Hi,
Currently client has 2 database companies with Financial year 1st September 2009 to 31st August 2010.
However, they want to close the 2 companies with only 8-months and they are legally setting up a new amalgamated company with posting period starting 1st May 2010.
Company 1 has more information. What would be the best option?
1) Create a new database for new company and move across opening transactions from 2 old companies.
2) Delete 4 periods from 1st company database for May to August 2010. Create new posting periods for new company in 1st database. Move across opening transactions from 2nd company to 1st. Change the Admin name of company 1.
3) Any other ideas?
What impact will option 2 have on financial reports?
Thanks.

If it is legally a new company, there should not be any open transactions. These transactions would be closed off in the old company? You may need to clarify whether you are just creating opening balances & transferring master data, or if open debtors etc need to be transferred
The best practice would be to create a new company. Changing the length of financial years impacts on the sbility to run XL Reports, and on the Fixed Assets module - which simply won't work at all after a change in FY.

Similar Messages

  • The QA process for new extension submission.

    Just have a few general questions about the process for new extension submission. I submitted a new extension to the exchange on June 21, but have yet to see the status of my item change. What's the typical turnaround time for the QA team on new extensions? As well, should there be any issue with a new submission, what kind of feedback is typically given? Thanks to those who've gone through the submission experience, and can answer my questions.
    kindest regards,
    Johannes

    To follow up on this question. On August 23rd my extension was approved. Not sure if this is the typical amount of time to expect for a submission to be approved as this is the only extension I've submitted so far. I never recieved any requests to change my extension, so the length of time wasn't due to changes that needed to be made on my part. Based on the large number of extensions approved on the same date as mine, my guess is that Adobe waits till they have a fair amount of submissions to QA, and then puts them through the QA process in batches.

  • Process for new hard drive

    Hi everyone,
    I was hoping somebody could point me to some tutorials for upgrading the hard drive in my PowerBook G4 (1Ghz).
    I own an external drive (usb only) that is the same size as the drive in my PB (80gb), this is what I'd use to back up my hard drive (I could borrow a larger drive from work if necessary).
    What is the best process for backing up? Should I use Carbon Copy? I already have Retrospect Express.
    How can I make sure that I won't need to reinstall all my 3rd party apps (ex; iLife, Photoshop)? Would all of this be ported over when I copy my old hard drive over to the new hard drive?
    What is the best process for copying the backed up/copied hard drive to the new hard drive? Won't I need to reinstall Tiger first? Then run updates?
    Thanks for the help!

    "What is the best process for backing up? Should I use Carbon Copy? I already have Retrospect Express."
    I just replaced my drive, I used SuperDuper, it worked flawlessly, a major first for me since using OS X. I swear I'm not from that company, but it made a perfect bootable disk, important since I was swapping drives directly after copying data via USB to external enclosure. Had drive duplication problems prior, carbon copy was a no-go for me, to complicated, something not right w/ the updates, i forget what, it has been a while, just remember I was forced to reinstall apps.
    Should have gotten a firewire enclosure, could have tested it first w/ target mode, oh well.

  • List of issues and fixes for procure to pay process and order to cash process for a trading company

    Dear All Gurus
    Kindly tell me where I can find the list of all issues arising in procure to pay process
    and order to cash process and there fixes for a trading company in support project
    Thanking You
    Abdul Baseer

    Hi Abdul,
    There are no standard list to provide, you should identify the issue through regression testing and raise an SR or create a thread accordingly we can help you.
    Note:- Issues are vary to instance to instance, version to version, installation to upgrade etc..

  • Accreditation process for new I Tune U site

    What's the process for getting accredited for a new I tunes U site?  how much course content does an institurion need to get started? How big/accredited does the institution have to be?

    iTunes U is a free service available to qualifying two- and four-year accredited, degree-granting, public or private colleges and universities in the United States, Australia, Austria, Belgium, Canada, China, Denmark, Finland, France, Germany, Greece, Hong Kong, Ireland, Italy, Japan, Luxembourg, Mexico, Netherlands, New Zealand, Norway, Portugal, Singapore, Spain, Sweden, Switzerland, and United Kingdom. Universities and Colleges must enter into an iTunes U Service Agreement before being eligible to use the iTunes U service. Apple reserves the right to determine eligibility.
    When reviewing an institution's accreditation, we utilize nationally recognized accrediting organizations such as The Carnegie Classification of Institutions of Higher Education.
    If you are an education focused cultural organization interested in becoming an iTunes U Beyond Campus provider, please send an email to [email protected]
    -Thanks

