Shipping data in stock transfer order

Hi  friends,
I try to configure stock transfer process between two plants,
Here is what I 've done
create shipping point and assign it to supplying plant
create supplying plant as affiliate vendor
create receiving plant as a affiliate customer
set up supplying plant 
when I create the PO, error message still say shipping data is missing.
Your help will be deeply appreciated.

Hi
First check you are doing the transfer between the plants within company code or cross compnay code.
Once you completed the configuration check the following
Customer Master for shipping condition
Material master for Loading grp
Configuration for shipping point for Plant/Loading grp/Shipping point
The system tries to determine a shipping point for every item to be delivered.
The system uses three fields as search keys for determining the shipping point
automatically. This data is normally defined in the following master records:
•1) Shipping condition from the sold-to party (view: Shipping)
2)• Loading group in the sales-specific material data (view: Sales: General/Plant
Data)
3)• Delivering plant - see the slide Determining Delivering Plant Automatically
Hope it helps
Thanks/karthik

Similar Messages

  • Fwding agent in Shipping Data fr Stock Transfer of Purchasing Document Item

    Hi,
    I want to know how to configure the Forwarding agent in Shipping Data For Stock Transfer of Purchasing Document Item (ME21N).
    I have used the Forwarding agent as Partner function in Header level but it does not appears in VL10D where we create deliveries from open Purchase orders.
    Regards,
    Abhilash

    Hi,
    Just follow the steps:-
    1) You should check the shipping point assignment under SPRO-> Logistics Execution-> Shipping->Basic Shipping Functions->Shipping points & Goods receiving point determination-> Assign shipping points.
    OR.....
    You may directly check from table also....>
    Put T-code SE16-Table TVSTZ
    Put your plant and shipping point and check the correct assignments.
    2 ) Go to table T001W and check the assignment of customer to plant.And also check the sales area in this table for both Supplying & Receiving plant.
    3) Check wether the customer is in the required sales area or not.
    If still u face problem kindly reply me.
    Regards,
    Savita

  • Table for  the PO Date and Stock Transfer Order Date of a material no

    Hello Everyone!
    I am having a requirement where I want both the Purchase Order Date and Stock Transfer Order Date of a perticular material no.
    On the basis of difference of these two dates I want to find out the period for which the material was present in supplying plant.
    I am not getting the table through which I can get these two dates for a material.
    Please help me out.
    Its urgent.

    hi,
    see these tables:
         EKKO – Purchase Order Header Table
         EKPO – Purchase Order Item  Table
         EKBE – PO History table.
    reward if its useful

  • Re-calculate delivery date in Stock transfer order ( STO UB ), V_V2

    Hi, running the transaction v_v2 only Sto (Stock Transfer Order) At item level.
    Scenario:
             Sales order in Plant 2.
             Sto ,  Plant 1 to Plant 2.
             Purchase Order To Vendor in Plant 1.
    When I run V_V2 in Plant 1, the First execute transaction V_V2 is OK, This system availavility check the STO and confirm the delivery date and the quantity.
    Now I change the delivery date in Purchase Order but the transaction V_v2 in plant 1 don´t  make any change in the STOCK TRANSFER ORDER (STO) in the Delivery Date field.
    Why the systen don´t change the delivery date in STO automaticaly, Becuase I can change manualy in ME22N transaction, and the sytem confirm the quantity and  the confirm date.
    Other Example.
    I have good issu the Purchae Order in Plant 1 and execute V_V2, the sytem do not re-calculate the delivery date in STO, Why ?.
    Thanks.

    A solution has not been identified for this issue...query closed.

