Hello,
what are the tables which capture confirmed scrap cost.
thanks in advance

Hi Pat,
Please try table CPZP
Elias

Similar Messages

  • Tables for Target costs

    Hello All,
    Can anyone please tell me the tables for target costs in controlling.
    Thank you
    Nivas

    No answer received

  • Table for plan cost

    Which is the table where we can get wbs description & plan cost in PS?
    Amit

    For WBS description, please use table PRPS. Use the field POSID.I dont know whether there is any table for plan cost.However we use table COSS for Cost totals for internal postings & table COSP for Cost totals for external postings.
    Hope this helps.
    Regards
    Tushar
    PS: Reward points if it is useful.

  • Tables For Secondary Cost Elements

    Dear Folks,
    Please Help me for getting details (TABLES) of Secondary Cost elements Actual Line items Date wise and Cost Center wise
    Thanks in advance
    Regaards
    ASHOK K

    Hi Ashok,
    some important Costing tables
    COEP  - Line Items (by Period) 
    COEJ  - Line Items (by Fiscal year 
    COKA  - Control Data for Cost center wise
    COEJT - Line Items for Prices  
    COEPT - Line Items for Prices
    CSKA Cost Elements (Data Dependent on Chart of Accounts)
    CSKB Cost Elements (Data Dependent on Controlling Area)
    CSKS - Cost Center Master Data
    CSLA Activity Master
    COBK  - Document Header       
    COEJL - Line Items for Activity 
    COEJR - Line Items for SKF
    COEPL - Line Items for Activity
    COEPR - Line Items for SKF  
    COKL  - Control Data for Activity
    COKP  - Control Data for Primary
    COKR  - Control Data for Statics
    COKS  - Control Data for Secondary 
    AUSP - Characteristic Values       
    A132 - Price per Cost Center             
    A136 - Price per Controlling Area      
    A137 - Price per Country / Region        
    COSC - CO Objects: Assignment of Original 
    CSSK - Cost Center / Cost Element       
    CSSL - Cost Center / Activity Type      
    KAPS - CO Period Locks -  
    regards
    Gokul

  • Table For Secondary Cost Elements

    Dear Folks,
                  Please Help me for getting details (TABLES)  of Secondary Cost elements Actual Line items Date wise and Cost Center wise
    Thanks in advance
    Regaards
    ASHOK K

    check this might help you..
    Tables to be refered for secondary cost element.
    Regards
    Kumar

  • Table for Material-Cost center-Settlement Rule_REM product cost collecter

    I want to generate a report to see for particular material which cost center and which settlement rule is available.
    If we go in Product cost collecter (PCC) there we have an option to see settlement rule under header tab, I want to fetch that data for material as selection parameter, can anyone suggest how to get the data as,
    Material        Cost Center        Settlement Rule
    Thank you.
    Regards,
    Deven

    Hi,
    pleasefind tables related with cost.
                          TKA01               Controlling areas
                         TKA02               Controlling area assignment
                         KEKO               Product-costing header
         KEPH               Cost components for cost of goods manuf.
         KALO               Costing objects
         KANZ               Sales order items - costing objects
         Cost center master data
                        CSKS               Cost Center Master Data
                        CSKT               Cost center texts
                        CRCO               Assignment of Work Center to Cost Center
                        COSP               CO Object: Cost Totals for External Postings
                        COEP               CO Object: Line Items (by Period)
    .     COBK               CO Object: Document header
         COST               CO Object: Price Totals
    Regards
    SANIL

  • Doubt for Scrap Costing

    Dear Friends,
    I Need help regarding Scrap costing - My views as follows,
    Operations would maintain Scrap % for components at MAterial Master level  MRP view, as well as in the Bill of materials. However, when you create Std Cost Estiamte, system will consider the scrap quantity and include that in the material costs.
    The system works like this while creating Cost Estimates when Scrap % are maintained
    1.First System looks for Assembly Scrap for Component items in BOM . If available, that is added to the Raw Material quantity as per BOM when doing costing.
    2.If Assembly Scrap and Component Scarp % maintained in Component items in BOM, system first applied Assembly scrap and then adds Component Scrap over that.  For example if a Raw Material quantity is 200  in BOM, system first assembly scrap, say 10% which is 20  nos and Component scrap is say 5%, it adds  11 (5% of  220) and hence total RM costed is 231 nos
    3,If no Assembly Scrap maintained in BOM but  Component Scrap maintained, system will apply the Component Scrap qty over the   Item qty in BOM while costing
    4.If Component Scrap in BOM is maintained, as well as  Scrap % maintained in MRP 4 view of material master, system will take only the  Scrap % maintained in BOM and ignore the %maintained in Material Master
    5.If  no Component Scrap maintained in BOM, and Scrap % maintained in Material Master, system will consider the scrap % maintained in Material Master for Costing
    Is there any way (through user exit or otherwise thro configuration) such scrap % can be ignored while creating cost estimate.
    Regards,
    KBR.

    No, you cant
    Remove the Scrap % from Material Master and restore it after Cost Run
    Create a Costing BOM w/o adding any scrap % in it
    br, Ajay M

  • Wrong picture in AFRU table for scrap...

