Open quantity not displayed in SUS for Scheduled agreement

Hi,
When trying to send a Scheduled agreement from R/3 4.7 to SUS using the
Idoc DELINS, we are getting the open quantity in SUS in column
Quantity. There is another column as Open which should display the
available open quantity in the system for the material which is not
displaying. Plz do let me know what should be done to get the open
quantity in the column.
Regards,
Anand

Hi
<u>Seems to be like some OSS note is missing in the system.</u>
Please refer to the following OSS notes.
<b>
865410 SRM50-SUS: Missing follow-on doc buttons in sched agrmnt rel
807935 SRM40-SUS: Create links do not show all purchase orders
608760 BAdI for flexible plnd indep. requiremt settlement/reduction
976264 Archiving enhancements in purchasing for ERP 2005
806361 Partner ID of the sold-to party in the SUS-MM scenario
791662 SUS-MM: U.S. postal codes are not transferred correctly
791006 SUS-MM: Updated IDoc creates new order</b>
Have you raised any OSS message with SAP on this yet ?
Regards
- Atul

Similar Messages

  • IPad will open but not display information entered on a form sent as a PDF.

    iPad will open but not display information entered on a PDF file. Same file will open and display all information on my iMac. Anyone had this problem?

    I think that you are trying to view a form fields PDF file and you cannot see the content that was filled in on those fields. Form fields will not show in the mail app or in iBooks. Download Adobe Reader for the iPad. It is free and it offers a lot of features for a free app. Save that PDF to Adobe Reader and see if the text in the fields appear.

  • Header text not printed for scheduling agreement

    Hi All,
    I have issue with header text print out for scheduling agreement (SA).
    In SA when I am manually writing some note and then taking print out, system is giving me correct output with maual note.
    I have one standard text (ST) which I need to be printed in evry SA, so in SPRO I created new head text for vendor and in copying rule for text for SA, I created linkage of SA header text with Vendor head text.
    In vendor master, I inserted ST in newly created vendor header text.
    So now when ever I create new SA for vendor system will determin header text from vendor master.
    Now after creating SA when I check the SA, I am able to my ST in SA, but at the time of print out this ST in not printing.
    Please let me know what could be the reson.
    Regards,
    Sameer

    I dont understand about what you mean by expand.
    When you a print PO, PO text  (header or item) it will check to the configuration setting.
    The system didnt care if its adopted from vendor master or info record, or whatever you make in the copying rule.
    In your case : you create a standard text then it get copied into PO , then you set the standard text to the PO for print out, example the standard text : word is
    "xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
    xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
    xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx"
    Then in the PO the text appear will be like below(the same, because it get copied)
    "xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
    xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
    xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx"
    If you configure it in define text for SA, then it the print out it will also (the same)
    "xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
    xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
    xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx"
    So what text need to expand?

  • MIGO not displaying GOITEM-SGTXT for new posting

    Hi All,
    MIGO not displaying GOITEM-SGTXT for new posting
    last year postings SGTXT  is visible,
    while checking in customer exits there is no no code.
    I want to make it visible GOITEM-SGTXT.
    Plz help.
    Thanks
    Saket

    Hi guru's,
    I have similar issue with MIGO Material Doc display,
    The screen field GOITEM-SGTXT on the 'Where' tab is not displaying for current year ,
    Previous years the Text field is displaying with the data.
    GOITEM-SGTXT is getting the data from ML18N ,  ESSR-TXZ01 as the text is not entering through MIGO.
    I checked the customer exit and the BADI's for the MIGO , but not activated for manipulating the
    GOITEM-SGTXT.
    Please give me an idea what makes this issue.
    System Details:
    ECC 5.0
    SAP_APPL - 5.0     Logistics.
    SAP_ABA -  6.40   Cross-Application Component
    Thank you

  • S_ALR_87013611 is not displaying any data for GL

    Hi,
    THe report S_ALR_87013611 is not displaying any data for GL. How to go about this
    Regards
    SM

    Hi,
    S_alr_87013611 is a report where we can see the  planned and actual costs  in cost elements in cost center wise  for a specific controlling are for a given period.
    Please check if your GL accounts are assigned with the cost elements in FS00.
    If not create them.
    You can assing all cost elements to many GL  at a time using
    OKb2_ Give the range and the cost element for each range eg, expenses range - cost element 1, incomeange _Cost element as 11 etc.
    OKb3 _Create the batch input session
    SM30_ Run the batch input session created
    Also please check if you have given the cost center group costt senter range while you entered the ranges in the selection screen in this report.
    Similarly please check the cost elements and cost elements group also.
    Thanks,
    Shilpa.

