Good morning, i have a question about the difference between Stock material from MM and WM.
My customer, told me about difference in material stock in tables MARD and LQUA.
He told me that stock material in LQUA is greater than in MARD, because some users didn't work correctly.
Since correct stock is in MARD table ( and not in LQUA), my question is: is there any standard solution (transaction ,program, or others ecc.) to make equal the quantity values in both tables?
Thank you in advance for your cooperation and attention,
Francesco

Francesco,
Have you checked the warehouse activity monitor (transaction LL01) to see if there are any incomplete documents there?
In general, an Invneotry Movement (receipts, issues, transfers, etc) will trigger a WM movement via transfer postings and  transfer orders.
The best way to habdle this may be on a case-by-case basis, and use the appropriate transactions to correct your issue.
<B>Example scenario:</B>
User does a goods issue (reduces MM quantity). The transfer order may not have been created or may not have been confirmed. In either case, WM quantity is not reduced, causeing WM to be higher than MM.
If the TO was not created, there iwll be an open transfer requirement - try processing it in the foreground.
If the TO was created but not confirmed, try confirming it.

Similar Messages

  • T-Code for reporting stock quantity difference between IM and WM

    Hi All
    I'm probably going to kick myself for asking this quastion but is there a report to show the stock quantity differences between IM and WM?
    I have searched the forum first but cannot find info.
    We have various differences in IM and WM shown in MD04 and LS26. This is usually the result of an unplanned plant to plant transfer not being recipted in at the destination plant.
    If no standard T-code is available, which tables can I join to create my own query?
    Thanks in advance
    Darren

    compare MMBE with LS26
    Make sure you dont enter a storage location and storage type in selection screen of LS26.
    if you post a difference with LI20, then you have just posted a difference within WM, means you moved a quantity from a bin into the difference storate type 998.  The balance of both is still equal to your stock shown in MMBE. You have to clear the difference with IM by executing LI21 transaction. Only then the quantity will disappear from difference storage type and will be adjusted in MM and FI.
    LX23 will only report real inconstencies and will adjust them.
    If you do a MM movement like 303, then this creates a transfer request in WM, this TR needs to be converted into a TO. to move the stock from the bin to the interim storage type for goods issue.
    In your case you created just a negative quant in the interim storage type for goods issue and still have a positive quant in the bin, the balance is equal to the stock shown in MMBE.

  • Stock account difference between GR and IR

    Hi Friends,
    PO is created for some quantity and price.
    No taxes and discounts are maintained so net price is equal to gross price.
    While doing GR, stock account is debited with different value instead of net price in PO.
    However IR is done with proper value.
    In a nutshell, for the same qty, GR value is different from PO price.
    Thanks in Advance.
    Raju

    Hi,
    Check the Accounting View of the Material and the Price control used.Whether it is Standard Price or Moving Average Price.Accordingly the system will behave.
    Dhruba

  • Differences between view and materialized view

    Hello,
    Please tell me the Differences between view and materialized view in oracle 9i.
    Thanks and regards
    Madhuri

    How can I create index in a view?
    Please read reply of Justin Sir.
    Regards
    Girish Sharma

  • What is the difference between view and materialized views

    Hi
    What is the difference between view and materialized view ? can we update the base table using views

    can we update the base table using viewsYes:
    VIEWS
    1. an updatable view is one that lets you perform DML on the underlying table
    (see Oracle Database Concepts 10g - 5 Schema Objects)
    2. non-updatable view requires INSTEAD OF Triggers
    (see Oracle Database Concepts 10g - 22 Triggers)
    SNAPSHOTS
    You can have updateable (and writeable) snapshots - in updateable (writeable) MV replication.
    Oracle uses snapshots (Materialized Views - MV) for two different purposes:
    1. replication
    2. automated Query Rewrite facility (first introduced in Oracle Discoverer, later included in Oracle database 8i).
    Replication types in Oracle are:
    a) Basic replication (MV replication)
    - transaction based
    - row-level
    - asynchronous from master table to MV (Materialized View)
    - DML replication only
    - database 7 / 8.0 / 8i / 9i / 10g
    - Standard and Enterprise Edition
    1. Read-only MV replication
    2. Updateable MV replication:
    2.1 asynchronous from MV to master
    2.2 synchronous from MV to master
    3. Writeable MV replication
    b) Multimaster replication
    - transaction based
    - row-level or procedural
    - asynchronous or synchronous
    - DML and DDL replication
    - database 7 / 8.0 / 8i / 9i / 10g
    - Enterprise Edition only
    1. row-level asynchronous replication
    2. row-level synchronous replication
    3. procedural asynchronous replication
    4. procedural synchronous replication
    c) Streams replication
    - (redo) log based
    - row-level
    - asynchronous
    - DML and DDL replication
    - database 9i / 10g (10g has Down Streams Capture)
    - Enterprise Edition only (Standard Edition 10g can execute Apply process)
    Regards,
    Zlatko Sirotic