  • Process for changing a company code

    Looking for information regarding the process required to change a company code.  We have an existing company A and need to change to company 100.
    Areas that I need to address are FI/CO, SD, MM.  The existing account balances of company A need to be transfered into company 100.
    Thanks,
    Robert
    Edited by: Robert Roe on Mar 5, 2008 1:55 PM
    Edited by: Robert Roe on Mar 5, 2008 1:56 PM

    hi,
    i found this.
    Sometimes during your IDOC/BAPI communication you will get error "No global company code is assigned to the company code" & Message no. FC 326 in Idoc status record.
    This problem is very frustrating. The solution is simple, but hard to find.
    There is a very long menu to get there. It is: IMG > Basis Components > Application Link Enabling (ALE) > Modelling and Implementing Business Processes > Cross-Application Settings > Global Organizational Units > Cross-System Company Codes
    1. Create a cross-system company code.
    2. Assign the cross-system company code to a chart of accounts to which it is also assigned on the central system. This setting is needed on the decentral systems in order to determine the chart of accounts of the company code on the central system.
    3. Assign cross-system company codes to the local company codes. Specify the identifiers of the relevant cross-system company codes for each of the individual company codes.

  • Suggestation for new IT Company

    Hello,
    One of my friend is going to open an IT company in India. The main business will be software development and data processing. He is going to adopt around 80-90% Oracle technologies and products and rest other i.e. open source tools. He requested me to write here to get couple of good tips, some expert comments to make it a successful decision. Will you please share your good advices, comment few lines which help him to get his goal. I mean, what he should do, what should not etc.
    I know that this is not really 100% relevant to this forum, but hope for something which i have got many time please. Since in many companies, Oracle DBAs are playing master role in their company's business, i hope i may get really good points. I shall be thankful to forum administrator if they don't delete my question and lock the thread please.
    Thank you.

    user12050217 wrote:
    Hi Ed,
    What kind of "more" advice is your friend looking for?Something like :
    The main business of the company will be data processing, data entry and medium level software development. So,
    1.What sort of precautions should be taken at the initial stage ?Insurance: Product Liability, Business Continuity.
    2.Good tips to catch the project ?
    3.Customer satisfaction guidelines using Oracle tools, technologies and Open source.
    4.Cost reduction tips.
    5.How to handle the situation when guys want to leave the company due to higher salaries in other company ?
    6.Good relation tips for competitors.
    7.How to maintain healthy business environment at work place.
    8.Etc...
    Once again, i know these are no more related to Oracle Database Technology issues, but if anyone write/share some tips, advices, i hope it would be helpful to others too.
    Thank you.

  • Hi i want to insure my mobile but they need prove of purchase but i dont have plz tell me what is a process for new print  plz...

    Hi i want to insure my mobile but they need prove of purchase but i dont have can i have new print plz..

    Did you buy the iPad from the Apple online Store?
    If you did, you can browse to the Apple Store > click Account in the top right > click View Order History. From there, you can view orders over the last 18 months and print invoices.

  • Increase the number of background work processes for data load performance

    Hi all,
    There are 10 available background work processes in the BW system. We're doing some mass load to multiple ODS.But system uses only 3 background processes. How can i
    increase the number of used background work processes for new data load.
    I tried to change number of prosesses with RSODSO_SETTINGS. But no successes. Are there any other settings need to change?
    thanks,
    Yigit

    Hi sankar,
    I entered the max proc. number into ROIDOCPRMS. But it doesn't make difference. System still uses only 3 of background processes. RSCUSTA2 is replaced with
    RSODSO_SETTINGS in BI 7.0 and this trans. can only change the processes for data activation, SID generation and rollback. I need to change the process numbers for data extraction.

  • Down payment process for Poland, new business process or not ?

