Dear friends
This the scenario with respect to product cost by sale order settlement profile. When I am settling the process order, which is created with reference to Sale order, system throwing an error "Define a settlement cost element for receiver type SDI".
When I see the explanation given by system, the following message displayed :
"Diagnosis
In allocation structure Z1 (controlling area RI01), you did not define which cost element should be used when settling costs/revenues of the sender. Nor did you define receiver type SDI.
Procedure
Assign a different allocation structure to the settlement sender (-> Master data -> Settlement rule -> Goto -> Settlement parameters), or maintain allocation structure Z1.""
For this I have defined one Secondary cost element and assigned to Allocation Structure under Settlement cost elements.
Still I am getting the error. What could be the reason?
Please do the needful.

Hi Kiran
In the Allocation Structure Z1, you need to define the Settlement cost element for the receiver category SDI. Have you done that?  Cost element should be created with 21 Cost element category.
Dont Select By Cost element.
Regards,
Suraj

Similar Messages

  • How to create planned order from the sales order for a processing item

    In the MTO sceanrio, assembly order is created directly from the sales order. I would like to create a planned order from the sales order.
    I tried the Planning strategy group 81 in the material master but it didnt work.
    Could you please let me know how to do it? Is it Schedule line config that controls whether planned order is created?
    Thanks
    Harish

    Narayana,
    Planning strategy 82 is the best & standard way of getting production order created on sale order create.
    just assign this strategy  in MRP 3 view under strategy group.
    If not then using sale order reqt type ( KMFA- Assembly with production order) & assigning this to your sale order item category is also another way to create prodcution order without using planning strategy in material master.
    Follow steps in SPRO-->Sales & dist --> basic functions >avail check &transfer of requirements> transfer reqts-->determination of reqt type using transaction
    Here you may select the item category you in sale orders & assign KMFA to your item category. this will then give option in sale order create to change reqt type to KFMA for assebly orders.
    If you need KFMA to be default assign it to Item cat/ MRP type ( PD) combo.
    Regards
    Ritesh

  • Uploading Purchase Order Against the Sales Order through DTW

    Hi Experts,
    I searched the forum but could not see anything regarding this.
    Can I upload Purchase Orders against the Sales Orders using DTW upload facility? Manually we do it through the Logistics Tab in Sales Order.
    Thank you in advance.
    Kind Regards,
    IC

    Hi,
    You can use the BaseType, BaseEntry and BaseLine columns for this in the row level template (DLN1):
    BaseType: it's the Object Type of base document (ORDR.ObjType) which is '17' in case of Sales Order
    BaseEntry: it's the Document Entry of the base document (ORDR.DocEntry)
    BaseLine: it's the row number of the line in the base document (RDR1.LineNum)
    If you import your Delivery Notes with this info, the link to the Sales Order will be updated just as if you used Copy To in SAP.
    Regards,
    Nat

  • Can not delete a Production Order is the Sales order item is rejected?

    Hello everyone,
    I can not delete the production order as the Sales order line item is rejected.
    Does anybody know if any configuration change is required or any work around?
    Thank you,
    BG

    Hi,
    Could you pl. explain how the production order is created?
    Also did you try by choosing Function in the menu (CO02 transaction) & try to set deletion flag or Technically complete?
    If so did you get any error message ?
    Regards,
    Senthilkumar

  • Any batch process to release the sales order with status profile

    Hi,
    The sales manager need to release the sales order 1 by 1.
    This is very tedious.
    Is there a process for her to release selectively?
    For example,
    if the sales value of the order is visible and within the approval limit or too small,
    she could release, says, more than 10 sales order in a single click.
    Possible?????
    Bye

    Hi,
    I like to perform a mass release of multiple Sales order from the proposed custom report.
    I would like to built the releasing coding into the report.
    I need some references on how to set the release.
    Maybe, there is a standard function for me to pass it in and it would release the sales order status.
    if that the case, it is BONUS.
    Otherwise, there must be some steps that need to be built to set the release.
    what I am asking, is there any such routines that would define the steps to release the sales order in coding?
    I understand there would be a change in status aftef the released and it is also vital to enable the audit log for future investigation.
    Having a BAPI would result the audit issue as the system would have taken care of it.
    I hope it is clearer now as to why I am requesting a sample of the standard routine.
    If there is no such routine, do let me be aware of it.
    Thanks

  • Automatic creation of production order against the sales order.

