Primavera and Operational Planning processes

Dears
I am actually looking into implementing a Project Management and Control Methodology using Primavera P6. May be this question will be more business related one, but I wanted just to get a clearer overview about Primavera capabilities. Some of the organization need to organize their planning activities through a special operational planning approach to make the planning much more organized an streamlined inside the organization.
Does Primavera P6 provide the needed capabilities to support Operational Planning management?
Looking forward for your reply
Best regards
Mohamed Chargui

Dear David,
Thanks for your immediate reply. Actually we need to develop the Operational plans for each an every division in the organization. I fact we will need to be able to:
1) Develop the Operational Plan.
2) Update the operational Plan.
3) Remove the Operational plan
Thanks in advance
Best regards
Mohamed Chargui

Similar Messages

  • SOP - Routing data consideration in the Sales and operation planning

    Hi,
    Please share knowledge how to take the consider routing while doing the sales and operation planning.
    I have done the resource planning in the sop and it is picking the data's from the rought cut profile also. As per sap help it is mentioned that in sop we can use routing or rate routing also to do the resource planning in sop.
    Where the setting to be done?
    If answered.. full pointed will be rewarded....
    Regards,

    Hi,
    Thanks for your reply.
    As per my knowledge T-code will be OPU4 for the Sales and operation planning.
    The T code OPU5 is applicable for planned orders not for SOP internal orders.
    I have checked the senario and reverting back to you.
    Did you checked the senarios for the resorce leveling with out creating the rough cut planning profile by t code mc35?
    Please give you yahoo or gmail messanger or telephone number ....
    Regards,
    Mahesh Garg

  • AND OPERATION  AT PROCESS CHAIN

    Hi bw experts,
             I am facing a problem  frequently. Daily a process chain failed frequently at the AND operation.  What is the exactly the situation is before the AND operation there are three  local chains are there and after the  AND operation there are one more local chain and  program is there. Even it not taking repeat at the AND  operation.The message showing that previous chains are not completed.   Anyhow we running it manually . What are the possible reasons for  failure of the AND operation.
    But  what may be the  permanent solution to this problem.
    Thanks& Regards
    Vinod kr

    Hi Vinod,
    Before AND operation there are three Local process chains if these three local chains  are successful completion only then AND operation is success.
    Suppose if you correct the three local chains errors manually ,you have to start the AND process by REPEAT option.Because the the three local chains are not success through the chain.
    If it is useful please assign some points
    Regards,
    Madhu Ponnada

  • Sales and Operational Planning

    Hi,
    Currently i am working on the scenario of SOP . With due respect, please let me know if tere is any report related to comparison b/w production nd sales figures. Or if instead of that tere is any other report on SOP please let me know. 
    Thank you

    Do you mean transactiopn MC94? It's for checking and editing planning data  via the Planning Table.
    Claire

  • Version related problem in Sales and Operations planning

    The system has been upgraded from 4.6C to ECC 6.0. We are facing the following problem in production (the problem was not there in upgraded development server)
    upto last year client has consumed version number up to 321. Yesterday they have created and saved a plan with version number 322 for material M1 and Plant P1. Now,
    1.     T-code MC87. for material M1 and plant P1, Hit enter.Current version shows as , say, 323.
    3.     But if you try to create another plan and enter a new material in MC87 (say M2), the version number shows as 322 instead of 323.
    Please suggest what may have gone wrong and how to correct.
    Thanks in advance.

    Dear,
    OMP2 is only use to create the version number  please check the version number here.
    Also note only active version will relevant for MRP.
    Regards,
    R.Brahmankar

  • Sales and Operations Planning - forecast on customer/material

    Experts,
    What are the possibilities to maintain a forecast for customer/materail combinations?
    The requirement is only to maintain a forecast and the actuals should be updated automatically (from sales requirements). These actuals should consume the forecast so that it's always up to date. A link with PP is not needed.
    I'm not so familiar with S&OP --> what is possible in standard and how?
    Thanks

    Jan,
    As I see ur reqt, certainly doable if u use the SOP within PP mmodule. With Flexible SOP u can def'ly plan a combi of Cust & Materials (in the sequence u want - Matl > Cust or Cust > Matl)..Chk out the options, help is pretty elaborate..
    cheers

  • "standard" SAP roles for Sales and Operations Planning (SAP SOP)

    Hallo,
    I´d like to ask SOP specialists, if there are any "standard" SAP roles, which could be created when SOP is implemented into the SAP system.
    If not, could you please send me advice, what is (are) the general role(s) for SOP (which SOP transactions and roles)?
    Thank you for your effort,
    Martin

    -->
    If you dont have the role --> open OSS
    if you dont find it because there are so many:
    Good luck :-)

  • Difference between standard SOP and Flexible planning

    Hi, Pls explain the difference between Standard SOP (sales and Operation planning) and flexible planning?

