Stock transfer between two WM managed storage locations
Hi,
I want to transfer some stock between two wm enabled storage loc (wm 120 and sl 0001 to another wm 200 and sl 0006) but
not able to do so. Got to know that there are two components involved in this one IM and WM. I am new in WM so do not have much idea please provide me the right solutions.
Thanks and Regards,
Rahul
Edited by: Rahul Shukla on Aug 23, 2010 12:30 PM
Stock transfer w/o delivery:
You can execute the goods movement in IM (one-step or two step) and after that you can process the TRs which are generated when posting GI/GR (hopefully your config is OK and TR is created automatically; else you have to maintain WM-IM interface). You can process the relevant TR from LB10 both in supplying plant (TO wiill be created from TR --> stock removal) and in receiving plant (TO will be created from TR --> putaway TO)
Stock transfer with delivery:
In supplying plant you have to pick the delivery (you have to create TO), you can do this e.g. via trx LT03, VL06O, VL02N (from "Subsequent functions" manu). In receiving plant you have to process the TR (from LB10) which is generated when GR is posted.
(based on your WM-IM interface setting you may not get TR but immediate TO creation can be triggered, etc. If you are using inbound delivery as well you have to create putaway TO, etc.)
Please specify your problem you are facing - in this case you may get specific answer.
Edited by: Csaba Szommer on Aug 23, 2010 1:51 PM
Similar Messages
-
GATP Stock transfer between two sublocations
Hello,
Is it possible to use Rules Based ATP to create an Stock Transfer between two sublocations in the same plant?
The source sublocation (Storage Location) is assigned to a Storage Location MRP Area
In the Rules we have defined a Location determination procedure that if it does not find ATP quantities in the main location it searches in the Storage Location MRP Area (Location Type 1077). The idea behind this rule is to treat the Storage Location MRP Area as a diferent location, but it does not works.
I thank in advance for your kind cooperation.Hi Loknath / Verma,
The STR is between a Production Location an a MRP Area Location.
I have created the rule, but no STR are created. It does something very strange instead of what is expected.
For example,
I have 2 storage locations in PLANT1:
- STL1 has 100 units of product 1
- STL2 has 200 units of product 1. This SL is assigned to an MRP area
In APO the No check on sublocation level check is unchecked.
I have cifed production location and the MRP area so two locations are created: one is type 1001 and the other is type 1007.
I have defined a Rule, so if there is not enough ATP cuantities in PLANT1 (Type 1001) it should search in the MRP Area (type 1007)
If I have a sales order that asks for 150 units, rule is trigered.
First thing that is very strange: when I see the Storage location substitution list, I cannot see the MRP Area. What I see is the production location.
The other problem is when i look at the ATP quantities during ATO verification, they do not match with the ones I can see in RRP3.
Anyway, I have taken a look at the link that Verma sent me, and I understand that if I use RBATP to create STR between storage locations, sub positions are created, and there is a requirement in our project that no subpositions should be created. So, even if I can make it work, I cannot used... Seems that I may investigate the problem in my spare time.
Thanks a lot for your help. -
Billing in Stock Transfer between two plants of two different company codes
Hi Friends,
I am doing the scenario of stock transfer between two plants of different company codes.
I have some issues in Billing for this..
What are the settings do i need to to for Pricing in SD point of view.
Ex:
Supplying / Receiving
Com.Code:2000 / CompanyCode:1000
Plant:2100 / Plant:1100
SA:2000/10/00 / SA:1000/10/00
I created Customer 5555 w.r.t sales area of supplying company code (2000/10/00)
I created Vendor 7777 and assigned Supplying Plant 2100 in add purchasing data.
In IMG Settings:
Define Shipping Data for Plants: In Receving Plant i assigned customer 5555 and sales area blank
In Supplying Plant i assigned customer blank and sales area as 2000/10/00
Create Checking Rule: Standard(B SD Delivery)
Define Checking Rule: Standard(Avallability-01assigned to checking rule B)
Assign Delivery Type and Checking rule: Document type(NB)-Supplying Plant(2100)-Delivery Type(NLCC)-Checking Rule-(B)
Assign Doc Type:Supplying Plant(2100)-Receving Plant(1100)-Doc type(NB)
What are Pricing settings in SD i have to do?????????
Process:
ME21N->VL10B->VL02N(PGI)->VF01(IV)->MIGO->MIRO
I have gone through many threads in Forum but confusion in Pricing Part..