  • Intercompany Stock Transfer order - Shipping data

    We are in the process of implementing intercompany PO/STO process and we have hit a roadblock.
    Taking the example of one of our sites - Plants in Ireland supply material to plants in UK. Although they are part of difefrent company codes they are treated as INTRA-COMPANY transfers so we need to use the distribution channel IN
    But some plants in northern Europe (Finland/ netherlands) also supplys material to UK and they are INTER-COMPANY transfers so we have to use distribution channel IC
    Issue : IN SPRO, When you define shipping points for plants, you can assign only on distribution channel for a plant but as per the example above We need two distribution channels.
    Has anyone else come across any similar issue? Is there any work around or user exit that we can use for this please?
    Cheers,
    KB

    SPRO > MM > Purchasing > Purchase Order > Set up Stock Transport Order > Set up sTock Transport Order Between Storage Locations > Define Shipping Data for Stock Transport Orders Between Storage Locations (V_T001W_L) - here you can define different sales area / customer master for Plant / SLoc combinations.
    SAP will recognize the proper sales area when you input the issue SLoc during creation of STO (issue SLoc is the last field in the line of the PO item, it appears after hitting enter key).
    Regards,
    Csaba

  • Shipping point determination in stock transfer order,

    Hi, experts,
                            I have one problem regarding stock transfer note, In my business scenario, product wise SR no use for excise invoice, So, i had maintain no range as per shipping point wise, But , when i have create stock transfer order, at a time system take default shipping point , as per shipping point determination, But i want to different shipping point in this stock transfer order, but i can not change shipping point in stock transfer order, Can u give me any solution of this problem,
    T.code - Use - ME27
    Order type - UB
    Regards:
    Happy

    First create a STO with a Plant as per your Requirement by maintaining the same Plant in the Material.Also maintain the same Plant in determining the Shipping Point Determination.
    Otherwise to change the Shipping Point Manually is not a good habit by the Users.
    Best Regards,
    Ankur

  • Changing shipping conditions in stock transfer scheduling agreements EKPV

    I am wondering if anyone has a solution or knows if SAP has any functionality enhancements to allow shipping data in stock transfer scheduling agreements to be changed. Currently we are on ECC 6.0 and are going to be applying EHP5 within the next few weeks. I see that SAP has made changes to stock transfer orders with EHP5 however, the shipping data does not appear to be changeable. Any help is appreciated.
    Stan Olszyk
    Allison Transmission Inc

    Check OSS  Note 303453 - User exits for shipping data determination in STO would help you.
    Regards,

  • Combine stock transfer orders with different delivery dates into 1 delivery

    Hello,
    In transaction VL10B, the system normally combines stock transfer orders that have the same ship-to-party and same delivery date (if the combination indicator in the customer master specific to sales and distribution is checked). My business requirement is to combine stock transfer orders that have the same ship-to-party but different delivery dates. Is this possible through standard configuration? Is there a user exit that can allow this?
    At the moment the system is creating different outbound deliveries according to the delivery dates specified in the stock transfer orders.
    Please advice a solution.
    Regards,
    Felipe

    Felipe, please have a look at OSS note 386340, it may help to solve your problem about combining STO items with different delivery dates to one delivery (as I understand the code correction overwrites the delivery dates...).
    Edited by: Csaba Szommer on Jan 21, 2011 5:06 PM

  • Shipping Tab in Stock transfer Purchase order

    Hi,
    while making a PO,there is Shipping Tab appears in Stock transfer order though all concerned settings are done.
    1.Shiiping condition is attched to customer.
    2.Ctreate material for both the plant.
    3.Create vendor and customer settings.
    still the shipping tab is missing in PO ,please suugest me.

    Hi
    Check the shipping point determination setting in
    SPRO-Logistics execution-Shipping-Basic shipping functions-Shipping point and goods reciept point determination-Assign shipping points
    Also check  SPRO-MM-Purchasing-Purchase order-Set up stock transport order-assign delivery type and checking rule
    Regards
    Sandeep
    Edited by: sandeep13 on Apr 16, 2010 11:29 AM

  • Delivery Date Re-Calculation in Stock Transfer Order PO

    Hi All,
    We have Transportation scheduling activated and maintain 'Transit Duration Times' in our Routes (Populated 'TransitDur' field in Route <0VTC>) R/3 46c
    When we create a stock transfer order the 'Delivery Date' in the STO PO is determined by the 'TransitDur' (Transit Duration) value maintained in the route between the 'Supplying and 'Receiving' plants.
    After creating the STO PO, if the delivery is delayed and we need to reflect this change in the STO, when we attempt to change the delivery date - the system re-calculates the delivery date using the date on which the changes are made as the starting point and extending out the full length of time based on the value in the 'TransitDur' field in the Route.
    This means we are not able to change the delivery date in the STO PO to a date that is later than the original delivery date but still earlier than the date re-calculated by the system using the date on which the changes are made as the starting point.
    Is anyone aware of any functionality/config which allows you to manually change the delivery date in the STO PO - but not be restricted to changing the date by the value in the 'TransitDur' field of the Route, when it is a subsequent change to the PO and greater than the original date determined by the system?
    Thanks,
    Ravelle

    A solution has not been identified for this issue...query closed.

