UserExit for priority in production order

Hi SAP-Gurus,
a friend of mine told me that they had an userexit in place which automatically determines the priority of an order according to the reduction level in the production order...
Supposedly it works according to the following logic...
reduction strategy 4 (100% reduction) -> priority 1
reduction strategy 3 (75% reduction) -> priority 2
reduction strategy 2 (50% reduction) -> priority 3
reduction strategy 1 (25% reduction) -> priority 4
reduction strategy ' ' (no reduction) -> priority ' '
Moreover, the exit has three different triggers. Creating/saving & releasing a production order. At first glance doesn't seem to be to complicated, however I need more info....
Has anybody ever heard of such a functionality and is able to give me the number of the exit?!?
Any help is greatly appreciated....
Regards,
Bobby

Dear Boban,
maybe you mean BAdI Workorder_Update instead of Userexit? In workorder_update you have methodes for at_release, at_save and in_update. You can check in SE18.
Otherwise you can check the user exits in SMOD, the exits in production order start with PPCOxxxx.
Regards,
Sabine

Similar Messages

  • Priority of production order

    hi
    how to set Priority of production order according sales order ?

    Hi,
    try to use be.as manufacturing addon or lisa manufacturing addon. For detail, download the pdf file from this link:
    https://websmp208.sap-ag.de/~sapidb/011000358700004044122006E/
    Rgds,

  • Priority to production order

    Dear all,
        I want to assign the priority to production order in the priority field. But I was not able to find the customization for the same. Pl help me in that regards.

    Hi Mangesh,
    The Priority field is useful at the production level. In the header table of creation of production order,we can assign the priority of that particular order like 1,2,3,4.if we have two or more production orders using same workcenters based on the priority, we can use this priority field.It is only for information purpose.
    It reflects on the execution of capacity planning(CM01).This is for manual verification at the shop floor control for completing the production order.
    Regards,
    srivas

  • FM for creation of production order creation

    Hi All,
    Can anyone tell me the BAPI for the production order creation.
    BAPI for creation of production order through CO01 transaction code.
    Thanks in advance
    Ramesh.

    Hi,
    Please check this FM CO_ZF_PRODUCTIONORDER_CREATE.
    Regards,
    Ferry Lianto

  • BAPI/FM for Confirmation of Production order at operation level

    Hi ABAPers,
    I am using the 'BAPI_PRODORDCONF_CREATE_ACT'for Confirmation of Production order at operation level.
    I am able to pass the Production order number and Active Operation get the confirmation done.
    But the Confirmed Qty is not being updating in AFKO table.
    The 'BAPI_PRODORDCONF_CREATE_HDR' cannot be used for Confirmation of Production order at operation level as there is no Operation/Activity(Vornr) field in the input table. Hence using this bapi confirmation of Prod order can be only at Order level.
    Can someone know any FM/BAPI which can be used for the Confirmation of Production order at operation level(not order level).
    Thanks in Advance
    Ramesh Babu Cikka

    Hi Ramesh,
    Please use FUNCTION 'BAPI_PRODORDCONF_CREATE_TT'.
    This will work as like as T/Code "CO11".
    I hope this will help you.
    Example :
      CALL FUNCTION 'BAPI_PRODORDCONF_CREATE_TT'
        EXPORTING
          POST_WRONG_ENTRIES = '0'
          TESTRUN            = ' '
        IMPORTING
          RETURN             = ZRETURN
        TABLES
          TIMETICKETS        = ZBAPI_PP_TIMETICKET
          DETAIL_RETURN      = ZBAPI_CORU_RETURN.
      CALL FUNCTION 'BAPI_TRANSACTION_COMMIT'
        EXPORTING
          WAIT = 'W'.
    Lanka

  • Committed Date For Components in Production Order

    Dear All,
    I m facing this,  Committed Date For Components in Production Order,
    the date appeared as 31.12.9999,
    How can i make this correct.
    please tell me..
    Thanks
    Raghu

    Hi, Thnkx,
    You Are correct, I got this while doing Availability Check, 2 dates.
    Requirement Date, and Committed Date.
    I tried your solution,
    I change the Quantity of one of my BOM , I tried to change the Quantity by Change Number,
    So in CS 03 I can see the Validity of that component up to 01-09-2010,
    I run MRP agian, new planned Order, tried to convert, the question is same.
    I still get the date as 31-12-9999.
    Thanks
    Regards
    Raghu

  • Worklfow for GR of Production order.