  • Differences between MD01 and MD02.

    Dear SAP Experts,
    Please tell me the various differences between MD01 and MD02.
    In which specific cases, MD01 should be used??
    Thanks and regards,
    Kaushik Basu.

    Hi,
    1. Md01 is the MRP Run for  plant by giving planning scope.
    2. Md02 is the mrp run for single Material from plant .
    Also refer following T code for your information
    Menu Nodes
    Transaction
    Activity
    Master Data
    MD25
    Create planning calendar
      MD26
    Change planning calendar
      MD27
    Display planning calendar
      MDSA
    Display BOM explosion number
      MDSP
    Edit BOM explosion number
      MEQ1
    Maintain quota file
      OPPP
    Explode BOM by date
      MDUS
    Display project assignment
      MDUP
    Process project assignment
      MDL1
    Create production lot
      MDL2
    Change production lot
      MDL3
    Display production lot
    Planning
    MD20
    Create planning file entry
      MD21
    Display planning file entry
      MDAB
    Set up planning file entry in background
      MDRE
    Check planning file entry
      MD01
    Total planning online
      MDBT
    Total planning in background
      MD03
    Single-item, single-level planning
      MD02
    Single-item, multi-level planning
      MD43
    Interactive single-item planning
      MD50
    Multi-level, make-to-order planning
      MD51
    Multi-level project planning
      MF52
    Display planning table
      MF50
    Change planning table
      MF57
    Planning table by MRP lists
      MF51
    Planning table by production list
    Evaluations
    MD04
    Stock/requirements list
      MD07
    Collective access of stock/requirements lists
      MD05
    MRP list
      MD06
    Collective access of MRP lists
      MDLD
    Print MRP list
      MD45
    Planning result
      MD46
    Collective access of planning result
      MD44
    Planning situation for a material
      MD47
    Planning situation for a product group
      MD48
    Cross-plant planning situation
      MD4C
    Order report
      MD09
    Pegged requirements
      CO46
    Order progress
    Planned Order
    MD11
    Create planned order
      MD12
    Change planned order
      MD13
    Individual access of planned order
      MD16
    Collective access of planned orders
      MD14
    Individual conversion of planned order into purchase requisition
      MD15
    Collective conversion of planned orders into purchase requisitions
      MDUM
    Convert planned order into purchase requisition in background
      CO40
    Convert individual planned order into production order
      CO41
    Collective conversion of planned orders into production orders
      CO48
    Partial conversion of planned order into production order
      COR7
    Individual conversion of planned order into process order
      COR7_PC
    Collective conversion of planned orders into process orders
      COR8
    Partial conversion of planned order into process order
      MDVP
    Collective availability check
      MDAC
    Execute action for planned order
    Hope it clear to u.
    Edited by: Atul Zod on Nov 21, 2008 6:59 AM

  • Which is difference between Pipeline and Consignment..

    Hello  All...
    I need your help... Can you help me to understand the difference between Pipeline and Consignment?
    Many thanks and I appreciate your Help and comments!

