Hi,
Is Product Costing absolutely required before implementing Production Planning, specifically PP orders? My client does not want to plan costs or need any cost estimates. They want to use a PP order to check availability for a BOM, and then issue it out to an external vendor for services. After this material is processed by the external vendor, he would ship it back and we would be doing a goods receipt at the parent level of the BOM. The whole purpose of this is to get the accurate price of the BOM parent which would include all service costs. This parent would finally be sold via the regular SD sales order process. Our Logisitics consultant suggested that the only way this could be accomplished is a PP order. All this looks okay, but he also mentioned that a PP order cannot work without Product Costing and the process cant be accomplished CO-PC. I am unable to grasp why SAP would force us to have costing when the client doesnt need any cost estimates, planning etc. Could any one please tell me if we need CO-PC for this scenario?

Dear SAPFicon,
Technically, to run PP without using product cost planning would cause a lot of problems during business process of production order. Because, once a production order is created then the data structured is freezed in the PO and if there is any missing data it will cause errors. Any errors in production order would stop the following transactions. We never know what would be the error level of the production order. The worst case, the production or should be cancel and start it all over again.
But by using product costing or product cost planning, this is a preliminary step to prevent and eliminate any error of the products tobe produced.
So, ideally, there is one person in charge to ensure that the products which be produced in the production orders are free of error.
So, the product costing is an integrated module that take data from variouse module such as PP, MM, CO, HR.
The product costing use the Logistic master data such as folllowing;
1. Bill of material
2. Routing
3. Work center
4. Material master
How you can say, that running PP without PC will run, while the to run the smooth production order, you need to mandatory parameter in Material Master that belong to Costing area.
Without having product costing, I can assure that your client will trap in a lot of troubles with their business process.
Please see the online documentation for product costing for a better overview or you are welcome to ask again
Regards,
Irhasni

Similar Messages

  • How the Trading Goods mapped in to Product costing and COPA in Controlling

    Dear Experts,
    I have a trading goods scenario in my client. How the mapping into Product Costing and COPA.
    They just purchase FG products from Vendors and Sell to their Customers, they received FG Products to Main Plant from Vendors and then sends to Branches from Main Plant, In between some expenses accured like Transport, Fright etc. this is my scenario.
    How the settings to be made in Product costing and COPA.
    I am waiting for your favorable reply.
    Thanks,
    KBR.

    Hi Bhaskar
    I believe branches are also created as Plants
    You have 2 choices....
    Choice 1: If the Freight amount is known @ the time of Transfer from Main plant to Branches, include the same in STO so that inventory value in Branch = Purchase Value + Freight amount
    CHoice 2: If thats not possible, then inventory value in Branch will be same as the Main plant... The expenses incurred on freight needs to be posted to a cost center... Then allocate them @ month end based on revenue / Quantity sold etc using KEU5
    Whichever choice you make, Product Costing is not relevant and required as well... You dont need to do any CK11N
    If you want to see in COPA Purchase value separate and the Freight, etc separate - Then choice 2 is the route for you
    br, Ajay M

  • Difference Aetween Overhead Cost and Product Cost

    Sir,
    What is the difference between Overhead Cost and Product Cost
    Thanking You
    Juhi

    Product cost indicates the cost of making a product which includes
    1) materials (contained in the BOM)
    2) labour  (specified in the routing)
    3) Overheads (charged via costing sheet).
    1) and 2) are directly identifiable to the product made.
    3) is not possible to directly associate to a making of product. This is more a common cost. Eg. Material handling charges. The material handling department, say, employs a few workers to do material transfer from warehouse, their cost is hard to associate to a particular production order.  Hence, usually a percentage is applied , where in the order is charged proportionate to use of materials in that order. The corresponding credit is given to the Material handling departmnet/cost center.

  • Product cost or Product unit cost

    Hi,
    Does anyone know if there is any standard content for product cost or Product unit cost?  Please let me know.  I don't know under which area this belongs to ie SD, MM....etc.
    thanks
    Sabrina.

