The "net due date" of a Credit memo

Hi All,
if a creatate a credit memo (t.code FB75), and fill in a "Payment Term", SAP doesn't calculate the "Net due date" according to it (the Payment Term).
SAP shows a "Net due date" equal to the "bline date", ignoring the "Payment Term".
Could anyone tell why does it happen?
Thanks

Invoice related credit memos:
1. Credit memos can be linked to the original invoice by entering the invoice
number in the "Invoice Reference" field during document entry. In this case,
the terms of payment are copied from the invoice so that the invoice and the
credit memo are due on the same date.
Other credit memos:
2. Terms of payment in other credit memos are invalid. These credit memos are
due on the baseline date. To activate the payment terms on these non-invoice
related credit memos, enter a “V” in the "Invoice Reference" field when
entering the document.

Similar Messages

  • Customer credit memo can't auto calculate the net due date

    Hi all,
    Our user used F-27 to entry customer credit memo (PK = 11),
    [F-27|http://www.flickr.com/photos/44956360@N08/5206144134/]
    and payment term use net 60 days,
    [F-27 - screen 2|http://www.flickr.com/photos/44956360@N08/5206144210/]
    but the system display the net due date doesn't add 60 days
    [F-27 - screen 3|http://www.flickr.com/photos/44956360@N08/5206144292/]
    To use fbl1n display the net due date doesn't add 60 days
    [FBL1N|http://www.flickr.com/photos/44956360@N08/5206144344/]
    Why the system can't auto calculate the net due date when user used PK = 11, but If user use PK = 01, the system can auto calculate the net due date.
    Best regards,
    Eric

    Hi Henri,
    I found the answer, when user enter the original document number in reference field of credit memo, the system can auto calculated the net due date!
    no reference doc
    [PIC1|http://www.flickr.com/photos/44956360@N08/5208025267/]
    input reference doc
    [PIC2|http://www.flickr.com/photos/44956360@N08/5208623198/]
    Thanks for your help.
    Best regards,
    Eric

  • Net Due Date differences in Credit Note

    Hi FI Gurus,
    I have pass an entry for returns Credit Note based on return order u2013 This Credit Note was created on 11/05/08 with Payment Term (T60B) 60 days from B/L date so the due date should 60 days from the B/L date means the net due date should be 10/07/08.
    But in my case system is showing the same due date as the document date means the document date is 11/05/08 and the net due date is also the same 11/05/08 in FBL5N customer line item report.
    Kindly can any body help me why system is behaving like this, while only passing the CN entry system is showing the same due date as doc date, for the normal customer invoice for same payment term (T60B) is calculating accurately 60 days from the baseline date.
    Thanks and Regards,
    Yasir

    Credit memos are of 2 types
    Other Credit Memos.
    Terms of payment in other credit memos are invalid. These credit memos
    are due on the baseline date. To activate the terms of payment in these
    non-invoice-related credit memos, enter a “V” in the invoice reference field
    during document entry.
    Invoice related credit memos:
    Credit memos can be linked to the original invoice by entering the invoice
    number in the invoice reference field during document entry. In this case,
    the terms of payment are copied from the invoice so that the invoice and the
    credit memo are due on the same date.
    If you look at the second option you need to give the Invoice referevce to default the terms from Invoice or use "V" in the reference feild.
    Hope you have understood the concept.
    reward if useful.
    sarma

  • Change the Net Due Date of a vendor Document

    Hi,
    Can anyone please tell me if it is possible to change the net due date of an AP Local document (doc. type = RE) generated by MIRO?
    I`ve tried to change the base line date (Bline date) but this field is unavailable to be changed in my company`s SAP.
    There is any other way?
    Thanks in advance!

    Hi
    You can change the payment terms
    Also
    To make any field as modifiable check the document change rules in OB32
    Regards
    Sach!n

  • Payment terms - net due date same as credit days?