Some are mixing with the inter company sales proces..
Pls guide me..
With RegardsDo the following steps for STO Customizing:-
1. Create a customer master record for the issuing plant.
2. Create a vendor master record for the issuing plant, and enter customer account number in the Customer field on the Control screen.
3. Repeat steps 1 and 2 for the receiving plant.
4. Assign the plants to the customer master record in Customizing for Materials Management (MM), by choosing Purchasing <Purchase Order < Set Up Stock Transport Order< Plants.
The Process Flow would be as follows :-
Create a stock transport order, following the standard procedure, and send the order to the issuing plant.
Issuing plant has processes your order, and when it is ready to ship,the storeperson at the issuing plant issues the goods using a transfer posting. The excise clerk there creates an excise invoice.The excise supervisor verifies and posts the excise invoice.It then sends the goods to you, together with the excise invoice.
Once the goods arrive, you follow the standard procedure for incoming excise invoices:
The excise clerk captures the excise invoice, using the stock transport order as the reference document. The storeperson enters the goods receipt, again using the stock transport order as the reference document.Alternatively, you can first enter the goods receipt and then capture the excise invoice.
The excise supervisor then posts the excise invoice.
Best Regards,
Ankur -
Stock Transfer Between two plants within same company code
Hello,
We are using scenario-'Stock transfer between two plants within same company code. Scenaro is like Plant A is receving plant and Plant B is delivering Plant.
Plant A release PO for 100 nos to Plant B
Plant B issues 100 nos (via delivery) to Plant A
But Plant A receives only 50 nos physically so they do Goods receipt for 50 nos , but document got generated for 100 nos (when plant B issues material).
Now Plant A do not want to receive remaining 50 nos physically, but wants to reduce material document which got created when goods issue posted by plant B
Now stock in transis (mb5t) is 50 nos.
How to reduce this material document. or any another alternative solution for this?
Thanks,
ShaileshHi There
Reversal of partial is not possible ,
But you can use the Mov Type 557 and 558 to do the adjustments in Stock in transit qty
Few more details on STO adjustments
Hi There
it can be settle in many ways,,,
1. Receive the goods as 100 and Scrap the 50 nos from the received plant,,- If the receiving plant is responsible
2.Revert the PGI/Transfer movement(Vl09) and send the 50 nos again from the supplying plant- of the Supplying plant is responsible,
3.Also we have the movement type 557 and 558 without doing the above two steps you can correct the qty from stock in transit itself,,
4. also you can check the below similar thread
STO - material lost during tranfer from plant A to plant B
5. If above are not ok, then receive the goods as 100, And raise the STO as your plant as supplying plant and receiving plant is (Supplied 50 nos less) plant,, Do the process without sending the material.. in this way that 50 nos can be adjusted,,
6.Here is some more details
557 Issue from stock in transit (adjustment posting)
Only use this movement type (also the reversal movement type) under the following circumstances:
Using movement type 557, you can correct purchase-order-independent stock in transit if
- a good receipt cannot be posted to a purchase order without stock in transit, even though there is still stock in transit according to the purchase order history
- stock in transit still exists, even though there are no open stock transfer orders for the particular material
This movement type may ONLY be used in the cases mentioned above after careful analysis, to correct stock in transit that has rounding errors.
This movement type may not be copied.
Note!
Before using this movement type, note the following:
- 392205 Analysis stock in transit / Correction if split valuation
Possible special stock indicators:
E, Q
7. As previous post says if you have the note for this issue you can use that also
You can use any one of the way to solve the issue, Hope it helps
Cheers
Senthil P -
Intra-company stock transfer between two ERP Systems without SAP APO
Hi,
I'm looking for information regarding the scenario Intra-company stock transfer between two ERP Systems without SAP APO.
On help.sap.com, I can only find below image, but I'm actually looking for the configuration settings required to implement it.
Does anyone have experience with this scenario?
Thanks & regards,
OliverHi Jagdeep,
Thanks for the reply. I understand that I need to use iDocs and setup communication between both systems. What I am actually looking for is detailed information on the setup of the purchase order type and sales order type. Especially because there is no invoicing involved in this flow.
Regards,
Oliver -
Stock transfer between two St locs of same warehouse
Hi All,
I am new to WM and trying to config/simulate st loc to st loc transfer 311
one step between two st locs that belong to same warehouse number.
