Same operation for different production orders

hi, we use different sheets (like aluminium, steel etc). each sheet (as roh material for certain operation) is for different production orders. we keep all sheets as one bundle and cut all the sheets at a time. say aluminium sheet is for order X, steel sheet is for order Y. How to handle this during confirmation and GR, Settlement of individual orders etc? pls advise the best practice with this type.

Yadav,
As per my understanding, you maintain the sheets of different materials as different raw materials.
The cutting operation takes place altogether for cost effectiveness.
I don't think it would be a problem for you do deal with.
Different sheets will be part of different orders.
The GI would take place accordingly.
The confirmation will be independent untill it is linked with backflushed.
Explain the scenario in details.
Hope this helps you.
SmanS

Similar Messages

  • Current operation for the product order

    how do i determine a current operation for the production order? in what table shall i get this indicator? ive been searching in afru and i cant seem to find it?

    In your production order, there might be a sequence of operations. Each operations will be having the status. Based on the confirmation, the operation status will be updated. If the order status is CNF means it is completed. If the status in not CNF, then it is not completed. Based on the operation sequence, you can find out the current operation in your production order.
    This information you can get from the table AFVG. AFVG table is for order operation details.
    Hope this clarifies your doubt.
    Regards,
    V. Suresh

  • PP : Need to find Multiple Batches for different production Orders

    Hi Experts,
    I have a requirement that, user wants to see the  "Single batch assigned for multiple production orders and different materials"
    Which its a off case, it cannot be done , but i have gone with 1. So user wants to know all the Orders which has same batch but for different  materials & Orders.
    Please help me in this regard.
    Br,
    SandeepCH

    Hi Shri,
    Please find the attachment  for your better understanding.
    Yes, as you said one material can have multiple batches, But that same batch cannot be linked with other material. This was my requirement.
    So now i want to know all the  batches which came in double for different materials.
    Br,
    SandeepCH

  • For a Production order - Operation wise Inspection Lot

    Hi Experts,
    Please help me out to resolve the following problems.
    1. How can we create inspection lot for each operation for a production order?
    If a production order has 10 operations, I will have to have 10 inspection lots for that order.
    2. I have a final assembly called A with components B & C. Some other material called D has similar characteristics of B.
        But sometimes, for A, instead of B (if stock is not available), i want to use D also. Please note that, if B is not available, then
        only, I will use D. Otherwise always B only, so we cannot go with probability.
    How can we map this scenario? and MRP run also should consider D if B is not there.
    Thanks in advance.
    Regards,
    Vijay.

    Dear
    Answer Q1 : Go to SPRO > Production> Shop floor control> operations > confirmation> define confirmation parameters
    Maintain
    1)Operation sequence u2013 error when operation sequence is not adhered to
    2) Over delivery u2013 Error when over delivery tolerance is exceeded
    3) Results Rec. (QM)- Error message if no Insp results exist
    So what these setting helps is that  :
    1)All operation has to be confirmed operation wise means 0010 has to be confirmed for confirming 0020 operation. SO production guys can only confirm 0040 operations only after 0030 operations is confirmed by quality personal.
    2)Over delivery is not allowed means of in 0030 operation if only 50 quantity is confirmed in 0040 operation only 50 can be confirmed. Production people cannot confirm more than 50 quantities
    3) Also PP personal cannot confirm operation 0030 through C011N till the result recording of that operation is done through QA32.
    4)Maintain Operation Control Key -PP01 with marked Inspection Character Marked -OPJ8  and maintain this Control Key for   those operation which are required for Inspection Lot .
    Now For QM stand point , activate inspection type 03 and 04 in material master. For 03 type of inspection, you have to make routing in CA01. So when you release your production order, an inspection lot will be generated. This lot will not be stock relevant. This is just to check that you production is in accordance with quality norms. Only after clearing this lot from quality you can do your order confirmation, otherwise system will give hard error due to 3rd point of prev post.
    For 04 type of inspections, prepare inspection plan in QP01. Now when order is confirmed, an inspection lot of 04 origin will be created in quality, and this is stock relevant and for final inspection of production order material.
    If you need you can set for early inspection as well. That will give you another intermediate stage before final inspection. Inspection points are also an option if suites your requirement.
    If you need more inspections, I suggest go for manual inspection lots of 04 origins, they are created in ref to order and are not stock relevant.
    Q2 : Please explore this thread for options explained for Alternative Item selection .
    Alternate Item in BOM
    Regards
    JH