    Hi,
    Following links will help you to understand.
    https://forums.sdn.sap.com/click.jspa?searchID=20534538&messageID=6314185
    The contents are as below :
    Steps
    1) Create Planning for material MC87
    2) Copy to Active Version MC78
    3) Transfer to Demand Mangement MC74
    B) STD sop for Product Group
    Here also the Characteristics are same material->product group
    You have to maintain master data Product group
    steps:
    1) Create Product Group MC84
    2) Create Plan for Product Group MC81
    3) Disaggregate Product Group Plan MC76
    4) Copy to active version MC78
    5) Transfer to Demand Management mc75 for Pg or mc74 for material
    FLEIXIBLE PLANNING
    Here you can able to Define your own characteristics and Key figures
    Char like Sales org,Dis chann, Div,......
    Key figures like stock,invoice qty,....
    steps
    1) Create Info structute MC21
    2) Maintain Planning Parametes MC7F
    3) Create Planning Type MC8A
    4) Create Flexible Planning MC93
    5) Copy to active version MC8V
    6) Transfer to Demand managemet
    5) Create Std SOP Planning -MC
    6) Transfer to DM from change mode of Flex Plann with active version MC94
    if you want use the flexible planning info like SIS in std sop
    after the 4th step of above it will be like
    5) MC87 std sop there Sales data from SIS it will ask for info str and version then you can get it automatically then the std steps like
    6) Copy to Active Version MC78
    7) Transfer to Demand Mangement MC74
    Please refer this link also,
    SOP Process

  • I have tried to update the operating system on my ipad several times without success.  Each time it reaches 353.2mb of 353.2mb and starts to process the file.  Nothing happens and then I get a message saying the network connection has timed out.

    I have tried to update the operating system on my ipad several times without success.  Each time it reaches 353.2mb of 353.3mb and starts to process the file.  Nothing happens and then I get a message saying the network connection has timed out.  The network is still connected.

    Have you tried temporarily turning off your firewall and antivirus software whilst the download is happening ? A number of people on here have had success downloading it after doing so.

  • Career and Succession Planning Business Process

    Dear Friends,
    Can anyone send me anyone client Model Career and Succession Planning Business Process.
    Regards,
    M

    Career and succession planning are generally different business proceses.
    Generally you would need to map the client's own processes; as using a standardised approach here might not serve the purpose
    Suggest that you check with your client to share with you their ISO / EPM documentation for these processes.
    Else, ask the process owner to shared with you a PFD for the process.
    Hope this helps.

  • My iMac computer was recently worked on and in the process it was completely stripped down and new operating system installed.

    My iMac computer was recently worked on and in the process it was completely stripped down and new operating system installed.
    OS X Yosemite version 10.10.1.
    After this trip to be serviced, when I try to open Photoshop, I get a message "Licensing for this product has stopped working".
    At the bottom of the error window,  Error: 150:30
    If you continue to see this message after restarting your computer, please contact Adobe technical support for help.
    Any help resolving this issue would be greatly appreciated!
    Thank You,
    joe

    Error "Licensing has stopped working" | Mac OS

  • Issues with CAL Free Solution - SAP BPM and Operational Process Intelligence on SAP HANA [developer edition]

    Hi,
    When I want to suscribe to the CAL Free Solution - SAP BPM and Operational Process Intelligence on SAP HANA, on the Terms and conditions page, even if I scroll down, the button "I accept" is not available.
    Do you have any tips ?

    I am trying to download the SAP BPM and Operational Process Intelligence on SAP HANA [trial edition] - AWS version and get a security error.
    Any ideas where we can get a 90 demo version of SAP PO/PI that will work with AWS?  I am trying to refresh myself on PI7.4?

  • How to analyse actual cost for each operation in Process/Production Order?

    Hi all,
    IN SAP, I know that we can analyze plan cost for Operation in Process Order/ Production Order.
    However, I can not analyze Actual cost for Operation .
    I know the object when I good issue material is ORDER, not OPERATION.
    But, as requirement of users, they want to analyze actual cost for each Operation.
    CAn SAP do this analyze?
    If Yes, What should I do in SAP to have this reports?
    THanks in advance,
    Emily Nguyen

    Hi Emily,
    as I see from one other message that you're using material ledger. Then your expectation is apparently to also see the actual costs of materials in your production order by operation.
    This is not supported. Actual material costs are handed up in material ledger multi-level settlement from one material to the next, bypassing the production orders.
    That means the production order will always contain the material costs valuated at plan price, not at actual price.
    For activity prices that might be better, when you revalue the orders at actual activity prices with CON2. But even there I am not sure that it will always be assigned correctly to the operations.
    There is currently an enhancement in development, the operation level costing. But that will affect more the planned cost side not the actuals. Might be interesting to learn more about your requirements and the use case behind.
    best regards,
                      Udo

  • Sales Operation Planning

    Hi All,
    In Sales Operation Planning , Can we plan a Bulk of 200 materials without Product grouping or individually.
    Please suggest if any solution available.
    Regards
    Subbu.