    Hi Experts,
           My client requirement is he wants the production order to be generated or created automatically as the sales order is created, please suggest weather it is possible or not.
    Regards,
    Naveen.
    Edited by: vaddapalli naveen on Mar 13, 2010 9:03 AM

    Hi,
    It is possible by selecting proper Planning strategies.
    Example you can use the planning strategy Assemble to order with Production order, it is possible.
    please refer the below help link for more details,
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/41/191eb845fd11d188ff0000e8322f96/content.htm
    Thanks,
    R.Loganathan

  • Table : Production Order in the sales order

    Hi,
    When can we found in the tables of the sales order the link to the PO numer.
    And, In which field screen in the sales order document we can find the order number.
    Thanks for yur quick answer.

    Dear Omar,
    tables of the sales order the link to the PO numer
    Table: VBKD
    Field: BSTDK
    Screen: 4001 (if, for Incompletion Log, maintain as KBES)
    In which field screen in the sales order document we can find the order number
    Table: VBAK
    Field: VBELN
    Screen: 4001
    Best Regards,
    Amit

  • Want to see 80% of Net Value of Purchse order in the Sale Order

    Hi Gurus,
    Iam working for a software clinet, we are having Subsidiaries in Australia and Germeny.
    We Mapped those subcidiaries as Our Customers(Sold to Parties) in SAP.
    Our Sub wil get the order from the Customers(Ship to Parties) and they will place same order in our Company. So we will create a Sale order against to that perticuler subcidiary.
    In the Sales Order we will Our Sub Name as Sold to Part and the End Customer name as Ship to Party.
    Up to here Everything is fine.
    In the  sales order we have to Give 100% Amount of that Purchase order and we have to Generate invoice of 80% of amount to Our Subciadiary. So our Sub will get remaining 20% amount  from the End Customer.
    Here Our Sub is taking 20%amount of the Ourchase order for using thier Permises at thier ciountry.
    SO how can i map this into SAP Sytsem
    Cheers,
    Sumith

    Dear Sumith
    Insert a condition type ZSUB which is for subsidiary and maintain it as 80% which takes the value from the 100% value and then caries on with the calculation.This condition type will get hit only if customer is a subsidiary.May be u might have to right a routine with the help of ABAPer
    Hope this solve the problem
    Jyotsana

  • Changes in colums order of the Sales Order at Item level

    Hi Friends,
    I had a special requirement to map in my clients business process
    In the item level of a sales order, the columns like Plant, Shipping point, and Route are not visible at the first glance of the order. They want these columns to be appeared after quantity column.
    Can any one suggest solution for this?
    Helpful Answers will be rewarded

    Hi hariprasad
    If the requirement is to change the fields place then you can go with user exit USEREXIT_MOVE_FIELD_TO_VBAPKOM  or else you can go with the transaction variants SHD0 and you give the business object as BUS2032 and then change the field into the area where you want but for that you need to change the standard transaction variant only
    Regards
    Srinath

  • Copy the Purchase order # to the Sales order created with reference

    Generally if you create a new sales order with reference to a pre-existing sales-order, then the PO# does not get copied.
    What would you have to do in-order to get the PO# copied into the new sales order ?
    Thanks

    Dear Noel,
    As per the standard it will not get copy if you want you need to take help from the technical people (ABAPers) they may able tohelp you on that.
    I hope it will help you
    Regards,
    Murali.

  • How settlement rule will be created for Sales order with cost object

    Dear Experts,
    We are using product cost by sales order with valuated stock. In addition we are not using COPA
    We also consume some materials at sales order level and at the end of month we want to do the result analysis and settlement for the same amount. In this case can any on explain how system will behave regarding settlement of sales order cost and what entries will get pass in the system.
    In our case we have done below activities...
    we have created sales order,
    All production order activities completed till final GRN including month end activities
    Material consumption against sales order
    Result analysis executed
    At the time of sales order settlement, system throwing error (Sender doesn't have valid receiver, please create settlement rule for sender object)
    Then i checked in sales order there sales order settlement rule not defined.
    I guess this settlement rule need be generated by system automatically. If not, please let me know the process of it.