    Hello,
    I'm a little bit confused about implementation down payment process for Poland.
    The OSS-notes 818079 and 1007635 describe a solution for this.
    How do I have to implement the correct down payment process for Poland ? Do I have to create an extra business process with new sales order type, new billing type, separate calculation procedure, new output type and so on ?
    Or is it possible to use existing business processes in sales and distribution for down payment processes ?
    Thanks in advance
    Holger

    hi,
    Check the process for down payment processing
    The following Customizing settings have to be made for down payment processing:
    Settings for the billing plan - To activate the billing plan function, maintain the materials, for which you wish to process down payments, with item category group 0005 (milestone billing). This gives the item type TAO via item type determination. The item type TAO calls up the billing plan function.
    You need to implement the following activities in the billing plan for down payments:
    Maintain deadline category - This determines the billing rule (percentage or value down payment) for the down payment request. The system assigns billing type FAZ (payment request) defined in the standard system with billing category P. (For the billing type FAZ there is the cancellation billing document type FAS in the standard system).
    Maintain the deadline proposal - Use the down payments that are due for the proposed deadlines.
    Maintaining a Pricing Procedure with the Condition Type AZWR:
    In the standard system the condition type AZWR is delivered for the down payment value already provided but which has not yet been calculated. You must include this condition type in the relevant pricing procedure before output tax.
    Enter condition 2 (item with pricing) and the calculation formula 48 (down payment clearing value must not be bigger than the item value) for the condition type AZWR.
    Before the condition AZWR you can create a subtotal with the base value calculation formula 2 (net value). If the condition AZWR is changed manually, you can get information on the original system proposal from the subtotal.
    Maintain the printing indicator - The pricing procedure can not be marked as a transaction-specific pricing procedure (field Spec.proc.) The condition type AZWR has the calculation type B (fixed amount) and the condition category E (down payment request / clearing).
    Maintaining the Billing Document - In the standard system there is the billing type FAZ (down payment request) and the billing type FAS for canceling . The down payment is controlled using the billing category P of the billing type. A billing type becomes a down payment request when the billing category P is assigned. You have to maintain blocking reason 02 (complete confirmation missing) for the billing documents and assign it to billing type FAZ.
    Copying control - Copying requirement 20 must be entered in copying control at item level for the down payment request. In the standard system the order type TA for copying control is set up according to the billing type FAZ for the item category TAO.
    Copying requirement 23 must be entered in copying control at item level for down payment clearing. In the standard system the order type TA for copying control is set up according to the billing type F2 for the item category TAO.
    Financial Accounting settings - A prerequisite for down payment processing is that the account is assigned to the underlying sales document. To do this, change the field status settings in Customizing as follows:
    Set reconciliation accounts (transaction OBXR) - For the `received down payments' and `down payment requests' from
    the G/L accounts you have selected, you should assign the field status definition G031.
    Maintain accounting configuration (transaction OBXB) - For the down payments (posting key ANZ in the standard system) and the output tax clearing (posting key MVA in the standard system), you must maintain the posting key.
    You must also carry out a G/L account number assignment for the tax account.
    Maintain the posting key (transaction OB41) - For posting key 19, set the sales order as an optional field !!!
    Maintain the field status definition (transaction OB14) - For field status variant 0001, field status group G031, set the
    sales order as an optional field !!!
    Assign the company code to the field status variants (transaction OBC5)
    chandu

  • BPM process for manufacturing company-PBL code.

    I am very new to Oracle BPM and I'm currently using Oracle BPM 10g. I have done the expense report tutorial once.
    And now I'm designing a process in a manufacturing company. I have a group,'items' with attributes name, pricePerItem, Quantity and Total. here Total is the product of pricePerItem and Quantity. the PBL program i wrote for it is :
    amt as Decimal(3)
    for each item in items do
    amt = item.pricePerItem * item.quantity
         end     
         return amt
    I have another attribute grossamt which is the sum of the every item's total value. the PBL program for this is:
    amount as Decimal(3)
    amount = 0
    for each item in items do
    amount = amount + item.total
    end
    return amount
    However after I run the project, the 'total' field doesnt get calculated or populated which in turn leaves the grossamt field empty. Without this my process cannot proceed.
    Please let me know if there is any error in the code i wrote above.
    Or if there is any other work around for the same.
    Thanks a lot in advance.