    Hi,
    http://sap-pphelp.blogspot.com/2010/01/sop-flexible-planning.html
    http://www.scribd.com/doc/23491525/How-to-Work-With-SIS-Structures
    1.     Create Field Catalogue MC18
    2. Create Info Structure MC21
    3. Create Update Rules for Characteristics and Key Figures MC24
    4. Activate Update Rules OMOZ
    5. Testing (Use Sales Order, Purchase Order, Material etc.) to test data
    MC30
    6. Set Parameters for Info Structures MC7f
    7. Create Planning Type for Info Structure Planning Table MC8A
    8. Generate Master Data and generate proportional factors MC9A
    9. Create Planning Hierarchy MC63
    10. Create Forecast Profile MC96
    11. Create Planning Activity MC8T
    12. Setup Mass Processing Job to generate forecast MC8D then MC8G
    13. Maintain all Material Master records with unit of measure conversions
    so that the planning table can aggregate materials into a common unit of
    measure. MM02
    14. Apply OSS patch program that enables visibility of all nine hierarchy
    planning levels in planning table. (Check version 4.5 and prior)
    15. Set up program to collect Historical transaction information (Need
    Custom ABAP program to populate the SOP table with historical data)
    16. Run Monthly Sales Forecast MC8D
    17. Transfer to COPA (if applicable)
    18. Run COPA Analysis (if applicable)
    19. Transfer forecast to Demand Management MC94 (Extra Menu -> Transfer to demand mgmt)
    20. Demand Management receive the updated Sales Forecast quantities MD61
    Regards,
    Ravi

  • Control Plane and Data Plane

    Hi there,
    I'm trying to figure out how to determine and how to differentiate between control plane and data plane especially in troubleshooting MPLS VPN. Any keyword that distinguish between them? It seems to be confusing for a newbie here :)
    Thanks in advance.
    maher

    Hi Maher,
    The control plane is simply the set of processes that are responsible for disseminating information on routes, labels etc within a network. This includes routing protocols whose job is to communicate information on routes between different routers. The information provided by these protocols is then used to building routing/forwarding tables.
    The data plane is simply an abstraction used to describe the actual flow of data packets using paths determined by the control plane. The control plane traffic carries control traffic (which is not end-user data) whereas the data plane traffic is actual end-user data.
    There is no single command that you can use to distinguish between the two. The commands you have on a router that can be used to view control plane operation are as such:
    sh ip route
    sh ip cef
    sh ip bgp ...
    sh ip ospf ...
    sh mpls forwarding-table...
    etc... and many, many more
    Typically, there isn't a clear demarcation between commands that display control plane info and those that display data plane information... You could use commands such as the following to get some idea of data traffic flowing through a router:
    sh interfaces
    sh policy-map interface
    etc.
    Hope that helps - pls rate the post if it does.
    Paresh

Maybe you are looking for

  • How do I select multiple albums in Revel to start/stop sharing?

    How do I select multiple albums in Revel to start/stop sharing?

  • Can't connect to AOL website---​but other sites are fine

    To whom it may concern..... Im having a really odd problem here that has been plaguing me for the last 6 months, my wife can not get to www.aol.com on one of the following devices, one of 3 laptops (2 win 1 mac), 2 iphones, 1 ipad or a desktop comput

  • Slow WiFi only on home network and only on Mac

    I have a 2010 MacBook Pro and internet downloads and especially viewing any videos (like youtube) are painfully slow at home. Videos basically load for a few minutes, play about 5 seconds of video, then load for a few more minutes. I know it is not t

  • Auto eject volume with SuperDuper doesn't seem to work

    Not sure if there's a problem with my system or what. I use SuperDuper to backup and create a clone of my MacBook Pro and have checked the feature for SuperDuper to eject the mounted volume after the backup is complete. Once the backup is finished, I

  • Usage Report not showing data

    Hello, When I am opening usage reports under Site Settings > Site Administraton > Popularity Trends, i cannot see any data after 9th May 2014. It stopped working and all the numbers coming to zero after 9th may.  I tried many solutions that are given