Mrp run to do  for different numbers in a sale order

Dear Sir,
we are doing make to order planning strategy 20  and receiving sale order on august 2008 of 7 nos and delivery date  is of 21 july 2009.
my  client needs to do mrp run  as per the client planned date  , but in md04 the sale order is showing of 7nos .
the client planning date are as follows  to do mrprun :
31st May 2009 - 2 nos
30th june 2009 - 2 nos
21st july 2009 - 3 nos
so I kindly request you to help me how we can do the mrprun as per the client planning date and also what is the flow  path to be done.
In making a finished product we are giving packing as outsourcing ( i.e. labour coming from outside getting wood and othermaterial for packing )  for this how can i show in the routing of packing.
regards,
muralidhar.t

Muralidhar,
Let me understand, on what basis the client decides to run MRP for Schedule Line 3 & 4? Is is based on the deliveries for the next 2months and the other schedule line are behyond 2months from now?
Though your scenario is not clear, with my little understanding I can suggest couple of options,
1. You can define Planning Horizon for the Plant say for example "60" - Days, and then your MRP run can be with "NETPL"- Processing key in MD01. What this means is that deliveries or requirements which are falling within this 60days will only be planned.
Planning horizon should be configured in the MRP - Parameter Master data section in SPRO.
2. For all the schedule lines you can change the Schedule Line category to "CN" instead of "CP". CN related schedule lines are not considered in MRP for planning.
Regards,
Prasobh
Regards,
Prasobh

Similar Messages

  • How to create a running total formula for different calendar years

    Hello everyone,
    I am looking for some help in creating a running total formula for different calendar years in Oracle. This is what I currently have organized in the crosstab report: vertically I have the cities from our database organized, then horizontially have the following information for each city:
    2006 /2007 /2008
    Amount /Amount Spent /Unspent Amount Amount Recieved/Amount Spent /Unspent Amount Amount Recieved/Amount Spent/Unspent Amount
    Recieved
    I am trying to create a formula that will specify each calendar year. For example, I'd like to have a formula in 2007 which would total the: 2007= {2006 unspent amount + the unspent amount in 2007} and same for 2008= {2007 unspent amount + the unspent amount in 2008}. I hope this is clear, I have simplified the report into a basic interpretation of what i've been trying to accomplish.
    Would anybody know if this is possible and how to approach this?
    Really appreciate it! Thanks.
    Alex

    Hi,
    you can try and define a running total as a calculation in the crosstab as:
    sum(Unspent Amount) over (partition by city order by year)
    i find the crosstab format comfusing sometime since the aggregation is auto applied.
    I would start with a flat table and then "duplicate is as a cross tab"
    for your running total you can sort the data by the city,year and get it to 3 lines for each city, for example:
    city year Unspent Amount all other amount...
    X 2007 10
    X 2008 20
    X 2009 30
    Y 2007 5
    Y 2008 15
    Y 2009 25
    then you can use a funtion to calculate the amount :
    sum(Unspent Amount) over (partition by city order by year)
    this is the sql i used just to check it:
    SELECT city,year,"Unspent Amount"
    ,SUM("Unspent Amount") over (PARTITION BY city ORDER BY YEAR)
    FROM (
    SELECT 'X' city, 2007 YEAR, 10 "Unspent Amount" FROM dual UNION ALL
    SELECT 'X', 2008 ,20 FROM dual UNION ALL
    SELECT 'X', 2009 , 30 FROM dual UNION ALL
    SELECT 'Y', 2007 , 5 FROM dual UNION ALL
    SELECT 'Y', 2008 , 15 FROM dual UNION ALL
    SELECT 'Y', 2009 , 25 FROM dual
    Tamir

  • Different pricing procedures for two different items in a sales order.

    Hi ,
    In a sales order I have two items , one is TAN item and other item is TAD (services).. Since the tax structure is different for above mentioned items, user wants to apply two different pricing procecdures for two items in a sales order.
    Can any one suggest how to get this functionality.
    Thanks,
    Ashok S

    Dear Ashok,
    As Rithivika rightly mentioned that in one sales oder you can't get two pricing procedures.
    Because pricing procedure determination will takes place based on these combination
    Sales areaDocument pricing procedureCustomer pricing procedure-->Pricing procedure.
    So If you want different pricing procedure either one of the combination should be different.
    But you try this
    You can maintain service related tax condition types also in the same procedure,but when you maintain condition record you can maintain material wise.
    So when you create sales order system will pick the pricing based on the material(standard item or service item).
    I hope this will help you,
    Regards,
    Murali.