What should be the config and under
LE->WM->Interface->IM->movement types -> assign WM Movement Type
References to IM Movement Types. In my system for 311 movement type entry with
only the quantity check box checked and no other spl stock I see that there are
three columns mentioned below
For mvt types on WM side first one “Reference movement type for WM from
material movements” = 311
Second one “Reference movement type for transfer in warehouse mgmt.” =312
Third one “Reference movement type for posting change in whse mgmt.”=309
The reason I am confused is when I do a MB1B 311 from one st loc to another
st loc from unrestricted to unrestricted on IM side it is triggering 309 on WM
side where as I am expecting 311 to trigger with TR to pick from issuing St loc
and another TR/TO with (312 or 311 I am not sure) to putaway the stock in to
the receiving st loc. Can someone help in explaining how should the stand SAP
IM/WM interface work and what should I be doing to make it work that way
Thank you in advance
JHi J,
To explain you in simple way,
When Sloc is Wm managed and stock is transferred at IM level using 1 step within plant, stock is directly transferred from one sloc to other sloc(no TR/To is created to pick and putaway unless configured) Due to this difference is created between IM & WM level, Hence mvt type 309 is triggered for PCN . This Mvt 309 is picked based on std config at
LE->WM->Interface->IM->movement types -> assign WM Movement Type
References to IM Movement Types
If you want to create TR immediately then put x in 9 column against mvt 309 and w/h combination.
LE->WM->Interface->IM->movement types -> LE-WM Interface to Inventory Management -
To stock transfer the RM to Production storage Location
Dear All,
I want to stock transfer the RM from Store to production storage location after that I have to pick the material against Production Order from Production Storage Location.
How I can carry out this scenario.
I am trying through Pull list.
please give ur valuable inputs.
Thanks in advance
Vijay Mankar.Hi Vijay,
To tranfer the stock from store to Prod storage location , u can do in two ways,
1.Pull list - By accesing the Pullist with the production order .if there is no enough stock to meet production qty at production storage location , system calculate the missing part and asks replenishment storage location. here u have to give your store as repl.storage location
2. Enter tranfer posting.( MB1B) - using this u can tranfer the stock dierctly from the store to prodution storage location. u have to use 311 Mvt type and define Rec storage location is store.
3. Enter good issue MB1A - u can pick the raw material with reference to your prodution order using 261 Movement Type.
please reward if it helps
regards
pradeep -
Stock transfer between two company code
Hi experts !!!!!!
Would like to have u r suggesations
We have two company codes. (1000 and 3000)
Company code 1000 has one Distribution Center (e.g.1100)
And Company Code 3000 has Five Store (e.g. 3100, 3200,3300,3400,3500)
please suggest how to transfer the article stock , (by using Stock transfer order) from Company code 1000 Which has Distribution Center (e.g.1100)
TO
Company Code 3000 has Store (e.g. 3100, )
please tell detail in step by step
thanks in advanceHi,
Steps to be followed will be
1) Define the shipping data for Sites
2) Assign a delivery type and checking rule
3) Assign a Purchasing document type for the Supplying site and Receiving site combination
4) Assignment of movt type 643 and field selection for the same as per requirement.(OMJJ)
5) Change filed controls for Vendors by vendor account group. Change the General data> Control to optional and Additional Purchasing data from site to Optional. (OMSG)
6) Define the partner function in Vendor master data for supplying site. (XK02).
Hope this helps.
Regards,
Vinod Kapote. -
Stock transfer between two plants in same company code at price
Hello,
Hello,
I have a scenarios. One plant is selling a part to other plant at a margin. Both plants belongs to the same legal entity.
How can I map this scenario in SAP?
What will be the cost of my part in these two plants?
What mechanism I would use to transfer the stock from supplying plant to the buying plant?
Your urgent reply is appreciated.
Thanks,Prem,
Yes, for this scenario, you will have to implement EC-PCA. This is different from CO-PA.
Detailed information can be found in http://help.sap.com/saphelp_erp2005vp/helpdata/en/eb/13759643c411d1896f0000e8322d00/frameset.htm
The Stock valuation is different from MM and PCA point of view. Stock Transfer within Co Code does not have any effect on the Stock value from MM point of view. The Stock value changes only from the PCA point of view. The solution works the same way with Standard Cost also. Your Standard Cost can remain the same in both the Plants.
