Hi,
Is there a standard report in SAP which will give me the cost of the material in different periods.
The issue is the material price is changed frequently for a perticular material "X''. I want to have a look at the cost of material in different periods.
I can track the changes from MM03,but the user needs a feasible solution than this.
Thanks
Aravind

Hi,
I got the required from MBEWH table.
Thanks
Aravind

Similar Messages

  • Extract a report from SAP to see the POs' recommended ship date

    Hi there,
    Can I extract a report from SAP, to see the recommended ship date of my POs, based on the MRP? As I need it to do the pull in and push out.
    Edited by: Cindyye on Jul 20, 2011 8:22 AM

    Refer ME80FN report wherein you can list out PO delivery schedule by clicking on change view icon after executing the report.
    In Change View options select Del. sched this will list out POs with detailed delivery schedule. You can export the same to excel also.
    Njoy SAP...

  • Update of cost in the material master

    Hi all,
    From the purchasing point of view,In the normal process Cost in the Material master gets updated from purchasing documnents automatically.In this case,manually if the cost is changed in the purchase order affects the cost in the material master.My requirement is this should be done automatically after receiving the vendors confirmation of list of material costs.There may be chance of change in the cost of the materials.so the costs of the materials which were changed should get updated in the material master automatically(VPRS).
    Ie changing of the costs of the materials in the purchase order should be reduced .How this will done??
    If we have more than 2000 line items in the purchase order,it will be quite little bit difficult to update each material cost in the purchase order .
    Thanks in advance..
    Regards...VM

    Hi,
    Normally material will be valuated with two types of price controls S -standard price and V-moving avaerage price.
    A std price as its name indicated it is std and will not chnage.
    A moving average price will chnage accordingly with the change in the material price.
    Normally it will be better create a info record for the material and vendor combination for the plant or purchase organisation with a info update indicator in the purchase order will serve your pupose .
    With the proper settings at SPRO system creates info record during creation of PO if it does not exist or updates the existing record if it has one with the latest price details in the form of last purchasing document so that these details get defaulted during creation of PO.
    However you can create a outline aggrement so that a PO can be created with reference to that.
    Or you can create a condition record for the price for your combination so that it can get defaulted.
    The price which is there in PO will not be defaulted to material master.
    Or time to time you can review the prices and maintain via MR21.
    Regards,

  • Inclusion of planned cost to the material while Invoicing

    Hi Everyone,
    We are facing a problem, kindly guide me to solve it:
    We are purchasing 'X' Material (split valuated) through a Purchase Order in which we did not provide any planned cost.
    But after GR we came to know that planned cost should also have been entered in the PO. But in the PO, while creation we did not select any planned cost line for the item. So after approval of PO and GR, we were not able to enter any planned cost.
    Now while adding up planned cost during Invoicing through MIRO, we are facing an error message:
    Error saving valuation data for material P1S002 0002
    Message no. M8829
    Diagnosis
    Error occurred when the system tried to save the valuation data.
    Please guide me how to do invoicing by including the planned cost and booking the planned cost in the material.
    Thanks and Regards
    Edited by: MP Vashishth on Jan 10, 2011 2:21 PM

    Hi,
    Thanks for your reply please.
    When i am trying to enter this freight value in the Material Tab, i am facing an error message :
    Error saving valuation data for material P1S002 0002
    Message no. M8829
    Diagnosis
    Error occurred when the system tried to save the valuation data.
    Procedure
    Contact your system administrator.
    Please guide.
    Thanks and Regards

  • How to add the purchasing overhead costs to the material costs

    Hi,
    I have a requirement to add the purchasing overhead costs like transportation costs to the material costs so that the costs is added to the material costs and update my material price accordingly.
    Can u tell me how to do it for both standard price and MAP price?

    Hi,
    Please attach a accrual key in customization (Pricing procedure) to the overhead condition type you use.

  • Is there a Report in SAP that lists the slow moving inventory?