  • My Mac Pro is not displaying any images for videos or games, it is showing sound and working but nothing else. DVD player is also coming up with an error.

    My Mac Pro is not displaying any images for videos or games, it is showing sound and working but nothing else. DVD player is also coming up with an error. I'm not sure why neither is working, it just suddenly happened. I have done nothing different.

    Lao Bo,
    yes, you can locate and copy a file from your HD to a USB key using UNIX commands. If you know the exact name of the file which you’re trying to locate, try this:
    find / -iname filename -print
    This command will search your entire internal disk for the particular filename. If you know that it’s within a particular user account, then you can save search time with this variation:
    find /Users/username -iname filename -print
    Either variation of this command will print all files found which have the given filename. Presuming that you’re able to identify the correct file, you can copy it to a USB key using the command
    cp -p filename_returned_by_find /Volumes/USB_volume
    If you’re not sure which volume name your USB key has, this command will show you what the possibilities are:
    ls /Volumes
    Please let me know if you have any trouble with these commands.

  • Error in MIGO for Scheduling Agreement

    Dear All,
    I have created a Scheduling agreement in LP document type and saved with Net price.
    When i do the MIGO the error appears as below.
    Transaction cannot be posted due to errors in price determination
    Message no. ME573
    Diagnosis
    The error marked with 'X' occurred during the price determination process for purchasing document 5500000087 00010:
    [X] Net price is 0.
    [ ] Net price is negative.
    and/or there are no valid conditions or the duration of the
    contract has ended.
    [ ] Effective value is negative.
    [ ] Mandatory condition missing.
    [ ] Negative delivery costs.
    [ ] Delivery costs have been recorded although invoice
    receipts are not defined for the item.
    [ ] Error during quantity conversion
    [ ] Error during currency translation
    [ ] Field overflow
    [ ] A condition involving delivery costs exists without a
    transaction/event key.
    [ ]Error during maint. of delivery costs in master conditions
                  Delivery cost conditions in different validity  periods not identical
    System Response
    The transaction cannot be posted without successful price determination.
    Procedure
    Check the purchasing document and the associated conditions:
    Display purchase order
    Display scheduling agreement
    If the problem cannot be resolved in this way, contact your system administrator.
    The latter can check the Customizing settings for price determination in Purchasing under Conditions -> Define Price Determination Process
    When the foregoing steps have been carried out, try posting the transaction again.
    Kindly advice how to avoid this error.
    Regards

    Hi
    What type of document type are you using for Scheduling agreement? I think you are using time dependent conditions. (see it in document type definition config). If the tick mark is done for time dependent condition then in additional data of scheduling agreement line item pr.date category will be 5-GR date. So Your validity period for condition is not valid for today thats why you are getting error. You need to change validity period for your conditions. Then you will not get error.
    Regards
    Antony

  • MRP To Generate SCHEDULE LINES for Scheduling Agreement

    Hi
    I have followed the below steps but still the Schedule lines is not generated for scheduling agreement.
    1Maintain MRP views 1,2,3,4 for the material in material mste.(MM01)
    2. Maintain Purchase Info Record for the vendor plant & material combination.(ME11)
    3. Create Scheduling agreement using ME31L
    4. Maintain source list for the material & the scheduling agreement # and Line item set the MRP relevant indicator 2 (Necessary ?) ME01
    During Run MRP for the material.the below details entered///
    Processing key NETCH Net Change in Total Horizon
    Create purchase req. 1 Purchase requisitions in opening period
    Schedule lines 3 Schedule lines
    Create MRP list 1 MRP list
    Planning mode 1 Determination of Basic Dates for Planned
    Run MDBT or MD02 but still doesn't create the schedule lines......Anything else missing.
    MRP1:
    MRP Procedure: PD
    MRP Group: 0000 (External Procurement only)
    Lot Size: EX (Lot For Lot)
    MRP2:
    Procurement Type: F
    Sched Margin Key: 000
    MRP3:
    Avilablity chec: 02 (Individual requirement)
    MRP: 4
    Nil

