Reg:MRP,SFC,SOP

1) suppose i have 4 seperate routings
how do i choose one among the four and link it to MRP
2) what  is use of OrderType Dependant paramaters
3) i want Process FLow in SOP scenario
4)what is  Planning Strategy =40

Raj,
1.
With T-Code C223, you can create production versions for each routing. That will have different lot sizes and validity dates.
With respect to each production version routing will be selected.
2.
Order type Dependent parameters controls the following things.
                                     a. Selection of PV: (0-Automatic, 1-Manual)
                                     b. Routing (Selection ID, Routing Selection, TL Type)
                                     c. BOM Application (PP01)
                                     d. Inspection Type
                                     e. Missing part List
                                     f. Documentation Goods movements
                                     g. Controlling data such as costing data and Result analysis Key.
3.
Process flow for SOP ( Consolidated from different blogs and libraries)
   a. Maintain self defined information structure----MC21
                 Sales department in discussion with planning department prepares the sales plan for different product range or for
  different product groups.
   b. Create planning type----MC8A
                 Act as a template to maintain data for specific information structure. It is a customized view of planning table. You may  have one view for sales planner and another view for production planner. There is no restriction on number of planning type per info structure.
   c. Create planning hierarchy---MC61
               It is a combination of characteristics value. It provides framework for planning in flexible planning.
   d. Create product group---MC84
              A product group combines other product groups and materials according to whatever criteria best meet the needs of enterprise. Product groups are classified according to whether they are multi-level or single-level. A product group is multi-level if it contains other product groups. However, the lowest level in a product group hierarchy always consists of materials.
   e. Resources---CR01
             Resource or work center is the standard essential master data in PP module.
   f. Rough-cut planning profile---MC35
             It is a kind of resource leveling tool. One can have a visibility of target in terms of resource required to meet them. This gives the input to fine tune the target and optimize the use of resource.                                                                                Example: a product has to undergo processing in four machines. Machine three is a bottleneck operation. It is essential to check the capacity of this resource to the planned quantity. Then rough cut planning profile will be created to this resource and evaluated for capacity.
    g. Create plan in inactive version---MC81
            Sales department in discussion with planning department prepares the sales plan for different product range or for
different product groups.
   h. Disaggregate product group plan and check capacity---MC76
            Planning is done at the product group level at highest level. Now it is required to disaggregate the plan to plan the down level product group and finally the material.
   i. Version management---MC78
           "Presently the plan is available in inactive version. With this version, capacity situation is verified. If it is found
satisfactory, it may be transferred to A00 as a Active version.
    j. Transfer product group to planning---MC75
             Transferring disaggregate sales plan in to planned independent requirements i.e. planning table.
4.  
Planning Strategy 40 (Planning with Final Assembly)
This is a Make to Stock strategy.
This strategy is preferable where quantities of the finished product can be predicted.
In this strategy, existing stock is considered and sales order will consume PIRs
Following fields need to be maintained in MRP 3 view along with use of 40 strategy .
a. Consumption Mode
b. Bwd Consumption Period
c. Fwd Consumption Period
Regards,
Samir Wadajkar
Edited by: wadajkar on Dec 14, 2010 8:54 AM
Edited by: wadajkar on Dec 14, 2010 8:54 AM

Similar Messages

  • Std Reports in MRP & SFC

    Hi,
    Could anyone provide me Std available SAP Reports in MRP & SFC
    Regards

    Dear Srividya,
    Enter the T code SAP1 only when you are in SAP easy access screen.when you are working with some other T code check
    with /osap1.
    Importatant reports for MRP
    MD04                 Display Stock/Requirements Situation
    MD05                 Individual Display Of MRP List
    MD06                 Collective Display Of MRP List
    MD07                 Current Material Overview
    MD08                 Reorg. MRP Lists
    MD09                 Pegging
    MD45                 MRP List Evaluation
    MD46                 Eval. MRP lists of MRP controller
    MD47                 Product Group Planning Evaluation
    MD48                 Cross-Plant Evaluation
    MD4C                 Multilevel Order Report
    MDLD                 Print MRP List
    SFC Reports
    MCP1                 SFIS: Operation Analysis Selection
    MCP3                 SFIS: Material Analysis Selection
    MCP5                 SFIS: Material Analysis Selection
    MCP6                 Goods rcpt analysis: repetitive mfg
    MCP7                 SFIS: Work Center Analysis Selection
    MCP8                 Goods rcpt analysis: repetitive mfg
    MCP9                 SFIS: Select Run Schedule
    MCPB                 Operation analysis: Dates
    MCPD                 Production order analysis: Dates
    MCPE_CUS             Commodity Pricing Customizing for MM
    MCPE_DOC             Commodity Pricing in MM Documents
    MCPE_FA_ACC_SEQ      Access Sequence for Formula Assembly
    MCPE_FA_COND_TYPE    Condition Types for Formula Assembly
    MCPE_FA_CT           Cond. Tables for Formula Assembly
    MCPE_FA_DET_PROC      Det. Procedure for Formula Assembly
    MCPE_FA_FC           MM Field Catalog
    MCPE_FA_GCM           Formula Master Data Maintenance
    MCPE_MD              Commodity Pricing Master Data for MM
    MCPE_WB              CPE Formula Workbench for MM
    MCPF                 Material analysis: Dates
    MCPH                 Work center analysis: Dates
    MCPK                 Operation analysis: Quantities
    MCPM                 Production order anal.: Quantities
    MCPO                 Material analysis: Quantities
    MCPQ                 Work center analysis: Quantities
    MCPS                 Operation analysis: Lead time
    check and revert.
    Regards
    S Mangalraj.

