Process order not picking up a batch...

Hello gurus,
I have created a process order for a mater FIN in which iam using a RAW...but when i create a process order for the FIN and go to MIGO to do a GI, its not picking up a batch of RAW automatically and instead i have to pick a batch manually...
Any suggestions much appreciated
Sri.

HI
1.you have to assign the batch in COR2 for the components.
or
2.you have to use batch determination process
COB1 - is used when you want to do Batch Determination in Production / Process order itself.
MBC1 - is used during Goods issue / Goods Transfer
For doing Batch Determination on the basis of any characteristic you have to maintain sort rule.T.code is CU70.
go with link
http://www.sap-img.com/sap-sd/some-light-on-batch-determination.htm
forum answer
batch determination
-ashok
Edited by: Ashok Keerthipati on Dec 18, 2008 11:24 AM

Similar Messages

  • Stock should kept in block till Process order not settled

    Hi,
    My client requirement is like, untill process order not get settled, confiremd stock against process order sholud not transfr or consumed from storage location.
    Please let me know the best possible solution.
    Regards
    Rakesh

    Hi,
    There is no direct control of order status on the relevant stock.
    Either do GR to quality stock or block stock & utilize the same after order settlement.
    Also use batch management to trace the order specific GRN.
    Could you pls tell us why does your client require this?
    Is that client is going for MAP in case of SFG & FG?
    Hope this helps you.
    SmanS

  • Changing BOM-items in Process Order not allowed

    that Hello,
    Mi client is asking me if it is posible, once created a Process Order, upon modifying the order (COR2), that the user can not change any of the cuantities and batches of the material list (BOM) updated in the Process Order.
    Is there any way one can protect the material list from being modified once created, or once liberated the order?
    Is it posible, moreover to just protect the BOM ítems updated in the Process order but let the option open to add exta BOM ítems manually.
    Is there a userexit or a Badi one can use to acomplish this?
    Thanks for any reply.
    Aart

    Hi Aart,
    Yes, you can use BADI to protect the BOM items from not to change the BOM items in Process order.
    In one of our project we have taken the help from the ABAPer, has has done the same thing.
    Then we have acheived the same requirement.
    You check with the ABAPer, he will help you for the requirement.
    Thanks

  • Investment Order not picking

    hi all,
    I am not able to trace the date of the Investment Order in the Asset master data....
    I have made the IO has the optional in the Asset Master data in the Screen layout... eventhough it is not capturing the data..... what could be the reason?....
    as far as my thinking that it will pick the new data which we create the new asset from now onwards.. But it is not picking for the new Assets also.....
    Please let me know what and where should i have to change it....
    Waiting for the inputs...
    Cheers

    hi Vishal and Paul,
    Let me expalin my process what i am doing and it is not tracing the Internal order in fagll03 report for the Depreciation account ( xxxxx) in the Assets side.....
    Process is
    Step 1: I have created the Asset and enter the Investment Order also I:e it is linked to the Internal Order.
    Step 2: Posted through F-90
    Step 3: Run the Depreciation for that Asset.
    Finally When i see the FAGLL03 for that Depreciation account (xxxxx) it is not reflecting....  What could be the reason?
    Please assist me....... is there any settings for this to effect?
    Cheers

  • Scheduled finish date for process orders not updating in BW

    We are having problems with the scheduled finish date (GLTRS) for process orders. When the process order is already released, changes done in R/3 on the scheduled finish date will not result to a delta hence data in BW is not updated. Table AFKO, where data is coming from, is always updated with the changes though. 2LIS_04_P_MATNR is used in extracting the data.
    Has anyone experienced the same problem? We are looking for possible ways on how to have a delta whenever there are changes on the process order even after it is already released.
    Any help would be greatly appreciated...

    Hi Donna,
    If I've understood your problem correctly, you can increase the load frequency as Sriee has pointed out.
    If you want latest data frequently and if you are on BI 7.0 then you can look at Real Time Data Acquisition(RDA)
    Regards,
    Tom.