    HI kishore
          the reason is that sale order always carry the revenue  and production order and production period carry the cost .
       cost you can settle to the Material and even management want  to be settle the cost to material only in production order OR period
    but in sales order  when u sell the product it carry the revenue not the cost and management want see and analysis based on profitability segment are profit center level .
    Prerequisites
    If CO-PA is active, the system generates a settlement rule when you create the sales order. The settlement rule determines whether data is settled to other objects or other areas in Controlling. In accordance with this settlement rule, the relevant data is settled to CO-PA.
    If CO-PA is not active, create a settlement rule. This settlement rule that you create manually normally contains a G/L account as a receiver (such as 399999). You can also settle costs and revenues or results analysis data to objects with revenue.
    You can also settle the cost of sales calculated in results analysis to a fixed asset or a cost center. To do this, you must add to the allocation structure the results analysis cost elements under which the cost of sales is updated to the order.
    The settlement rule includes a distribution rule for the sales order item. The distribution rule is made up of a settlement receiver, a settlement share, and a settlement type:
    The settlement receiver (such as profitability segment or G/L account) specifies the object to which the actual costs and revenue of the sales order item are settled. The settlement receiver can be proposed through the settlement profile.
    The settlement share defines the percentage or the equivalence numbers used to distribute the costs to the individual settlement receivers. The settlement share for sales order items is usually 100%. A settlement share of 100% is preset in the system.
    The settlement type specifies full settlement of the sales order item. This ensures that all the data on the sales order is available for results analysis.
    Settlement still takes place in each period. The revenues and the cost of sales are transferred to CO-PA by period, and the work in process and the reserves are transferred to FI.

  • Overall processing status issue for sales order regarding services

    Hello,
    I have the following issue. I am billing a standard service (service without delivery) to a customer. The process goes ok, I issue an invoice, post it and generate an accounting document. Then I create a cancellation invoice. Now I want to reject my sales order. I assign reason for rejection to the item. The header and item status says it is u2018fully rejectedu2019, but the overall processing status says the sales order is u2018openu2019 and therefore appears in reports regarding open orders. I gave also a billing block, deleted the schedule line for the service so that the ordered quantity for the item equals to u20180u2019, but still the overall processing status of the order is u2018openu2019. This is standard SAP functionality (as I checked it). So can anyone explain me how to change this status to exclude this order from open order list? Or maybe someone may want to explain me why this is standard SAP process and what is the reason for the system to want to keep my order u2018openu2019?
    Thanks in advance,
    BR,|

    Place the reason for rejection in the status tab at item level, we are doing same, and the order lines does not show in open lines .
    Regards
    Chandrasekhar

  • Error when i reject the sales order

    Hi:
    I´m in Upgrade to 6.0, and when I reject a sales order in SD, the system show me this message "Subsequent function 'Production order/plan order from sales document' not possible: Item 000010 was rejected Message no. V1579".
    In the implementation the products was delivered for the company, but today they work with service orders but the integration SD with PP is until running but they user the order for documentation and to saw the costs.
    I wrote a SAP message and read this notes 964813 and Note 1028464 but both are already aplicated. SAP responce to me but I don´t konw to much of the SD and PP integration. Please, can any one help me?
    SAP responce:
    Info to SAP    
    12.03.2008 - 12:49:44 CET - Reply by SAP     Attachments
    SAP Note 97272  - Rejections of individual order items possible
    SAP Note 356895  - Rejection of third-party items and individual PO items
    SAP Note 549972  - FAQ: rejecting third-party or individual PO items
    SAP Note 1054121  - The SAP Ecosystem in a Nutshell
    Dear Gina,
    I was analyzing the problme in your system.
    If I understand you rigt you are expecting that the link between the
    sales order and the production order is not deleted when you set the
    reason for rejection. When you set the reason for rejection again then anew production order is created.
    The standard behaviour is that the link between sales order and
    production/assembly/service order is deleted. As field vbep-aufnr is
    deleted also no later restructuring is possible.
    In the header table of the order aufk-kdauf there is still the relation
    to the sales order number but there is a deletion flag set for it and
    the link can't be reactivated.
    I am sorry that I could not give you a more positive reply.