    HI .... is there any standard worflow template for GR of production order using MB31.
    Thanks in advance.

    Hi ,
    Please check this SAP provide WF: WS20000387.
    You can copy and make changes as per your requirement.
    Thanks and Regards,
    Swaminathan

  • Query for Alert on production order to be released

    Dear all users and experts,
    I need a query for getting an alert on production orders to be released (from planned status to release status) by whether reading the release date of production orders created from 'order recommendation window' or by reading the due date of production order and substract the lead time(days) of the item from its due date or by any means you know best.
    Thanks and best regards,
    Farhan Sufi

    Hi Gordon and Joseph,
    Thanks to both of you for giving me queries.
    Gordon, I made 3 production orders for testing from MRP order recommendation window from which 2 production orders has release date of today 9th July, 2010 (due date 12th July monday) and the 3rd one has release date of after weekend i.e. 12th July 2010 (due date is 13th July). release dates are calculated by MRP acording to the items' lead time and due date.
    Gordon, when I applied your query It gave me msg 'no data was found as a result of this selection criteria' Can you explain what your query will give me in result?
    where as Joseph, when I applied your query on alert, it gave me all 3 production orders as an alert to be released. I was expecting it will give me alert for 2 production order for today as their release date in MRP is today(9th July, 2010) and the alert for 3rd production order should come on 12th July and not today.
    what I understood your query is displaying all production orders which have status 'planned' regardless of their release date.is it?
    Joseph can you edit this query in such a way that It should consider the release date (calculated from due date and lead time in MRP order recommendation window) and display only those production orders which should be released today and exclude those which have release date in future. so that I can get alert for only those production orders which should be released today.
    I hope good response from both of you
    Thanks and best regards,
    Farhan

  • IDOC for Creation of Production order and also adding components

    Hi ,
    I have a requirement like I get the data from a 3rd party system and using that i have to create production orders and also should be able to add more materials in COMPONENTS part of that Production order. I was looking for a BAPI which can handle this process.
    And also can any one help me by letting me know is there any Message type available for handling this process of Production order creation and Adding extyra components to it.
    I have a  message type LOIPRO (for Production Order) and associated function modle CLOI_MASTERIDOC_CREATE_LOIPRO for creation of master IDoc, but not sure can i handle the Components part in this.
    Please do send replies ASAP, its very urgent.
    Or else atleast suggest me the other ways of doing this .
    Also send me any BDC program if anyone has already developed for this.
    Thanks
    Kumar
    Edited by: Phani Kumar Peddagopu on Mar 19, 2008 6:56 PM

    Resolved .

  • BAPI for creation of Production Order with Ref to sales order

    Hi all,
    we are using BAPI_PRODORD_CREATE  for creating Production Order with ref to sales order.
    As per the Business Scenario, we are not creating any masters like BOM and Routing, instead
    we are creating Routing directly into the Production Order under operation overview screen.
    during creation of routing system is generating a default operation.
    the following is the error results after running the Bapi.
    "No routing selected"
    Best Regards.
    GTNRNR.

    Hi GTNRNR,
    with out creation of BOM you created routing and in routing for the operations which components did you allocated so that can be used to manufacture the final product. Can you be please specific?
    Regards,
    Madhu.G

  • User exit for confirmation of production order for mandatory fields

    While confirming the production order ( CO11 & order type -PP01) , production order should not be saved/confirmed without entering the mandatory field (No. of employees), which is the mandatory field set in the config of "define field selection for confirmation"
    It is allowing if user does't click on the tab (personal/additional data).
    Without entering the mandatory fields in any tab system should not allow user to confirm the order
    How to apply this lock ?
    Also while doing the production confirmation (Co11N) ,user should not have the rights to changes ,adds or delete the component and its quantity OR if user make the changes , suystem should not allow to post the confirmation?How to make this in SAP?
    regards,
    Ramesh Bandi