    A pipeline material is a material that flows directly into the production process from a pipeline (for example, oil), from a pipe (for example, tap water), or from another similar source (for example, electricity).
    A material from the pipeline is always available; i.e. it can be withdrawn from the pipeline at any time and in any quantity.
    Depending on the system configuration, a material can be withdrawn only from the pipeline or, in addition to the pipeline, normal stocks of the material can also be managed.
    STEPS TO MAINTAIN PIPELINE MATERIAL
    1. You can create a material with PIPE material type or else you can use any material type but that should allow pipeline process.
    2. You should have Inforecord for the material with valid conditions, price will pick only from inforecord.
    3. If requied you can maintains ource list or else you can select during goods issue.
    4. From the Inventory Management menu, choose Goods movement ® Goods issue.
    Maintain the data on the initial screen. Choose Movement type ® Consumption ® To cost center (or To order, To network, All account assignments) ® From pipeline (Movement types : 201 P, 261 P, 281 P, or 291 P)
    5. On the collective entry screen, enter the account assignment. Enter the items.
    You do not have to enter the vendor as this will be found automatically by the system.
    If more than one vendor is possible, a pop-up window appears with a list of pipeline vendors, from which you can select the vendor you require.
    Post the goods movement.
    we can not stock pipeline material. It is readily available. directlly it is avilable at cost center. you need to pay for that consumption

  • Difference between SCM242 and SCM250

    I am preparing for certification and wanted to know What is the difference between SCM242 and SCM250?

    am not sure of SCM242. where did you see the reference to this?
    but here is some more info. You can also find it in https://service.education.sap.com
    SCM250 (Production Planning and Detailed Scheduling (APO-PP/DS))
    contents:
    Brief overview of prerequisites and master data
    Preplanning and sales orders in APO-PP/DS
    Requirements planning
    Planning quantities and capacities
    Planning heuristics
    Planning strategies
    Advanced production planning functions
    Planning tools for requirement and capacity planning
    Corresponding Customizing settings
    SCM240 (Production Planning (ERP))
    contents:
    Material planning overview
    Consumption-based planning and MRP planning
    Demand management
    Requirements strategies for make-to-stock production
    Requirements strategies for make-to-order production
    Performing requirements planning
    Processing of material requirements planning results
    Master production scheduling
    Long-term planning
    Technical details of the planning run
    MRP areas

  • Difference between configurable and non configurable finished goods master

    Hi
    Pl explain the difference between configurable and non configurable finished goods master data.
    Thanks
    kamala

    Hi,
    Configurable material are used when you have a large number of combination of parts that go into a product. It means different combinations of the parts for same material. If you maintain a unique material code for each combination , you require a large number of material numbers. KMAT is used in such a case where you maintain just one generic product code. You assign class to this material having all variant characteristics.
    A super BOM is maintained for such a material consisting of all possible alternatives. A super routing is also maintained consisting of all possible operations that could be used.
    Typically configurable material is used in Made To Order (MTO) environment. However frequently ordered configurations may be planned with a material variant which needs to have a material master record. Thus Material variants may have stock and value. Depending upon characteristic values chosen at sales order entry Sales Order BOM is created. Routing operations are also chosen depending upon which BOM components are assigned to them.
    Non configurable materials are like finish, semi finish materials having fixed BOM.  A separate/single BOM exits for every finish material.
    Revert back for more info.
    thanks and regards,
    Man

  • Difference between cumulative and non-cumulative key figures

    Hi,
    What is the difference between cumulative and non-cumulative key figures and under what conditions they are used. What is snapshort and where it is used.