    There's a trick you can employ that should make this easy. When you open an attribute, notice that you have a "Virtual" checkbox. After checking this, you'll notice that under the attribute in the Project Navigator tab that there will be "read" and "write" method.
    For your line item total attribute inside the group add this logic to the read() method associated with the virtual attribute:
    // this sets the line item “itemTotal” attribute of a Group.
    //   (defined as Virtual). This code is in the Read Access
    //    method for the itemTotal attribute and
    //    “pricePerItem” and “quantity” are attributes in the group
    return pricePerItem * quantityFor the overall total of the order that is based on the sum of the indiviidual order item lines in the group, add this logic in the virtual "grossAmount" attribute's read() method. The logic shown below assumes that your group's name is "items" and your order line item attribute inside the group is called "total".
    // this is in a Virtual attribute’s Read Access code (the sum
    // of all the order line items in a group is the order’s total)
    return items[ ].total.sum( )Dan

  • Configuration for new company

    Dear Experts,
    If new company is getting created in SPRO then does EHS also gets impacted. I mean do we also  need to do customization in EHS, if yes then what is the configurations or customization that are required to be created? Could you please list them. As far as my knowledge is concerned data in EHS is not company specific hence no separate customization is required.
    Devdatt

    Dear Devdat
    MSDS distribution is triggered by SAP SD process; please check the corresponding EHS customizing, it is "well" explained what need to be done if additional company is activated. On the top there is an OSS existing explaoining the whole set up to be done in SDS/MSDS distrbution starting with SAP SD process; if you read cross it should be "clear" what need to be done if new company is coming up.
    The "same" is true for SAP EHS DG process; it is highly integrated in SAP SD process; if new company is activated in most cases you need to add entries here
    Regardin GL;M the answer here is not easy. Depending  on the "needs" for the new company you need to establish the "whole" GLM process (mainly scenario Make to Stock, Make to Order etc.). There is no documentation or guideline availabll to be used; and as GLM is used in most cases company specific no clear answer can be provided regarding the needed activities.
    Check may be: SAP EHS Management for Beginners
    You will find a lot of references for MSDS/SDS distribution, DG checks etc. Regarding GLM and your specific quesition / topic: I am not aware of any similar thread in this FORUM.
    On high level: in EHS BD no action is needed; in EHS-SAF (SDS/MSDS), ESH-DG actions are needed
    C.B.

  • Transportation process for Logistic company

    Hi Experts,
    We are going to open a new Transportation Company, provide Cargo & Transport service to inside/outside customer. Plz tell me what is the process from the begin & how am implement this in SAP system?
    Regards,
    Sanjay