  • Reg:MRP -Exclusion of open orders

    Hi,
    I want to run MRP without consideration of open orders(Production order).Is it possible.
    I tried thru availability configuration.Its not working.
    Regds
    bhuvan

    Dear ,
    Just an work around : Did you check setting Technically complete status  to Production Order .Goto -CO02-Function-Restrict Processing -Technically Complete  and SAVE for those order which you do not want to consider in MRP .For mass teco use COHV.
    Check with 2-3 sample orders in sand box and run MRP
    Availabilty check is not fulfill the requirement bacause , it is not plant specifc and also for an particualr order type .
    Try this and let us know the result .
    Regards
    JH

  • Reg: MRP Run for all Materials

    Hi Abapers,
    I have an issue where in using MD01( Material Run), i need to raise one PR for all materials below the re-order stock. Currently system creates one PR for each material below the re-order stock.
    Please throw any ideas regarding this.
    Thank you

    Hi ,
    to procure assembly take 10 days.
    And delivery date is after 2 days
    After MRP run , system will take first backward schedulling from delivery date will take 2 days and going forward scheduling and take 8 days .
    So that from current date system will take 10 days so assembly will procure easily .
    Suppose today date 19/05/2011. And delivery date is after 2 days .( on date 21/05/2011 )
    if MRP is run on 19/05/2011. System will create delivery date 29/05/2011.So assembly will be easily procure within span of 10 days from 19/05/2011 to 29/05/2011. Delivery of FG is easily available on 29/05/2011.
    Regards
    Vinod

  • Reg mrp elements

    Hi all,
    can any one know me the mrp elements in md04
    As we call Value stock at vendor as Subcst
                     To.quality inspection as QM-Lot
                      In transfer ( storage location) as Sloc st
    and i want to know for Returns,in transfer (plant), unrestrected consignment,
    blocked consignment,Rest.Consignment,consignment in inspection.quality inspection stock at vendor.
    Thanks,
    Narsimha Reddy

    i need the mrp elements i.e.in md04 transaction we can see the stock. if we click on stock we will find all the stocks dispalyed so where can we see that all mrp list elements.

  • Reg.MRP Run without sale order

    Dear Experts
    We are in need of MRP run without sale order. I have created Finished product material (T-Shirt) and assigned components to that and then I ran MRP, If I do so, MRP is exploded but result is not satisfied some non components are displayed.
    What is my requirement is ,when I run MRP if there is stock availble production order should be created otherwise Material requirement has to created.
    Pls help what is the configuration for MRP run,
    Thanks
    Rajakumar.K

    Hi Raja,
    One of your requirements isn't available in R/3.
    What is my requirement is ,when I run MRP if there is stock availble production order should be created otherwise Material requirement has to created.
    Standard MRP will create Dependent requirements (demand elements).  MRP will create order PROPOSALs (purchase reqs or planned orders)(supply elements).  MRP can be immediately followed by an additional program that will convert planned orders to Production orders.  All these things are possible.
    However, MRP will not check for the availability of components, and then selectively create production orders.  Availability check, which is not part of MRP, is usually performed at a later part of the production order cycle.
    Regards,
    DB49

  • Reg MRP

    Hi,
    The output for MRP is in the form of Planned Orders/ Procurement proposals after netting all the available stocks, Pending PO's/PRQ's & Productio Orders.
    But i want to know the requirements list with out considering the pending PO's/PRQ's/ Production Orders.
    Is that possible to view?
    Regards,
    Sirisha