  • Target Cost in Process Order not calculated

    Hello,
    In Process order, after deliver of FG the target cost is not getting calculated,
    Could you please help me why the target cost is not calculated in process order.
    I have configured all setting for WIP and Variance

    Hi,
    Target costs are only calculated after goods movements have occured on the order, the Target Costs are then calculated during the Variance calculation.
    Target costs will only be calculated after the first goods receipt has been posted to the order. Also you have to ensure that the information to calculate target costs exists on the system in particular in OKV6.
    This estimation is based on the customizing for the Target cost version in transaction OKV6 as in turn will the "real" calculation of the Target costs via the variance calculation.
    So in OKV6 the Target cost will be based on preliminary costing on the order, an alternative cost estimate or the current standard cost estimate. Importantly if the choosen option is not fulfilled e.g. no current standard cost estimate, the target costs will not be predicted or calculated.
    regards
    Waman

  • Import Standard Purchase Order not picking data when submitted from backend

    Hi,
    As part of my code, I am inserting Purchase order information in the interface tables with process_code = 'PENDING'. Then using fnd_request , i am triggering the Standard Program for importing these Purchase Orders. The standard program is getting triggered and completing normally. But it is not picking any records. I am calling the program as follows:-
                  -- Setting the org_id so that the import program will run for that particular org_id.
                  fnd_request.set_org_id(r_org_id.org_id);
                   -- Submit the Import Standard Purchase Orders by calling the standard program for respective org_id
                  l_req_id := FND_REQUEST.SUBMIT_REQUEST(application  => 'PO'
                                ,program      => 'POXPOPDOI'
                                ,description  => 'Import Standard Purchase Orders'
                                ,start_time  => SYSDATE
                                ,sub_request  => FALSE
                                ,argument1  => NULL
                                ,argument2  => 'STANDARD'
                                ,argument3  => NULL
                                ,argument4    => 'N'
                                ,argument5    => NULL
                                ,argument6  => 'APPROVED'
                                ,argument7  => NULL
                                ,argument8  => NULL
                                ,argument9  => NULL
                                ,argument10  => NULL                                                   
                  COMMIT;
    When I am submitting this same program from front end, for the same set of records using the same set of parameters, the records are getting picked.
    Any suggestions for this?                 

    Hi
    Do you have a copy of your insert statement?
    regards

  • Target costs on Process orders not calculating

    Hi All,
    We have released standard costs for all the materials. We have also done Goods receipt for the process order but still the TARGET COSTS are not getting updated.
    Can some one tell is any specific config present for the same.
    We need to fix the process orders but how?
    Thanks,
    Hari

    Dear Harihara,
    <b>You must have all manufacturing master data associated with your manufactured material(s) set up.</b> This includes bills of material, work centres, routings, and activity prices. If you are charging overhead, you must also have maintained the costing sheet and the material master overhead key field.
    Hope this is helpful.
    Regards,
    Naveen.

  • Process orders not reflecting in SNP planning book

    Hi,
    I am facing a problem here that the SNP planned orders once converted into process orders in ECC are not reflecting in the SNP planning book.
    However if i check the /sapapo/rrp3 product view, the process orders are visible here.
    Kindly help me understand if i am missing out something here.
    Thanks,
    Nalin

    Hi,
    Please Check whether the ATP category is assigned to the Category group which is assigned to KF in the planning.
    If that is assigned rightly then run TS cons check.
    Regards,
    Kishore Reddy.

  • Conversion of planned order into process order not respecting F-S

    Hi Experts,
    I am working in Upgrade project from 4.6c to ECC 6 .
    I have an isuue in PPPI
    I have a process order which has to be converted to process order .
    This operation should take place by phase 210 first then phase 300 .
    But in our case the Phase 300 is starting first .
    please suggest me where to find the trouble.
    Thanks in advance

    Hello,
    I am afraid that when I enter procurement type=X & special procurement=30 in material master data, planned orders created by MRP have then a order type = NB (standard purchase order) and special produrement type = 3 (subcontracting).
    So this kind of planned orders can only be converted into purchase request and NOT into production order.
    It looks like it is not standard to do so in SAP and that I will have to manage subcontracting in prodution order; 1 routing for internal operation and 1 routing for subcontracting.
    Thanks
    Amaury

  • Order not picking bom chnges

    during booking of order, some component of my order is to be changed in its BOM i know it can be done with the help of Read PP master data, but if my order Status is PCNF, then what to do plz tell me steps

    Hi,
    Cancel those Confirmation using CO13 (Production Order ) or by CORS (Process Orders).Then try to do Read Master Data.And yes if you are using 03 type inspection then it will also create hurdles in case of RR is started.
    Regards,
    Dhaval

  • Batch not updated in process order

    hi all,
                When i am doing batch determination and goods issue through coik pick list batch not update in process order. presently we are not doing batch determination in process order.after goods issue component batch fields are grey out in the process order

    HY,
    Batch field are filled only if you do Batch determiantion of components whether it is by auto or manual.And it is logical also becasue if you split the material qty. in more than one batches during goods issue( whether it is in COIK or in COR6N)then think what should be the case in Component screen in process order?
    As soon as you complete the Goods Issue This field becomes gray but the filled of Quanity withdrawn is update with qty you have withdraw.
    Regards
    Dhaval

  • Batch Splitting in Process order

    Dear all,
                I created the process order . Now Executing batch Determination  for Qt 265  of Component X .
    Now in Batch Determination screen of Process order, out of three available  batches ,  I am selecting one batch by doing copying
    Now in Process order screen component overview , I am getting spilt qty. as 52 as first line item and 213 as second line item with selected batch number.
    Why this splitting is coming , How to avoid this splitting ???