    Transportation Configuration:
    Process 1
    Step: 1
    Maintain Purchase Organization
    Path: Sprou2014Enterprise Structureu2014Definitionu2014Materials Managementu2014Maintain Purchasing Organization.
    Step: 2
    Create Purchasing Group
    Path: Sprou2014Materials Managementu2014Purchasingu2014Create Purchasing Group.
    Step: 3
    Maintain Transportation Planning Point to Company Code.
    Path: Sprou2014Enterprise Structureu2014Definitionu2014Logistics Executionu2014Maintain Transportation Planning Point
    Step: 3A
    Assign Transportation planning point to company code.
    Step: 4
    Assign Purchasing Organizations to Company Code.
    Path: Sprou2014Enterprise Structureu2014Assignmentu2014Materials managementu2014Assign Purchasing Organization to Company Code.
    Step: 5
    Assign Purchasing Organizations to Plant.
    Path: Sprou2014Enterprise Structureu2014Assignmentu2014Materials management-- Assign Purchasing Organization to Plant
    Step: 6
    Create Vendor Account Group
    Path: Img u2014Financial Accountingu2014Accounts Receivables and Accounts Payablesu2014Customer Accountsu2014Vendor Accountsu2014Master Datau2014Preparations for Creating Vendor Master Data--Define Account Group
    Step: 8
    Create Vendor
    T-Code: XK01
    Step: 9
    Define Modes of Transport
    Path: Sprou2014Logistics Executionu2014Transportationu2014Basic Transportation Function---Routesu2014Define Routesu2014Define Modes of Transport.
    Step: 9A
    Define Shipping Types
    Path: Under the Same Menu path---Define Shipping Types
    Select New Entries and Assign the Shipping Type (e.g. Road or Train) and Assign Mode of Transport (Mdtr) and Assign Shipping type Procedure group.
    Step: 9B
    Define Transportation Connection Point
    Path: Under the Same Menu path--- Define Transportation Connection Point.
    Step: 9C
    Define Routes and Stages.
    Path: Under the Same Menu path--- Define Routes and Stages.
    Select the New Entries and Enter the Details
    Then Select the Routes stages and define
    Step: 9D
    Maintain Stages for all Routes.
    Path: Under the Same Menu path---Maintain Stages for all Routes.
    Step: 10
    ROUTE DETERMINATION
    Define Transportation Zone
    Path: Sprou2014Logistics Executionu2014Transportationu2014Basic Transportation Function---Routesu2014Route Determinationu2014Define Transportation Zone.
    Step: 10A
    Maintain County and Transportation Zone for Shipping Point.
    Path: Under the Same Menu path--- Maintain County and Transportation Zone for Shipping Point.
    Select the Shipping point and enter the Country and Transportation Zone
    Step: 10B
    Define Transportation Groups.
    Path: Under the Same Menu path---Define Transportation Groups
    step: 10D
    Maintain Route Determination
    Path: Under the Same Menu path--Maintain Route Determination.
    Select New Entries and Define the Route Determination.
    SHIPMENTS
    Path: Sprou2014Logistics Executionu2014Transportationu2014Basic Transportation Functionu2014Shipments
    Step: 11
    Define Shipment Types
    Path: Sprou2014Logistics Executionu2014Transportationu2014Basic Transportation Functionu2014Shipmentsu2014Define Shipment Types.
    Select the New Entries and define Shipment Type
    Step: 12
    go to Customer master data.
    In Address of General data. Enter the Transportation Zone id. And save
    U will get the route.
    Process 2
    1) Maintain transportation planning point through Menu as follows:
    Enterpriseà Definition à Logistic Execution àIMG Maintain  transportation planning point.àStructure
    Create your own like BP01 enter the general data¡¯s required
    2) Defining modes of transport:
    Logisticà Transportation àBasic Transportation Functions àIMG Routesà àDefine routesàExecution Define modes of transport
    Use the standard like:
    Shipping type: 01
    Description: Road
    3) Define shipping types :
    IMG DefineàLogistic Executionà Transportation àBasic Transportation Functionsà Route àshipping types
    Or through T-code: SM30
    PT: 01
    Description: Truck
    Mdtr: 01
    STPG: 0001
    4) Define transportation connecting point :
    BasicàRoutes àIMG DefineàLogistic Execution Define transportationà Transportation àTransportation Functions  routesàconnection points
    Copy the std point and make it FB01 as departure zone and FB02 as destination zone
    5) Define routes and stages.
    Logià BasicàRoutes à Define routes àIMG Defineàstic Execution  Transportation routes and stagesàTransportation Functions
    Use the standard route and copy it as FB0001 and enter the departure zone and destination as what we created.
    6) Defining Transportation Zone:
    àIMG Define transportationàLogistic Execution à Transportation àBasic Transportation Functions zonesà Route àRouter determination
    Use the standard transportation zone depending on the route so as for the example use 0000000003 - Southern Region
    7) Maintain country or transportation zone for shipping points
    à Route determination àIMG à Logistic Execution à Transportation Maintain country andà Basic Transportation Functions àRoute  transportation zone for shipping point
    Shipping point be ASH1 and route as 0000000003 which is assigned to country India
    8) Maintain route determination:
    Basicà Route àIMG Route determinationàLogistic Execution  Maintain routeà Transportation àTransportation Functions  àdetermination
    Country of departure: India
    Departure Zone: 0000000003
    Country of destination: India
    Destination Zone: 0000000003
    And enter the datau2019s needed like shipping condition 01, etc.
    Maintain Transportation relevance for shipping point, sales document type and delivery types.
    9) Now create shipping types
    IMG Defineà Logistic Execution typesà Transportation à Shipments àshipment
    Copy the standard 0001 and make it to AFIL
    10) Define and assign traffic zones through T-Code: T_76 (or) thru menu as follows
    BasicàIMG Defineà Logistic Execution and assignà Transportation à Shipments cost àfunctions  tariff zones
    Copy the standard and make it to FABTARIFF and assign our transportation planning point as ATP1, ATP2 assign tariff zone to every particular transportation planning point
    11) Define and assign pricing procedures
    IMG define andà Logistic Execution à Transportation àShipments cost proceduresà Pricing à Price control àassign pricing
    Copy the standard shipping cost pricing procedure SDFC00 to FBSC01
    12) Assign purchasing data:
    àIMG Assign purchasing dataà Logistic Execution à Transportationà Shipments cost àSettlement 
    13) Assign transportation planning point to shipping condition, purchase organization, purchasing group and to plants.
    14) Define Automatic G/L account determination:
    à àIMG Automatic G/L Account Determinationà Logistics Execution àTransportation  Shipment CostsàSettlement 