    Dear all,
    I need to set up a payment term with 20 credit days, 2%. Invoices should be due also after 20 days.
    I would like the payment term to be set up as follow:
    Term           Percentage           No of days
    1.                2                           20
    2.                                             20
    The problem is that the system doesn't let me to set due date to the same number of days as the credit days.
    We will have baseline date = invoice date for our payment terms, if that matters.
    How could I acheive to have due date 20 days after invoice date (baseline date) and deduct 2% cash discount the whole time?
    Thanks and regards,
    Helene

    Hi,
    Please create a payment term as below, if your requirement is "I need to set up a payment term with 20 credit days, 2%. Invoices should be due also after 20 days"
    Term           Percentage           No of days
    1.                2                           20
    2.                                             21
    In case your requirement is to give 2% discount if paid within 20days and due net after that:
    Term           Percentage           No of days
    1.                2                           19
    2.                                             20
    Hope this will solve your issue.
    Thanks,
    Kiran Yelamarthi

  • Credit memo net due date is not correct

    Hi experts,
    In most cases the net due date of customers credit memos (posting key 11) is correct based on payment terms but sometimes itu2019s not (e.g. payment terms 30 days end of month but net due date is the same as document date).
    Any ideas why?
    I checked payment terms in customer master data and in FI and they are the same.
    Thanks for your help,
    Ben

    The general rule is that the due date of a credit memo is the baseline date.
    There are 2 exceptions: if you put the number of an invoice in the field BSEG-REBZG (Number of the Invoice the Transaction Belongs to), the due date of the credit memo is the due date of the invoice.
    2nd exception: if you put the constant 'V' in this field REBZG (you can do it thru a substitution rule), the due date will be calculated the same way as for an invoice.
    You can see this in the documentation of the data element REBZG:
    A special rule applies to credit memos which have a "V" in this field.
    The due date is determined in the same way as for an invoice. If the field is empty (containing neither a document number nor a "V") the due date is the baseline date for payment.

  • Mismatch in net due dates in credit note output and FBL5N

    Hi SAP gurus,
    In my case, there is a credit note with 30 days payment terms and it is without reference to an invoice. The net due date on output is 30-10- 2010, while in FBL5N, it is 30-09- 2010. As per the analysis, it is right as in case of without ref. to invoice, the baseline date will act as net due date.
    Now the user, wants to have the same due date at both the places( FBL5N and invoice output) irrespective of standard settings, I came to know that it is possible through some change in output type.
    If so, kindly suggest me the logic as how to fetch the date appearing on FBL5N on invoice output. Need is to take the FBL5's date as input to be printed on output.
    thanks a lot in advance for the inputs.

    Credit memos are of 2 types
    Other Credit Memos.
    Terms of payment in other credit memos are invalid. These credit memos
    are due on the baseline date. To activate the terms of payment in these
    non-invoice-related credit memos, enter a “V” in the invoice reference field
    during document entry.
    Invoice related credit memos:
    Credit memos can be linked to the original invoice by entering the invoice
    number in the invoice reference field during document entry. In this case,
    the terms of payment are copied from the invoice so that the invoice and the
    credit memo are due on the same date.
    If you look at the second option you need to give the Invoice referevce to default the terms from Invoice or use "V" in the reference feild.
    Hope you have understood the concept.
    reward if useful.
    sarma

  • Table name for the field FAEDT(net due date)

    hi every body,
    plz can any body tell me the table name for the field net due date(FAEDT).
    its very very urgent
    thanq.

    Hi mark chalfen,
    thanq very much ur reply.
    actually my client want to change the payment term for all the vendor invoices.so wt we did is... we created aprogram to change the old payment term to new payment term in the vendor line items(fbl1n).
    when we run the program its changing the payment term and the base line date and the NO of days in the vendor linitems.but it not changing the net due date based on the new baseline date.
    i think with out changing the net due date only changing the payment term is use less.coz the item again show as due in the same date.
    so how can we change the net due date based on the new baseline date.?from which table we can take the field FAED and update with the new date.
    plz advise me?
    thanq.