    Dear
    You need to deal with following table for your requirement to extract the list of MRP elements as they are NOT in a single table also
            MDKP,  "Header Data for MRP Document
            MDTB,  "MRP table
            MDTC,  "Aggregated MRP table items
            T457T. "Description of MRP elements
    For more details , i would rather suggest you to discuss with your ABAPer with following code as one of the referbce :
    DATA: BEGIN OF MDTBX OCCURS 0.
            INCLUDE STRUCTURE MDTB.
    DATA: END   OF MDTBX.
    SELECT-OPTIONS: PLANT FOR MDKP-PLWRK OBLIGATORY,
                    MATNR FOR MDKP-MATNR OBLIGATORY.
    CLEAR: MDKP, MDTB.
    SELECT * FROM MDKP WHERE DTART EQ 'MD'
                         AND MATNR IN MATNR
                         AND PLWRK IN PLANT.
        WRITE:/ MDKP-MATNR, MDKP-PLWRK.
        IF MDKP-CFLAG EQ 'X'.
           CLEAR MDTBX. REFRESH MDTBX.
           IMPORT MDTBX FROM DATABASE MDTC(AR) ID MDKP-DTNUM.
           LOOP AT MDTBX.
             MOVE MDTBX TO MDTB.
             SELECT SINGLE * FROM T457T WHERE SPRAS = 'E'
                                          AND DELKZ = MDTB-DELKZ.
             IF MDTB-PLUMI = '-'. MULTIPLY MDTB-MNG01 BY -1. ENDIF.
             WRITE:/ MDTB-DAT00, T457T-DELB1, MDTB-VSTAT,
                                              MDTB-MNG01, MDTB-LGORT.
           ENDLOOP.
        ELSE.
           SELECT * FROM MDTB
                         WHERE DTNUM EQ MDKP-DTNUM
                         ORDER BY PRIMARY KEY.
             SELECT SINGLE * FROM T457T WHERE SPRAS = 'E'
                                          AND DELKZ = MDTB-DELKZ.
             IF MDTB-PLUMI = '-'. MULTIPLY MDTB-MNG01 BY -1. ENDIF.
             WRITE:/ MDTB-DAT00, T457T-DELB1, MDTB-VSTAT,
                                              MDTB-MNG01, MDTB-LGORT.
           ENDSELECT.
        ENDIF.
    ENDSELECT.
    Regards
    JH
    Edited by: Jiaul Haque on Nov 22, 2010 4:25 PM

  • Coverage profile and Stime period profile in MRP

    Can anyone explain what is the importance of coverage profile and safety time period profile in MRP2 view and what is their implication in MRP and SOP ?

    Hi,
    Coverage profile is used in Material Requirements Planning for calculation of dynamic safety stock. This dynamic safety stock is calculated by using formula: Average daily req*range of coverage.
    Average daily req is calculated by considering requirements in specific periods and no of days for the total period length.
    You can find all the setting in
    MRP--> Planning-> MRP Calculation---->Define range of coverage profile.
    e.g.
    You have maintained in coverage profile:
    Period indicator: W(week)
    Number of periods to be considered for ADR: 2
    Period length: Standard days (5 days)
    Range of coverage: 5 days
    Req for 1st week: 1000
    Req for 2nd week: 1000
    then Ave daily req.= (1000+1000)/(5 period length*2 no. of periods)=200
    then Dynamic safety stock= 200 (ADR)*  5(range of coverage)=1000
    Hope you got it.
    Sachin

  • REGARDING PROCESS ORDER CREATION

    Hi All,
    While creating the process order for material, system showing the message that "Manual process order cannot be created for this product". But if we try with another user id, i could able to create the order for the same material.
    Plz suggest the solution to get rid of this error.
    Thanks
    Arvind S

    Hi,
    The message "Manual process order cannot be created for this product" clearly indicates that the user is not authorized for Manual process order creation by COR1 transaction for this material and may be this material is planned through MRP or SOP etc. and in critical or certain situations manual process order creation is allowed to another user/user id for the same material ( type of materials/material code).
    Some time organizations put such restrictions through enhancements. You can search the exact reason or logic of restriction by the help of ABAP consultant.
    Regads,
    Narresh

  • MC74 : how transfer SOP to PIR for a specific mrp area

    Dear guru ,
    i want to transfer Planning Data of a SOP Version for a single material to Demand Management.
    The copy to Demand is run directly into the plant of the SOP Version.
    I manage MRP Area.
    How can I transfer directly SOP to PIR for a specific mrp area ?
    Thanks in advance

