Hi..
Note: I have posted this message earlier ......but couldn't find that. I am just reposting the message:
In our quality environment, we have two SRM and two backend systems. One for testing purpose and other for training purpose. We are planning to remove one back end system and connect both the SRM systems to one backend system.
1. Is it possible to have this landscape?
2. In SRM & R/3 we can define two RFC connnections but from R/3 side, I am not sure how the system will determine the respective RFC connection during GR or any other process.
3. Are there any other difficulties?
We are in SRM 4.0 using Extended classic scenario. We are using SRM for processing shopping cart, Po and confirmations.
Please advise.
Thanks.

Hi Prashanth,
is  very much possible.
for this you need to configure the partner profiles.
need to define port
need to configure inbound paramters and outbound parameters.
we20 - create partner profiles.
define outbound parameters and inbound parameters of the message type.
we21 - define port.
under Transactional RFC.
and create a distribution model and add message type.
revert back to me if any problem still you find.
regards
sai

Similar Messages

  • Can two different SRM clients systems connect to one R/3 Back-end system?

    Hello,
    Trying to developing SRM Co-Exist/Global strategy, based on the following scenario:
    1.  Two different SRM client systems, each at DIFFERENT SRM Version/Release Level.  SRM system "A" runs in Stand-Alone and Extend Classic Scenario mode.  SRM system "B" runs in Classic Scenario mode
    2.  Two different R/3 back-end systems, each with SAME R/3 4.7 Version/Release Level.
    Question 1:  Can the two (2) different SRM client systems be connected to one (1) of the R/3 back-end systems?
    Question 2:  Are there any Basis Plug-In (PI_BASIS) issues/difficulties to consider from either the SRM client or R/3 back-end side?
    Question 3:  Does each SRM client need it own unique transaction document type(s) and number range(s) definitions?
    Question 4:  Are there any other difficulties, for example, with RFC and Partner Profile related definitions and what are the steps to address/resolve difficulties?
    Please advise and thanks in advance for your feedback!
    Regards,
    Ed
    Edited by: Ed Shigo on Mar 16, 2009 6:40 AM

    Question 1: Can the two (2) different SRM client systems be connected to one (1) of the R/3 back-end systems?
    They can be connected
    Question 2: Are there any Basis Plug-In (PI_BASIS) issues/difficulties to consider from either the SRM client or R/3 back-end side?
    Make sure that you have unique consumer entries for Middleware for Material replication, RFCs etc
    Question 3: Does each SRM client need it own unique transaction document type(s) and number range(s) definitions?
    Yes you need to have them.
    Question 4: Are there any other difficulties, for example, with RFC and Partner Profile related definitions and what are the steps to address/resolve difficulties?
    Don't see any difficulties as long as the a structured approach is followed.

  • Vendor Replication and Different Back-end Systems

    Hello,
    Currently, we have vendor replication were the vendor number from the back-end is used in SRM-EBP.  Now, we want add another back-end but there are vendor number conflicts.  Is there a way to configure it so that the new back-end replicaition generates new numbers in SRM-EBP? 
    Honestly, there should be a cleansing and alignment of vendor numbers between the two back-end systems. However, that is big task that the organization doea not want to take on at this time.
    Has anyone encounter this issue and how did you resolve it?
    Regards, Dean.
    Edited by: Dean Hinson on Feb 3, 2010 3:26 PM

    Hi,
    You can find option "If R/3 number assignment is not possible: Internal number assignment" in the bottom of BBPGETDV transaction screen.
    Regards,
    Masa

  • Connection between CRM back end and ASP front end website for Ecommerce

    Hi All,
    I want to establish the connection between a ASP website and CRM back end server(we are replacing th existing ERP back end system with SAP CRM ).
    I want to know whether I have to go with XI or any other connectors provided by SAP to establsih the communication between the existing ASP website and CRM back end server..
    Can anyone please help me out.
    Thank you,