  • GI for every Operations, not for whole production order

    Hi,
    I have assigned the components into operation and would like to do goods issue for every operations.
    But MIGO or MB1A only do goods issue for whole production order, there is no selection fields for operation no.
    How can I only do the good issue for production order by operations?
    thank you very much.
    Best Regards,
    John H

    Hi,
    You can do goods issue for each operation using backflushing while confirming each operation.
    In CA02 that is in routing go to component allocation select the components which you want to issue for certain operation and select new assignment. In new assignment select the operation.
    In the same manner select the components which you want to issue and assignment it to operation.
    Hope it will help you.
    Regards,
    Alok Tiwari

  • Target cost for a Production order

    Hi
       How to get Target Cost for a production order?
    Thanks
    Naga

    Well Naga, Right now I’m on HR implementation , but I programmed same kind of requirement two years before , but I got planned cost and actual cost .
    I also notice “cost analysis" the cost is not exact , it wont read the value from KP26 of that particular month .
    Here I am talking about 4.5b system.
    You can find the sales order ref on production order, and your production order is made up of your different kind of material like scarp, raw, semi-finished etc
    Here are the steps I followed .
    1- I read the material which you can see in material component on production order in Co03.
    After that I take the qty and also multiply by the cost at which machine is posted .
    I have that programs, as I need to find out . I’ll post you later .
    But you have to read the tables afko,afpo,afru,caufv,cost ..etc
    Do you see information structure I refer you , If i am not wrong this CO3 ( cost analysis ) report use report painter ( Tr.Gr51,Gr52 ) . you can also see by going in to said transaction which information structure its populating . This’ll also help you.
    Hope this’ll give you idea!!
    <b>P.S award the points.!!! DOn`t forget :)!!!!</b>
    Good luck
    Thanks
    Saquib Khan
    "Knowledge comes but wisdom lingers!!"
    "Some are wise and some are otherwise"

  • In house mfgd. raw materials for a production order- Cost capturing

    Hello Experts,
    The scenario is as below:
    Client wants to manufacture in house some of the raw materials for a production order of sub assembly. These raw materials are made from scrap, with some manhours spent on it. After making them in house, these are handed over to stores for kit preparation.
    The planner wants to create a stock of these materials (without making individual prod. orders since there are many of these). One option is, planner can do the cost centre issue reversal (202 movement). But the raw material cost is also getting captured in it from the material master.
    From costing point of view, the cost of raw material should not be included since it is made from scrap. Only the cost of man hours spent is to be accounted for.
    Please help as to how to map this scenario. For capturing cost of man hours spent, we can include a routing for it in the production order of the sub assembly. But how to eliminate or exclude the material cost. All inputs from your side are appreciated. Thanks in advance
    Regards,
    Chetan.

    Hi Chetan,
    Your scenario has some major issue.
    1. You cannot produce RAW material in SAP.
    2. The cost of material produced inhouse will be different than that of original RAW material.
    3. There will be some cost effect in the final finished product if you consider this inhouse produced material for product costing of finished goods.
    We have similar scenario with my client and here is what I have implemented.
    1. Create a new HALB type part number for the inhouse manufactured RAW material. This will ensure that you assign Routing and BOM to same and can capture the COST for the same.
    2. Creating new material will enure that the product costing for inhouse produced RAW material is done.
    3. You can create single Production order for the same as you only have to capture cost. This depends on your Business scenario.
    4. Once you have inhouse produced raw material, you can create alternate BOM for the FINISHED Material with this new Part number in BOM.
    5. Create Production Version for the two BOM and ask Planner to select the Version 2 if he requires new part number in Production Order. I assume that this case would genrally appear in very small numbers.
    6. Now coming to product costing for final assembly. Since we are going to reuse scrap material to create the new part number, only activity cost and component cost will be used to determine cost. This cost will be less than that of RAW material cost.
    So we always suggest our customer to consider OLD part number to determine the PRODUCT COST of final material. BUT business will have to take a call on this.
    Do let me know if u need any thing else.