    Hi..
    In  MC87 you have to first create  planning data.. SOP.
    Then if you go to MC74 your planning data will be transferred..
    Ii.e you will get the PIRs automatically from Demand management..
    Hope the above clarifies..
    karthick

  • Reg SOP and flexible planning

    Dear all,
    Please explain what is the difference between SOP and flexible planning, similarly in an industry when do use Longterm planning, when we will use SOP and when we use Flexible planning, when we should use MRP planning
    Please advice
    regards
    venkat

    Dear,
    Standard SOP:-
    Standard SOP, you work with one organizational unit, the product group hierarchy, and plan predefined key figures in a planning table with a set layout. All plans in Standard SOP are based on the standard information structure S076.
    If there are more regions for an organization, planning can not be done at different region or different sales organization level using Standard SOP.
    Flexible Planning:-
    Flexible Planning, on the other hand, can be based on any information structure of your choice, either a self-defined information structure or a standard information structure.
    If there are more regions for an organization, planning can be done at different region or different sales organization level using Flexible planning
    Please refer my reply from this thread,
    [SOP - Flexible Planning |SOP - Flexible Planning u2013 Demand Management.]
    Regards,
    R.Brahmankar

  • Reg creation of MRP element

    Dear all,
    Where can we create MRP elements for ex BH for process order, we can check in MD04 but i want to know where they are created
    Regards
    Venkat

    Venkat,
    If you are talking about creating a new type of MRP element, this generally cannot be done.  I believe the only way implement a new element would be to modify all existing programs that manage this field.
    I have never heard of 'BH' for process order, the standard MRP element for Process order has already been assigned to 'BR'.
    There is a configuration where you are permitted to assign different text elements (human-readable names) to existing MRP elements OMD5.
    Best regards,
    DB49

  • MRP issue -reg

    Hi Friends,
    The quiery is like this
    MD01 is scheduled as a background job using MDBT transaction . Here  values are maintained for MRP control parameters which appear on MD01 initial screen like
    Processing key  
    Create purchase req
    Schedule lines  
    Create MRP list 
    Planning mode   
    Scheduling      
    Planning date   .
    Though here it is given that no schedule lines , MRP output is giving schedules for BOM components
    quiery is which control parameters are preferred while system is executing  MRP   ,
    1.The Plant parameters which are maintained  at plant level  
       thropugh OPPQ
    2. The Plant parameters which are maintained  at MRP Group
         level thropugh OPPR
    3. The MRP control parameters entered in  MD01 initial screen
    4. Master data maintained like planeed delivery time , etc... for
        material in material master
    another doubt is while running how the system considers the MRP control parameters pertaining to the BOM header parts and BOM components
    regards,
    Madhu Kiran

    Hi,
    For MD01, system will check MRP group parameters for particular material. MRP group creation indicator overwrite the initial screen of MD01 creation indicator.
    If MRP group not found system will use initial screen of creation indicator.
    For MD02, system will overwrite MRP group creation indicator. MD02 initial screen indicator has priority over MRp group.
    For your last question also system will work as above.
    Check the following taken from SAP Help.
    The creation indicator for purchase requisitions is only valid if the MRP group does not override it. The creation indicator for scheduling agreement schedule lines is only valid if the MRP group or the plant entry in Customizing does not override it (see Creation Indicators in the Initial Screen and the MRP Group ).
    In single-item planning the creation indicators in the initial screen overwrite the creation indicators in the MRP group (see Creation Indicators in the Initial Screen and the MRP Group).
    Regards,
    Dharma

  • Reg LPA Delivery schedules - MRP

    Hi
    Delivery schedules got created via MRP - LPA document type
    We haven't released to vendor [JIT or Forecast]
    When i manually change quantity in generated delivery schedule, Firmed indicator is ticked as expected
    i am unable to uncheck this indicator when go there change mode it is grayed out
    Please suggest

    SAP Help says 'You can only change it from the planning result. To do this, double-click on the schedule lines in the planning result.'
    Planning result ??
    How do i make changes to firm indicator, Please help

  • MRP run reg.,

    Hi guru's can anybody tell can it be config., in such a way that the ext., req., can also be
    taken into account while MRP run in consumpotion-based planning if VB is selected as MRP type.
    thanx in adv.,
    tulja singh

    Hi,
    In spro/ prodn/mrp/master data/check mrp type :
    For mrp type VB you can include external requirements in total horizon or with in the replenishment lead time.
    Select the external requirements to be considered by the system such as sub contract req, released purchase req, reservation etc.,
    You can copy VB &make required changes & give a different name.
    Hope this helps...
    Regards,
    Ramasamy