    Is there a Report in SAP that lists the slow moving inventory? For example: Inventory that has not sold in the last 6 months?
    Thanks.
    Points will be awarded

    Thanks so much.
    Points rewarded.
    Kathy

  • Report for expiry date of the material

    All SAP Gurus,
    We have certain Materials which are expirable.
    These Materials are batch managed, and each batch is having different expiry date.
    Is there any standard report available which can give is the days remaining to reach the expiry date (for that material)?
    Regards,

    Hi,
    Try MB5M,
    here
    Field name                                Field value
    Material                                Enter the material code to which the report is desired.
    Plant                                Enter the plant in which the report is to be generated.
    Storage Location                     Enter the storage location in which the report is to be generated. Optional entry. Leave it blank.
    Batch                                 Batch number to be displayed. Optional entry. Leave it blank.
    Remaining shelf life           Minimum amount of time for which the material must keep upon goods receipt for the goods receipt to be accepted by the system. Optional entry.     
    Remaining shelf life warehouse     Indicates that the remaining shelf life of a batch in                                                         
    Total remaining shelf life         Indicates that the system displays the total remaining shelf life of a batch.                                                                               
    The total remaining shelf life is calculated from the shelf life    
    Expiration date minus the current date.  Select this radio button.                              
         Indicates that the system also displays materials with zero stock. Optional, leave it blank.
         Display of remaining shelf life in days. Select this radio button to display the remaining shelf in days in the report.
    Regards,
    Pardeep Malik

  • Standard report in SAP to see the Purchase Order and corresponding PR

    Dear All.
    Is there any Standard Report in SAP , which can provide details of the Purchase Order and the corresponding Purchase Requsition.
    Regards
    Shyam.

    Hi
         ME2L     Purchasing Documents per Vendor
         ME2M     Purchasing Documents per Material
         ME2K     Purchasing Documents by Account Assignment
         ME2W     Purchasing Document by Supplying Plant
         ME5A     List Display Of Requistions
         ME2W     Purchasing Document by Supplying Plant
                        ME80FN     General Analysis of Purchasing Documents

  • Standard SRM reports excluding SAP BI in the landscape.

    Dear Experts,
    Kindly give the standard SRM reports available other than SAP BI.
    My system landscape doesw not have SAP BI. We are working in SRM 7.0 classic scenario and we dont have BI.
    Is there are any standard reports available for SRM7.0.
    Thanks in advance.
    Regards,
    B.N.Karthikeyan.

    Hi! Thanks for the reply. I am aware that these reports can be accessed from the GUI. However, they were also available on the browser in the previous versions but I cannot find them in SRM7, via the portal and hence the question whether they are no longer valid. At the moment, I can see one of those reports appearing under Reports but I encountered error running it.
    Regards
    SF

  • What SAP table houses the Material Classification values?

    I cannot for the life of me figure out what SAP table actually stores the material classification characteristic values. These are the related tables I have found so far but none of them link the information to a material number:
    TABLE: CABN
    ATINN (characteristic ID)
    ATNAM (characteristic name code)
    MSEHI (UoM associated with characteristic)
    TABLE: CABNT
    ATINN (characteristic ID)
    ATBEZ (characteristic full name)
    TABLE: KLAH
    KLART (class type)
    CLASS (class name code)
    CLINT (class id)
    TABLE: KLAT
    CLINT (class id)
    TXTBZ (class full name)
    TABLE: KSML
    CLINT (class id)
    IMERK (characteristic id)
    POSNR (characteristic positional location for class)
    TABLE: CAWN
    ATINN (internal char.)
    ATZHL (int counter)
    ATWRT (char. value)
    TABLE: CAWNT
    ATINN (internal char.)
    ATZHL (int counter)
    ATWTB (description)
    I have also identified these structures, but I am no good at finding where values from a structure actually reside.
    STRUCT: RMCBC "I/O field for include screens from classification"
    contains MATNR, KLART, CLASS, KLTXT, ATWRT
    STRUCT: RMCLF "Classification I/O structure for Assgmt of Object to Class"
    contains KLART, CLASS, KLTXT
    Can anyone please help me and advise where the actual relationship between material number and classification information is? I'm trying to import this information from MDM to R/3 but I have no idea what to map it to or what Idoc segment to use.
    Thanks!