    Okay here is the general concept for your scenario:
    -You will call standard/custom RFC's(could be BAPI's) in the CRM system from the existing application. 
    -You will need to write a new model layer in your ASP application that calls the RFC layer in CRM
    -You decide what data you want to use from CRM in your application
    Let's assume at minimum you will want to use the product master, business partner master, and business transactions.  You will need RFC's/BAPI's for every interaction point where you will consume/publish data to CRM.
    So when an user creates an order from your e-commerce site, you will need to support saving an order in CRM.  This is example of how you need to map out each function in your existing site to a part of the CRM system.  Since we don't know what your site currently does, this is something you would have to do.
    Once you have mapped out the business level data to the CRM system, then you can evaluate where you will need a BAPI and/or RFC call.  Once that is done, then you can look at the CRM system and see what standard pieces can be called.  Then everything else is custom development.  Your ASP application will call CRM via RFC. 
    It is possible to do what you want to do, but it is going to require a lot mapping work and a fair amount of development effort to integrate the two pieces.  I don't know if you might be better off looking at the SAP Internet Sales Solution instead so you could focus only customizing that application, instead of worrying about an integration problem.  It just depends on how much special functionality your existing e-commerce site has today.
    My general recommendation would be for you to hire a consultant that has done an SAP e-commerce project using SAP CRM in the past and let them guide you on the implementation issues.  An on-site resource could better answer your "high-level" questions.
    However if you have more questions please ask and I will try to answer to the best of my knowledge.
    Good luck,
    Stephen

  • Sharepoint recovery 1 front-end one back-end

    I have a simple SharePoint environment with a SharePoint 2010 front end and a dedicated SQL back-end. Both virtualized on Hyper-V 2008 R2 host. There are no complicated apps - it is just a file serving SharePoint implementation.
    The VHD for the front end server (it only had one drive) got corrupted. I have an export of the complete server from the 29th December, including the VHD.
    The back end (SQL and all the databases) if unaffected.
    I tried creating a new VM with the three day old VHD from the export, but it does not seem to correctly connect to the back end.
    I also have DPM 2012 backups of the whole thing systems, though they are made via the SharePoint front end.
    With a whole panoply of solutions I can:
    1. import the exported front end and see if that works better than just re-creating the machine (GUIDs and all that)
    2. Forget the export of the front end on the 29th and do a fully fledged DR from DPM
    Any other ideas?
    CarolChi

    One thing to note is that SharePoint does not support VM backups (that is, snapshots or full backups of the VHD itself). Since your VHD is older than the data within the Configuration database, it is best to start with a new front end.
    You should be able to install SharePoint up to the same patch level on the new front end, "join" the existing farm, and then forcibly remove the defunct SharePoint server from Central Administration.
    Trevor Seward
    Follow or contact me at...
    &nbsp&nbsp
    This post is my own opinion and does not necessarily reflect the opinion or view of Microsoft, its employees, or other MVPs.

  • Value for customized fields didn't get copied to back end system

    Hi,
    We are in SRM 4.0 and using extended classic scenario.
    We have defined two customized fields in account assignment tab in shopping cart and SRM Po and also in back end PO.
    SRM POs are having values for the field but while transferring the Po details to back end system, for some of the line items of the Po the entries are missing in back end system.
    Problem is only with few line items of the PO.
    Have tried with FM like BBP_PD_PO_TRANSFER_EXEC  and BBP_PD_SC_RESUBMIT, but it is not transfering the values to back end.
    Is there any other way to push the missing values to back end system.
    Please advise.
    Thanks.

    Sk,
    Table adjustment has to be done accordingly. Get in touch with your Basis team.
    Thanks.

  • Client Copy back-end system

    Hi Guys,
    We have made a client copy of the back-end system of SRM (SRM 5.0). Only the back-end and not SRM has been copied.
    After replication all the master- and customizing data again to SRM from the 'new' back-end I have found an issue with updating the suppliers.
    It seems that I can not remove old business partners from SRM with BUPA_TEST_DELETE if these are used already in SC's. However the new copy of the back-end system has completely different suppliers we need to use in SRM. This causes for an inconsistency with the supplier numbers, as we want to keep the R/3 numbers in SRM.
    Does anyone has a good idea how to proceed? That is, how can I remove the business partners (suppliers) in SRM which were used before the client copy of R/3, so that I will be able to completely get all the relevant 'new' vendors from the R/3 system after the client copy.
    When I execute BUPA_TEST_DELETE it will end up in error saying the suppliers can not be removed. Do I need to archive all the old documents (SC & PO) before I can remove all vendors in SRM, or is there a way to force the removal of all the business partners from before the back-end client copy?
    Thx.
    Skander

    Hi,
    I already figured out how to solve the issue.
    For anyone who wants to know how to:
    -First clear the vendor groups in the vendor hierarchy; do not renove the root node
    -Then run BBPGETVD which will get you the new vendors from the back-end; for me only role LF for suppliers.
    -Then run BBPUPDVD which will update all the fields for the old business partner numbers in SRM which were used in documents, and replicated from the old back-end system.
    In my case I had to play a litlebit with the setting 'only creditors', to update BP numbers which were not suppliers in the new back-end.
    After performing these steps everything should be fine.
    So it's perfectly possible to make a client copy of only the back-end system without copying SRM (in the classic scenario that is).
    Rgds,
    Skander