    Raj,
    Source List a Mandatory for Scheduling Agreement, if you want to create automatic Scheduling line.
    Plz use (2) in MRP RELEVENT tab in ME01 (Source List).
    rest of the thing is ok, make sure a material master(MRP 2 VIEW) in that view you have to give a planed delivery days. it is must.
    HOPE IT WILL WORK
    Regards:
    Poision

  • Delivery Schedule for Scheduling Agreement

    Hi Gurus,
    Can I do GR for scheduling agreement(with delivery schedule) if the GR is earlier than delivery date? What should I do to be able to do so?
    Thank you very much

    Hi
    'Propose all Items" is ticked so that MIGO proposes all the items irrespective of the delivery date and quantity. This means that even if the delivery date has not yet been reached or the complete qty has been received, the system will still allow you to do the GR.
    Hope this clarifies.
    Thanks

  • Automatic delivery schedule for Scheduling Agreement

    Hi all...........
    I like to create automatic delivery schedule both JIT & FRC schedules for Schedule agreement, means system has to suggest the schedule lines.
    I created SA and creation profile, when Im trying to generate JIT schedule system showing "Error generating release against scheduling agreement  (cause 2)".
    Pls let me know wht configuration I hve to do and pls let me know all the steps.
    I like to know output determination setting for SA releases also.
    regards
    Durga Ram

    Hi
    'Propose all Items" is ticked so that MIGO proposes all the items irrespective of the delivery date and quantity. This means that even if the delivery date has not yet been reached or the complete qty has been received, the system will still allow you to do the GR.
    Hope this clarifies.
    Thanks

  • Inbound Delivery For Scheduling Agreement Lines using LSMW

    Hi,
    We need to create inbound deliveries for scheduling agreements. Our scheduling Agreements are too big with 200 lines. But the vendor used to send only few discrete lines in his ASN. Is it possible to create inbound deliveries for the Scheduling agreement using LSMW? Is there any standard BAPI or IDOC available to handle this in LSMW? Has anyone done this before?
    Our requirement is as follows.
    1. Create Inbound Delivery for few lines of the Scheduling Agreement
    2. The delivery quantity of the inbound delivery will be a partial quantity of the Scheduling Agreement
    3. Materials are batch managed and the batch number for each inbound delivery item need to be captured.
    4. Vendor's ASN Number and its item number need to be captured at inbound delivery header and item level respectively.
    Note: Delivery Schedule of the Scheduling Agreement is not used in the above scenario.
    If you have any input, it will be really appreciated.
    Regards,
    SP0526

    Hi,
    You can give your scheduling agreement number in the field Purchase Order.
    If you want select from the list, you can click on PO tree (just under create inbound delivery). There selet document category as "L". You will get the scheduling agreement list.
    Regards,
    Prabu

  • Excise base amount is not changing as per the scheduling agreement

    Sub: in migo excise base amount is not changing as per the scheduling agreement type LP ( time dependent ).
    I have created the scheduling agreement type LP with time dependent.
    I have maintained the price value in two validated period i.e
    01/07/08 to 31/07/08 price is 100 rs.
    01/08/08 to 31/08/08 price is 200 rs.
    I have maintained the delivery schedule on
    15/07/08 of quantity 1 nos.
    When I am doing the goods receipts for the scheduling agreement on
    Document date I am giving 15/07/08.
    Posting date I am giving 15/07/08.
    I am giving the posting date in the excise also 15/07/08.
    After item ok.
    When I will the excise base value it is taking 200 and also excise duty is also calculating on 200.
    When I will post the document
    The stock account and GR/IR account is taking 100 only
    And excise duty is posting for rs: 200 only
    Why the excise base value is not changing as per the validity period.
    What setting I have to do the change the excise base value as per the validity date maintained in the time dependent .
    regards
    jrp

    dear sir
    doc date and posting date i have given 15/07/08 and also excise posting date i have given 15/07/08,
    but excise base value it is taking Rs:200 .
    in inforecord price date category 5-goods recepit date i have given
    yes i ahve changed the excise base value it will post , if i will not change the excise base  value i will post rs:200 only and GR/IR clearing account will post Rs100 only.
    why the excise base value will not take based on the time dependent.
    regards
    JRP