  • Stock Transfer Order, is there any field called "commit to ship"

    Dear Experts,
    While doing Stock Transfer Order, is there any field called "commit to ship"  which means that the qty is confirmed to transfer from Plant A to B.
    Regards

    I am not sure exact field are you reffering in PO there is commited qty in delivery schedule tab this will shows commited qty in po once qty confirmed

  • Stock transfer order

    Hi Gurus,
    While doing Stock Transfer order - assigning deliverying plant
    to sales organisation : I could not assign and message is giving :
    "The sales org is part of company code Z222, Plant Z223 is part of company code Z223. Organization data for inter company billing missing in plant Z223."
    For you kind information :
    I have maintained regular enterprise structure ie everything is Z222 means comp code, plant, shipping point etc. for my memory.
    Stock transfer order step
    Step 1 I maintained another enter prise structure ie. everything is Z223 company code, plant etc.
    Step 2 Intercompany billing customer, I assignd customer no. in relevant sales org ie, Z222
    Step 3 I am assigning deliverying plant ie Z223 to sales organisation ie Z222 but I could not assign, the message has come.
    Kindly anyone help me out.
    Thanks
    rakesh

    Hello.
    Go to SPRO --> Materials Management ---> Purchasing ---> Purchase Order ---> Set Up Stock Transport Order --> Define Shipping Data for Plants. Select the ordering plant (Z223) and assign the intercompany customer, and the sales area of the deliveing plant.
    Once you maintain this try to assign the Delivering plant (Z222) to Ordering sales organisation (Z223) and Distribution channel.
    Prase

  • STO Stock Transfer Order with HU (Handling Units) - Error Hugeneral 319

    Hello,
    We implemented a Stock Transfer Order process with the following details:
    MM side
    - PO is type NB, supplier is F_8001;
    - In table T001W, supplier F_8001 is assigned to plant 80GP;
    - WERKS = 40TV and LGORT = 41P in all PO items;
    - In each item, the shipping tab is filled with NLCC as delivery type and customer C_4000 (this customer corresponds to plant 40TV in table T001W). The sales area is also defined as the sales area to be used in the sales order that will be created in plant 80GP;
    SD side
    - Sales order is created automatically for customer C_4000;
    - In plant 80GP we have a HU managed stloc (32P). In this stloc we have a HU with the exact contents of the sales order. This HU has X in the HU storage loc field;
    - We created the outbound delivery and chose our HU. From this moment the HU storage loc field changed to D and the HU was assigned to the delivery;
    Now for the problem:
    When we click Post Goods Issue button, we get the following error for each item:
    HUGENERAL 319 - HU item contains different data than the stock posting
    The HU contents are exactly what we need to ship, so we do not understand this error. We need this HU to be transfered to stloc 41P in plant 40TV (this stloc is also HU managed). Any clues?
    Thanks in advance,
    Joã

    Hi,
    Have you checked your HU material and material to packed both having stock in Inventory.
    Even check the table HUMSEG is correctly updated or not.
    check this table correctly Hu assignd to you material and created materil document or not.
    check for for material master clearly for both material like plant, storage location, batch etc..
    Ask your MM consultant to check all entry is correct in material master and delivery or not.
    Regards
    Karthik.

  • Define Shipping Data for Stock Transfers Between Storage Locations

    Hi Guru,
    Can i know what is the purpose to maintain Customer, SHipping data for each storage location for the STO between storage location?
    Purchasing --> Purchase Order -->
    Set up Stock Transport Order-->
    Set Up Stock Transfer Between Storage Locations-->
    Define Shipping Data for Stock Transfers Between Storage Locations

    The Sales org, Distribution channel, Shipping point, Vendor and Customer are maintained to created the delivery.
    It is for the transfer of stock between storage locations with any movement type.
    Eg: When you do a 311 movement type from Sloc A to Sloc B, then it will create a inbound delivery with the Vendor specified for Sloc A and an outbound delivery from Sloc B with the Customer specified assuming the customer and the vendor as the Plant.
    You have to create a internal Vendor and Customer.
    Hope it helps.