    Or through T-code: OMWB
    Use G/L account 614000 as used in standard
    15) Automatic determination of CO assignments:
    Transportationà Shipment Costs à Settlement àIMG Automaticà Logistics Execution Determination of CO Assignmentsà Or T-code: OKB9
    16) Maintain shipping point address.
    à Logistics Execution à Enterprise Structure Define, copy, delete, check shippingàDefinition  point
    17) Creating G/L account centrally.
    Financial à General Ledger à Master Records àAccounting àAccounting Individualà Processing Centrally
    Or through T-Code: FS00
    18) Enter the G/L account 614000 to the company code AFIL
    19) Create transportation condition records:
    Master dataà Transportation à Shipment cost à PricesàLogistic Execution createà Or thru T-code: TK11
    Enter condition type FB00 that is freight condition type, which is used as standard in the shipping cost pricing procedure.
    Enter the price and save it
    Process:
    1. The system determines the pricing procedure for the shipment cost item-using transportation planning point, service agent and shipment cost item category
    2. Calculation Basis
    3. Condition Record
    4. Access sequence.
    For the sales order, create a delivery using VL01N and pick the goods. Now create a shipment using VT01N and assign the delivery to the shipment document. Make sure to enter the carrier and other details before performing the transportation planning and execution. Save the shipment document and PGI for the delivery would be done automatically.
    A shipment represents a physical goods movement between two or more locations.
    For the system to create a shipment, shipping-relevant deliveries must exist.
    You use Transportation Planning to group pending deliveries into shipments and then to perform the shipments.
    The outbound delivery documents contain routes that the system calculates in route determination, and a transportation planning date for the delivery.
    Dynamic transportation planning is responsible for grouping together outbound deliveries into shipments that have at least the same route, visit plan type and the same transportation planning date.
    The following restrictions can be taken into account for a shipment in Dynamic Transportation Planning:
    u2022 Weight
    u2022 Volume
    u2022 Variable capacity
    u2022 Number of stops
    u2022 Maximum duration
    u2022 Loading units
    Create Shipment Document
    Use
    After the status of the delivery is open for transportation planning, it is possible to create a shipment document to schedule the transportation.
    Single documentà Create àTransportation Planningà Transportationà Logistic Execution ®Logistics
    T.code: VT01n
    Enter your transportation planning point and shipment type. Press enter.
    Creating the shipment cost document
    Use
    After the deliveries are scheduled by shipment and the shipment is executed, now it is time to maintain and close the shipment document in order to record all relative information and ready for the shipment cost settlement.
    Single documentà Createà Shipment cost à Transportationà Logistic Execution ®Logistics
    T.code: VI01.
    After creation of shipment cost doc. You settle the Shipment cost.
    Go to VI02, enter shipment cost no.and press enter.
    Then go to Overview -- Fright cost items, Select the line item and double click it.
    Go as main menu: Item --> Acc. assignment, you enter G/L acc. and cost center to which the transportation cost will be posted.
    On the Standard change, details u2013 Freight cost items screen, then check the check box u201CTransferu201D, which means you will transfer the relative transportation cost to FI/CO, in this case, the system should determined which Purchase Order will used to settle the cost, so after you check the u201CTransferu201D check box.
    Press save button on the current screen.
    Shipment cost settlement and documents:
    Use
    After the shipment cost settled in shipment cost document, it has the following affects:
    It creates a service entry sheet that refers to the purchase order determined.
    It posts acceptance of services performed.
    It creates an accounting document for the accruals.
    Further subsequent documents are created in FI.
    Create Delivery:
    T.code: Vl01n
    Create TO:
    T.code: LT03
    Create Shipment Document
    Use
    After the status of the delivery is open for transportation planning, it is possible to create a shipment document to schedule the transportation.
    Single documentà Create à Transportation Planning à Transportationà Logistic Execution ®Logistics
    T.code: VT01n
    Enter your transportation planning point and shipment type. Press enter.
    Creating the shipment cost document
    Use
    After the deliveries are scheduled by shipment and the shipment is executed, now it is time to maintain and close the shipment document in order to record all relative information and ready for the shipment cost settlement.
    Single documentà Createà Shipment cost à Transportationà Logistic Execution ®Logistics
    T.code: VI01.
    After creation of shipment cost doc. You settle the Shipment cost.
    Go to VI02, enter shipment cost no.and press enter.
    Then go to Overview -- Fright cost items, Select the line item and double click it.
    Go as main menu: Item --> Acc. assignment, you enter G/L acc. and cost center to which the transportation cost will be posted.
    On the Standard change, details u2013 Freight cost items screen, then check the check box u201CTransferu201D, which means you will transfer the relative transportation cost to FI/CO, in this case, the system should determined which Purchase Order will used to settle the cost, so after you check the u201CTransferu201D check box.
    Press save button on the current screen.
    Shipment cost settlement and documents:
    Use
    After the shipment cost settled in shipment cost document, it has the following affects:
    It creates a service entry sheet that refers to the purchase order determined.
    It posts acceptance of services performed.
    It creates an accounting document for the accruals.
    Further subsequent documents are created in FI.
    Generally process is-
    1) VL01N
    2) VT01
    3) VL02N - PGI
    4) VI01
    5) ML81N u2013 Service Entry Sheet
    6) MIRO u2013 Invoice Verification
    Shipping docs (VT01) are created before PGI...
    You cannot carry out transportation planning or creation of shipment after the goods issue has been executed. Once goods issue is done it means that the material has left your premises so there is no need for a transportation planning after it.
    In case you need carry out the shipment documents at the end of the day you could just create the delivery documents during the day and at end of the day create the shipment documents and the goods issue
    Regards
    Amit