    Hi Sabrina,
    You can evaluate CO-PC datasources in your R/3 system and the corresponding sources, objects etc. in BC.
    Also you may look at Product Cost Controlling Analyses at BI best practice:
    https://media.sdn.sap.com/html/submitted_docs/Best_Practices/BW/index.htm
    Best regards,
    Eugene

  • Replication of product master and Product category

    Hi
    Please let me know steps involved in replicating
    Product master and product category from R/3 to SRM
    Regards
    Ashish

    Hi Ashish,
    The blogs mentioned by Kathirvel explains clearly the entire replication procedure of Master data from R/3 to SRM.
    Neverthless find some points which needs to be taken care during replication :
    1. Ensure that the tables CRMCONSUM, CRMSUBTAB, CRMPAROLTP, CRMRFCPAR are duly filled in R/3 system.
    2. Endure that SMOFPARSFA table is duly filled in SRM system.
    3. Maintain the filter settings using R3AC3 and R3AC1 as per your requirement in SRM system.
    4. Set up the Administrative console using SMOEAC and create both R/3 and SRM nodes and define the site attributes.
    5. Ensure that all the queues (both inbound and outbound) are empty in both the systems before replication.
    6. Start initial load of customizing objects (DNL_CUST_BASIS3, DNL_CUST_PROD0 & DNL_CUST_PROD1) using R3AS and monitor the loaded jobs using R3AM1.
    7. After successful replication of customizing objects, load the business objects (material_master, service master) using R3AS.
    8. The replicated material groups and product types can be seen using COMM_HIERARCHY txn.
    9. The replicated materials can be seen using COMMPR01.
    Hope this makes you more clear about the settings required.
    Clarifications are welcome.
    Award points for helpful answers.
    Rgds,
    Teja

  • Product hierarchy and Product allocation

    Dear SD Gurus,
    Can I have some good docs on Product hierarchy and Product allocation related to SAP SD.
    my mail id is [email protected]
    Regards,
    Rakesh

    Hi
    Product allocation helps in allocating prodects based on customer requirement.
    Please go through this link for product allocation
    http://www.sap-img.com/sap-sd/implement-the-product-allocation-functionality.htm
    For product hierarchy go through this link
    http://help.sap.com/saphelp_46c/helpdata/en/77/1a39516e36d1118b3f0060b03ca329/frameset.htm
    give points if this useful
    Thanks
    Anil

  • I have an education version of cs 6 creative suite, I have the box and used in once on my old laptop I am now trying to find serial number to reuse on new laptop but only have product code and product number

    I have an education version of cs 6 creative suite, I have the box and used in once on my old laptop I am now trying to find serial number to reuse on new laptop but only have product code and product number

    Hi Sophie,
    Normally you can find your serial registered to your AdobeId. To find it please login to the Adobe website and check if you did register it to your account.
    Serial number, Redemption, and Product codes | Student & Teacher Editions
    In general you will go true a educational verification afterwards you get the serial. So its in your email or account. If you still have issues get in contact with the chat team to get help.
    Good luck!

  • Product costing without production planning module

    Is there any way to work with product costing module without production planning for service sector.

    Hello
    You may use the product costing without quantity structure. This is useful if you do not have PP module but have materials and you need to calculate the standard cost of the materials.
    In case you do not have materials and only have kinds of services then these can be created as activities for a cost center like a FICO consulting activity for SAP cost center. You may then calculate a price per hour of the activity and may charge it to the service order/ internal order.
    Sangram

  • Product Costing and Labour Hours

    Dear All
    We have a basic process for product costing which follows the flow below:
    0. Creation of material master which is costed (transaction MM01). If material master already exists for this material, this step is skipped;
    1. Creation and release of CO production order to collect the costs of material production (KKF1);
    2. Posting of actual costs to the CO production order created (goods issues, labour and services costs);
    3. When production is completed, Overhead costs has to be calculated for this production order (KGI2);
    4. Produced material delivery to stock has to be carried out (MB31);
    5. CO production order has to be settled (KO88) and closed (KKF2).
    We would like to start posting labour where the hours will be posted to a secondary cost element and included in the cost of the product. Can you please provide information on the steps to configure this.
    Many thanks
    PRG

    Never mind

  • Tickets of Product costing and COPA

    Hi
    Can any body working product costing or CO_PA
    Could you please send the ticekts and analysis to me i want to become CO cosultant in these two sub modules
    Regards

    Please be specific,
    I am also a new  bee with little experience.
    if i know more about requirement what you want to get , I will try .
    Parthu

  • Product costing and cost center

    Hi,
    My client is a trading organisation. In order to do product costing, at which point in sourcing we need to enter the cost center.
    M.K

    Hi MK,
    In a trading organization, usually you do not need product costing as you are not manufacturing the product in-house.
    You can value your Inventory at MAP and when you do MIGO, the MAP will get adjusted itself with different p.O.rates that you purchase.
    And, even if you go for Product costing, you won't need Cost Center at any point of time for sourcing.
    Regards,
    Kavita

  • Costing and Production order

    Hi,
    Please give me clear idea on Production order , order settlement and variance.
    When we settle the production order and this is mandatory to settle the order?
    What entries posted in system while order settlement.
    What is the difference between production and variance.
    Please ............
    Sateesh Kumar V