    Hi.............
    Basically the key figures are of two types cumulative and non cumulative.
    Cumulative are the normal one which you use always and they always bring the new values of the key figures in the delta that is if suppose A has value 10 and after change the new value is 20 then you will use cumulative key figures there, and your delta( new value) will bring 20.
    but suppose your key figures field only the change in the prior value that is in this case the delta in the key figure value will bring 10 (20-10- change of 10 )as new value in the key figure A then you will have to model it through the non cumulaitve key figures.
    Now
    1) Cumulative is for the first case that is if the key figure alwyas brings the new values of the key figure and not the change sin the key fiures value.
    2)NCum. value with NCUM value change:
    In this case ther is only one field which brings the changes for a particualr key figure and you ahve to define that key figure as non cumulative.
    Ex: In case of stock only one filed brings both ingoing value and outgoing value so 10 ,-4,100,-34.....
    In this case you will this option and use the key figure here in the space provided.
    3) In this case you haev two separate key figures one for the inflow of stocks and one for the outflow of the stocks.
    you use one key figure for the inflow and one key figure for the outflow.
    The main key figure autiomatically takes care of the logic and gives the correct output upon the summation
    net value of stocks( inflow- outflow).
    Also do remember in this case the key figure for inflow and out flow are the basic key figures that is cumulative key figures.
    A non-cumulative is a non-aggregating key figure on the level of one or more objects that is always displayed in relation to time. Examples of non-cumulatives include headcount, account balance and material inventory. here the aggregation of key figure is based on the another info object
    There are two different ways to define non-cumulative key figures:
    • Non-cumulative key figure with non-cumulative changes:
    Before you can define the non-cumulative key figure, an additional cumulative key figure containing the non-cumulative change must exist as an InfoObject.
    • Non-cumulative key figure with inflows and outflows
    There has to be two additional cumulative key figures as InfoObjects for non-cumulative key figures - one for inflows and one for outflows. The cumulative key figures have to have the same technical properties as the non-cumulative key figure, and the aggregation and exception aggregation have to be SUM.
    Features of non-cummulative key figures
    A non-aggregating key Figure.
    Records are not summarized for Reporting
    Exception Aggregation is being applied on these key figures on the level of one or more info objects usually with time .
    Examples: Head Count, Account balance, Material stock
    consider simple senario
    Date Net Stock Quantity Sales Revenue
    01.02.2005 40 1000
    02.02.2005 50 2000
    03.02.2005 25 3000
    this is the query output if stock quantity has treated as cummulative and non-cummulative key figures
    if stock quantity taken as a cummulative key figure
    Date NET STOCK QUANTITY SALES REVENUE
    01.02.2005 30 1000
    02.02.2005 50 2000
    03.02.2005 20 3000
    RESULT 100 6000
    in the above result the key figure has aggregated to the total value that wont give sense to the net stock quantity
    if stock quantity taken as non-cummulative key figure
    Date Net Stock Quantity (LAST) Sales Revenue
    01.02.2005 30 1000
    02.02.2005 50 2000
    03.02.2005 20 3000
    RESULT 20 6000
    Hope this helps you..............
    Regards,
    Debjani................
    Edited by: Debjani  Mukherjee on Sep 15, 2008 7:22 AM

  • What is a difference between MB01 and MBST  for GR Cancellation

    Hi,
    What is a difference between MB01 and MBST  for GR Cancellation.
    Regards,
    Aditya

    Hi,
    MB01 is used for doing the GR for collective PO at a single instance.
    This transaction will be utilize when an individual needs to create a material document.  A material document can only be displayed or changed after it has been generated in the SAP system.  In a computer based inventory management system, the principal of "no posting without a document" applies.  A material document is generated and stored in the SAP system for every transaction that causes a change in stock.
    As mentioned, when a goods movement is posted a material document is created.  It serves as proof of the movement   If the movement updates a G/L account; an accounting document is also created. The material and accounting document s are identified by unique document numbers
    Once you have posted a goods movement, you cannot change material numbers, quantities or account numbers in the material document.  You can however use the Change command to enter additional or change text information such as comments or references.  To reverse the movement or change a quantity, a new transaction must be performed.
    MBST:-
    Perform this transaction when a previously performed goods issue must be cancelled due to an error in data entry or other circumstances deem the previous transaction unnecessary.
    Prerequisites:-
    A previously played transaction that requires cancellation.
    An existing Material Document in SAP.
    This Transaction will be utilized when an individual needs to cancel a material document due to a data entry error or other circumstances deem a previous transaction unnecessary. A material document can only be cancelled after it has been generated in the SAP system. A material document is generated and stored in the SAP system for every transaction that causes a change in stock.
    Performing this transaction will "undo" a previous transaction by reversing individual line items in a material document or by reversing an entire material document. This transaction will reinstate the affected cost center, purchase order or stock location to the state they were in prior to playing the original transaction.
    Regards,
    Archit

  • Difference between CO09 and  MMBE Transactions

    Hi All,
    Please let me know difference between CO09 and  MMBE Transactions.
    FOr particular material and plant ,Quantity 1 is there as FGI  in MMBE screen but it is not there in CO09 for same material in the same plant.
    Regards
    Nidhi

