MTO--Cost component transfer to COPA

Hi Friends,
I have MTO  with sale order as cost object. It means COPA documnet will be created not at the time of billing but at the time of Sale order settlement. So first i have finished the production order settlement , then sale order settlement. While doing this system is transferring to COPA cogs as  single amount but it has to go cost component wise.
Please advise me.
Regards
Rajesh A

Hi,
There is no problem in Cost component. Problem is that for each cost component i am not able to transfer to more than one value field. In my example CASH COST is not a cost compone , its description of the value field.
Cost componet is Raw materiala ( fixed+ variable ) = i want to transfer to two value field  - 1. Material and 2 .Cash cost.
But somehow system is updating the value only to the first value field which in this case material but not updating the second value field which Cash cost.
Regards
Ranjan

Similar Messages

  • Cost component split in copa

    Hi,
    I am looking cost component split in copa document ,
    Price for FERT(FG) materil valuation will at manufactured plant level is Standard price(S) and Depo level Moving avg price(V) i am doing standard cost estimate
    for that i have done ..setting.
    1) cost component structure ( Raw material, reprocess cost, additive cost, and overheads)
    2)Valuation Strategy (maintained with Point of valuation 01,02,03,04)
    3)Costing key  (Y01)
    4)Assign Costing Keys to Material Types  ( ROH and FERT, PV=01,02,03,04.)
    5)Assign Value Fields , ( Operating concern & Value fields are Raw material, reprocess cost, additive cost, and overheads)
    6)I have written copa report
    Cost breakup i am geting when i maintained standard price of the material, but
    when i maintain price indicator V (MAP) stock value will be different it depends on Goods movement, i am getting price converted standard price.
    Is their any setting missing to fulfill the same ( meet the requirement if goods movement taken in consideration)
    I am not getting proper cost split in COPA report.
    Please help me i am stuckup.
    Thanks in Advance
    Regards.
    Vinu
    Edited by: vinutha1010 on Jun 17, 2010 7:08 PM

    HI PietStrydom ,
    thanks for your valuable replay.
    could u tel me in detail..how can i achive in this transaction ..ie somthig like SCE access .
    I have taken parameater in t.code KEPC (source =  POV, Record type, material type, plant, Target = costing key, plant, type of error,
    Regards.
    Vinu,

  • Cost component structure in copa report

    HI Gurus
    1We are doing REM Process and costing variant "PREM"
    2. We are going for moving average price for all Material type there is no standard cost estimate
    3. My client want to see the  cost component structure in copa reports like
      sales
      exice
      ram material
      packing material
      labour
      overehad
      selling and distributioh overhead
    I have done all necessary setting in costing key
    I have done pa trasnfer structre also
    But Cost component spill is not happening in copa report
    Can we get cost component struture in copa report with moving average price if yes
    Please advice  me how to geneate the report
    Thanks & Regards
    KISHORE

    Hi Aravind
    Thanks for your reply, But in our  business process there is not Standard cost estimation,bcoz, Price control in material master is MAP. Can we get cost component strudcture in copa  if we are going for MAP in MM.
    I have done all the Setting IN KE4R also. But i am unable to see the values in COPA report
    Thanks
    KISHORE

  • Cannot bring material cost, labour, overhead to copa

    Dear Forum,
    Why it is saying that cannot bring material cost, labour, overhead to copa?
    "In all the system COGS clearing account exists.......but for COPA, condition type VPRS is attached to cost element Cost of Goods Sold because you can not bring all the cost like material, labour, overhead into COPA.....so all procuring cost flows to VPRS condition type and in turn COGS is deducted from the sales revenue to derive Gross Profit...."
    Thanks alot.

    Hi
    Please go throgh the below mentioned link
    Cost Component Structure in COPA
    Hope this will help you
    Regards
    Praveen P C

  • Cost component split transfer for Profit center valuation in ke27

    Dear All,
    We have activated multiple valuation/transfer prices. Material ledger is also activated.
    We want to transfer cost component split to CO-PA by ke27.
    We have defined separate costing keys for access to actual cost estimate for legal and profit center valuations.
    But cost component split transfer to COPA works only for legal valution. Even we have defined type of valution for profit center  costing key -transfer cost component split and total costs.
    What should be else customized to transfer cost components splitting in profit center valuation to CO-PA from actual cost estimates?
    With best regards,
    Kamila.