  • Error : No valid R/3 Back-end system

    Hi CRM gurus,
    I'm trying to connect SAP CRM 5.0 to SAP ECC 5.0.
    When I launch trx R3AS for downloading the first object of the list coming from Best Practise (DNL_CUST_ACGRPB), I am getting the above error: "No valid R/3 Back-end system."
    Now the point is that RFCs work smoothly, administration console as well and R/3 view CRMRFCPAR was filled correctly.
    Where is the problem? I'm looking into, but without results.
    Any suggestions in this issue will be rewarded.
    Regards,
    AndreA

    Many thanks Praveen,
    I have carried out all the checks in the tables and it seems that everything is fine!.
    Creating a RFC Destication for CRM in R/3
    Maintain Table CRMRFCPAR and CRMCONSUM?
    In Table CRMPAROLTP, Parameter "crm release" should set to your CRM version ( ex 500 for crm 5.0)
    Maintain table TBE11, APPI should be NDI(new dimension integration),A yes
    I don't really know where the error could lay.
    Andrea

  • MOPZ - Error during call of SAP back end system

    Hi Experts,
    I have this error during MOPZ - "select OS/DB dependent files" and following option as well.
    I have checked SAP NOTE 982045, but still cannot solve the issue.
    SM59 - SAP-OSS and SAPOSS connection test is successful.
    I have no idea what else is going wrong. kindly advise id you have any idea.
    Below are some error logs.
    From MOPZ
    Error calling SAP back-end system: Local gateway not running / CPIC-CALL: 'ThSAPCMRCV'SAP-OSS via RFC destination.
    From SM21
    Call of function GwRead failed, RC: -095
    Communication error, CPIC return code 017, SAP return code 24
    > Conversation ID: 13681187
    > CPI-C function: CMRCV
    From dev_rfc8
    **** Trace file opened at 20140904 134347 Malay Peninsula Standard Time, by disp+work
    **** Versions SAP-REL 721,0,300 RFC-VER U 3 1498740 MT-SL
    ======> CPIC-CALL: 'ThSAPCMRCV' : cmRc=17 thRc=247
    Local gateway not running                                               
    ABAP Programm: CL_SM_DATA_SENDER_RFC=========CP (Transaction: )
    Called function module: /SPN/SBI_INTERFACE
    User: BT_BASIS (Client: 100)
    Destination: SAP-OSS (Handle: 4, DtConId: 22F633E42CC0F1D280C9A0D3C1069543, DtConCnt: 1, ConvId: 12214252,{22F633E4-2CC0-F1D2-80C9-A0D3C1069543})
    EPP RootContextId: A0D3C10695431ED48CFEB45C956820C9, ConnectionId: D3F533E43BF2F12C80C9A0D3C1069543, ConnectionCnt: 1
    EPP TransactionId: D3F533E43BF2F12A80C9A0D3C1069543
    SERVER> RFC Server Session (handle: 1, 18243574, {D3F533E4-3BF2-F12C-80C9-A0D3C1069543})
    SERVER> Caller host:
    SERVER> Caller transaction code:  (Caller Program: CL_MO_SMP_ADAPTER=============CP)
    SERVER> Called function module: AGS_MOPZ_SMP_RFC
    Error RFCIO_ERROR_SYSERROR in abrfcpic.c : 3712
    CPIC-CALL: 'ThSAPCMRCV' : cmRc=17 thRc=247
    Local gateway not running                                               
    Error RFCIO_ERROR_MESSAGE in abrfcio.c : 1973
    Thank you.
    Por.

    Hi
    there are following things you can do
    1. log on to your SAP Router
    2. check entries in SAPRoutab.
    3. Telnet SAPSERV2 (Sap responding server) (Tcode oss1 will give you details of which SAP serve you are connecting ) on port 3299
    4. if you are able to telnet SAPserve from your Router server  then raise the call to SAP and ask whether they can reach your saprouter or not
    5. check /etc/services files and check for service 3299 defined or not
    6. telnet local Router server with port 3299
    7 try to download Sap Note from SNOTE in you solman system.
    all the best
    Regards
    Dishant.

