for confirmation control key one particulatr KEY.Where to upadte  it to allow only 10% tolerance

    Hi
    Maintain the config in
    SPRO-> IMG-> MM -> Purchasing-> Purchase Order-> Set Tolerance Limits for Price Variance
    Here you can miantain the tolernace limits for key PE: Price variance: purchasing
    Thanks & Regards
    Kishore

  • Line Item For Price Variance

    Hi,
    What non FI datasource in RSA5 can i find the line item for Price Variance?
    Thanks

    Hi Sam,
    I think 0CO_OM_CCA_9 will word best for me.
    what does it mean by:  Actual Costs Using Delta Extraction ?
    Also would the field REFBN Reference Dosument Number have the invoice number & the PO Number?
    Thanks

  • Tolerance for Price change

    Hi,
    Can we set tolerance for price change for particular material or groups of materials.
    say i dont want my material price to hit by more than 10% when using average price.

    Hi Ravi,
    SPRO - MM - Purchasing - Purchase Order - Set Tolerance Limit for Price Change
    Using the Above path, you can change the Tolerance limits for price at Company code level.
    Regards,
    Ashok

  • Tolerance Check for Price Variance is not working

    Hello,
    In SRM 5.0 IMS we have configured a tolerance group with tolerance Key ‘PP’ to allow Price Variance while Invoice entry.
    We have assigned this tolerance group to the user via attribute “TOG” in the organizational structure (Transaction Code: PPOMA_BBP)
    The user to whom this tolerance group is assigned is logged on into the system and created an invoice in the system with the higher amount as compare to the PO. This difference of price is very well within the tolerance limit configured in the system, but still it gives the following errors:
    •     Average price too high: Tolerance limit of 0.00 and USD exceeded  (Item 1)
    •     Value too high (tolerance limit of 0.00 and USD exceeded)  (Item 1)
    It’s not checking the tolerance limit assigned to the user through tolerance group.
    But the same works when we assign this to vendor group, but this we don't want.
    We want the system to check the tolerance group assigned to the user.
    Please suggest the solution to reslove the above errors.
    Thanks
    Sarabjeet

    Hi,
    Priority of tolerances is  PO tolerance limit,  TOG tolerance grp. for User, TOG tolerance grp. for Vendor (if user not logged on). Even absolute tolerance limit always has priority over percentage limit.
    In your case, you need to check PO tolerance first then TOG for user.
    regards,
    rahul

  • Invooice block for price variance

    Hi
    I require a block for the invoice for value more than PO value by 2Rupees. I have done the Tolerance key cuustomizing for PP (Price variance) by mainaining the upper limit as 2 Rupees and have checked the limits. I expected the system to block the invoice for value more than PO value by 2 rupees, but system blocks even for value more than 10 or 20 paise. Please clarify and guide what needs to be done.
    I also beleive system does not blocks invoice for the above tolerance for extra duties and taxes and unplanned costs. Pl brief.
    Regards
    Arvind

    hi
    u have given tolerence for PP     Price variance
    u check following
    BD     Form small differences automatically
    KW     Var. from condition value
    VP     Moving average price variance
    for the above keys make the option as do not chck and then try
    regards
    KI

  • Standard Report for Price Variance

    Dear Friends,
    Business is asking for the Price Varinace Report in standard SAP based on following criteriau2019s
    The requirement is to have a report which provide :
    ·         Purchase price variance u2013 PO V/s Invoice which is posted to General ledger.
    ·         By Vendor ( both third Party & Intercompany) with Vendor number and name.
    ·         By Material code & Material description and Material class
    ·         By Purchase order
    ·         For a given month or Year to date.
    ·         By GL code where the purchase price ( PO v/s invoice) is posted.
    Is there any standard report available for this in SAP or is it should be customised, if so is it complex...
    Please suggest me on the same
    Thank you for your promt reply
    Radhika Eluri

    Hi Santosh,
    I could not find the related reports for the same which i can show to the user.
    Could you please give me what are those reports available(Even they are not completed) so that i can provide the same to business.
    If they are not satisfied with them, then we will go for developemnt
    Thank you
    Radhika Eluri