    Hi:
    In the table AFKO I don´t have any order document. I searched this, before reject the sales order, and then, when I try to reject the sales order, and in both cases I don´t have the relation about the order and the sales order in this table.
    I looked at the table AUFK and in the field KDAUF I saw the sales order and the relation with the PM order, and this is my problem, I don´t no why the message error tell me something  about PP order,  I didn´t understand.
    I saw the customizing and I Know they works with the "Strategy group" in materials and it was customizing in "Demand Management" and the order was customizing in "Plant Maintenance and Customer Service", (PM) customizing the Order Types. I think when finally they decided that the material was only for services, they changed something, and the customizing is not complete in PP.
    In the old version 4.6C the rejection of sales order works, but in this version 6.0 and with MRP implementacion I don´t know in what step this was change. If you Know where can i find if something of MRP affect the previous integration please let me know, because I think is a PP customizing problem.
    Thanks
    Best Regards
    Gina

  • How to find out the purchase order# giving the sales orde numer?

    Hi Gurus,
    how to find out the purchase order# giving the sales order# or material
    with regards
    thambe

    hi
    use va02-t.code
    double lick on line item data--> click on order data tab.
    there you can find the po details relavant to that sales oreder & the material.
    Thanks & Regards,
    krishna.

  • Cost analysis through Purchase Order created from Sales Order

    Hi Experts,
    This is the scenario: There is an Item No. which is not stocked in warehouse and is purchased only when customers ask for it. The cost of the sales order line having this item is calculated by the Purchase Order line on which the item is there. (The PO have items for other Sales Orders as well. And, Sales Orders have multiple item types) The Sales Order have the PO no. against it and Purchase Order has SO no. against the line. This is all done using MS Access and Sage Accounts. Lots of free typing and manual cost analysis involved.
    I have gathered from this forum that we can create Purchase Order from the Sales Order. The Document No. information can be pulled from one another using Formatted Search. Can we do the accounting and cost analysis as well?
    Please let me know if I have not made myself clear.
    Thank you in advance and kind regards.
    IC
    Edited by: iancameron03 on Sep 20, 2011 4:35 PM