  • Role mapping between Portal and Back end systems

    I am new to SAP EP.
    I just want to know how the mapping between portal and back end system happens.
    Scenario : There is a role in ECC system...say FI India. Now there is a request by the FI team that they want to access this role from Portal. In this case, please tell me how the security team will do it. Because I guess, it has to be done by the security team.

    Hi,
    Usually the role from backend is uploaded to portal then it will be seen as Group and we need to assign our portal roles to this group. Please refer [this|http://help.sap.com/saphelp_nw73/helpdata/en/d6/7859ec80df46738e23ccb4f4c8c502/content.htm].
    Regards,
    Samir

  • 'SPROXY' - Multiple PI Systems connected to one ECC System for ABAP Proxies

    Dear Experts
    I am currently facing an issue when I want to connected multiple PI instances to one ECC client for
    ABAP Proxy purposes.
    In transaction 'SPROXY', in the Enterprise Service Brower, only one PI instance is shown and accessable.
    Can this setting be changed to allow multiple PI systems in this Enterprise Service Browser?
    Thanks for your ideas.
    Mathias

    Hi,
    Check these replies.
    R/3 connected to multiple XI instances
    'SPROXY' - Multiple PI Systems connected to one ECC System for ABAP Proxies
    Multiple XI Instances
    Multiple XI instances or multiple app server
    Thanks,
    Vijaya.
    Edited by: Vijaya Lakshmi Palla on Jun 4, 2008 11:43 AM

  • 2  Srm Systems connected to 1 R/3 system is it possible

    Hi friends,
    I was looking into a situation where you would have 2 SRM systems pointing to 1 backend R/3 system. I<b> dont believe its possible.</b>
    I believe you can have 1 SRM pointing to multiple backend systems, this is do-able.....
    cheers
    alex

    It is possible that there can be multiple SRM system connected to 1 R/3 system...You need to setup on...IMG>SRM->SRM Server->Technical Basic Settings>Define Backend System-> There you need to provide Logical System/Description/RFC Distination and Sys Type.
    I hope it clarifies your issue.

  • How to connect to MySQL back end in Syclo Agentry?

    Hello All,
           I have worked on Syclo agentry with Non-SAP back end (MsSQL) and with SAP back end(Work Manager App).
           But now I wanted to connect with MySQL Back end, I know that it is possible, because Syclo can deal with Oracle,IBM Maximo, MsSql and SAP(ERP,CRM...etc)
           But how to connect with MySQL Back end. What is the procedure and the Configuration changes.
           Could anyone help me out to find the way.
    Thanks,
    Swaroopa.

    Swaroopa,
    You may also need to create/define your database globals if you are using SDML database tags in your queries.  For example  <<database.getSystemTime>> will evaluate differently for MySQL compared to SqlServer or Oracle
    You will want to create a mysql_sd.ini file containing the various database SDML tags and their corresponding MySql values.  I would suggest copying the sqlserver_sd.ini and then update based on mysql syntax.
    You will then want to update your Agentry.ini queryConstantFiles entry for the mySql backend settings to point to your new filename.
    --Bill

  • SCM question -2 SCM system connected to single R/3 system

    Hi Gurus,
    What is the implication using two SCM systems with single R/3 system when both SCM systems using for different modules (say one for DP and other one for GATP).
    I know SAP recommends using multiple OLTP with single SCM. But this scenario opposit of that.
    Thanks,
    BKN
    Edited by: BKN on May 6, 2008 7:08 PM

    It is possible that there can be multiple SRM system connected to 1 R/3 system...You need to setup on...IMG>SRM->SRM Server->Technical Basic Settings>Define Backend System-> There you need to provide Logical System/Description/RFC Distination and Sys Type.
    I hope it clarifies your issue.

  • Move System Preferences Help file back into System Preferences folder?

    How do I move System Preferences Help file back into System Preferences folder.  I unintentionally moved it.  My Mac blocks putting it back.  Suggestions?  Thanks!

    Somehow I managed to delete my System Preferences shortly after upgrading, and was able to use the 10.4 one for a while until I applied the patch. Luckily, I already had Pacifist, and with your directions I was able to get close enough so that I could find the Applications folder within the ContentsofEssentialsSystemSoftwareGroup > ContentsofEssentials.pkg > Applications > SystemPreferences.app.
    For that, I owe you the deepest gratitude and a gigantic THANK YOU. My System Preferences is now fully reinstalled and working wonderfully.
    Pacifist might actually be worth purchasing.

Maybe you are looking for