    Hi,
    I have assigned the same value fields used for legal valuation to column 2, which was pointed in message.
    But now I got following message in ke27:
    For actual data, value fields that were already populated before CO-PA valuation cannot be changed in valuation.
    1. As a rule, value fields that were filled before CO-PA valuation - be it from SD or by a manual entry of a line item - can only be changed by means of user exits.
    (Note that for plan data, CO-PA valuation always has priority over the values planned manually.)
    2. The valuation steps in a CO-PA valuation strategy are numbered sequentially. These numbers determine the order in which the steps are carried out within that strategy. As a rule, value fields populated in one step can be used as a basis for calculating values for other value fields in a subsequent step.
    Value fields that were populated in a previous step are generally not overwritten by subsequent steps.
    The exception to this are steps that use a CO-PA user exit. User exits let you change individual value fields.
    3. If you valuate using multiple material cost estimates simultaneously, this means that the values of different cost components within the same cost estimate are aggregated and then entered in one CO-PA value field. However, value fields that already contain data from a previous cost estimate are not overwritten by a later cost estimate. Consequently, you should assign value fields in Customizing so that the values of different cost estimates are entered in different sets of value fields.
    4. When condition values are transferred to CO-PA value fields, note that condition types that are assigned to the same value field are added together. This is also the case when the condition types come from different costing sheets within the valuation strategy.
    So does it mean we should define separate value fields for PC valuation?
    With best regards,
    Kamila.

  • COPA Gross Margin report Cost component roll up

    Hi,
    I have a question about COPA valuation using standard cost estimate and roll up of cost components in Gross Margin report.
    I would like to build a simple Gross Margin Report in KE30 showing Billed quantity, Revenues and COGS split to Material, Labour and Overhead Components, but with cost components roll-up from SGH to FG.
    In order to have the split of COGS I believe I need to maintain Valuation using Standard cost estimate in COPA. However, from my experience, I think that in Gross Margin reports I saw in COPA in the past - there was no cost component rollup from Semi finished to Finished products.
    I mean if we sold 1 piece of FG at a price of 20 EUR and cost components for it would split into:10 - Materials, 2 - Labor,3 - Overhead (Total COGS of 15 EUR)
    If  this is 2-level production and this FG has SFG in its cost estimate, the SFG cost split into: 3 - Materials, 1 -Labor and 2 - Overhead
    From my experience all costs of SFG used to produce that FG would go under Materials Component in Gross Margin report (312=5 from SFG would go to Material component of Sold Finished Product). Is it possible to have in Gross Margin report situation where Material Component from SFG would be rolled up to Material component in Sold Finished Product, Labor component from SFG rolled up to Labour component in FG... etc?
    Regards,
    Karol

    Hi Karol
    I dont think that SAP functions this way... In your eg, the Cost of SFG (321) does not roll upto to the Material cost of FG
    Moreover, it is not controlled in COPA, but in Product Costing
    When you define your Cost Comp Str in OKTZ, you can tick the check box "Roll up Cost Component" in each of the cost components.... Once you do this, the Overhead cost in SFG will be rolled up to the Overhead cost of FG (And Not to Material Cost of FG)...
    Costing keys would simply fetch the cost estimates and transfer it to COPA.... So, set it up right at the source in OKTZ and it should be done
    br, Ajay M

  • Impact of Cost component structure on PA Transfer structure in SAP

    Hi All,
    We were using a single Operating concern and Controlling area for existing company codes. Now, we got a new company to be created all together a new company with the same chart of accounts.
    1. We have created Operating concern, COA, Company code..... and then completed the PA Transfer structure of FI-MM in KEI1
    2. I have created a new Costing variant in OKKN
    3. I have created the Cost component structure in OKTZ and assigned the new company code to it.
    When i go back and checked the PA Transfer structure for FI-MM, i see everything showing as blank.
    I have no idea the entire config got deleted.
    Do you have any idea how it happens and why it happens please?
    Also, will there be any relation b/n OKTZ and KEI1 and sequence to customize?
    Hope you understand my query.
    Appreciate your early response.
    Thanks,
    Narasimhulu

    Hi Ravi,
    Thanks for your response.
    I have created the FI-MM PA transfer structure for the new Controlling area. But after completing the Cost component structure and came back to check the PA Transfer structure, i was surprised since everything to deleted.
    I have no idea if we need to follow a sequence while doing these two activities (KEI1 and OKTZ).
    Thanks,
    Narasimhulu

  • Transfer between cost center and to copa

    Dear Forum,
    I have 3 points to clarify.
    1) Assessment or distribution, sender cost center is credited and receiver cost center will be debited. cost in sender will reduce and receiver will increase. correct?
    2) For keu3 where cost center to copa, will cost in cost center reduce when transfer to cops?
    3) For keu3, how is the double entry like with the use of assessment cost element when transfer to copa?
    Thanks

    HI,
    when defining an aassessment cycle within T-Code KEU5 the sender is cost center / cost element (or a group of them), the receiver is always a combination of CO-PA characteristics that you define within the segment definition.
    This characteristics combination + some technical infos are stored with the key PAOBJNR (profitabilty analysis object number).
    SO the cost center is credited and the CO-PA receiver (a PAOBJNR) is debited during assessment execution.
    Best regards, Christian

  • Can Absorption costing transfer in COPA?