  • Transaction to see the Open stock transfer order for the plant

    HI ,
    i need to develop one report in that client to make the report for the all open stock transfer order & the cost of the open stock transfer order for the plant .
    I need how to cretae the stock transfer order for the material , whci material master is required for this process.
    please give me step by step details for this .
    regards
    satish
    Edited by: satish kapartiwar on Jul 16, 2009 9:33 AM

    Hi Satish,
    You can see open stock transfer quantity in MB5T and stock value in MB5L. If you want to make stock transfer, there is two types intra company transfer(with in same company code) and inter company transfer (different company codes).
    Steps for Intra company stock transfer:
    This is only within the comp.code(w/o SD)
    (w/o SD) 351101 MvT. and (with SD) 641101
    1. Mat.(1434)should be maintained in both the plants.(@1000&1100).
    2. Should have enough stock in supplying plant(1000).
    3. Make its supplying plant as a vendor in vendor master record in receiving plant(1100).
    4. Make it receiving plant as a customer in customization.
    Create customer (xd01) & and define the shipping data for plants in both the plants.
    Path: spro u2013 img u2013 material mgmt u2013 purchasing u2013 po u2013 set up STO u2013 define shipping data
    (1 by1 )
    In Receiving plant (1100)
    Customer num. 123345 (for ex.)
    Sales org. yyy
    Dist. Channel yy
    Sales div. y
    In Supplying plant (1000)
    Customer num. -
    (don't fill)
    Sales org. yyy
    Dist. Channel yy
    Sales div. y
    5. Assign doc. Type is "NL" for intra company STO. If STO is inter company, Assign doc. Type is "NLCC".
    Position doc type is "UB"
    Enter supplying plant(1000) & doc type (NL)&checking rule (ex:01)
    6.Assign doc. Type is "UB" to u'r plants.(PO)
    Go for new entries
    Enter supplying plant(1000) & Receiving plant (1100)&doc type (UB).
    7. Create a PO, choose the doc type is 'UB' & item cat.'U', Enter supplying plant as a vendor in PO of the receiving plant(1100).
    8. Provide this num (PO) to SD people, they will do the delivery by using transactional code is VL10B.
    9. Sales people they will provide "out bound delivery num".
    10. Do the GR. In GR the second tab 05 outbound delivery instead of PO mov.type 101.
    11. See the stock overview in the receiving & supplying plants.
    Steps for Inter company Transfer:
    1) Create one Customer Master in XD01 with respect to Supplying Plant Sales Area and assign this Customer no with Receiving Plant in OLME->PO-> set up STO->Define shipping data for plant and for the supplying Plant assign the above sales area.( Make sure, In Customer Master, sales Area Tab: you are maintaining shipping condition)
    2) For Receiving Plant Pur. Org and Co.Code Combination create Vendor master in XK01 and in this vendor master assign the Supplying plant in Pur.Org.Data screen->Extras--> Add.Pur.data
    3) OLME->PO-> Set up STO------>For your supplying plant assign document type NB, Delivery type NLCC and Checking Rule RP
    4)then For your supplying Plant and receiving Plant assign Document type NB
    5)Make sure you are maintaining Sales View for the material at supplying Plant and in Sales /Gen plant Data view maintain Availability check, Loading group and Transportation group.
    6) In SPRo-->Logistics execution> Shipping->Basic shipping functions->Shipping point Determination>assign shipping points-> For your Loading group, Shipping Condition and Supplying plant combination, Assign shipping point
    these are the configuration settings you have to do in background.
    Then Create STO from Receiving Plant in ME21N with document type NB.
    Based on that STO, Create Delivery in VL10B from supplying Plant
    Do PGI in VL02N from Supplying plant
    Do GR in MIGO at Receiving Plant keeping Outbound delivery as a ref. document.
    Now your STO bet. two plants belongs to diff. Co.Codes will be completed.
    Regards,
    Prasath