The PCA entries are triggered by the Profit Centre data in Material Master. The Profit Centres should be different for both the Plants.
Hope this clarifies.
Thanks -
Stock transfer between two plants under the same company code at profit
Hello,
Hello,
I have a scenarios. One plant is selling a part to other plant at a margin. Both plants belongs to the same legal entity.
How can I map this scenario in SAP?
What will be the cost of my part in these two plants?
What mechanism I would use to transfer the stock from supplying plant to the buying plant?
Your urgent reply is appreciated.
Thanks,Hi
To map this scenario, you should use Profit Centre Accounting.
Example
Matl XYZ is to be transferred from Plant 1000 to Plant 2000 at a profit.
Value of Matl XYZ in Plant 1000 is $100
Transfer Price: $120
From FI view point, there would not be any Accounting document as both Plants belong to the same Company Code.
From PCA view:
Plant 1000:
Internal Revenues Dr. 120
Stock Cr. 100
Profit Margin Cr. 20
Plant 2000:
Stock Dr. 120
Delivery from Profit Centre Cr. 120
Effectively, the value of Matl XYZ in Plant 1000 remains at $100 and in Plant 2000, it is $120.
Hope this clarifies.
Thanks -
Stock transfer between two plants within same company code at price
Hello,
Hello
I have a scenarios. One plant is selling a part to other plant at a margin. Both plants belongs to the same legal entity.
How can I map this scenario in SAP?
What will be the cost of my part in these two plants?
What mechanism I would use to transfer the stock from supplying plant to the buying plant?
Your urgent reply is appreciated.
Thanks,Hi Pream
You can do it through Intra Company STO, but in this scnerio the libility never gets generated to the receiving plant because it is transfer from one pocket to other. but you can always transfer the goods on the assessable valu. you have to maintain the ***. value in J1ID, then while bill system picks the same ***. value in UTXJ condition.
But if you want to salel at a margin then use SO-PO i.e. create PO from receiving plant and against sale order, do the delivery of the material to the respective plant.
I think this will help you.
In case of any qurty feel free to contact
Girish -
"sales order stock" transfer between two different sales orders
Hi,
I have 2 sales orders as follows:
.Sales order # 301324 for Plant 1000
.Sales order # 501324 for Plant 2000
Plant 1000 and Plant 2000 belong to same company code.
Now I wanna to transfer the sales order stock of Sales order # 301324 to Sales order # 501324 directly, is that possible? If it's, how to realize?
Thanks a lot.u cant transfer directly a sales order from one plant to another plant sales order
1 first step is u have to transfer ur sales order unrestricted stock to plant unrestricted stock 411 E movtype
2. then u have to transfer ur unrestricted stock to plant 1 to plant 2 301movement type
3. and then from there u can transfer ur unrestricted stock to sales order stock 412 E mov type
hope this may help u! -
Stock transfer between two subcontractors:
Dear Experts,
I posted some material using movement type 541 to first subcontractor(SC). This SC returned the material, for this GR is made. Now some quantities are left with this SC.
Now, I want to transfer this stock with first subcontractor to another subcontractor directly.
Please suggest me how to deal with this scenario?
Thanks in advance,
Prasanna A PHi
You have already completed part delivery of the material from the sub_contractor, GR done, You need to Lock the itme from further delivery for the balance materials.
Add a new line item for the balance ordered materials from the subcontractor just like the ist line item but only for the balance qty. For the second line item go to the Delivery Address Tab in the item detailsand just below Address Push buton you will find the Vendor Field & the chk box for SC vendor
enter the vendor number of the new Subcontract Vendor and activate the chk box.
Now do the GRN for the second line item for the ordered plant, once done if you check the stock at subcontractor No. 2 in MBLB or In MMBE you will find the stock lying with the vendor.
You need to regularise the stck availability now for the new vendor.
Regards -
Stock transfer between company codes
Dear Experts,
I am doing stock transfer between two different company codes. Purchasing order type wil be NB & SD delivery type will be : NLCC
i have done all w.r.t configuration requirement for between company code, when i go for ME21N, unable to get purchasing order type NB but its showing only UB & item category U. systme giving message like : item category U & pur order type is UB would like to proceed. But it would be for between plants within same company code.
Please assist me where i am doing wrong...