  • Re: Net Due Date

    Hi,
    With which FM can I find the net due date for payment in SD? For any payment terms.
    Thanks a lot
    Hitesh

    Hi,
    Based on the billing documents & the payment term you can define the Net due date.
    Look the source code in the FM
    J_1A_SD_CI_DUEDATE_GET
    J_1B_FI_NETDUE
    Check this
    Maintain Payment Terms
    In the following section, you maintain the payment terms. The rules for determining the due dates are copied as payment terms from the Financial Accounting (FI) component.
    You can carry out different assignments for incoming and outgoing payments. You can also make a calendar assignment which will then be valid for both incoming and outgoing payments.
    If you want to use the correction on a workday you must:
    1. Enter a factory calendar.
    2. Define how the non workdays are corrected.
    Requirements
    You must have maintained the payment terms in Financial Accounting. Do this by choosing Financial Accounting -> Accounts Receivable and Accounts Payable -> Business Transactions -> Incoming Invoices/Credit Memos -> Maintain Terms of Payment.
    Return ->
    Thanks
    Rajeev

  • Incorrect net due date in FBL5N

    Hi,
    I have problem with incorrect net due date in FBL5N. I made payment term "120 day end of month". Configuration of payment below.
    Maturity date whitch is invoice is correct. For example: Invoice was generated on 6th of February and the maturity date is 28th of June. Problem is that the net due date in FBL5N is incorect, it means net due date is 8th of June. This date isn't counted from end of the month.
    Does anyone have any suggestions on a fix?
    Thanks

    SAP has standard functionality for credit note (without invoice reference) to populate net due date as base line date itself irrespective of payment terms. Hence net due date and base line date is appearing same in FBL5N.
      For this, we have to put “V” in invoice reference field (BSEG – REBZG). By putting “V” SAP correctly populates net due date in FBL5N. We have done this manually for below mentioned customer and its working fine. It can be automated by writing user exit mentioned in the link.
    http://scn.sap.com/thread/342202

  • Interest calculation based on Net Due Date

    Hi guys: I want the interest calculation based on net due date and not document date or posting date.
    I tried to check the box "ALWAYS CALCULATE INT FROM NET DUE DATE in prepare item interest calculation step, but system gives me message
    "Do not select "Calc.intrst from net due date" for this int.calc.type
    Message no. F7128"
    Here are my questions:
    1- how can i make the system to calculate interest only after the item is due for payment - right now its calculating anyday after the document date
    2- Is this the correct place in configuration to do this?  (ALWAYS CALCULATE INT FROM NET DUE DATE )
    3- Also in T code FINT, how can i run interest posting for only one item rather than all that show up in test run? I tried selecting/highlighting only one but it posts all.
    thanks much
    brian

    HI,
    The system always calculates the interest from the document date of the invoice,
    as of my knowledge there is no setting for the interest calculation from the net due date, so
    what u need to do is when u are running the open item interest run u specify the period of only the date
    from the net due date to required date as of u.
    if u  want to calculate the interest to paticular invoice and  having two invoices
    then u can run  as per the document date and other thing is u can block the invoice for dunnig.
    Regards,
    Padma

  • Net Due Date - FBL5N

    Hi All
    There is a request to change the net due date at the report FBL5N : if the net due date is on a weekend or holiday, it is necessary to change it to the next business day..
    I realized that this field is calculated using FM DETERMINE_DUE_DATE (when running FBL5n).
    Questions:
    -  Is it possible to change this date as requested? If yes, is it an ABAP issue?
    -  Modifying this net due date at this point, may affect the integrity of other reports or transactions?
    Thanks in advance.
    Regards.
    Gaia

    HI,
    As per SAP standard, it is not possible to link the due date calculation
    to a calendar so as to avoid having the due date fall on a holiday or
    weekend.  There is no provision in standard SAP to enable this.
    Only for automatic payment and dunning purposes, you can use a calendar
    to avoid payments on Saturdays, Sundays, and Holidays. Please see
    customizing transaction OBBA.
    One suggestion could be to use the substitution functionality, where
    you can substitute and change several fields from BKPF and BSEG. By a
    user exit you will calculate the adequate baseline date to avoid due
    date on Saturdays, Sundays or Holidays.
    Regards
    Madhu M