  • Data migration approach for Scheduling Agreements

    Gurus,
    Can anyone provide guidance on the data migration approach for Scheduling Agreements? How can we migrate the open delivery schedules and the respective cumulative quantities? The document type being used is "LZ".
    Can correction deliveries (Doc type - LFKO) be used update the initial cumulative quantities?
    Any help in this regard is higly appreciated.
    Regards,
    Gajendra

    Hi Zenith
    You might find useful information here: IS-U data export (extraction) for EMIGALL.
    I've done numerous IS-U migrations in the last 10+ years, but never one from IS-U to IS-U.
    One main questions to start with: Are the two systems on the same release level?
    If they are not and it would be too much effort to get them onto the same release level I would think creating your own extract programs and using the Migration workbench (EMIGALL) is the way to go.
    If they are on the same level, there might possible other ways to do it, dependent on the differences between the two systems (mainly around customising). Assuming there are significant differences - otherwise why would you bother migrating? - there's the high probability that using EMIGALL is the way to go as well.
    Yep
    Jürgen

  • Over Delivery Tolerance for schedule agreements

    Hi,
    we have overdelivery tolerance of 10%  in schedule agreement and system is allowing to do GR for more the the over delivery tolerance.
    can any one tell me how to get the error message while doing GR for more than the over delivery tolerance in case of schedule agreements.

    See OSS Note 874264 - MB01/MIGO: Default quantity for goods receipt posting
    3. The basis used for calculating the over or under delivery tolerance is the quantity ordered, in case of purchase orders, and the suggested quantity, in the case of scheduling agreements. If you want the system response to be the same for scheduling agreements as it is for purchase orders (that is, you need more generous tolerances) see also the SAP Consulting Note 741385.
    For items with a confirmation control key, the basis for the calculation of the over or under delivery tolerance is the quantity ordered or the total of the schedule line quantities.

  • Idoc Message type for Scheduling agreement

    Dear Experts,
    How to configure to create Idoc for Scheduling agreement (not the releaseed schedule lines) ?
    I am trying to use message type ORDERS05 but it is not working.
    Will any body guide me preferably step by step process for this ?
    Thanks in Advance,
    Best Regards,
    Raju

    Hi Anji,
    Thanks for the Reply. But i think ORDRSP is for Order Confirmations.
    But I have to send Outbound Idoc for a Schedule Agreement.
    Whether the same  Idoc type & Messge type used for SO/PO(e.g ORDERS05, ORDERS/ORDCHG) can be used for Scheduling Agreement.
    Please Advice.
    Regards,
    Anbalagan

Maybe you are looking for

  • X11 cursor not generated correctly with xcursorgen

    I need some help with the animated cursors... running:     sudo xcursorgen left_ptr_watch.config watch from the source directory generates no errors, but does not create a file for the cursor? The folder layout is: ~/Path to cursor/source/left_ptr_wa

  • General Ledger PLD month wise Debit,Credit,Balance total of a G/L account

    Dear all, How to customize template in General Ledger PLD monthwise Debit,Credit,Balance total of a G/L acct ? Jeyakanthan

  • Stream Device Driver Development

    Hai, I am doing "Stream Device Driver" in "SunOs 5.8" Using "Forte C++ " Compiler. This Driver Type is Multiplexer. My Coding is Over but i can compile my code. But I am not able Link the object file. Compiler giving error is # make cc -r -o /wacom /

  • [POL-5150] access violation

    I am running 8i Lite on Windows 2000. After creating a user (newuser)in Oracle8 Navigator, I then create a table and set owner to newuser. After logging into POLite using SQLPlus as newuser I get a [POL-5150] access violation error when I attempt to

  • Importing model for CU50 in NWDS

    Hello everyone, Is there a BAPI that I can use for CU50? I am trying to build a Web Dynpro Application where I am trying to import a model for the component in NWDS, but I am not able to find a BAPI which is used for Variant Configuration. Any help w