    Hi Ian,
    I concur with Faraz, it is better if you use procurement document facility in doing back to back transaction from SO to PO.
    However, in your case, I'm afraid you can't analyze the gross profit and recording the accounting related activity as your request using standard SAP B1 function.
    As for gross profit case:
    Since you're actually using workaround in order to evade all hassles in maintaining all item master data related to this case, you create just one item code called S1 right?
    SO DocEntry - SO Line # - Item Code - Item Name - Quantity - Price
    1001 - 0 - S1 - Table - 2 - 100
    1001 - 1 - S1 - Chair - 8 - 25
    1001 - 2 - S1 - Cloth - 3 - 10
    PO # - PO Line # - PO BaseEntry (SO DocEntry)  - PO BaseLine (SO Line #) - Item Code - Item Name - Quantity - Price
    2001 - 0 - 1001 - 0 - S1 - 2 - 100
    2001 - 1 - 1001 - 1 - S1 - 8 - 25
    2001 - 2 - 1001 - 2 - S1 - 3 - 10
    Note that standard B1 gross profit calculation is that system will compare selling price for each item with item cost / certain price list of each respective item. However, in your case, you put all item as a single item master. Thus, system couldn't compare Table to Table, Chair to Chair, Cloth to Cloth since the item cost for these 3 items will be the same, the price list for these 3 items will also be the same since it is actually only one master data. Of course you could update the gross profit calculation manually for each SO, but to be honest it seems rather weird to do this manually.
    So, in order to simulate the gross profit calculation, you need to create a custom query and comparing PO line no with SO line no.
    As far as accounting related recording concern, I'm afraid you can't do it
    1. SO 1 : Item Table - Selling price 130 ; Item Chair - Selling price 30
    2. PO 1 (linked to SO 1) : Item Table - Purchase price 100 ; Item Chair - Purchase price 25
    3. SO 2 : Item Table - Selling price 150 ; Item Chair - Selling price 40
    4. PO 2 (linked to SO 2) : Item Table - Purchase price 110 ; Item Chair - Purchase price 30
    Correct me if I'm wrong, you want to record accounting wise that CoGS of Delivery based on SO 1 is 100 for Table and 25 for Chair, isn't it? No matter what costing method you use, you can't achieve this.
    If you use moving average, system will average both Table and Chair cost price, since it is actually one item master data. Even if you distinguish each item as a master data, system will average the cost price for Table and Cloth by the time GR for PO 1 and PO 2 occurred.
    Example (order by sequence of event):
    1. GR based on PO 1 - Table - Purchase price = 100, therefore Item cost = 100
    2. GR based on PO 2 - Table - Purchase price = 110, therefore Item cost = 105 (considering quantity only one for both PO)
    3. Delivery based on SO 1 - Table - CoGS incurred will be 105, not 100
    To certain extent, same thing could be said with FIFO costing method
    1. GR based on PO 1 - Table - Purchase price = 100 (qty 1)
    2. GR based on PO 2 - Table - Purchase price = 110 (qty 1)
    3. Delivery based on SO 1 - Table - CoGS incurred will be 100 (qty 1)
    4. Delivery based on SO 2 - Table - CoGS incurred will be 110 (qty 1)
    At first glance, it seems right since the CoGS for SO 1 is 100, tied up with purchase price for PO 1. And CoGS for SO 2 is 110, tied up with purchase price for PO 2. But we're using assumption here, we're assuming the sequence of Goods Receipt of PO and Delivery of SO occurred in the very same sequence as the issuance of SO and PO.
    1. GR based on PO 1 - Table - Purchase price = 100 (qty 1)
    2. GR based on PO 2 - Table - Purchase price = 110 (qty 1)
    3. Delivery based on SO 2 - Table - CoGS incurred will be 100 (qty 1)
    4. Delivery based on SO 1 - Table - CoGS incurred will be 110 (qty 1)
    If above scenario / sequence that happened, you will get the wrong figure of gross profit since the Delivery of SO 2 will take the item cost based on GR of PO 1. Since we're actually talking about real life business process, who can guarantee that above scenario wouldn't happen? It is possible that you send goods to customer who ordered late in real life, too much possibility that it is better for you to mitigate such result.
    My suggestion would be that you record the accounting transaction based on standard business process, no need to really capture the actual cost and actual gross profit for certain SO and PO. Too complicated, and the software itself doesn't cater this kind of requirement. Best thing you could do only create custom query for gross profit simulation calculation, but for very accurate accounting recording, IMO you should forget it. Hope this help.
    Best Regards,
    Hendry Wijaya

Maybe you are looking for

  • IPad-Calendar I cannot view the month March 2013

    In iPad-Calendar I cannot view the month March 2013, the calendar crashes. To view the week or the day, no problem, but the month is not working. iPad III, latest updates on iOS installed.

  • File upload and download feature

    Hi, I want to make a application using APEX that will help to upload a file to a specified web directory and create a link to download it further. Can you please help me. Thanks & Regards, Kaushik

  • Safari not formatting the page

    I have Safari running on Mac OS 10.6 with an  Intel iMac. The system has 2 accounts on it.   Admin and User. When I log on as the User acount, and launch Safari, some web sites do NOT format correctly.   Safari OR Firefox do NOT show the fonts correc

  • Excel's _xlfn.PERCENTRANK.INC in T-SQL

    Hi all, any idea how to mimic this function in T-SQL? We are on SQL Server 2008 R2. Thanks in advance!

  • ESB TDM plug-in not found??

    I just upgraded from logic Pro 8 To 9 and now when I start up the application it says "Direct TDM: ESB TDM plug-in not found (-10800)" The application seems to be working just fine but does anyone know what this means and why it's happening?