    Hi All
    I would appreciate your help. Please provide me details explanation over.
    1) Can we transfer Absorption Costing in COPA?
    2) What is the procedure?
    ( It is my request please use full form rather than short words).

    Hi Shobhi,
    Absorption costing is charging all fixed and variable costs of production to sales effected in a period.To major extent it is possible to transfer Absorption costing to COPA. I am not sure about how to give effect of difference in openeing and closing stock.
    The procedure for costing based copa is as follows.
    You get Revenue as well as cost (standard cost) of goods sold through billing documents. The sales which cannot be effected through billing documents can be accounted through Financial entries having real cost object as "PSG" i.e. profitability segments.
    Now coming to production order variances, at the period end, you can transfer all these to COPA.
    Your production cost centers will have some debit/credit balances which can be assessed to COPA. So variable cost is abosrbed to COPA.
    About fixed cost ,service cost center balance and cost related to HR , Marketing etc  can be assessed to COPA. So this way you can absorb all the cost to COPA.
    Following example will help you in understanding.
    Assume the standard cost consist of Rs 100 for material and Rs 20 for Activity totalling Rs120 .Consider a production order where it is debited with Rs 100 for material and Rs 40 for activity totalling 140 Rs. Now credit is Rs 120 (standard cost) so the balance Rs 20 is transferred to COPA after variance calculation and settlement of variance.
    Consider a production cost center where activity cost is absorbed and the debit to this cost center is
    Rs 60 and activity cost is Rs 40 which is credit. So the balance of Rs 20 can be transferred to COPA through cost center assessment.
    The balance of Adminsitration,marketing cost center is Rs 10 respectively which can be assessed to COPA through cost center assessment
    Now COPA report will look like as follows
    Sales Rs 200
    less Standard cost Rs 120
    Gross margin Rs 80
    Less Production order Variance Rs 20
    Balance Rs 60
    less Cost center balance Rs 20
    Net margin Rs 40
    Less Admin/Mktg Cost Rs 20
    Balance net profit Rs 20
    You see the Profit and Loss account as follows
    Sales 200 Rs
    less
    Material cost Rs 100
    Other cost Rs 60 (Debited to Production Cost centers)
    HR /Mktg cost Rs 20
    Balance Profit Rs 20
    In the above example, how to account for difference between Opening stock value of WIP and closing stock value of WIP is not clear to me. May be experts can throw some light on this.
    Regards,
    makrand

  • Is it possible to have Auxiliary Cost Component as Value Fields in COPA

    Respected Gurus,
    Is it possible to have Auxiliary Cost Component as Value Fields in COPA - Please Advise?
    Thanks
    PM

    Hi Praveen ,
    It is possible.. in Transaction KE4R .. we have to specify the cost component structure .. where you map the cost components with value fields..
    Please use your auxiliary Cost Comp Structure in KE4R to achieve your purpose
    Regards
    Sarada

  • Table for cost component in COPA

    Hi All,
    I would like to know what is the table to get Cost component values of material in Product Costing like I have the material number and I want to know Cost estimate price of material against cost component rows?
    BR,
    Ankit

    Hi,
    Please check tables KEKO and KEPH.
    Regards,
    Hiten Patel

  • Report painter/writer for actual cost component split

    Hello Gurus,
    Any of you guys ever explored possibility of creating a report using report painter or writer that can give both Standard and Actual cost component splits in one report? Is it even possible without custom ABAP involvement?
    Thanks
    RG

    Hi Raghu,
    After your reply, I am getting a doubt..
    Have you Activated Material Ledger? When you say Actual Cost Component Split, are you talking about it what you get in Actual Costing/Material Ledger?
    If yes, then you can map your cost compnents for Actual Costing in the path SPROControllingProfitability AnalysisMaster Data Valuation--Setup Valuation using Material Cost Estimate -- Define Access to Actual Costing / Material Ledger
    Further, there are no standard reports available in COPA. Try to build a report comprising two columns, 1st column with the value fields which are mapped for Standard Cost Components and 2nd column with the Value Fields which you have assined for Actual Costing under the above path.
    You will be able to get the comparison...
    Pls don't hesitate to call me for further assistance....
    Srikanth Munnaluri

  • Cost Component Splits

    Hello,
    We're using Special Procurement Keys in order to transfer cost estimates in a production plant to a DC.  These cost estimates currently all come over with a full cost component split.  For plants that do not belong to the same company, we don't want to see the cost component split at the receiving plant. 
    Is there any way to use Special Procurement Keys or Transfer Control so that Intercompany plant relationships don't transfer the cost component splits?
    Thanks,
    Nick