  • How to change operation dates in Production Order /Capacity Leveling

    Dear Experts ,
    We are using ECC 5.0 .In production order , scheduling happing as Backward  based on the Sales Order Delivery Date .I am doing the following :
    1.Demand as Sales Order with Delievery date : 20.03.2010
    2.Running MRP with Lead Time Scheduling -2  in md02 and converting the Planned Order to Production Order .
    4.Production Order have following dates :
             Basic Finsish Date : 21.03.2010
             Basic Start : the day Pl.Or--Pr.Ord
             Schedule Start : 15.03.2010
             Schedule Finsish : 17.03.2010
            Schedule Release : 13.03.2010
    5.In schedueling margin key :  Float Before Production : 3    , FAP : 3 , Release Period : 2
    6.In material master : Work Scheduling View : Setup : 3 days , Processing : 4 ,Interoperation : 2 for one Base Qty 1
    7.In operation : Op1  : Start Date  : 15.03.2010    Finish Date: 15.03.2010
                             Op2 : Start Date : 16.03.2010      Finish Date : 17.03.2010
                             Op2 : Start Date : 17.03.2010      FD : 17.03.2010
    Question :
    1.How to change the Operation dates  in Production Order Operation over view screen ? Today,  operation over view screen , Start date and Finsih Date  of individual operation are not changable with in Production Basic Start /BF date  or beyond .It is only changing based on the Standard Value : Labor
    2.How to change/re-schedule operation dates d in CM21 (Graphical view -Work Center Capacity load as per   Production Order and Operation combination ) based on capacity availale in advance dates? I am using  Time Profile : SAPSFCZ002 -SFC Graph midterm-3 motnhs and Planning  ,
    How to solve this above issue in scheduling operation and capacity distribution .
    Regards
    JH

    Closing the thread

  • Multiple batches for a production order and mapping with components

    Hello Gurus,
    Our business requires to create multiple batches for one production order + they want to trace which component in the production order has been issued to the main equipment.
    For example, I am creating production order for 'A' equipment for 4 qty. Business wants to create 4 different batches for these equipment
    Lets say now 4 batches are created A001, A002, A003 and A004.
    Now lets assume 2 nos of 'B' component are required for 1no of 'A' component. So the requirement of B component is 8.
    Lets say 8 batches are generated B001, B002 ......B008
    Now lets say batch B001 and B002 are issued for A001 and packed together. How do we map this?
    I understand we can do some enhancement for creating the multiple batches but I still dont know how to map them with each other.
    Please help

    Hi Ethan
    There is a functionality called WIP batches, that allows you keep the batch traceability within an order.
    With WIO batches you can track which batch of component was used to produce each batch of finished product.
    See this link for more details:
    Work-in-Process (WIP) Batch - SAP Library
    BR
    Caetano

  • Tables for Confirmation Production Order.

    Hi Friends!
    we want to be find Tables for Confirmation Production Order[PP].
    reply,
    Rahul

    Hi Rahul,
    MAST     Material BOM
    STKO     BOM Header
    STPO     BOM Positions (detail)
    MAPL     Assignment fo Task Lists to Materials
    PLKO     Routing Group Header
    PLSO     Routing Group Sequence
    PLPO     Routing Group Operations
    AFKO     Production Order Header
    AFPO     Production Order Position (details)
    Thanks,
    Reward If Helpful.

  • Payment terms for different products from a single vendor

    Hi Pundits,
    Our client has a requirement to assign different payment terms for different products. Each product he buys from his vendor has it's own payment terms. He wants us to customize in such a way that when he/user enters the invoice, not only the vendor number is shown along with the product name but also the payment terms for that particular product are calculated.
    I know that only one payment term can be assigned in the vendor master data. Is there anyway to get around this?
    Creating the same vendor multiple times and assign payment terms looks a possible option but that looks quite hectic cause he has close to 1000 payment terms.

    Taurian, thank you for that suggestion!
    I can maintain as many existing payment terms as the client has with his vendors and let him choose the payment terms at the time of invoice entry.
    The only problem is that he might have to change it according to the current market rates for that product. So maintaining any payment term is of little use.
    Edited by: Dummy_Variable on Aug 16, 2011 8:26 AM