  • Which Smartform is used for output of a (confirmation) sales order ( in tra

    Where in customizing I can see which Smartform is used for output of a (confirmation) sales order ( in transaction VA02/VA03) and which print program.
    If the mechanism is different please let me know
    Thx in advance(right answers will be rewarded)

    Hi Tina,
    This is very simple.
    You can go to transaction NACE
    Now click on Output Types, here against your output type you can see what is the smart form attached in the field processing requirements.
    If its order confirmation, it would either be standard BA00 or a copy of that, maybe the naming convention would help you.
    Also If you click on the extreme left hand button in NACE, you can see against your output type what are the records maintained, and under communication tab, you could get to see the printer setting.
    Hope this solves your query.
    Reward suitably if helpful.
    Regards
    Ravi

  • Is it possible to have different pricing procedure at sales order level and

    Hi SD Gurus,
    Is it possible to have different pricing procedure at sales order level and invoice level?
    if is it possible to have different pricing procedures at sales order level and invoice level could you please tell me the steps how i have to do?
    Thanks & Regards,
    Nivas

    Hi,
    Yes you can able to map two different pricing procedure for order and invoice level
    You can achieve it through by document pricing procedure and assign it in document type
    In VOV8  assign document pricing procedure A for order type
    in VOFA assign document pricing procedure B for billing type
    Keep customer pricing procedure common
    Then in OVKK assign pricing procdures
    Kapil

  • How To Add a new column for ZPR0 price in open sales order report ??

    HI,
    my requirement is To Add a new column for ZPR0 price in open sales order report if the order/scheduling agreement is a cross-company code transaction l(company code of order/scheduling agreement <> company code of delivering plant), price = ZPR0 price as at estimated GI date

    k

  • To Add a new column for ZPR0 prce in open sales order report

    HI,
    my requirement is To Add a new column for ZPR0 prce in open sales order report if the order/scheduling agreement is a cross-company code transaction l(company code of order/scheduling agreement <> company code of delivering plant), price = ZPR0 price as at estimated GI date

    HI,
    my requirement is To Add a new column for ZPR0 prce in open sales order report if the order/scheduling agreement is a cross-company code transaction l(company code of order/scheduling agreement <> company code of delivering plant), price = ZPR0 price as at estimated GI date

  • Can we combine Query for cancelled requisitions and query for internal requisitions without internal sales order into a single query

    Hi All,
    Greetings.
    I have two queries namely,
    1.Query for cancelled requisitions and
    2.Query for Internal Requisitions without Internal Sales Orders.
    I was on a task to combine those two queries..
    Can we do that? if so, please help me do that..
    Thanks in Advance,
    Bhaskar.

    Hi All,
    Greetings.
    I have two queries namely,
    1.Query for cancelled requisitions and
    2.Query for Internal Requisitions without Internal Sales Orders.
    I was on a task to combine those two queries..
    Can we do that? if so, please help me do that..
    Thanks in Advance,
    Bhaskar.

  • SD - Manual entries allowed for item category in the Sales Order

    Hi experts,
    please do you know any OSS note related to SD, in order to increase the number of Manual entries allowed for item category in the Sales Order (table T184)?
    Thank you very much
    Andrea

    Hi,
    I searched OSS notes and did not find any OSS Note related to add more than 11 Manual Item categories or append T184 Table.
    Has any found solution for this, will this be a CORE MOD.
    Pavan Verma

  • Can we create two POs for the same 3rd party Sales Order?

    Hi MM experts,
    Issue: Can we create two POs for the same 3rd party Sales Order
    In Third party purchase process, first sales order created with a spl. item category  and it creates the PR automatically with the Sales order material and Qty and this PR converted PO.
    They got a pur.req. for sale order on same item for same delevery date. They did not get any warning msg. saying that a PO was prviously placed against this sale order.
    How it is possible that we were able to place another PO? concern is that second PO was palced against SO which was already used & completed. they were able to place 2 POs for the same customer same delevery date. How it is possible?
    If anyone face the same issue, please let me know if you have any answer to this questions.
    Thanks in advance.
    Suresh.