  • New company code configuaration is added for the existing company

    Hi Guru's
    New Company Code is to configure for the existing company. Already we 20 company codes.
    Now Business users want new code for the country australia.
    Please let me know what are the steps to configure the new company code.
    I appreciate your help and coperation.
    Regards
    Jenny

    Hi jenneyc,
    1.1 Define and Assign Company Code     
    1.1.3 Assign Company Code to Controlling Area
    1.1.4 Create new plant     
    1.1.5 Define and Assign Sales Organization     
    1.1.5.1 Copy Sales Organization     
    1.1.5.2 Change name and address of Sales Organization
    1.1.5.3 Assign Sales Organization to Company Code
    1.1.5.4 Assign Sales Organization ‑ Distribution Channel ‑ to Plant
    1.1.6 Delete Purchasing Organization assignment to Company Code
    1.1.7 Define Variants for Open Posting Periods
    1.1.8 Open and Close Posting Periods
    1.1.9 Assign Posting Period Variants to Company Code
    1.1.10 Create Number Ranges for document posting for company code
    1.1.11 Asset Accounting - Specify Number Assignment Across Company Codes      
    1.1.12 Creation of House Bank and Bank accounts
    1.1.12.1 Define House Banks
    1.1.12.2 Define Lockboxes for House Banks     
    1.1.12.3 Define Posting Data
    1.1.12.4 Set Up Payment Methods per Company Code for Payment Transactions
    1.1.12.5 Set Up Bank Determination for Payment Transactions
    1.1.12.6 Create Check Lots
    1.1.12.7 Create Program Variants for RFFOUS_C     
    Along with above we need to do LSMW for GL a/c company code data have to upload, and foreign currency Configuration require...!
    I hope this info will helpful to you..!
    Rds,
    ANil

  • Business requirement Questioneer/checklist for New Company Code Creation

    Experts,
    Can anyone provide Business requirement Questioneer/ Checklist or  say all the factors to be considered for New Company Code Creation from user's point of view.
    this questioneer we will send to User department to specify all the requirements and add if required.
    Eg; Fiscal year definition, Posting period, Doc. types, etc. 
    Please provide full list to be considered before we go ahead.
    - Nilesh

    Dear Vivek,
    Actually I need the factors to be considered while defining Co. Code settings.
    All such factors which will guide us (SAP Team) how to design parameters in the Co. Code.
    We will send this questioneer to User Department to fill up and on that basis we will conclude our design Parameters.
    Please help.
    - Nilesh