    Hi Sateesh
    Production Order after completion of the finished product is to be settled to Inventory in case of Make to Stock order. When you transfer to Inventory, the a/c entry will be Inventory Dr and Cr to Inventory change a/c(Prodn order). This transfer normally happens at Standard Cost because you'd given Price Control indicator S in the Inventory (Material) master.
    Variances arise because prodn order would have received various costs based on Allocations, etc and it transfers out at Std cost. Entry will be Dr Price difference a/c and Credit Inventory change a/c (prodn order). Now you can see that Prodn Order is fully settled.
    S Jayaram

  • Co product and By product product costing and settlement

    Dear Friends,
    Here is my question
    In Disrete manufacturing Product costing
    when we design product costing  Business blue print
    Instead of using co-product we wrongly map to co-product what will be the impact in costing point of view
    can any one explain  demerits  in costing point of view 
    Product costing is based on  Quanity structure
    if my question is not clear, please do not hesitate to ask for more information
    Thanks & Regards
    Raj

    Hi,
    Please consider the following:
    1. By-Product Scenario:
    You need to maintain a costing BOM, to determine the standard price of the by-product. In the BOM of main product, you can use this by-product as a credit, the system will calculate the target cost based on the std cost from coting BOM.
    If you dont maintain the byproduct in BOM of main product, and while confirming you are entering by-product, then the system will calculate production variance.
    2. Co-Product Scenario:
    You need to maintain Co-product tick in either MRP2 or Costing View and maintain the coproduct combination in the Joint Production. This is to be maintained for all the co-products. Once you are entering a production order, the system automatically uses this combination and brings in multiple lines in the production order for all the relevant materials (co-products).
    When cost estimate is done, the system divides the cost for materials, activity costs, etc based on the weightage maintained in equivalent numbers.
    Trust this helps.
    Please assign pts, if useful.

  • Product Costing and COPA

    Hi Friends,
    Could any one tell me the basic settlements done to COPA from Product Costing point of view and which tables will be updated at the periodic settlemnet of variences to COPA?
    Thank you ,
    Parthu

    Hi
    During settlement, variances are posted to CO-PA from the Production/Process Order/Production Cost Collecter at the same time that they are posted to the G/L. The fixed and variable portions of the variance are carried over into CO-PA with the same breakdown as the cost component layout that comprises the standard cost. Any characteristics that have been configured in CO-PA that are related to the product number are carried over for analysis, such as product number, product line, plant, and so on. This access allows the matching of variances with the product’s cost of sales.
    The variances are posted to CO-PA in the period when they are incurred, not the period when the product is sold.
    If you are using costing based CO-PA, the tables updated are:
    CExYYYY, where yyyy = the operating concern/
    Hope this helps.

  • Standar cost and product cost collector not updating the new price

    Hi,
    Created Standard cost estimate for one FG product and runned the product cost collector. Based on that consumption delivery everthing is made. Later on the work center and activity type changed in routing. Now i am trying to run the standard cost with new activity price (due to work center change) for the current period, system is showing only the previous rate(previous period) and it is not updating the new price becuase of already we have created the product cost collector.
    Can any one give the suggestion for how to update the new price in standard cost as well as new price updation in product cost collector.
    govind.

    Hi
    1. If the original cost estimate was run in the current month - Then you cant re-release cost estimate unless you reverse it from CKR1
    If the cost estimate was of previous months - then you can definetely release it again
    2. In cost collector, you need to manually cost it again using the Preliminary costing feature... Your cost coll will then show 2 cost estimates i.e. One from Original date to current date-1, and 2nd from Current date to 31.12.9999
    br, Ajay M

Maybe you are looking for

  • Iphone not working since update! Please help!!!

    I got one of those "update your iphone" messages yesterday so i did and since then it seems not to recognise the sim card, either in the phone or when i plug it into i tunes. Really not great with technology, so really need some help Thanks in advanc

  • Creating Custom Reports

    Hi, i want to generate custome reports in my project. There are almost 20 reports which needs to be generated. OIM provides only 4 or 5 reports types. How can i generate custom reports should i write any java code for it. phani.

  • Adobe flash cs6 language settings.

    i downloaded adobe flash cs6 professional and i accidentally changed the language settings. if anyone can help me with this i will be eternally grateful

  • Adding another Server

    Hey, Currently running one server, is it possible to run another server off the same machine? If this is not possible is it possible to have another domain in the system? Thanks, Shannon

  • Hi Guys, best process is upgrade or a fresh install for already existing solution manager?

    Hi Guys, best process is upgrade or a fresh install for already existing solution manager to SAP 7.1?