    Hi,
    You can check the user exit CONFPP05 (Customer Specific Input Checks when Saving) and its function exit  EXIT_SAPLCORF_105 in the transaction code SMOD.
    With this enhancement you can update your own data after saving the confirmation. You cannot change the confirmation itself.
    In this enhancement it is strictly FORBIDDEN to send error messages or other dialogs, otherwise data inconsistencies could occur, for which SAP accepts no liability.
    You can check with your ABAPer's.
    please check & revert back to me.
    Regards,
    Mohan.R

  • Function Module / BAPI for reprinting a production order

    Does anyone know a Function Module to do a production order re-print?   Not an original, just a copy.
    Thanks,
    --Amy Smith
    --Haworth

    Thanks Kevin,
    Been there.  Couldn't find anything.  Doing a BDC for testing. 
    Looks like you have to do a Production Order change.    So maybe is a BAPI for that.
    I'll post what we find in this thread...
    --Amy Smith
    --Haworth

  • To cancel reservations of  rawmaterial  for a particular production order

    Dear sap gurus,
    Initially planned order is converted into production order and released, because of some problem the order is cancelled so i did teco for that production order but the rawmaterials are not deleted so pls help me in this issue.
    regards,
    muralidhar.t

    Dear,
    When you do TECO for the order the reservations get cancelled
    Please refer my reply in this thread ,
    Re: Reservations held for production orders that are Teco'ed and Deleted
    Regards,
    R.Brahmankar

  • BAPI or FM for Transaction CO02 (Production Order Change)

    Hi I have to change fields(CHARG,LGORT,RGEKZ,MENGE,EWAHR) in sap transaction (CO02-Change Production Order) in COMPONENT LEVEL
    Can anyone suggest one BAPI or FM for this.

    Hi Ravi
    Thanks for your Suggestion.
    I tried with BAPI <b>'BAPI_ALM_ORDER_MAINTAIN'</b>.
    It is updating in the transaction CO02 also.
    Actually it is using for Internal Orders.Can i use this one for <b>PRODUCTION ORDER</b> Also.
    Umashankar

  • To find 'Maintenance Work Center' for Equipment (without Production order)

    Hi,
    I have a Report for - 'Equipment BOM' - IB03.
    Problem: How to find the 'Maintenance work Center ' For Equipment ? (IE03--> Organization > Responsibility> Main. W.Cntr)
    [ Note: For Client -->  It's not necessary that each Equipment has Production Order, Few Equipments are taken only for Repair purpose, Equipment is there in table - EQUI,
    So - Not possible to fetch from AUFK, HIKO or any other order tables. ]

    I have a Report for - 'Equipment BOM' - IB03.
    Problem: How to find the 'Maintenance work Center ' For Equipment ? (IE03--> Organization > Responsibility> Main. W.Cntr)
    [ Note: For Client --> It's not necessary that each Equipment has Production Order, Few Equipments are taken only for Repair purpose, Equipment is there in table - EQUI,
    So - Not possible to fetch from AUFK, HIKO or any other order tables. ]
    EQUZ-GEWRK has the main work center. Pass the equipment number and valid-to date to get the main work center.
    Cheers
    Sujay

Maybe you are looking for

  • ITunes wont load on my computer

    Hey itunes wont load on my computer. It has been working for years but now it dosent work any more.

  • A tms issue

    hello experts, this is rahul , Iam facing a problem in tms 1) I have send a request with no DREK904242 from client 008 to client 009  in development system through T_CODE SCC1 and it is been copied ,and it is showing as released request, but I want t

  • Embedded Quicktime videos will not fully load!

    I've been attempting to watch an embedded Quicktime video on a website but it will only load for a certain portion and stop loading. Everytime I refresh and try again a different amount will load but never the whole thing.

  • Balance Sheet G/L-PL reporting for period range by debit and credit amounts

    Hi, good afternoon This report displays period intervals. One column must display G/L accounts and the others must perform: Initial balance, total debit and total credit. Example: <b>Period: mm.dd.yyyy to mm.dd.yyyy</b> Columns: G/L Account - Initial

  • Calling a class from a servlet

    Hello, I have created this class for creating a connection pool, which I want to use in a web app with a bunch of servlets. My plan is to put this class in the classes folder with all my other classes (I hope that works). But first I am seeking an an