    Suresh,
    It is hard for me to give you a definitive answer since you have created a customized solution.
    How it is possible that we were able to place another PO? concern is that second PO was palced against SO which was already used & completed. they were able to place 2 POs for the same customer same delevery date. How it is possible?
    Normally, the system will not do this.  A third party PR or PO will be 'account assigned' to the Sales order.  SAP standard 3rd party will not create additional purchase reqs unless there has been manual intervention.  Try searching for changes in the Sales order and changes in the original purchase order.  They may give you a clue.
    I believe the normal Item category for third party SO is TAS (I am working from memory here, I am not in front of a system).  I don't know what ZTAG does.  I confess I am not an SD expert.  You might also want to post your question in an SD forum.
    You mention two custom applications, ZMMPLAN and ZSTPMP.  These somehow have functionality that is used to help you convert your PRs to POs.  If I were in your position, I believe I would also look at these applications for clues to how they might be contributing to your problem.  And please don't send me details about these apps.  I will not comment on custom code in this forum.
    Sorry I can't be of more help.
    Rgds,
    DB49

  • I want a push button for line items in my sales order entry screen.

    Hi,
    I want a push button for line items in my sales order entry screen.
    How can I do so?
    Thanks.

    Hi Kumar ,
    To have a push buttons you need to first assign a pf-status .
    here a sample code for a push button and its handling :
      set pf-status 'SELECT' .
    at user-command .
      describe table t_lpr lines w_lines .
      case sy-ucomm .
        when 'SELECTALL' .
          set pf-status 'SELECT' excluding 'SELECTALL' immediately.
          do w_lines times .
            read line w_line field value w_check . " INTO W_CHECK .
            if w_check = space .
              w_check = 'X' .
              modify line w_line field value w_check.    "INTO W_CHECK .
              add 1 to w_line .
            endif .                        " IF W_CHECK = ' '
          enddo .
    Thus when you say pf-status say 'select' , Double click on that and you find a screen eher you can select icons and assign a function code to it!
    Hope it helps!
    Much Regards,
    Amuktha .

  • Different Method to valuate sales order stock

    Dear expert,
         I came across a problem and I need your help:
         Scenario: Make-To-Order production without sales order controlling.  Uses standard price in material master record.
         As we know, There are a predefined sequence to valuate sales order stock: First, The system uses the standard price on the basis of your customer exit COPCP002 Material valuation for valuated sales order stock. If not defined COPCP002, Then, the system uses sales order costing.  Then, the system determines the standard price using the production order cost estimate. At the end,  the system determines that If you manufacture a material both for the make-to-stock-inventory and for the valuated sales order stock, the system reads the material master record of the collective requirements material.
         In SAP online Help, there is a note that: If you calculate the standard price of sales order stock in a preliminary cost estimate for the manufacturing order or use the price in the material master record, you cannot transfer cost component splits into COPA. This is my doubt: I don't know exactly where are the differences between sales orde costing and standard price in material mater to determine sales order stock.
         So, I have a question:  What are the extract diffences between using sale order cost estimate and the standard price in the material master record to determine valuated sales order stock?
         Thanks for your help.  Best regards,

    What you said is exactly what I want! Very thankful for your help.
    Yes, I have found that in EBEW table that standard price is valuated with preliminary cost estimate because I don't give a sales order cost estimate but I give an sales order stock in the customizing - requirement class. So, I have this question that how the sales order stock is determined.
    In COPA customizing (COprofitability analysismaster datavaluationSet up valuation using material cost estimate), standard cost estimate or sales order cost estimate can be transferred into COPA value fields in our system.
    But, I have still have a question: I found in our system, preliminary cost estimate in the linked production order is determined for valuation of sales order stock in EBEW table. As sap online help says, cost component splits can not be transferred to COPA.
    So, according to SAP online help, I think what you said u201Cu2026..However , when we start thinking about the result of this cost to flow into COPA , this cannot happen as the Inventory was valued with a Preliminary csot estimate. So , the Online help says that it will not be able to transfer Result of Preliminary cost estimate into COPA for transferrring COGS details. System would always require a Standard cost estimate or a Sales order Cost estimate to flow Cost details into COPAu201D is correct.
    But, in our system, cost component can be transferred into COPA!? When I create a sales billing (invoice) with tcode VF01, it can create a profitability analysis document (shown in VF03) which it had a cost component split for that material in the sales order stock valuated with the preliminary cost estimate. Or where is stored for the Make-to-Order materialu2019s cost component split in COPA?
    That is the real point that confused me. Hope you can help me. Thanks very much.