    Hello Nick,
    In SAP Product Costing, the cost will allway be stored in cost components and it will be tranferred in similar way to to higher level and tranfer to another plant. Even earlier we have faced similar issue. The better way is to understand how the system stores and do work around.
    Hope this helps.
    Regards,
    Santosh

  • Cost component with attributes restricted to 20/40

    Hello Gurus,
    The cost components have been restricted to 20/40 (SAP standard) either by combining more than one values or accommodating the CO-PA requirements within that number. Now, the requirement is to have more number of entries than the max limit of 20 each (fixed/variable), system is throwing following message - Maximum number of cost fields reached (40) (Message no. KQ304).
    Basic system design- The system is limited to 40 cost component fields. Each cost component can be set to variable or total (fixed and variable). However, the database has two fields: "total" and "fixed". "Variable" is derived. So if you set a cost component to "total" you, in effect, set up two fields (total and fixed) that need to be maintained. If you set a cost component to "variable" you, in effect, set up just one field (total) that needs to be maintained. So the basic limiting factor is that if you set every cost component to "total", you can only have 20 cost components.
    Because of this system limitation the only option left for us is to utilize 40 elements at the most without the internal split of fixed and variable portions. Now, the split is also necessary as such this workaround solution also can’t be implemented.
    Is there any additional way (user exit or some additional solution) which will allow overcoming this limitation and increasing the table entries by more than 20/40?
    Thanks & regards,
    Nikhil

    Dear Experts,
    Let currently I am facing the same issue.
    I need to increase the cost components to get the effective results in my COPA report.
    I tried to increase the Limit but I am also getting the same error.
    Maximum number of cost fields reached (40)
    Message no. KQ304
    Diagnosis
    The maximum number of cost fields defined in the system for saving the fixed and variable portions of the cost components has now been exceeded because of the new cost component.
    Regards,
    Jyosh

  • Cost component Split not transferring while costing using Spec Prc Key

    Hi Fellow CO consultants,
                                             I have come across an strange scenario in my work could you help me on it . We are using special procurement key to get the prices between cross company code costing while doing costing run the Materials which have the cost component split from KKPAN (costing without quantity structure ) we find an strange behaviour of update of the costing price .
    scenario 1:That is Using KKPAN  the FG materials are costed with fixed and variable cost and are marked (future ) but not released in the Production plant . Now while doing the CK40n at warehouse level the Cost component split is correctly picked up the receiver plant using the Spec Prc key properly the fixed and variable cost split .
    But
    Scenario 2: Using KKPAN the FG materials are  costed and then price is released and the material price is at current standard price .Now while doing the CK40N run the cost component split is not picking the variable and fixed contribution its picking up the Total price of the material .( this behavior is observed only in materials done with KKPAN other materials with quantity structure provides the variable and fixed itemization even in the current price of the material ) The prerequsite of the transfer control statergy is set as fist to check the future price for the fiscal year and next the current price of the material if no future price exist. The cost component split and the costing variant are the same .
    Appreciate your thoughts .. on helping Scenario 2 case why does the cost component split take the fixed and variable cost while the price of the material is in Current.
    regards
    GK

    Dear Prasad
    Try masking costing variant too at assignment to plant and co code.
    Rajneesh

Maybe you are looking for

  • Python-numpy broken

    Ok, my first pacman upgrade error ever I haven't been able to solve by a search in this forum, I'm afraid it might not be so straight forward. Last night doing a pacman -Syu gave me an error that said gcc-fortran was missing, found this http://bbs.ar

  • Automatic delete of dictionary baseline versions

    Hi, I'm using Grid Control 10.2.0.2. I'd like to set up nightly dictionary baselines so that I can quickly see what has changed if we experience a problem. However, I don't see any way of automatically purging data so that we avoid ending up with hug

  • WiSM 7.0.240.0

                       Guyz while checking on all WCS in security tab , attacks detected and then wIPS Denial of Service Attacks also wIPS Security Penetration Attacks does that means i have build in Wips coz im confused when i try checking Wips profiles

  • Work status

    Hi Gurus, I am trying to design security for users. For users who can approve the plan i am setting the authorizations with task profile as "set work status". But when user logs in to BPC web to change the work status, The data region is either blank

  • Fetching Data frm Table

    SQL> create table leave (sid number(10), leave_type number(2), start_date date, end_date date, days number(3)); Table created. SQL> insert into leave values (101, 12, '03-jan-2011', '05-jan-2011', 1); 1 row created. SQL> insert into leave values (101