    Hi,
    May be batch selected by you is not available in stock of 265  qty.
    Their fore system has taken 52 qty of  another batch.
    Just check again MMBe available batches
    Or accoriding to your sort rule line item 1 batch say A qty available is 53
    Then remaining qty  has taken 213 qty from your batch B in 2nd line item.
    If you want to select batch A & if full stock available then remove 52 Qty from 1st line item in batch determine screen & put 265 QTY in front of your batch of  which you want pick full qty.
    Regards
    SANIL

  • Batch Number field in IDoc for Process Orders (message type LOIPRO01)

    Hello PP experts,
    Just wanted to ask if anyone of you have worked with message type LOIPRO01 (IDoc for process orders)
    There is a segment-field in this IDoc  E1RESBL-CHARG which has description of "Batch Number"
    We tried to assign a Bath Number for an Order (using t-code COR2 --> "Goods Recpt" tab under "Receipt" section), generated an IDoc for this order, but upon checking the E1RESBL-CHARG field of the IDoc it is not populated with the Batch Number.
    The material in the process order is FERT, so technically we're trying to assign a Batch Number in one of the process orders for a Finished Goods material type,  so not on the component level.
    Can anyone here verify:
    1. is the E1RESBL-CHARG field of IDoc LOIPRO01 intended for the Product Batch Number?  If Yes, how do we populate that for in the IDoc?  --> Do I need to have a Reservation/Dependent Requirement for the Product for the Batch Number to be populated in the IDoc?
    2. If E1RESBL-CHARG can not be populated for a Product that has no Reservation/Dependent Requirements, Do I have any option of populating this field with just the Batch Number assigned to the Process Order of that product?

    Solved - LOIPRO01 IDoc does not pick up the Batch Number from AFPO table, instead from table RESB.    We need batch from AFPO and just created a lookup using the Process Order Number as import param

  • Batch determination in Process Order

    Hi Guys
    I am doing the automatic batch determination on the process order release. It gets rejected and the error is CO 691: You must enter the batch for material 1025301
    Now when I do the manual batch determination in the process order. On clicking the batch determination button I get the message: No Check exist for planning (item: 0010, mat: 1025301) message number C2119.
    Can you guys please advice how to resolve this error please!
    The SAP version in 4.7
    -Rahul

    Hi Ram,
    You are right. I am not getting batches with zero stock.
    By inadequate stock, I mean, say, for a raw material, I find from MMBE 1.448 kgs are there in the unrestricted and 1.448 kgs in reserved for the batch. When I check in the material list of the process order, total 9200 kgs are booked by the batch. How is this possible?
    Does the system cannot do the batch splitting automatically. Because everytime it is not possible to calculate the remaining stock and enter it manually in the order.
    Thanks and Regards,
    Jyoti

Maybe you are looking for

  • How do I change my email account on my mac from Mail to Icloud?

    Does anyone know how to change my mail account on my mac to I cloud? since i have changed to Icloud on my iphone it seems that I can't access the old mailserver anymore. What do I do? Thanks for any advise Alex

  • Why are my fonts in different groups in Illustrator CS5?

    I am running Illustrator CS5 on a Laptop PC. I am constantly installing new fonts to work on customer projects... I have noticed that sometimes the fonts appear in the font list in alphabetical order, and sometimes they appear either towards the top

  • Black screen, no response?

    I was running Tiger 10.4.10. I booted the computer, and it would not go past the white apple spinning gear screen. I took it to my mac store. They did not have my Tiger disks, and chose to install Leopard for me. If I do not touch it within 5 minutes

  • How do I convert from Open Office documents to Pages?

    How do I convert Open Office document files (.odt) to Pages documents? Also for Open Office spreadsheets to Numbers?

  • No picture when exporting

    i have a project made up of avi (optimized) (codec CineForm HD) + apple prores422 files. the first time i exported the project i was having some trouble but somehow was able to succesfully manage. exported onto vimeo+master file. now, after making a