    Hi Experts,
    When I confirming co11 and entering scrap, it show wrong picture in AFRU table.
    e.g. : For first time i entered 2 scrap.
            Seconf time i entered  1 scrap.
    But in table it shows 5 scrap.
    Which is the right table ? How to finf scrap qty for same prod. order. ?
    Yusuf
    null

    no answer. Closed.

  • Table for Settlement Cost(CJI3) for a project

    Hi All,
    I have a requirement to develop a report for a project, in that i got a req.  to find out the settlement cost for a project.
    we have standard report CJI3 to find the settel cost for a project but I am unable to debug the program as it use logical databases(PSJ).
    Please advise me and let me know any table or Function module exists for same.
    Regards,
    Venkat

    Hi,
    The table /s you are looking for could be one of these;
    RPSCO   Project info database: Costs, Revenues, Finances
    COSP: Cost Object: Cost totals for external postings
    COSS: Cost totals for internal postings
    COSB:Total variances
    COBK:Document header
    COEP: Line items
    You may need more than one table to meet your requirements.
    Pl confirm, if useful.
    regards
    Muraleedharan.R
    091 9880028904

  • Table for planned cost

    Hi All
    In which Table and field can i find planned costs for maintenance order. I need this info for individual orders and not collective planned costs.
    Thanx in advance.

    Ruhail,
      You should be able to get that from table PMCO. It holds the cost for the order at the Value category level. You would have to sum up the cost from different value categories to arrive at the total planned cost of the order. The estimate and actual cost at the value category level is also available from the same table.
      The same information can also be obtained from the controlling tables of COSS,COSP and COEP.
    Regards
    Narasimhan

  • Table for CCPC Cost

    Hi All,
         I have problem in finding the CCPC cost Estimated through transatction CK11N. 
    Excise Details we can get from J_1iexdtl Table but I didn't get the CCPC cost.
    Please suggest me how to calculate that cost.

    Hi,
    Thanks for your reply , This si costing Table But i didn't get the CCPC Value from this Table.

  • Table for std cost of material

    HI,
    in which table can we get Std cost of material?

    Try to check table MBEW for the field STPRS.
    Hope this helps
    Regards
    Sai

  • Table for Planned cost & Budgeted value with WBS

    Hi,
    Which is the table where we can get WBS description & planned cost in PS?
    and any other table or report where we can see the comparison & see the balance of planned cost value and budget value
    thanks & regards,

    Hi,
    You mean to say in CJ40 not in CJ30.
    Step 1: Go to PRPS Table and enter the WBSE and get the OBJNR no.
    Step 2:Pass the OBJNR in RPSCO and you can get the planned cost value.Note WRTTP should be 1.
    Muzamil

  • RW report on CCSS table: for some cost element key figure SWTG empty

    Dears.
    Could you kindly help to solve strange issue with report in Report Painter?
    I have 2 basic key figure in report
    SWTG - Total cost in transaction currency
    SWOG - Total cost in object currency
    In report some lines have the only SWOG figures and SWTG field empty.
    It looks strange, because all costs are posted similarly in the same transaction (via cash journal FBCJ) and they all have postings in accounting and controlling.
    Thanks in advance.
    Kind regards,
    Roman.

    I understand the reason - if there were postings in different currencies, the column "Total cost in transaction currency" is shown as undeterminable values. It's OK.
    But the problem is - if it is done even once, this "spoils" cost element and in "normal" period with one currency postings it will anyway show crosses as undeterminable values.
    How to fix it?
    Thanks,
    Regards,
    Roman.

  • Table for "Budget planning : Cost Center"

    Hi Gurus,
    can anyone pls tell me table for "Budget : Cost Centre" . We create budget with respect to cost center in KPZ2/KPZ3 but i am unable to find out in which this data can be found.
    Pls tell me the table to retrieve the data.
    Regards

    You can do it yourself.
    goto transaction St05. activate the trace. then execute the transaction. after execution goto st05. click deactivate trace.
    then click display trace...hit enter button. a list will be displayed. goto menu bar choose first menu then choose option "Summarice sql statements"...a list will be displayed from which you can know what all tables were affected by the transaction.

Maybe you are looking for

  • IOS 7 App Store review dates missing

    I notice since updating to IOS 7 that the dates for reviews are no longer appearing in the App Store app. They still appear in the reviews in the iTunes Store app. Is this supposed to be gone with the update? If so, it's a step backwards... funny how

  • Track delays before playing  -  Help please

    DSP - 3 One of my tracks seems to delay before playing and I end up with a black screen before it begins. I went back to Final Cut and can't find any problem with it there. All my other tracks start fine. Help please. Thanks.

  • How to integrate SIEBEL systems with SAP Enterprise portal

    Hi all, i need some materials or any links on how SIEBEL system can be integrated with portals.  thanks in advance                  vijay.k

  • Oracle.forms.engine.Main not found.

    Hi, I have a error when I try to call a form made in Forms 6i using 9iAS. Seams that something with the settings. Need help please. load: class oracle.forms.engine.Main not found. java.lang.ClassNotFoundException: java.io.IOException: open HTTP conne

  • Capture setting when using a firewire and camcorder

    does anyone know the capture setting I use when importing from a dvc camcorder using a firewire