  • Variances accounts - for Price variances

    Hi,
    I have a problem with deciding how many Price variance Accounts I should create.
    There are 3 Production divisions and there are 3 types of PP orders.
    Each PP order can create Finished Goods or SemiFinished Goods.
    Should I create separate variance account for Finished Goods and separate variance account for Semi Finished Goods?
    How can I assign these variances account (for settlement) to an order type, if one order type can do both FG and SFG. Maybe the PP order types should be divided into FG and SFG - so that there would be 6 PP order types?
    What can you suggest me?
    Best wishes,
    Karol

    Hi Karol
    Create two production variance accounts for FG and SFG.  These should not be created as cost elements and should have PRD PRF as account determination.  You dont have to create as many variance accounts for each PP orde type
    Create one more variance account - called Variances in production as cost element. 
    Order crated for a material and depending on the material type and valuation class assigned to material, different accounts will be hit
    You assign PRD PRF for FG and SFG material valuation classes
    Hope the above clarifies. Please assign points

  • Invoice blocked for price variance or quantity variance

    Dear friends,
    In case if in the PO, either there is a price difference between GR and IR or a quantity difference between GR and IR, then does the invoice posted stays automatically in a "blocked" status??
    If not, then can we manually do some configuration to make this possible? The intention is that such invoices(with price variance or quantity variance) should remain in blocked status and should not be picked for payment in F110 run.
    Please advise asap.
    Rgds,
    Kunal Vichare.

    check this links
    http://www.sapfans.com/forums/viewtopic.php?f=6&t=324521
    http://www.sapfans.com/forums/viewtopic.php?f=6&t=336490

  • Purchase Order - tolerance key SE for price variance

    Dear folks,
    In the purchase order config for tolerance limit, there is a setting for tolerance key SE.
    The SAP help defines that this limit is triggered with system message no. 231. This is a warning message, which appears when the specified cash discount percentage exceeds the predefined tolerances.
    Can anyone advice me where do I specify which cash discount or what discounts will trigger this warning messages?
    Also, is it comparing the discount % against the % in the config or against the discount value from the PO price?
    Best Regards
    Junwen

    Dear Folks,
    To clarify, I meant how do I trigger this tolerance limit SE?
    Which discounts will trigger this limit?
    If I add new discounts or delivery conditions like Freight, will it be subjected to this check?
    This setting is set in the SPRO in Purchase Orders setting together with the tolerance key PE. PE will be triggered in the purchase order when the price in the PO is lower or higher than the tolerance limit when compared to the material price.
    Thus, I think SE will be triggered in the PO also, but how?
    Best Regards
    Junwen
    Edited by: Junwen Huang on Jun 11, 2008 10:12 AM

  • PO Tolerance Limit for Price Variance

    All,
    For the key PE I have set Upper Limit for Percentage Check Limit to 0.01%.  At what point is the tolerance limit check?  Is it at PO creation or some other point?
    Thanks,
    Sean

    The related error message appears at the time of PO creation. It will prevent you from creating the PO with a price that is ourside the allowed tolerance value
    PE tolerance limits defines the allowed variation in price between the PO price and that of material price stored in the material master as standard price. The standard price is the output of the standard costing process

  • Tolerance limits for Price Variation

    Dear All,
    I have set the Following in Customizing.
    In the following node : IMG-------> Materials Management ----------> Purchasing -----------> Purchase Order --------->  Set tolerance limits for price Variance.
    In this, For Company code & Tolerance Key "PE" combination, it has been set " Check Limit 20%" in the  Percentage field ( Upper limit ).
    Now, I have a material having a Moving Average price of 100 INR in the material master Accounting view. When I create a PO for 130 INR, there is no warning/error message that is popping up? Isn't the system supposed to throw a message here, since 130 inr exceeds 120 INR, or am I missing something out here ?
    Note : 120 INR = 100 + (20%)(100) = 120 INR.
    Regards
    Sathya

    Hi Sathyanarayana Rao V N
    You can benefit from M8 messages for incoming invoices with tolerances to solve your problem. You have to configure your system messages with error.
    Regards.
    M.Ozgur Unal