  • Printing of Net Due date in report output

    hi Guru's,
    I have to print the net due date which is printed in fbl1n, but the problem is the field FAEDT is comming from the structure and i am not able to print it.
    The process is like this
        Base line date + Payment Term = Net due date.
        here the Payment Term is maintained in SAP code so how can i convert this so that i can do the above calculation.
    Payment terms like (Z001,Z002,Z003) etc.
    urgent.
    regards
    syama
    Edited by: syama sundar on Aug 11, 2008 10:48 AM

    hi,
    see:
    Link: [https://forums.sdn.sap.com/click.jspa?searchID=15042090&messageID=5792271]

  • How to see (net due date + payment term's days) in fbl5n as a date

    hi experts.
    i need some informations about fbl5n fields
    i can see net due date and i can see terms of payment fields in the fbl5n but  if the invoice has a payment term (30 day additional etc) i want to see (net due date + payment term's extra days) . for example if the net due date is 01.06.2011 and payment term is extra 20 days  , how can i see 21.06.2011 in fbl5n or any other sceens?
    Edited by: Burak Akdasli on Jun 22, 2011 3:43 PM

    Hi
    I understand from ur question whats the billing date?
    If this is ur question, you can fetch it from sales order>item>billing tab.
    The logic u had mentioned is confusing be more specifc as to what scenario u are trying.
    Reward if it helped
    Chandru

  • Calendar date & net due date (FI) PAYMENT TERMS - OBB8 Vendor Invoice

    I read many posts on SDN forum about the topic.
    Anyway, I didn't find a simple solution for that.
    My aim is is to calculate a net due date based on working days.
    So, If I've got a 30 days document days payment term  ("Deafult for baseline date" = Document date ; Additional Months = '2'), a Vendor Invoice (document date = 12.05.2011), by standard net due date will be 12.06.2011.
    FROM 12.05.2011 to 12.06.2011 =
    32 CALENDAR  DAYS         
    22 WORKDAYS (32 minus  10 holyday - 2 weekends)
    WORKDAYS PAYMENT TERMS  Within 30 workdays Due net
    Vendor Invoice  document date = 12.05.2011
    plus   30 workdays   =  DUE DATE  22.06.2011  (and not 12.06.2011)
    Can I obtain that with a standard functionality?
    Edited by: Roberto Buono on Jul 1, 2011 2:29 PM

    Hi,
    Sadly this is not available as standard.  As per your need the Net due date should be worked out by using a factory calendar; but what this does is it delinks the direct correlation between the number of days in the payment terms with the difference between the due date and baseline date.  I hope you are aware that Net Due date is not stored but is a variable calculated during run time in reports.
    There are four things you can try:
    1.  The simplest to do is: As the number of weekends are fixed; and if the intention is to give a 30 working day term, then add on the number of weekends and make the payment term effectively for say 40 days.  There will be marginal variations over what you want. Best part here is that config remains standard.
    2. All the receivable reports will use a function module (usually the same one) to calculate the net due date; enhance the FM and make it consider a factory calendar for calculating due date.
    3. Enhance the accounting interface, and in runtime; modify the days that are coming from the payment term; based on a factory calendar, and update the accounting document. This delinks the days mentioned in the payment term and the accounting document and may not be palatable.
    4. Enhance the accounting interface, and in runtime; calculate the due date and update the baseline date with it and make the payment term as "Immediate" yielding the desired due date. Not very elegant.  Alternatively add to the baseline date days equivalent to holidays and weekends and keep the days from payment terms constant and update the accounting document. Better...
    All four options have somes pros and cons.  I do not see any other means of acheiving what you want.  Maybe you could restrict users to a custom receivables/due date/ageing report which delivers what you want and lock the standard reports.