    Have a go with below table joint in SQVI or SQ01:
    KSSK (Allocation Table: Object to Class), joint together with KLAH (Class Header Data).
    Link will be field CLINT.
    Choose the below from KSSK:
    Key of object to be classified - KSSK-OBJEK: you will enter the material number here. Watch out - you have to add 10 leading zeros before your material number, eg. number 40524281 will be altered to 000000000040524281.
    Class Type - KSSK-KLART: here you can specify the class type which is 001 for material master.
    Choose the below from KLAH:
    Class number - KLAH-CLASS: this field will return the class number you assigned to your material in Classification view.
    HTH,
    Laszlo

  • Standard Reports in SAP HR for The Sales Promotion Employees

    Dear All,
    I wanted to check whether we have any standard reports / formats in SAP HR for The Sales Promotion Employees
    (Conditions of Service) Rules, 1976.
    Like Form A, Form B, Form C and Form E
    http://www.google.co.in/url?sa=t&rct=j&q=sales%20promotion%20employees%20act%201976&source=web&cd=2&sqi=2&ved=0CCQQFjAB&url=http%3A%2F%2Flabour.nic.in%2Fact%2Facts%2FTheSalesPromotionEmployees(ConditionsOfService)Rules%2C1976.doc&ei=fwXwTvLXBcrPrQet3_TyDw&usg=AFQjCNEXxqcRUzJ8M4LXxYYzTSm75Cdc_Q&cad=rja
    Pls provide some inputs on this...
    Kind Regards
    Nag

    Hi,
    this link will give you all the list of cubes, datasources, dso etc in payroll.
    http://help.sap.com/saphelp_nw70ehp1/helpdata/en/86/3a1d3c55a0f503e10000000a114084/frameset.htm
    regards,
    ray

  • Fixed & Variable cost of the Material at CK11N

    Hello Experts,
    Before posting this thread, i have gone through several threads about my query.  Still I have a doubt.
    Material Cost always should be Variable.  Cost Component Structure OKTZ also the Inventory Valuation would be Variable Cost as per as Std SAP.
    But where as the Raw Material Price control would be "S" & the Cost Component Structure of OKTZ having Inventory Valuation Fixed + Variable Cost then what would be the effect..?
    I have run a SCE for a Material & both Material having standard price 140.6 & 1.09. Then how come the Fixed Value shows here as 10.37 & 0.9 & How can it be divided into Total & Fixed Value..?
    Regards
    Raj

    Dear Raj,
    Please check the following settings in OKTZ:
    Materials are of 3 types:
    Finished: Valuation (Fixed + Variable)
    Semi Finished:Valuation (Fixed + Variable)
    Raw Materials: Variable
    Why Inventory Valuation (Fixed + Variable) for Finished Goods:
    It contains material price as well as overheads.
    Overheads may contain fixed portion also in addition to variable nature.
    So Finished goods valuation should be (Fixed + Variable).
    For Raw materials valuation  should always variable:
    You can make the settings in OKTZ as mentioned below:
    Please check these settings and change the settings accordingly.
    Hope this will helps you.
    Regards,
    Pavan Kumar Arvapally

  • Report for MM for seeing the material old price and new price

    Hello friends,
    For the ROH material we are maintained the Moving average price. So that material is calculated the average price of that material,
    Know My clint wants old price of that  material i.e. one year before And
    he wants comparison report for old price and new price of the all raw materials
    is there any reports are there  such kind.
    Regards
    Pramod

    Hi Pramod,
    If you want to view the old and new prices on a frequent basis, u can go for an
    ABAP query (SQVI) with the base table as MBEW.
    Cheers
    Arun.

  • How to create a custom Report in SAP CRM using the Bol Framework

    Hi Guys
    I have developed a report in SE38 which calls a custom Function Module within it and it works all good.
    Now I want to take my Function Module as well as the external structures I created for this report and use them to make a View in SAP CRM which will allow the user to make selection and then when they click on a button another view has to be shown which should have the content of the report based on the selection.
    I know how to create a view based on the standard object types but this time I want to use my custom function Module..
    Kindly advice or refer me to a link that might be useful.
    Regards
    * Thato                                                                        *

    You want to create a View in SE11 calling FM that you created? Is it?

  • Problem in printing Crystal Report from SAP Business One - the printing cut in it width margins

    Hi
    i'm trying to print crystal report layout from sap b1. when i preview the report as pdf file, i have the option to choose Fit in size option and then the layout print O.k with out any margins that been cut.
    The problem start when i'm trying to print the layout directly from sap b1 (printer button) which cause the page to be cut in it width margins.
    How can i control the printing of crystal layout when i'm printing it directly from sap b1? do i have the option to chose 'Fit page size' from sap system?

    Hi,
    Please check SAP note:
    1820939 - Page settings of Crystal Reports not transferred
    correctly
    Thanks & Regards,
    Nagarajan

Maybe you are looking for