    Dear Nidhi Srivastva      
    MMBE(Stock over view ) : By using this transaction code we can get the information pertinent to the particular material stock levels in the respective plant and storage locations.
    With the help of the detailed display we will know wether the material is in transit mode ,restricted ,unrestricted and so on........
    CO09(Avilability overview): With the help this we will know when the order was raised and the confirmed quantities.
    Apart from that we know about the  goods issues and goods recites of respective plant.
    Please let me know if you have any further clarifications
    Thanks&Regards
    Raghu.k

  • Difference between techo and close order

    Dear all
    plz tell what is a difference between techo and close production order
    guide me
    Rgds
    SDB
    Edited by: surendra patil on Aug 21, 2008 12:18 PM

    TECO  means ending a production order from a logistical viewpoint. This function is usually used, if the execution of an order has to be stopped prematurely or if the order
    could not be executed in the required manner and open requirements for the order (reservations,capacities) should be deleted.
    The following actions are executed if an order is set to TECO:
    · The order is not relevant for MRP planning
    · Reservations are deleted
    · Capacity requirements are deleted
    · Purchase requisitions for external operations or non-stock materials are deleted
    · The order and its operations receive the system status  (TECO)
    If an order is technically complete, you cannot change it. The fields in the order are displayed but
    cannot be changed. You can however cancel technical completion, for instance if order data has
    to be changed.
    After technical completion you can still make  posting for order.
    For instance,material withdrawal or a confirmation can be posted if they were previously forgotten.
    *Closed Order :
    *The Closed (CLSD) status has been introduced in the production order. It has the following
    characteristics:
    · No more costs can be posted to the order, that is, confirmations and goods movements are
    no longer permitted for the order.
    · The order can no longer be changed. Exceptions to this are revoking the CLSD status and
    setting the deletion flag.
    · All actions relating to the status technically completed are executed
    · In a collective order, the CLSD status is also set for subordinate orders.
    · If the system comes across an order in the collective order that cannot be closed, the orders
    that come between this order and the leading order are also not closed. Other subtrees are
    closed if they only contain orders that can be closed.
    Regards,
    Hrishi.

  • What is the difference between 651 and 653 movement types

    Hi
    What is the difference between 651 and 653 movement types
    Points will be rewarded
    Regards
    Suddu

    Hi,
    Whenever goods movment happens following things are going on in the background:
    A material document is generated, which is used as proof of the movement and as a source of information for any other applications involved.
    If the movement is relevant for Financial Accounting, one or more accounting documents are generated.
    The stock quantities of the material are updated.
    The stock values in the material master record are updated, as are the stock and consumption accounts.
    651 - two steps - with a transfer posting using 453
    653 - one steps - direct post to unrestricted used
    *Using movement type 651, you post returns from a customer with a return delivery in Shipping to blocked stock returns.
    Using 653 movement type, you post returns from the customer with returns delivery via Shipping directly to the valuated stock.
    <b>Reward if helpful.</b>
    Thanks

  • Difference between VMI and collaboration with customer

    Hai,
             I am trying to understand the difference between VMI and collaborative planning with customer(CPC)
    Please correct me if I am wrong. In VMI, a vendor or manufacturer sells his material to customer and through EDI, the customer gives the information such as forecast, stock etc.
    In CPC, the vendor and customer interchange information, such as demand, stock levels, promotions, delivery dates etc., based on ITS.
    What is the difference between these two?
    If I am not wrong, EDI is used for outside company communication andITS for within. So, can I say that VMI is for customer outside the company and CPC for internal customer?
    Thank you.

    Hi Visu,
    Service provided by a vendor for a customer, whereby the vendor plans material requirements in the customer's company. Vendor-managed inventory is only possible if the vendor has access to the customer's current stock and sales data.
    In the ERP system, the following functions are available for vendor-managed inventory:
    Transfer of stock and sales data by EDI
    Receipt of stock and sales data by EDI
    Replenishment planning for customers
    Creation of a purchase order for an external EDI order acknowledgment
    supply chain management tool that synchronizes demand signals and supply chain activities by utilizing Internet technology. Collaborative Planning enables supply chain partners to view, share and synchronize common information within the supply chain.
    Hope this helps.
    Regards,