Best Regards
Badari
Edited by: badaripro on Feb 23, 2010 7:15 PM
Edited by: badaripro on Feb 23, 2010 7:15 PMDear Badari,
I don't understand. Do you say that you just start ME21N and can only choose order type UB there? In this case it has nothing to do with the question if the STO is cross-company or not, since the system doesn't know the plants yet.
I would assume somebody just deleted the document type NB in your customising or you are not authorised to use it - please start ME21N again, observe the error (can't choose NB), leave the trs and run trs SU53 to check your authorisations.
BR
Raf -
Stock transfer between Plant/Storage location to Plant/Storage location
Dear Experts,
This is a MM component of SAP Retail.
We have 4 brands ( Plants of type B, Plants of type C etc) that needs inventory from the same Distribution center (Plant A) for some common products. Here the direction is to prioritize the inventory per brand. The requirement is one brand should not take the inventory of the other brand.
To overcome this problem , the solution proposed is to have different storage location for different brands in the same DC.
When we run replenishment planning for the brands and do a ATP check, the availability check should consider only the one issuing storage location in the DC which we allocated for the brand.
I do see the following set up in SPRO and I have done the following.
Step1: Activate Stock Transfer between Storage Locations SPRO->Material Management->Purchasing->Purchase Order->set up stock transport order->set up stock transport order between storage locations-> u2018Activate Stock transfer between storage locationsu2019
Step2: Assign Delivery Type and checking rule according to storage
SPRO->Material Management->Purchasing->Purchase Order->set up stock transport order->set up stock transport order between storage locations->Assign Delivery Type and Checking Rule According to Storage
Step3: Define Shipping Data for Stock Transfer between Storage Locations
SPRO ->Material Management ->Purchasing ->Purchase Order ->set up stock transport order ->set up stock transport order between storage locations -> Define Shipping Data for Stock Transfers between Storage Locations
Step4: Define Rule for Determination off Shipping Point SPRO->Material Management->Purchasing->Purchase Order->set up stock transport order->set up stock transport order between storage locations -> Set-up Storage-Location u2013dependent shipping point determination->Define rule for determination of shipping point
Step5: Shipping Point Assignment According to Storage Location
SPRO->Material Management->Purchasing->Purchase Order->set up stock transport order->set up stock transport order between storage locations-> Set-up Storage-Location u2013dependent shipping point determination-> Assign Shipping Points According to Storage Location
Question.No:1- After completing the above set up in me21n, the issuing storage location field is greyed out. I am not able to enter any value here. Can you please help.
Question.No:2
I do see the following setting.
Under IMG ---> Material Management ---> Purchasing --> Purchase Order --> Set up Stock Transport Order -->Business Add-In for Determination of Issuing Storage Location
Display the IMPLEMENTATION
Double click on the method GET_SUPPLYING_SL
Click the Execute button
Click the detail button on IF_EX_MD_EXT_SUP
Execute GET_SUPPLYING_SL
There is a prerequisite for this BADI .I have done those things.What i dont understand is where to force the combination of supplying site/issuing stor.loc/receiving site/receiving stor.loc
Kindly provide your inputs.
Thanks,
VasanthanDear,
Have You configure MRP in second plant (where you want to transport the Material).
Please try with this and do again Po for stock transport.
Regards
Piyush Patel
Maybe you are looking for
-
my ipod touch 4th gen 32g ios 4.3 i tried to update it and when i unplugged it it wasent updated and all the factory apps(settings, music, videos, calander) were gone. now when i try to restore it it says "your device is not eligible for the reques
-
Cover Flow bug in Simplified Chinese version
in both OS 3.1.2 and 3.1.3 Simplified Chinese version. If I use the English/Traditional Chinese version, the bug doesn't exist. Thanks. Message was edited by: cavaus
-
IPod 60gb Video sitting on 0 play time on tracks :(
hi guys, not sure if you can help with a issue I've been having for some time. every now and then I've had a issue when you select a track to play or select shuffle it will load the track title and cd cover but sit on 0 track time not moving, nor pla
-
Transport shows successfull but why it is not taking effect in test
Hi all , I have changed my dataource and added some Z fields . But when i transport that to test system, i can not see the effect in test . Transport shows successfull but why it is not takin effect from the Dev Datasource changes to Test systems ? P
-
Last GR date information if the material is not batch managed
Hi Gurus, Is there a way to extract the Last GR date if the material is not batch managed? Thanks.