  • Val.Price for the requisition on the sales order

    Hi,
    I am creating automatically purchase requisition on the sales order with NLAG material type.
    My problem is system asking Val.Price for the requisition on the sales order. I don't want the this screen when sales order create.
    My Purchase Req. Doc Type = NB
    Field Selection key = NBB for the NB
    NBB Field Label >> Quantity and Price >> Price and price unit = Optional Entry
    Thank you
    Gulay Celik

    Hi Gulay,
    The error is coming because you have not maintained Accouting view of this material for teh plant, from where you want to procure/ship the material.
    Or even after you have maintained the Accouting view, Material price (Moving avegare price when price control is V must be Zero)
    Kindly check the master data records.
    This will resolve your issue.
    Regards,
    Dnyandeo H. Ainarkar

  • How to sets the Reason for Rejection of the Open Sales Order Lines

    Hello gurus,
              I want to set the Reason for Rejection of the Open Sales Order Lines, Case is like :
    If current date is exeed the Auto Void Confirmed Back Order Days(for item level) +  date (last responding from customer), then reason for rejection should be set, So i want the logic to find out the date is exceed or not.
    Thanks
    Anjana

    Hello anjana,
       Actually your question is some confusing, but if u want to get eldest change as active sales order then logic is as follows:
    1.  On base of OBJNR u have to get UDATE from JCDS table
    2. then write logic as:
    SORT i_jcds BY objnr stat chgnr DESCENDING.
          LOOP AT i_jcds INTO wa_jcds1.
            CLEAR lv_stat.
            lv_stat = wa_jcds1-stat.
            AT NEW objnr.
              AT NEW stat.
                CLEAR: wa_tab.
                wa_tab-objnr = wa_jcds1-objnr.
                wa_tab-stat = lv_stat.
              ENDAT.
            ENDAT.
            IF wa_jcds1-inact = 'X'.
              CLEAR lv_tabix.
              IF sy-tabix > 1.
                lv_tabix = sy-tabix - 1.
              ELSE.
                lv_tabix = 1.
              ENDIF.
              READ TABLE i_jcds INTO wa_jcds2 INDEX lv_tabix.
              IF sy-subrc = 0.
                wa_tab-chgnr = wa_jcds2-chgnr.
                wa_tab-udate = wa_jcds2-udate.
                wa_tab-utime = wa_jcds2-utime.
                APPEND wa_tab TO i_tab.
              ENDIF.
              CONTINUE.
            ELSE.
              wa_tab-chgnr = wa_jcds1-chgnr.
              wa_tab-udate = wa_jcds1-udate.
              wa_tab-utime = wa_jcds1-utime.
            ENDIF.
            AT END OF objnr .
              AT END OF stat.
                APPEND wa_tab TO i_tab.
              ENDAT.
            ENDAT.
          ENDLOOP.
          DELETE ADJACENT DUPLICATES FROM i_tab COMPARING objnr stat.
          SORT i_tab BY objnr stat udate utime.
          DELETE ADJACENT DUPLICATES FROM i_tab COMPARING objnr.
    3. now in i_tab table u'll get eldest UDATE
    Hope its work for u.
    Thanks & Regards,
    Sumit Joshi

  • How can I run the report for different input values at the same time?

    Reports version: Report Builder 6.0.8.13.1
    Oracle version: Oracle8i Enterprise Edition Release 8.1.7.0.0
    I want to run the same report for different input parameter values and spool each o/p to different file and ftp to a server. For this, as a first step, I am spooling different input values in to a file, reading those values through a loop and calling the report for that input values. Each report run/execution is taking 15 minutes. Total report execution is taking approximately 4 hours (assuming 16 different input values) to complete. So I have to wait 4 hours to see ALL outputs.
    I would like to run the report parallel for ALL the input values and I should be able to see the ALL outputs with in 15 or 16 minutes.
    In my shell script, I added & symbol at the end of the report call to start/run the job in the background. Due to this the control passed to the next step after the report call. At this place I have an ftp command to send the output file to a different server and it is giving error some thing like “o/p file is not available/created yet". This is due to the fact that report writer is NOT yet completely started/initiated or it is NOT completed the spooling.
    How can I run the report at the same time for all the input values and save the time?
    Thanks in advance.
    Kishore.

    Increase the number of server engines running right now it seems there is only one engine running ,increase it to 4 or 6
    and then atleast 4 or 6 reports will run simultaneously.
    For FTPing the output add to your sript to check whether it is locked and if not then only try to ftp .
    Also for more better functionality read the document (chapter 15 ) for 10g reports for its new fuinctionality.
    http://download.oracle.com/docs/cd/B14099_17/bi.1012/b14048/toc.htm
    Thanks
    Subodh