  • GR  for a Production order to be controlled on actual /planned cost

    Hi,
                   When I do a GR for a production order I want to restrict the GR if my actual cost of materials consumed for the production order is less that 80 % of the planned cost of that production order. There is no provision for restricting the above.
    When GR is done for a partial quantity of the production order, the system should consider and compare the GR quantity material cost against the same GR quantity Planned cost in the production order. If the GR quantity actual material value is less than 80% of the GR quantity material planned value, then the system should stop the GR to stores.
    Eg:
    Production Order for 10 Units of material “X”
    BOM for “X” are Material “A”, “B” and “C”
    Planned quantity to manufacture 10 units of material “X” is: “A” – 10 unit, “B” – 10 Unit, “C” – 10 Unit
                                    The planned value for the material BOM is : “A” – 100
                                  “B” – 75
                                  “C” – 25
                                         Total Value to manufacture material “X” is Rs .200                                        
    Case 1
    If only 5 units are manufactured using the production order.
    The GR to stores must be allowed only after the system check the total actual materials consumed in the production to produce 5 units exceeds 80% of the 5 units planned material cost.
    Planned Material Value               Actual Material Value
    A. 510 = 50                         A. 59 = 4     
    B. 57.5 = 37.5                         B. 56 = 30
    C. 52.5 = 12.5                         C. 52 = 10                    
    Total planned material Value is Rs 100            Total actual material Value is Rs 85
    The above case shows that the actual material consumed in the production order is more than 80% of the planned materials. So, the system should allow the GR to stores.
    It should check only material cost only.
    Case 1I
    If 10 units are manufactured using the production order.
    The GR to stores must be allowed only after the system check the total actual materials consumed in the production to produce 10 units exceeds 80% of the 10 units planned material cost.
    Planned Material Value                    Actual Material Value
    A. 1010 = 100                         A. 109 = 90     
    B. 107.5 = 75                            B. 56 = 30
    C. 102.5 = 25                                     C. 52 = 10                    
    Total planned material Value is Rs 200          Total actual material Value is Rs.130
    The above case shows that the actual material consumed value in the production order is less than 80% of the planned materials. So, the system should not allow the GR to stores.
    It should check only material cost only.
    CAN ANY ONE SUGGEST ME ON THE ISSUE
    Regards
    Madan Mohan

    Madan,
    Try using the userexit in enhancement MBCF0002.
    (A) Now the Planned cost can be calculated from the RESB table passing the Order no. For all the line items in RESB calculate the planned cost = Price * Qty.
    (B) For actual costs take it from AUFM for mvt type 261. The fields DMBTR will give you the value. Sum for all line items.
    Now suppose the GR bing done now is 5. This you will get in the user exit. In the exit check from CAUFV whta was the GR already posted. Say this is 2. So the total GR is 5 + 2 = 7.
    Planned cost for 7 = (A) / Order Qty * 7
    Actual cost = (B)
    Compare planned and actual and give yr message,
    rgds
    ram

  • Subcontracting of one of operations in the production order of SPK

    Dear All,
    Example:  
    Material A (soft) having special procurement key SPK as "52". In the routing of this material there r 3 operations 10, 20, 30.
    We have generated production order of this material A.
    We want to get 20 th operation done from outside i.e.  subcontracting.
    When we receive the material from subcontractor we should able to confirm 30th operation in the production order by CO11.
    outgoing material & incoming material will remain same i.e. material A. (Material A has special procurement key SPK as "52")
    How to do this in SAP ?  Pl' give detailed steps.

    Hi,
    sorry to point you to help ....
    check out whether this std scenario is a best fit
    http://help.sap.com/saphelp_46c/helpdata/en/51/95303ca1fa11d189ba0000e829fbbd/frameset.htm
    SAP Std BPL: http://help.sap.com/bp_bblibrary/600/BBlibrary_start.htm
    Thanks,
    sudhakar

  • BAPI for Open production orders

    Hi All,
    Any BAPI for open production orders?.... Using BAPI i want to upload open production orders informatiomations.... Please help
    Thanks & Regards
    Santhosh

    Hi,
       Please check the following BAPI,
    Goto BAPI tcode, select hierarchical tab
      Production orders,ProductionOrder ,ProdOrdConfirmation , RCVPRORDCF and check the BAPIs

  • Open the reservation for the Production order

    Hi,
    I have post the GI for Production order MB1A with movement type 261 from 100 peaces components. I would like to cancel a partial quantity of components from this posting (about 30 peaces). After cancel it the reservation for the production order has to be open for 30 peaces of components.
    I've canceled it through MB1A and mtype 262 but the reservations weren't open and in the PO (component overview there is always the sign"the Final Issue for This Reservation").
    Which T.code and mtype could I use.
    Thanks
    Dede

    Hi,
    Have you cancelled the movement (of 30 pieces) by selecting the "with reference" option from the menu?
    If not, then reverse the current cancellation document. Then again cancel the 261 movemtn by selecting the with refernce button from the menu. It will sove the problem.
    Check & revert.
    Regards,
    Rohit.